Professional Documents
Culture Documents
This paper was prepared for presentation at the Abu Dhabi International Petroleum Exhibition & Conference held in Abu Dhabi, UAE, 13-16 November 2017.
This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents
of the paper have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect
any position of the Society of Petroleum Engineers, its officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written
consent of the Society of Petroleum Engineers is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may
not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright.
Abstract
The present article collects the main activities carried out by Eni on FLNG in the past years. As such, it
reports Eni’s view of the FLNG technology and it constitutes a subjective assessment and evaluation of
the involved technologies and the associated risks. The same evaluation and assessment may lead to very
different results when based on a different risk perception, which is proper of each Oil Company.
At time of writing, Coral South FLNG Project has obtained Final Investment Decisions from all the
Project Partners and the FLNF EPC contract has been awarded, with consequent commencement of detailed
engineering and construction activities.
The paper will present the activities carried out in Eni about FLNG in the past years, then used to
validate and enable the development of Coral South FLNG Project. In particular, it will briefly present the
main technological features studied and selected by eni for the Coral South Project. It will summarise the
main studies carried out and the main advantages and disadvantages considered by Eni when selecting the
technologies adopted in the Coral South FLNG Project.
As a conclusion, the paper will summarise the main technological configuration of Coral South FLNG
facilities based on the validation activities carried out.
Coral South FLNG Project finds its basis in an extensive preparation activities, as FLNG technology has
been studied in Eni since 2008, when some stranded oil&gas fields required valorisation with offshore LNG
technology. A series of activities and project-based pre-feasibility and feasibility studies have been carried
out in the following four years, preparing the ground and unlocking Coral South Project in Mozambique.
The main technologies studied and screened are:
– Liquefaction process technology;
– Refrigerant make-up production technology selection;
– LNG offloading system configuration;
– Mechanical drivers for liquefaction compressors and generators;
– Heating medium system;
– Containment system including sloshing issues;
– Mooring system;
For each of these systems, a rigorous and common technology validation approach has been adopted,
consisting in a screening of different technical alternatives with a qualitative analysis. When necessary a
2 SPE-188704-MS
quantitative evaluation has been carried out, including a detailed engineering assessment, scale tests and
a cost and risk comparison.
The final selection has been made taking into account safety, costs and operability. For each technology,
a preferred one has been selected firstly as Eni Corporate and then checked and validated for the specific
Coral South FLNG Project application.
As result of the extensive application of the technology validation procedure, the originally selected
technologies for the generic Eni FLNG have all been confirmed for the Coral South FLNG Project even if
in some cases scale tests have been required to further assess the identified criticalities.
When it comes to FLNG application, even the most common and widely adopted technology can be
considered as a novelty as there are no previous floating and/or LNG application for it.
Eni approach to this novelty-in-complexity environment is based on an internal ad-hoc developed
technology validation procedure which has been demonstrated to be very effective even when applied a real
demanding Project like Coral South FLNG.
INTRODUCTION
The liquefaction and regasification systems of natural gas have so far been developed and realsed on the
ground. However, several projects have also been proposed and sanctioned in recent years about floating
liquefaction plants located on special vessels that may be anchored at the coast or offshore. The first offshore
liquefaction plant became operational in 2017 (Petronas PFLNG in Malaysia) and another one is planned
to commence production very soon (Shell Prelude FLNG in Australia), while several offshore rigassifiers
are already operating today.
• Producing natural gas from subsea wellheads to supply an FLNG installation (the FLNG);
• Processing the natural gas received on the FLNG and liquefying it;
The Project plans to produce 3.37 million tonnes per annum (Mtpa) of LNG over the 25-year Project life.
The Coral South FLNG vessel adopts the following taechnologies which contribute to determine its
overall performances:
– Dual Mixed Refrigerant (DMR) liquefaction process;
SPE-188704-MS 3
TECHNOLOGY SCREENING
Before commencing any activity on the design of the FLNG, an extensive technology screening has been
carried out internally in Eni with the main objective to minimize the technology risk for the Operator. Among
these technologies, the main ones are reported below.
