You are on page 1of 26

SPE 108665

HP/HT Gas-Condensate Well Testing for Shell's Onyx SW Prospect


Arild Fosså, Expro; Derek MacKenzie, Norske Shell; Odd Steinveg and Eric Henderson, Expro; and
Bart van den Bosch, Halliburton/Shell

Copyright 2007, Society of Petroleum Engineers


first well 6406/5-1 in the Tott East prospect was drilled in
This paper was prepared for presentation at Offshore Europe 2007 held in Aberdeen, 2002 to intersect sands of the Middle–Lower Jurassic Garn, Ile
Scotland, U.K., 4–7 September 2007.
and Tofte formations2.
This paper was selected for presentation by an SPE Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
presented, have not been reviewed by the Society of Petroleum Engineers and are subject to Well 6406/9-1, Onyx SW, was planned as a vertical
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Society of Petroleum Engineers, its officers, or members. Papers presented at exploration well, with a HTHP pressure regime. The HPHT
SPE meetings are subject to publication review by Editorial Committees of the Society of
Petroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper
conditions in the well were marginal; however it was designed
for commercial purposes without the written consent of the Society of Petroleum Engineers is and executed as if under full HPHT conditions. Maximum
prohibited. Permission to reproduce in print is restricted to an abstract of not more than
300 words; illustrations may not be copied. The abstract must contain conspicuous anticipated surface pressure, with anticipated reservoir fluids
acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O.
Box 833836, Richardson, Texas 75083-3836 U.S.A., fax 01-972-952-9435.
to surface, was deemed to be less than 690 bar. Anticipated
bottom hole static temperatures were anticipated in excess of
Abstract 150°C. This well was drilled using a semi submersible drilling
This paper covers the HPHT Gas-Condensate Exploration rig.
Well, 6406/9-1 on the Onyx SW prospect of the Norway Sea
in the late spring of 2005 (Figure 1 and 2). The well test The Geological objectives for the well were to test the Middle
design and execution is presented in the paper, including; up and Lower Jurassic; Garn, Ile, Ror/Tofte and Tilje Formations
front planning, job design, technology selection and review of for the presence of Hydrocarbons (see Table 2 for details). The
the test results vs. the objectives for the well test. The paper stacked reservoirs were sandstones with intercalated shales
also addresses how health, safety and environmental belonging to the Fangst and Båt Groups. Separate by shale
considerations were handled. intervals (Not, Ror) typically formed intra-formational seals.

Traditional well testing methods and equipment have evolved The main objective of the Onyx SW well test was to
over the years, adapting to changing requirements. This has investigate the stacked formations Ile, Ror/Tofte and Tilje by
resulted in requirements for more complex data gathering over conducting a multi-zone DST, with each interval being tested
a shorter time with much stricter environmental and safety separately. Testing of two zones with a third as a contingency
constraints. Coupled with increased needs for more accurate was planned to cover the formations of interest. Results from
reservoir data for prospect evaluation, this has put a higher the well logging narrowed this to execution of a two zone
emphasis on upfront planning and improved technical DST, from a cost vs. benefit stand point.
performance together with extensive use of advanced fluid
data gathering methodologies. Key performance indicators
One of the most important and basic requirements in the
This paper demonstrates how the above was addressed for the Norwegian and international oil industry is to have control of
Onyx SW and how the results compared with the set goals. the activities offshore, to act on issues in a proactive manner,
The application of the latest technologies in Gas-Condensate and to capture experience data. For the Onyx SW well the
well testing was used on this job. Experiences from this were operator used their KPI system to the fullest in close
later used as the basis for other gas-condensate prospects, cooperation and supported by the corresponding service
including those in the Russian sector of the Barents Sea. company systems.

This paper focuses in particular on Fluid Sampling, Surface The objectives set for the job were clear and concise;
Well Testing and Subsea equipment. As several service • Zero LTI’s
companies were involved on this particular job, we have only • Zero HPI’s
included some general and limited content for the other • Zero Environmental incidents
services involved. • All well test objectives achieved
and driven by the operator throughout the planning and
Introduction execution phases of the job with full support from the service
The Onyx South West exploration well, 6406/9-1, was the companies.
second well to be drilled within licence PL 255 (Table 1). The
2

The drivers used by the operator company to achieve the KPI cost. This also impacts the accuracy of seismic interpretation
objectives were; and reservoir modelling9.
• To work to client technical standards and procedures
• To work to all 3rd party standards and procedures Design considerations
• Accountability and performance through HSE From the operator company’s perspective several design
• Good pre-job planning and communication (working to requirements were set for the equipment solution, due to the
well services quality plan) uncertainties associated with the Onyx SW prospect. The key
• Competent personnel factors which had to be included, in addition to the HPHT and
• Good HSE awareness throughout the operation expected fluid properties were:
• Unknown H2S concentration
In addition to the client’s KPI system, the service providers • Sand Monitoring due to uncertain formation properties
utilized corresponding KPI systems providing supplementary • Fire fighting
activity controls. All these systems were ISO 9001 type • Personnel Safety
continuous improvement systems, supplemented by ISO • Shut-down system(s)
14001 type systems for environmental control.
Several of there factors were not unique to the Onyx SW
The lessons learnt below stem from these systems, which were exploration well, but took on a higher significance than usual
instrumental for the control and successful completion of the due to the HPHT conditions and the fact that this was an
Onyx SW well test. exploration well, not an appraisal of a known prospect.

