Professional Documents
Culture Documents
Francis Nwaochei, SPE; Adebayo Olufemi, SPE; Vincent Eme, SPE; and John Ibrahim, SPE, Chevron Nigeria
Limited; Eseoghene Nakpodia, SPE and Wole Areo, SPE, Flostar Oil & Gas Nigeria Limited
This paper was selected for presentation by an SPE Program Committee following
review of information contained in an abstract submitted by the author(s). Contents
Numerous gas lift opportunities have been
of the paper, as presented, have not been reviewed by the Society of Petroleum identified in the Meji Field (offshore location) which
Engineers and are subject to correction by the author(s). The material, as
presented, does not necessarily reflect any position of the Society of Petroleum currently has no gas supply. Wells in the shallow,
Engineers, its officers, or members. Papers presented at SPE meetings are subject
to publication review by Editorial Committees of the Society of Petroleum Engineers.
strong water drive, reservoirs of this field flow
Electronic reproduction, distribution, or storage of any part of this paper for naturally to terminal water cuts of between 60 to
commercial purposes without the written consent of the Society of Petroleum
Engineers is prohibited. Permission to reproduce in print is restricted to an abstract 70%. Based on the observed trend of terminal
of not more than 300 words; illustrations may not be copied. The abstract must
contain conspicuous acknowledgement of where and by whom the paper was
water cut, the challenge for the team was to
presented. Write Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836, quantify the incremental oil gain if this terminal
U.S.A., fax 01-972-952-9435.
water cut is raised by introducing gas lift. If this
proved to be substantial, it will make a case for the
expenditure on pipelines and associated
Abstract infrastructure.
Application of improved Oil Recovery in mature
fields is almost inevitable. However, the method In a bid to confirm that installing the gas lift
applied in the IOR process is dependent on the infrastructure is a viable project, a simple
economics and value of the method. In the operational approach of installing a temporary
Southern Offshore area of Chevron operations, piping system was implemented after the
there are huge cost implications in the necessary engineering analyses which are all
implementation of gas lift on several offshore discussed in this paper. Other operational
jackets. methods of confirming the viability of applying
New facilities for gas lift operation entails the artificial lift technology (gas lift) on the jackets
installation of a compressor, liquid knock out were also reviewed with a resolution to utilize the
equipment, pipelines, manifold configuration and temporary solution. An estimated production gain
associated piping etc. In many cases, gas lift of about 1105 BOPD from three wells, through gas
sourcing might require completely fresh lift was identified in the field. The total production
construction of entire facilities, which will involve gain from the simple operation yielded 1540
project development, management costs, BOPD.
infrastructure cost and space limitation especially
in the case of offshore locations. This paper reviews a safe and simple operational
approach to evaluate the viability of a gas lift
In the Southern Offshore Area of Chevron project in an offshore environment. This was
operations, several wells have quit and require applied on Meji jackets X and Y by using gas from
some kind of support to flow to surface. Artificial lift a high pressure source well delivered to the target
(gas lift) has been identified as the best method to wells with segmented pipe to ensure deliverability
optimize production from the wells reviewed in this and accelerate production based on a 3-well pilot
case. However, the infrastructure required to case on the 2 jackets.
implement the gas lift in the offshore location will
2 F. Nwaochei, A. Olufemi, V. Eme, J. Ibrahim, E. Nakpodia and W. Areo SPE 128337
1” Bleed off
T w o Pha se valve and
S eparato r
testing point.
Flu id Fluid Tan k 2” 1502 pipes
an d
Ga s
F luid PSHL
001
G G CP
Check Valve
G as M et ering
D ev ice
Gauge Point
G as G as
F low F low Data header w/ certified
needle valves for tie ins
O ffs hore
J ac k et
M anif old
Gas lifted well
2
Fig. 1 Typical Gas lift distribution system
preferred alternative as it offered the following Also the economics was run to see the viability of
benefits over the US Hose Corp hard pipe.- the simple piping installation vis a vis waiting to
• High-pressure (10Kpsi) and NACE design, fabricate and install the permanent piping
compliant pipe and seals. system. The results of the economics
• The pipe is used in the oil field for flowing demonstrated that:
back wells under various working
conditions. • It is more economic to accelerate
• The high strength steel and 2” diameter production by renting and installing a
pipe is more erosion resistant. This will temporary hard piping solution, than wait 5
limit the effect of erosion that was found to months to install permanent hard piping.
have caused problems with the stainless
steel tubing.
• Available through Flostar Oil and Gas • Chevron can rent for over 1.5 years before
Nigeria Limited. switching to the permanent solution and
• Currently being used in Nigeria by another still be economic.
major E & P company for high pressure
fluid flow solutions. • Greater annualized production gains
means more barrels to meet and exceed
The existing ¼” stainless steel pipe was eliminated our targets
for safety and security reasons due to its
vulnerability to damage by heavy equipment and
• For our larger GL opportunities (500+
vandals.
BOPD), there is a larger disparity in NPV
between the two scenarios - strongly in
Themes Stainless Steel 1502 Weco Temporary Hard Hard Piping favor of accelerating.
Tubin Pipe (Conventional Option)
(Proposed Option )
Erosion R esistance Small diameter pipe 2”, high strength alloy steel. 2”, Standard grade pipe.
(Larger diameter = makes it susceptible (More erosion resistant than
Lower to erosion – standard ASTM A106 Grade
especially in well - B piping)
t -well hookups.
Pressure Rating 2000 -5000 psi (?) 15,000 psi 15,000 psi (+/-)
Oil Field Application Used in other areas. 1) Currently used in Nigeria
b leading multinational oil &
1) Standard permanent
installation
Gas lift Supply cost
gas company . 2) Also used in
another Multinational ’s
Angola deep water hookups.