• The lower the HC liquid inventory, the safer the process (and less sensitive to motions);
• Hydrocarbon based refrigerant implies LPG import / production. HFC based cycle needs its import
to the FLNG.
SMR (any licensor) – several licensors offers similar technologies – refrigerant make-up needed
– applied for medium scale onshore plants – efficiency intermediate between nitrogen and DMR
– simple and low equipment count
DMR (any licensor) – high efficiency – Limited existing references, (1 onshore plant for Shell
– several studies completed for offshore applications DMR, 1 offshore under construction)
– Shell DMR technology is chosen for Prelude FLNG – refrigerant make-up to be provided
– minimal HC liquid inventory (especially when C3 is not
stored)
Aiming at production higher than 2.5 MTPA, DMR should be selected as liquefaction process in order
to enhance plant efficiency with an acceptable degree of safety.
4 SPE-188704-MS
REFRIGERANT SELECTION
Refrigerant can consist of pure or mixture of hydrocarbons (methane, ethane, ethylene, propane, butane),
inert gas (such as nitrogen or CO2) or industrial refrigerants which can be selected to be non toxic and not
combustible (such as HFC).
If hydrocarbon refrigerants are used, the flammable fluid inventory in the facility is increased, increasing
potential for incident escalation. Refrigerant make-up is facilitated if hydrocarbon refrigerants are produced
by the plant (which can be the case for methane, ethane, propane, butane). If hydrocarbon refrigerant is not
produced by the plant (like Ethylene) periodic ship to ship transfer has to be considered for refrigerant make-
up supply which can be considered as an unnecessary and risky additional constraint in an offshore context.
Using non combustible refrigerant reduces the risk of incident escalation. Non combustible refrigerant
have to be produced by dedicated facility (for nitrogen) or imported and stored onboard (for HFC).
To achieve very low temperature the choice of available non combustible refrigerant is limited to nitrogen,
HFCs being reserved to pre-cooling duty due to operating temperature limitations.
– referenced for all onshore plants (mature technology) and – Limited by metocean conditions, in terms of relative
for offshore regas/storage units motions and accelerations.
side by side rigid arms – selected by all the currently existing or under – safety of SBS operation is lower than tandem
development plants offshore as offloading system – require tugs assistance
– need for fenders davits according to carrier size(s)
– safer than rigid arms due to greater relative distance – limited in relative motions and accelerations as rigid
– similar system is proven for LPG ship to ship transfer arms
side by side aerial hoses
– known references for LNG ship-to-ship transfer (regas – safety of SBS operation is lower than tandem
unit)
When metocean conditions seem to be not harsh, SBS rigid arms can be selected as offloading technology.
Confirmation will be based on detailed specific metocean conditions.
– many vendors for 20-40 MW size – Emission reduction system requirement could impact on
– Simplicity of related items fuel gas system
gas turbines
– references for offshore applications – Maintenance activities shall be planned accurately
– lower footprint – Availability of the plant is lower than other options
HEATING MEDIUM
Heating medium selection is strictly dependent on the other choices, especially liquefaction technology and
compressor drivers, LNG production.
Membrane technology is the most proven and referenced for offshore application and is also considered
the one to be selected in order to reduce the containment system CAPEX. However, some aspects
are peculiar for FLNG application, inparticular the possibility to incur in the sloshing phenomenon.
Therefore, careful sloshing assessment studies have been carried out during early feasibility studies with
the involvement of the containment system Licensor and the Classification Society with the objective to
evaluate and certify that the risk of sloshing is below the acceptable level.
MOORING SYSTEM
The mooring system selection impacts many aspects of the FLNG, like layout, motion response, operating
procedures, CAPEX, etc.
The first choice to be made is between spread mooring and single point mooring. Spread mooring is the
cheapest solution but is generally applied in mild environments with high directional metocean conditions.
Moreover, the spread mooring system can pose problems for side-by-side offloading operations because
FLNG heading is not always the best one and this can compromise the terminal availability to offload.