Well test objectives A review of the potential leak & rupture sources for the well
The primary well test objectives, for each of the reservoirs, test showed the following key points to be taken into account
were to assess the productivity and to obtain representative for the equipment and procedure design:
fluid samples. Obtaining reservoir pressure and temperature, • Test string leak below SSTT
determining kh and skin, and identifying possible reservoir • Packer leak or Seal Assembly leak
boundaries and heterogeneities were the secondary objectives • Landing string leak or rupture
for the formations to be investigated by the well test. • Surface line failure
• Process failure downstream of choke
To achieved the well test objectives, it was determined that a
set of special requirements to the quality of the test design had In addition the following key points were identified as design
to be met to obtain the desired data quality. These considerations for the overall well test.
requirements were: • Rig mooring system failure
• Down hole shut-in • Weather
• Well had to be tested with seawater as the packer fluid8 • Wave height
• Down hole memory gauges had to be used • Heat radiation
• Single phase sampling had to be used
The potential leak & rupture sources together with the key
These objectives and special requirements fell in line with overall points were included in the pre-job design work.
industry recommendations9, without lessening the importance
due to the universal nature of such exploration objectives. Addressing the KPI goals and well test objectives the service
provider undertook a detailed job design taking governmental,
For the Onyx SW exploration well which was in unknown industry standards and client technical standards into due
formations, the primary objective of assessing the productivity consideration. An overview of the well test plant can be seen
and to obtaining representative fluid samples were natural in Figure 3. The number of planned shut-ins was minimized to
since both affect the value of the discovered reserves. reduce the likelihood of hydrate formation.

The secondary objective obtaining accurate reservoir pressures To avoid accidental environmental discharges a two pronged
and temperatures was selected due to the importance for safety approach was selected. Firstly highly efficient, well proven
and equipment selection for future wells, along with giving the burner heads (Figure 8) were included in the design4, 5, 6, and
start point for further reservoir analytical work. The kh and secondly no fluid flushing to sea via the burner heads was
skin could not be satisfactorily attained for HPHT wells in any planned. Both approaches have been in use since around 1995
other way, since alternative methods have a poorer in Norway and have proved to be highly successful in
performance under such well conditions9,10. kh and skin were reducing recordable spills to sea to a negligible level for well
also selected as a target to further aid analytical reservoir test and well clean-up operations. Practical handling of the
simulation work and to enable improved use of the clean-up fluids included the use of a Storage Tank for fluid
productivity data. The detection of possible reservoir interface collection (Figure 3). The Storage Tank was set up
boundaries and heterogeneities was included as a secondary for decanting into transport tanks for slop transfer to shore, or
target due to the significance of this information when for alternative routings on the rig for added flexibility.
planning a future field’s drainage strategy and development
3

The anticipated reservoir fluid was a lean gas-condensate Well program and procedure summary
system and both choke cooling effects and hydrate issues were The well test program for the Onyx SW well was based on a
anticipated. To provide for sufficient heating and reduced variation of the n-rate test method7 (Figure 11), tailored to
pressure drop a highly efficient multi-tube heat exchanger each of the two zones tested. A DST consisting of the
design was provided. This style heat exchanger was following main periods was planned for both zones:
approximately twice the heat exchange efficiency of a • Initial clean-up flow and build-up (surface shut in)
traditional coil & shell type well test heater. The equipment • Main clean-up flow
also can handle the flow at pressure drops below 1 bar. • Sampling flow
• Main flow with main build-up (downhole shut-in)
Numerous safety features were also included into the design,
for example welded walkways and pipe support with full Additional contingency periods could be added to adapt to the
consideration for escape routes. Enhanced firefighting actual well and reservoir conditions.
capability was also taken into consideration by using well test
equipment fully equipped with deluge lines incorporated into The above test-outline translated into the following practical
each skid. In addition an Electric / Hydraulic ESD / PSD tasks set by the operator company to meet their goals and
system was included for overall protection. objectives:
Preparation (only for DST #1)
High specification well test equipment was included • Rig up surface test equipment
throughout the plant, including 250 psi calibration tanks, state RIH procedures
of the art detonation flame arrestors capable of handling flame • Drift, log and set the permanent packer
kick-backs at the speed of sound and a degassing unit for • Make up and run the gun system, BHA and tubing
potential heat exchanger coil / tube leak detection. Several string
back-up pumps incorporated into the design further enhanced • Space out and run the SSTT and landing string.
the flexibility and redundancy in the system (Figure 3). • Pressure test string
Initial clean-up flow and build-up
A sand monitoring system was included in the equipment • Fire perforation guns and unload water from string
design to enable accurate monitoring of any solids production • Close in well for initial reservoir pressure
from the well, which covered the formation property Main clean-up flow
uncertainty. • Flow well clean
Main flow and build-up
To cater for subsea disconnect capability and to enhance the • Perform multi flow rate test – 2 rates
BOP barrier, a robust and proven SSTT solution was elected. • Take good quality samples (during 1st rate)
In addition a new temperature sensor was introduced to • Perform build up using downhole shut-in valve
monitor sea bed temperatures to avoid over exposing the BOP Zone Kill procedure
ram elements. • Kill zone and recover DST string.
• Check gauge information.
The fluid sampling technologies selected took account of the • Isolate zone
client requirements for single phase fluid samples. This was
coupled with detailed discussions with the client during the The use of the combined Sampling and Main flow to provide
design phase11, 13. All technologies chosen were proven and the required step rates effectively saved a build-up plus two
qualified; with the exception of newly developed tubing flow rates during the main flow, saving rig time in the design
conveyed carrier based fluid sampling technology aimed at phase. On DST #1 a contingency extended flow period was
collecting fluid samples downhole, whilst avoiding included as a second chance to obtain fluids samples
contamination from chemical injection for hydrate-formation illustrating the usefulness of having a flexible job design in
temperature suppression. (See below sampling program case unexpected reservoir behavior.
information for a complete overview of the techniques
included.) It was also planned for optional separator sampling, Another job design point was to minimize the number of shut-
but this was always understood to be a technique to be used if ins on the two zones tested, due to risk of seeing hydrates on
deemed advantageous as the job progressed. this job. By keeping the well flowing as much as possible
reduced the risk of forming hydrates by keeping the well
A particular point in the design planning was the Norwegian warmed up.
flow velocity limitation for erosion control. This drove the
decision to employ double choking (heater and choke The overall time allotted for the well testing operations on two
manifold simultaneously) to restrict the flow velocity between zones was 51 days of testing at a cost of NOK 130.5 million.
the heater inlet and the choke discharge. This had the knock- Figure 12 gives an overview of the original 90% probability
on effect of reducing the temperature drop at the choke plan for the well test with the corresponding actual time
manifold, thereby removing a temperature low point in this consumed. (The cut off point for the days referenced above
pipe segment. This again had a further implication that it happens in the middle of the step).
reduced the likelihood of hydrate formation.
4