Gas lift supply to the well candidates being
Cost Per Installation <$100 1) $10,500/month per well +
~$3000 tree cap
1) $430,000/well
(recent AFE costs)
reviewed here involved installation of gas pipelines
Time to Install 1 Day 1) 1-2 Weeks to
equipment + 2 days to install .
1) 4-6 Months to design
& fabricate. 2-3 days
from the gas gathering Compression Plant to the
2) 1-2 months to order new
piping, but for the first few
installation respective jackets referred to as Meji Jackets X &
installations the equipment
will already be in country.
Y.
Potential Operational High velocities 1) Need to ensure the hammer 1) Although viewed as a
Excellence Concerns result in rapid unions are made up properly permanent solution,
erosion of the pipe using brass hammers. 2) Seals erosion is still an issue
if sand is present. must be NACE compliant and and could go unnoticed. Pip
Pipeline
eline Pipeline Cost Average cost Average Comment
properly installed and
maintained. 3) Installation will Sta
Start
rt Point End Point ($MM) to hook Line NPV
require proper support . 4) to well ($M)
Need to plan out installation to
avoid creating trip hazards.
Others Easy to install. 1) Relatively quick to install. 1) Welded joints. 2)
2) Known successful use of Proper gas monitoring
Meji
Meji GGCP Meji 37.6 198 5.30
pipe by a kno n mu ltinati nal instrumentation. Jacket X
c mpan y in Nigeria.3)
Servicing of pipe ensures that
erosion issues are addressed .
4) Allows us to t est
questionable gas lift Meji
Me ji Meji 47.2 198 6.00 Pipeline is an
opportunities without Jacket
Jacket X Jacket Y extension
committing to hard piping.
Other negat ive Operational 1)B -annual maintenance & Requires a construction from jacket X
Excellence issues servicing is required. crew to install. 2) Long
when used during (However, th is will help catch lead times and expensive.
well to well any erosion issues and is 3) In some cases, by the
installations performed by the contracting time the piping is installed
company.) 2) Possible theft it might not be required Fig. 5. Investment cost of transporting gas from Gas Plant to
3) Additional OPEX for much longer.
associated with renting candidate wells. Note that costs are exclusive of produced
fluids handling cost
Economics is based on the total field gas lift pipelines were also a deliverable of the field visit.
project comprising of 16 wells and 11 jackets. The A security factor which included painting the pipes
length of the pipelines are between 2500 to 4000 similar colour to those already on the jackets so as
meters. The water depth for the supply lines range not to attract vandals was also considered.
from 6 to 8 ft and the size of the pipelines are 6”. The suitable candidates were ranked and formed
part of the decision criteria in the selection of the
Well Candidate Selection well candidates.
II. Mark pipe route from source wells to Jacket Gas Source Well GL Well Reservoir Before Hook-up After Hook-Up Gain
target wells as identified during site BOPD BOPD BOPD
surveys. X XS1 XH1 C-01 1373 1269 -104
X XS1 XH2 C-01 0 1143 1143
Y YS1 YH1 D-01 0 501 501
III. Install hard pipe, adjustable choke, valves, Total 1540
elbows, flow tees, check valves and cross-
overs to cover gaslift requirements from Fig. 7. Table showing Pre and Post Temporary Hook-Up
source wells (high pressure well) to production gains
target wells.
The project yielded a total production gain of 1540
IV. Test mechanical integrity and perform BOPD with 2 of the 3 wells being successful. The
proper pressure test on installed third well (on jacket X) did not yield the desired
equipment. result because gas supply could not be optimized.
Inability to optimize gas supply to the two wells on
V. Install automatic shutdown valve and the jacket was due to the fact that gas supply was
pressure switches on the temporary gas- being controlled by one choke.
lift line.
An estimated 1150 BOPD was planned as
VI. Install fittings, SS tubings, and isolation production gain from the wells. However, this was
valves necessary for the installation of the exceeded by 33%. Two of the wells MJ-XH2 and
PSHL and SDV on the platform. MJ-YH1 had quit on LTP (Low Tubing Head
Pressure) prior to execution of the project.
VII. Tie-in the new instrumentation to the
existing emergency shutdown system on A review of the Pre and Post Economics of the
the platform. project showed that not only was the temporary
solution viable but the execution yielded better
VIII. Function test all safety devices. than expected results.
Conclusions
Piping to casing Hook up to source
The simple temporary hard piping system solution Of candidate well well crown valve
to channel gas from a high gas source well on an
offshore jacket location to lift candidate wells on
the same jacket proved quite successful in
confirming the viability of embarking on laying
flowlines from the Gas Gathering Compression
Plant to the jacket and subsequently deploy the
same method to ascertain the viability of a full field
wide gas lift network in the Meji field. It also
accelerated production from the candidate wells
that otherwise would have been idle until the
Fig. 9. Gas lift hook up to source well
seabed gas flowlines are laid. A permanent
solution to the gas lift system is currently being
reviewed in the final stages and will be
implemented soon.
Acknowledgments
The authors gratefully acknowledge the
management of Chevron Nigeria Limited for
permission to publish this work and would also like
Shut Down
to thank their co-workers for their contributions to Valve
the material presented herein.
References
1. Zelimir Schmidt (n.d.), “Gas Lift Optimization
using Nodal Analysis” Course manual:
Fig. 10. Shut down valve system for the gas supply line.
University of Tulsa Division of Continuing
Education.
2. Tang, Y. L. et al., SPE 38814 (n.d.), “Transient
Dynamic Characteristics of the Gas Lift
Unloading Process”.
3. FMC Energy Systems product brochure
3
Fig. 12. Seals/ Union specifications