Therefore single point mooring was selected in order to have weathervaning capability which can increase
offloading availability, safety and flexibility to different meteocean conditions.
Several options have been identified:
– Ship is more stable than with external turret; – Part of the hull can not accommodate storages;
Internal turret – Turret can be on the EPC schedule critical path;
– No possibility to convert an existing ship;
Internal turret has been selected as base case for FLNG, even if external turret possibility should be
assessed when metocean conditions are favourable in order to reduce CAPEX.
The adoption of disconnection capability is not considered as required, because cyclones are assumed
to be fast events, posing doubts on the efficacy of the solution. Moreover, CAPEX and OPEX are
increased while revenues are decreased due to the lower plant availability linked to lengthy disconnection-
reconnnection procedures.
SPE-188704-MS 7
For this study, developed at a Basic engineering level, the main Vendors (machinery, exchangers, etc.)
and Licensors (liquefaction, containment system, etc.) were involved in order to ensure the best accuracy
in terms of feasibility and cost estimate.
An Approval in Principle (AiP) has also been released by a major Classification Society.
1 MTPA FLNG
This FLNG configuration was studied to be applied to some "stranded" gas field, which could not be
economically developed with other "traditional" technologies (i.e. gas export, pipeline, etc.).
The proposed liquefaction scheme is a Nitrogen Expander process without any pre-cooling loop, so that
the process is kept as simple as possible. The scheme has all the advantages linked to the use of nitrogen as
refrigerant, such as enhanced safety due to the inert nature nitrogen, no requirement for refrigerant storage,
minimal impact on performance due to vessel motion as the refrigerant is used in gas phase only, and allows
the deletion of all the equipment linked to the HFC pre-cooling loop. The use of that simplified scheme
is possible due to the limited production capacity which leads to the installation of a reasonably limited
number of equipment of industrial already proven size.
The studied scheme is based on a Triple Expander Dual Pressure scheme using wound coil exchanger
for liquefaction. It has been developed in-house for the purpose of the study only without any specific input
from liquefaction Licensors.
In order to produce 1 MTPA of LNG, the required process power for the nitrogen refrigerant overall
compression is estimated to be about 50 MW. In order to obtain this power, two 30-35 MW (@ISO
conditions) gas turbines can be installed with parallel compression trains, therefore requiring a process
compression power of 25 MW each at site conditions.
As a result, the FLNG has the following estimated dimensions:
– Overall Hull length: 325m
– Hull Breath: 60m
– Hull depth (moulded): 31.6m
– Design Draft: 14m
– Total Lightship weight: 92,000 tons
Conclusions
Eni has extensively assessed the technologies required by the FLNG application in the past ten years and
based on the Company’s risk perception has selected the ones deemed most suitable for future FLNG
projects and in particular Coral South Project.
Based on these technologies, different FLNG sizes have been studied with the objective to have the best
solution for every Gas field that may require a FLNG development, from as low as 1 MTPA LNG production
up to the Coral South Project with 3.4 MTPA capacity.
These studies have been carried out for a period of about four years before the commencement of the
Coral South Project, which then started on those same basis and further developed and tailored them to
Mozambique Project requirements.
In this sense, the pre-feasibility and feasibility studies set the basis and actually made the technology
available for the real application on Coral South Project. These studied involved the participation of the main
Vendors, Licensors and Classification Societies, in order to assess the CAPEX and the main technological
issues since the very beginning.
On these basis, it appears evident that the FLNG is not an "off the shelf" product which can be bought
on the market or copied from other projects. Many years of technological studies are required in order to
minimize the technological risk perceived by each Oil Company and to tailor it to a real Project application.
Each Company and Project Team has different perception of risk acceptability, which is based on Company
policies but also Project constraints, such as environmental conditions, schedule, required LNG production,
reservoir gas composition, Partners involvement, project financing, stakeholders, etc.
Eni has organically applied its internal development procedures, from pre-feasibilities to real application,
which demonstrated to be very efficient to make technologies available for real application and ultimately
to unlock the FLNG application.