To capture the required data from the well tests a program chemical make up.
containing the following elements was planned: • Rerun the packer assembly
• Bottom Hole Pressure & Temperature from memory • Failed pressure test. POOH the string. Change BHA
gauges. components. Reran string with pressure test every
• Surface Data Acquisition of flow rates and process 1000 m.
parameters. Initial clean-up flow and build-up
• Fluid Sampling • Unexpected shut in resulted in Hydrate. Dissipate
In addition a subsea temperature sensor was added to monitor hydrate.
the 121ºC temperature limitation of the BOP rams. Main clean-up flow
• Continues injection of hydrate preventative chemical
The planned fluid sampling program on the Onyx SW well Main flow and build-up
planned with the following main data gathering elements14: • Bottom hole samplers not available due to lack of
• Bottom hole carrier based single phase fluid sampling qualification for the client
• Single phase well head fluid sampling (Figure 13) Extended flow (contingency used)
• Iso-kinetic fluid sampling for CGR (and WGR) • Extended flow rate to reduce OBM contamination in
• Optional Separator recombination sampling fluid samples
• Additional fluid samples taken
• Gas Trace element analysis (including mercury12)
Zone Kill procedure
• Contamination of reservoir liquid phase (to monitor for
• Bottom hole tester valve failed to open.
OBM base oil lost in reservoir during the drilling phase)
• Kill line kick-out sub leak. Secured well and
• Process parameters for the Surface Data Acquisition disconnected on SSTT, pulled LMRP for repair.
system (densities, BS&W, etc.) • Rerun of BOP and landing string. Reconnected and
gained control of the well.
Results and discussion
Prior to DST #2 both the client and the service providers used
KPI results the time lag while securing the well after DST #1 to learn as
The resulting KPI from the Onyx SW job gave the following much as possible from the first zone and to incorporate these
overall performance picture for the entire job. into the job procedures. This work resulted in a reduced
ƒ Planned time, 51 days actual, 72 days number of additional tasks required to meet the set goals. For
ƒ NPT, 24% actual 20% DST #2 the only additional steps required were:
• Displace well and cushion with inhibited seawater
Main NPT events seen on the job were rig related issues, (water glycol mix used on DST #1)
which were just below 50% and a downhole leak which • Clean tubing when running tubing in hole
resulted in an aborted first DST. Weather also contributed to • Bent tubing joint and replaced it
the NPT, but to a lesser degree. • 4 ½” slips hinge pin broke. Replaced same
All steps occurred during the RIH procedure, and the two
Of the overall NPT the Surface Well Test, Subsea and Fluid main ones were improvements done to minimize hydrate and
sampling side contributed with 6% of the overall well clean-up issues, actually having an overall positive effect
(approximately 22 hours). The overriding reason for the NPT on the job execution.
allocated towards the Surface Well Test, Subsea and Fluid
service company was due to a single hydrate plug event. This Lessons learnt
has been discussed further in the lessons learnt below. For the Surface Well Testing, Subsea and Fluid Sampling part
of the job the following learning points were experienced for
Objectives – theory vs. reality the two DST’s, grouped under DST #1, DST #2 and General:
All above mentioned well test objectives were met satisfactory
for this well, including boundary and heterogeneity DST #1 – Learning points
identification. In addition the well test provided useful Rig-crane lift radius
corrective data vs. wireline deployed tools. During the installation of the main well test equipment the
crane was found to have inadequate lifting capacity for
However, on the operational side there were several lessons handling the Steam Heat Exchanger, which on this job
learnt. The following is a summary of the additional practical weighed 26 tonn.
tasks that were required to achieve the goals for the two
DST’s. Confirmation of the lifting capability of the crane had
been reviewed in the pre-job planning meetings onshore.
Additional tasks for DST #1 grouped under each main step of However, a communication breakdown led to an
the design: erroneous conclusion that the crane was capable of lifting
Preparation the heat exchanger. This was overcome (Figure 4, 5 and
• Rig preparation. 7) by installing the unit on the other side of the cat-walk.
RIH procedures
• Review and change the cushion and annulus fluid Consequence – the final position of the heat exchanger
5

necessitated two additional crew members for operation High pilot activated – hydrate plug
of the heater choke, adding cost to the job. On the job the operational procedures for well flow were
based on using double choking, both at the choke
Learning point – equipment weights vs. crane capacity is manifold and at the heat exchanger (Figure 3). This
an increasingly important check point as unit weights required changing from a normal clean-up job set point to
have increased over the years. a less used DST set point for the PSD input signal
between the choke manifold and the heat exchanger inlet
H2S readings on water cushion returns (higher than normal). This set point change was not
During the execution of the job significant, but relatively implemented prior to the operational start, and not caught
low H2S levels were detected. This was due to the filtered in the pre-job check-outs. This resulted in a PSD shut
seawater not being inhibited, coupled with bacteria down early in the clean-up phase on DST #1.
growth at elevated temperatures.
Consequence - the interruption of the flow caused a
Due to no significant H2S seen at the earlier stages of the hydrate plug in the landing string, which was the major
well, no plans had been made for bringing H2S NPT incident during the DST’s from the services covered
scavenging chemicals offshore; for tasks like vessel entry by this paper.
and inhibition of well fluids.
Root-cause was human error, not capturing the non-
Consequence – no practical impact on the job, but could standard pressure set point for the electronic PSD system.
have been one.
Learning point – same as for the previously described
Learning point – plan for having inhibitors offshore. plug in the SSTT chemical injection port. (Procedure
change to a non-standard solution not clearly conveyed to
Plug in sub sea test tree the personnel involved.)
During the pre-running checkouts of the Subsea
equipment it was found a plug had been installed in the BOP temperature cable
chemical injection port. This was corrected prior to RIH. After DST #1 it was found that the cable used for the
temperature probe measuring the sub sea BOP
Consequence – a minor NPT incident. temperature was not sufficiently robust. Although the
temperature signal transmitted throughout the job the
The investigation of this incident showed that it was an cable was damaged during POOH. The investigation
onshore maintenance procedure which had not been showed that the fastening procedure for the cable to the
followed correctly. Also, a contributing factor was that the landing string had not been applied correctly.
normal pre-job checks offshore prior to RIH had been
prevented due to client procedures. The client procedures Consequence – none for this job.
banned high pressure testing on deck for safety reasons.
Learning point – use armored cables for future jobs with
Learning point –procedures require to be reviewed more more emphasis on following the fastening procedure for
critically if deviations from normal practices are to be the cable.
accepted. (In this case an offshore pre-job procedure
could have been run at the onshore workshop in addition SSTT Disconnect
to the normal maintenance procedures, with a 3rd party During the Zone Kill procedure after DST #1 a leak was
witness present, and prevented the near miss offshore identified in the Kill line kick-out sub. This led to
issue.) securing the well and a planned disconnect on the SSTT,
along with pulling of the LMRP to surface for repair.
Bottom Hole Samplers did not qualify in time for the job
Carrier based, tubing deployed bottom hole samplers were While repairing the LMPR a review of the SSTT relatch
planned for this job. However, during a pre-job and pressure integrity check procedures was conducted.
verification of the equipment they failed, and the The procedure was amended since the original landing
qualification testing had to be re-done. This took more string design with a Fail-Close Retainer Valve can not be
time than allocated. Due to this carrier based bottom-hole used to pump through for washing of the SSTT top prior
fluid samplers could not be run on this job. to re-latch. The amended procedure with the Retainer
Valve removed was reviewed and used during the re-
Consequence – less single phase fluid samples than connect at the SSTT after the installation of the repaired
planned. However, the surface samples taken were valid LMRP. The reconnect of the SSTT was successful in line
therefore no consequence. with the revised procedures, allowing completion of the
Kill procedure.
Learning point – plan for sufficient time to allow for
recovery if equipment fails during the pre-job checkouts. Learning point – Review on the Retainer Valve
philosophy in the early stages of the design. The aim
6

should be to determine if the valve should be run in Fail- extra sensor from a neighboring rig with the service
Close or Fail-Open mode, taking the implications for an provider’s equipment installed. The cause for the back-up
Unlatch / Re-latch into consideration. sensor being faulty was found to be a combined lack of
faulty equipment tagging, and inadequate handover notes.
OBM contamination of fluid samples
Some OBM base oil had seeped into the formation during Consequence – cost of diverting boat paid by service
the drilling phase of the Onyx SW well. After the provider. No rig time loss.
successful and quick off loading of the well bore content
the base oil was produced back from the reservoir. This Learning point – focus on procedure and importance of
combined with a dryer than expected reservoir fluid gave handover notes in the pre-job meetings with the crew on
a contamination issue. future jobs.

The contamination levels in the liquid phase normally Well fluid contamination
ranged between 10% and 50%. The base oil content in the During DST #2 it was found that the well fluids did not
condensate had a target of 2%, something which was heat up sufficiently to allow the glycol / methanol
never achieved. However, since the overall reservoir fluid injection to be switched off. This led to more than
was dryer than anticipated the contamination did not play expected contamination of the fluid samples. The
a significant role for the overall sample quality, which contamination however was well within acceptable limits
was within set quality parameters. Regardless if the fluid due to the lean nature of the gas-condensate system.
samples were well within the set quality requirements
nevertheless, it was felt that the samples could have been Learning point – carrier based bottom hole samplers
better, so it was decided to use an Extended Flow at the would have been useful for obtaining better fluid samples,
end of the job in an attempt to improve the sample quality and this was viewed as an important improvement for
further. future lean gas-condensate jobs.

Consequence – use of an Extended Flow period in an DST #2 other issues


attempt to reduce the contamination levels. Reduced Other issues seen for the other services employed on DST #2
contamination levels were achieved, further improving the included the following:
fluid sample quality. The implementation of the Extended • Reoccurrence of packer setting issues – 6 attempts
Flow cost more rig time. required prior to setting of the packer.
• Production packer setting sleeve got stuck in BOP
Learning point – be prepared for an extended clean-up ram cavity
period (longer weather window), and higher clean-up flow • One memory gauge rejected during pre-job checkouts
rates. due to leak between oil trap and gauge connection.
• Overall poor memory gauges performance for one
DST #1 – other issues brand.
Several other issues were seen offshore during DST #1, not • Poor internal tubing cleanliness
related to the primary services covered by this paper. The • 4-½” hand slips with sheared hinge pin
following is a brief mention of these points aimed at • Bent tubing joint
completing the overall scenario for the job;
• Faulty memory gauge chip found offshore General learning points
• Firing panel malfunction resulted in two attempts at In addition to the above DST #1 and #2 specific learning
setting the production packer. points a number of general learning points were seen.
• Early downhole string leak seen, causing a DST #1
re-run. Calibration Tank Ladder position and Sight Glasses
• Non-heat treated explosives (for packer setting) During the job the position of the Calibration Tank ladder
• Downhole tester valve failure caused implementation and the Sight Glass types caused problems reading the
of back-up bullhead procedure after DST #1. tank level (Figure 9). This led to difficulty in reading the
• A memory gauge failure seen together with some tank level accurately when it exceeded approximately
unreliable data sets in the surviving gauges. (Data 40% tank filling, and made it difficult to distinguish
gathered, but show importance of back-up between condensate and water levels.
equipment.)
Consequence 1 – Operational constraints when taking
DST #2 – Learning points meter factors, limiting the overall tank level to about 40%,
Separator gas meter differensial sensor (delta P) and potentially diminished meter factor accuracy.
When preparing for DST #2 an operator error caused
damage to the differential sensor on the gas meter. When Consequence 2 – Problems distinguishing fluid levels
changing to the back-up sensor this was found to be out of when transferring liquids to the Storage Tank (Figure 3
calibration. This was corrected by sending over by boat an and 9).
7

minutes. Both operations proved the SSTT for this well and
Consequence 3 – Shut down initiated by gas alarm in mud Norwegian Sea conditions.
room when accidental transfer of condensate to pits
occurred due to undetected condensate / water level in Verification of the BOP temperature using the temperature
Storage Tank (Figure 3 and 9). probe proved to be a successful way of verifying the flowing
sea bed temperature, providing useful data throughout the job,
Learning points: by measuring the steel temperature on the outside of the
• Do not transfer fluids to rig mud pits, use landing string. Improvements to cable type should be looked at
independent handling equipment for fluids. for future job.
• Tank instrumentation must be adequate for accurate
interface identification, and it must be accessible. The only technology that did not qualify for DST #1 was the
• Design and operational procedures must be reviewed carrier based tubing conveyed bottom-hole sampler
if well conditions are found to be significantly technology. This did qualify in time for DST #2, but fluid
different from originally predicted. sampling experience from DST #1 prompted the client not to
• Fluid transfer procedures should be job specific. employ this technology for DST #2. Due to this the
• Non-routine fluid transfer procedures needs to be technology was neither proven / nor disproved during the well
added to the rig controls. tests. However, if the technology had been used and it had
worked as intended, the fluid sampling results show that this
Loss of rig main electrical power due to water ingress could possibly have further improved fluid samples.
During the well test job the equipment was sea fastened
and secured by welds to the deck. Welded walkways were Avoiding pollution by using the burners elected4, 5, 6 and the
used. While cutting loose the equipment for Storage Tank in conjunction with transport tanks, gave further
demobilization after the job, a pin hole was accidentally proof for correct design for this job, avoiding recordable spills.
made in the rig main deck (Figure 10) when removing a
walkway. Water subsequently ingresses through this hole, Flow velocity control by active use of the heater choke also
entering the high voltage electrical switchgear room, proved a successful technique, except for the above mentioned
tripping the primary power generation circuit breakers. PSD set point error, and was used throughout the two DST’s.
This also posed a procedural challenge to the well test crew
Consequence - shut down of the generators causing the since they could not by-pass the heat exchanger due to the
emergency generators to come on-line. required backpressure. The crew successfully met the
challenge and conducted this rather unusual procedure without
Learning points: any significant difficulty.
• Adjacent-area consequences must to be taken into
consideration for all 3rd party operations on rigs. Multi-Tube heater performance throughout the job proved that
• Double structural plates for all fastening points this heater type removed the common heat exchanger flow
should be used for all equipment welded to the deck capacity bottle-neck caused by the older coil & shell designs.
or main structure. Experience from the job also showed that there was an issue
related to the heater performance being on the low side vs.
• Implement verification checks to ensure that all
fluid heating requirement. However, this was linked to lack of
personnel involved in hot work understands relevant
steam generator capacity rather than the heater design.
procedures.
Experience from other jobs in Norway has shown that the
• Include deck inspection for pre-job rig surveys.
Multi-tube heater is capable of condensing steam quicker than
• Include demobilization as a specific Hazop item. a large 6 MM Btu/hr generator can produce. This has the
effect of moving the heat transfer bottle neck traditionally
Technology benefits proven / disproved caused by the exchanger to the generator. It is very likely that
All the applied technologies were generally proven on this job. a simple inclusion of an additional generator would have given
However, some of the benefits anticipated did not materialize. the sought after performance margin. This was looked at as an
improvement potential between DST #1 and #2, but in the end
The inbuilt flexibility of being able to route suitable fluids it turned out to be insufficient deck space on the rig for adding
back to the mud pits from the Storage Tank did not a steam generator to the equipment rig up.
materialize, due to difficulties in reading the condensate /
water interface. This caused a shut down from a minor gas Except for some minor hydrate issues the employed single
release in the mud pit area, which led to having to ship the phase well head sampling technology worked as intended.
water to shore in transport tanks (as normally done in This technology used a high end injectable probe high
Norway). pressure sampling manifold installed upstream of the choke
manifold14. This technique was specifically developed for lean
The SSTT disconnect / re-connect capability was proven on gas-condensate systems.
this job. The disconnect at the end of DST #1 was executed as
per procedure and within specified parameters, while the re- The other fluid sampling techniques for this lean gas-
connect and mechanical verification took approximately 20 condensate system were also proved. The onsite laboratory
8

performed onsite gas compositional analysis, OBM well testing. Therefore the overall data gathering must be said
contamination analysis, CO2, H2S, Hg, Radon and other to be useful.
analyses successfully and consistently throughout the jobs.
When reviewing each element of the data gathering offshore:
The only part of the fluid sampling which did not prove to be a • Single phase fluid sampling (at well head)
success was the CGR measurements using the Mini-lab on • Iso-kinetic sampling for CGR / WGR measurements
location. This was due to unusually high water saturation of • Trace element analysis
the gas, combined with the hydrocarbon composition being • Contamination of reservoir liquid phase (OBM base oil)
leaner than expected. This caused water condensing from the • Process parameters for the Surface Data Acquisition
gas throughout the jobs, and the water was by far the most system (densities, BS&W, etc.)
dominant phase. Due to this, small differences in condensate • Surface Data Acquisition (flow rates and process
vs. water readings had a large impact on the dry CGR reading. parameters)
The unusually high water content had not been captured as a • Sand monitoring
design parameter prior to the job. However, the on-site CGR
• BOP temperature monitoring
measurement was not an objective for the job and the single
It becomes clear that all of these data sources have their
phase well head samples proved to contain the required
particular usefulness.
information to satisfy the well test goals. Hence the CGR
measurement issues did not diminish the value of the well test.
From an operational stand point the least successful data
gathering was the Iso-kinetic sampling for CGR / WGR.
Another point which was proven was the usefulness of real
However, the failure to detect a stable CGR measurement
time data transfer. This allowed the client team onshore to
proved another unexpected point. The reservoir fluid had an
follow the job as it progressed and to give advice / make
unexpectedly high water saturation level, something which
decisions as the job progressed. From the client’s side this was
was a surprise since other data sources had indicated this. Post
seen as a positive experience from the job.
job review of the equipment set-up for the Iso-kinetic
sampling also showed that had the water saturation level been
Other proven / disproved
known further optimization could have been carried out and
Of the other technologies applied (outside Surface Well
the CGR measurement quality improved.
Testing, Fluid Sampling and Subsea), some technologies
should be mentioned to complement the experiences
Conclusions
mentioned above. The production packer with seal assembly
The Onyx SW lean gas-condensate HPHT well tests were
performed well throughout the job. The stab-through TCP gun
conducted in a safe and environmentally responsible manner,
design also proved itself together with the downhole tool
meeting all the well test objectives, proving that a well
string design. Another technology that generally worked very
planned well test can yield good results.
well was the special water cooling / curtain system provided
for the job. This effectively kept the radiated heat load down
The job lasted 21 days more than anticipated, but this was to
throughout the job, and prevented heat damage on the rig. The
an extent caused by unrelated occurrences, which could have
tubing handling and procedures also proved to be generally
happened at other stages of the well. Even if the cost for the
satisfactory with a relatively low number of threads recuts
two well tests was high to the client, the question of the cost of
after the job.
not having the data needs to be taken into consideration.
Data gathering – usefulness
The main overall learning points from this well that were
The main reasons for conducting the two zone DST on the
carried over into the plans for the follow up appraisal well
Onyx SW prospect was rooted in the fact that alternative
campaign for Onyx West and SW-2 were:
methods to well testing were not perceived to be able to
• Adjustment of the setting sleeve on the packer to prevent
deliver sufficient data on the prospect. Experience has shown
being stuck in BOP cavities.
that alternatives to well test frequently yield in-sufficiently
accurate data alone for HPHT wells10. There are also further • Upgraded packer setting explosives with high temperature
issues related to the alternative methods for lean gas- ones. Special testing and heat treatment for the explosives
condensate systems in combination with OBM contamination was carried out.
of the reservoir9. • Qualification testing has been done for the gauges from
two different suppliers, one additional supplier failed the
In retrospect when comparing the WFT data back to the well test, while yet another one is being looked at.
test results for the Onyx SW prospect clear knowledge • Qualification of bottom-hole single phase sampling has
improvements can be demonstrated (based on interview with been carried out; one company failed one qualified.
client experts, confidential data unfortunately not available for • Fluids should not be transferred from the well test plant to
publishing in this paper). the rig systems in the future. Independent handling should
be planned for.
All the primary and secondary objectives for the DST’s on this
well were met. These objectives were partially set to fill gaps
in the knowledge base not covered by alternative methods to
9

This does not mean that the other learning points do not count, Abbreviations
but these 5 bullet points were the most important ones for the
operator company. BHA - Bottom Hole Assembly
BOP - Blow Out Preventer
Acknowledgements BS&W - Base Sediment & Water
We wish to express appreciation to Norske Shell and Expro CGR - Condensate Gas Ratio
for their support and permission to publish this paper. DST - Drill Stem Test
DWOP - Drill Well On Paper
Special thanks are extended to the Norske Shell’s Onyx team ESD - Emergency Shut Down
and Expro’s QA department in Norway which were supportive HPI - High Potential Incidents
and forthcoming with advice and background information for HPHT - High Pressure High Temperature
this paper. HSE - Health, Safety & Environment
ISO - International Organization for
References Standardization
1. The Norwegian Petroleum Directorate – Factmaps – kh - Permeability x formation thickness
www.npd.no KPI - Key Performance Indicators
2. The Norwegian Petroleum Directorate - Fact-pages – LMRP - Lower Marine Riser Package
www.npd.no LTI - Lost Time Injury
3. IFP Drilling Data Handbook, 1st English edition MM - Million
4. SPE 35687 - Environmentally Safe Burner For Offshore OBM - Oil based mud
Well Testing Operations, Timothy M. Young, P.E., SPE, POOH - Pull Out Of Hole
Halliburton Energy Services RIH - Run In Hole
5. Report: “Fallout from Well Test Burners,” Halliburton PSD - Process Shut Down
Burner Tests, Norsk Energi, (Oct 1994). SSTT - Sub Sea Test Tree
6. OLF Status Report – Environmental Developments in TCP - Tubing Conveyed Perforating
Well Testing, March 2000, Revision 1 WFT - Wireline Formation Tester
7. Overview & Selection of Well Testing Methods & WGR - Water Gas Ratio
Equipment, Sjur Hundsnes & Sigurd Hundsnes, Stavanger
3
University College, 2001 Conversion factors
8. Well Testing Network - HT/HP Welltesting from a
Mobile Drilling Unit with an Under-Balanced Annulus Metric Oilfield
Fluid - Martin Rice, Norman Day, Myo Thant - Shell, Length 1m = 3.2808 ft
1997 Pressure 1 bar = 14.5038 psi
9. 2001 SPE Applied Technology Workshop - Well Testing Flow rate 1 m3/d = 6.28994 bbl/d
- To Test or Not To Test: Risks and Rewards”, 14-16 Temperature ºC = [(ºC * 1.8) + 32]ºF
November 2001 – Summary report and conclusions Volume 1 m³ = 6.28994 bbl
report.
10. Well Testing Network Multi-Topic Meeting #3 – 2007,
WFT Mini-DST-Advantages and Limitations, June 6th
2007 - Kåre Otto Eriksen – Statoil
11. SPE ATW – Gas Condensates, Moscow, 2007 – Session 2
paper - A systematic Approach to Sampling and Fluid
Characterisation during Well Testing, Bjørn Dybdahl –
Expro
12. JAAS – On the Determination of Total Mercury in
Natural Gases Using the Amalgamation Technique and
Cold Vapour Atomic Absorption Spectrometry – W.
French and D. C. Baxter – University of Umeå, Sweeden,
and G. Dyvik and Bjørn Dybdahl, Petrotech
13. SPE 19729 – Sampling Gas-Condensate Wells - W. D.
McCain Jr., SPE and R.A. Alexander, SPE, Cawley,
Gillespie & Assocs. Inc.
14. SPE 69668 – Testing of Gas Condensate Reservoirs –
Sampling, Test Design and Analysis - H. Kool, M. Azari,
M. Y. Soliman, M. A. Proett - Halliburton, C. A. Irani –
Westport, and B. Dybdahl, Petrotech
Tables

Table 1 – Well facts page2

Table 2 – Formation overview


11

Exploration wellbore: 6406/9-1


General information

Well name: 6406/9-1


Drilling operator name: A/S Norske Shell
Geodetic datum: ED50
Coordinates: 64° 26` 46.85`` N 6° 48` 55.23`` E
UTM coordinates: 7148739.49 N 394862.07 E
UTM zone: 32
Drilled in production licence: 255
Area: NORWEGIAN SEA
Discovery: 6406/9-1
Field: NOT YET DEVELOPED
Drill permit: 1077-L
Drilling facility: TRANS. LEADER
Drilling days: 353
Wellbore entry date: 15.06.2004
Wellbore completion date: 02.06.2005
Original wellbore purpose: WILDCAT
Wellbore purpose: WILDCAT
Wellbore status: P&A
Wellbore contents: GAS
Discovery wellbore: YES
Seismic location: HWE95m:inline 4340 & xline 1540
Kelly bushing elevation (KB) [m]: 24
Water depth [m]: 308
Total depth (MD) [m]: 5080 (See below note)
Deepest penetrated age: EARLY JURASSIC
Last updated by NPD: 17.05.2007
Note: All depths are relative to kelly bushing (RKB)

The NPDs recoverable resource estimates as of 31.12.2006 (Norwegian share)

Resource category 5F
Oil [mill Sm3] 0.00
Gas [bill Sm3] 40.83
NGL [mill tonn] 0.00
Condensate [mill Sm3] 1.41

2
Table 1 – Well facts page

Note from Norske Shell: The correct total depth of the well, including RKB height is 5076 m.
12

Geological objective
The objective of the well was to test the Middle and Lower Jurassic Garn, Ile, Ror/Tofte and Tilje Formations for the presence of
Hydrocarbons.

Group Formation Depth


(m TVD
Lithology
MSL)
Nordland Seabed 308 Clay and sand streaks
Top Kai 1230 Claystone and sst streaks
Hordaland Top Brygge 1645 Claystone, occ. siltst/lst streaks
Rogaland Top Tare 2260 Claystone, tuff, traces of dolomite
Base Tertiary 2400
Shetland 2400 Claystone with some siltst. and sst streaks, occ. dol/lst
Cromer Top Lysing/Lange 3145 Claystone, siltst and sst beds, occ. dol/lst streaks
Knoll Fm
SK84 hrz 3330
Base Cretaceous 4275
Viking Spekk 4275 Claystone/shale with occ. lst streaks
Melke 4305
Fangst Garn 4440 Sandstones and claystones/shales
Not 4515
Ile 4555
Båt Ror 4665 Sandstones and claystones/shales
Tilje 4790
TD 4840 50 m into Tilje
4965 contingent if HC bearing, below HWC;base Tilje at ca. 4965
m

Table 2 – Formation overview


13

Figures

Figure 1 – License map of the Onyx prospect1

Figure 2 – Shell license maps

Figure 3 – Simplified P&ID for well 6406/9-1

Figure 4 – Overall rig General Arrangement drawing

Figure 5 – General Arrangement drawing (well test area zoom)

Figure 6 – Bill of Material for Figure 4

Figure 7 – Equipment layout seen from the derrick

Figure 8 – Flare pictures from the rig

Figure 9 – Shell EPE HS&E Learning Bulletin – Condensate to mud pit room

Figure 10 – Shell EPE HS&E Learning Bulletin – Loss of main power

Figure 11 – Generic n-rate well test7

Figure 12 – Onyx SW time plan – Original plan vs. reality

Figure 13 – Single phase well head sampling

Figure 14 – Cooling at choke manifold


14

1
Figure 1 – License map of the Onyx prospect
15

Figure 2 – Shell license maps


16

Figure 3 – Simplified P&ID for well 6406/9-1


17

Figure 4 – Overall rig General Arrangement drawing


18

Figure 5 – General Arrangement drawing (well test area zoom)


19

Figure 6 – Bill of Material for Figure 5


20

Figure 7 – Equipment layout seen from the derrick


21

Figure 8 – Flare pictures from the rig


22

Figure 9 – Shell EPE HS&E Learning Bulletin – Condensate to mud pit room
23

Figure 10 – Shell EPE HS&E Learning Bulletin – Loss of main power


24

n-Rate Flow Test

The advantages with a complex (n-rate) flow test is that the complex flow test provide extra data compare to the
two-rate flow test. The extra data obtained during multiple rate test is the data for turbulent skin and max sand free
rate. Figure 4 schematically illustrates an example of a complex multiple-rate test
Bottom Hole Pressure
Flowrate

Time
1 2 3 4 5

Figure 1. Complex Multiple-Rate Test

Explanation to figure 4:
1. Initial flow with build-up.
Usually two string volumes are produced before shut in.
Initial pressure is measured at the end of the build up period.
2. Cleanup flow with cleanup build-up.
The intention is to flow until no solids and mud filth is detected in the hydrocarbons.
Typical time on each rate is 6 hours.
Max sand-free rate can be obtained in the end of the highest flow rate.
Data is used to decide sampling flow rate.
3. Sampling flow with build up.
4. Main flow with main build-up.
5. Mini-fraction.

Main application today: Extensive exploration-well testing for gas and oil wells.

7
Figure 11 – Generic n-rate well test
25

Figure 12 – Onyx SW time plan – Original plan vs. reality


26

Figure 13 – Single phase well head sampling

Figure 14 – Cooling at choke manifold

You might also like