Professional Documents
Culture Documents
SPE 57459
The field is comprised of 65 wells (61 The re-entry/sidetracking plan for KW-34 was further
injection/withdrawal and 4 observation). Reservoir capacity is complicated by the fact that a depleted “Thief Zone” existed
17.34 billion cubic feet (BCF), with 5.81 BCF (33.5%) being above the 100 Foot Sand in the South Bend Field. This
turnable top gas. horizon (the Murrysville Sandstone) was found behind pipe in
the candidate well at a depth of 1500’-1612’ MD. The
Geology/Reservoir Description existing 5 ½” casing in KW-34 was set at 1622’ MD, therefore
an openhole sidetrack from a cement whipstock plug was
The South Bend Storage Field is a stratigraphic trap, mandated, as opposed to the more conventional and error-
meandering, fluvially-deposited reservoir trending NE/SW. proof technique of setting a mechanical whipstock, and
The storage horizon is in the 100 Foot Sand (Upper Devonian milling a window to initiate sidetracking operations. A
System) and averages approximately 100’ thick, and is located summary of the engineering parameters from the candidate
at an average depth of 1530’. Reservoir extent is 6977 acres. well is illustrated below.
The sand quality and resultant well deliverability are very • Existing Casing- 5 1/2" at 1622'
heterogeneous at South Bend, primarily due to the meandering • PBTD: 1575' (Cement whipstock plug inside 5 1/2
nature of the channel deposit and resultant changes in facies casing-set on 5/28/98)
and net sand thickness. Twenty percent of the wells at South • Gross Reservoir Depth- 1660'-1732'
Bend make up 75% of the deliverability. The average well test • Horizon- 100' Sandstone (Upper Devonian-Channel
value at South Bend is 2.6 MMcfd at a delta-pressure squared deposit)
of 100,000. Maximum storage pressure at full inventory is 710 • Target Depth- 1706'-28'
psig wellhead (738 psig bottomhole). Permeability derived • Direction- South 25 degrees West (205 degrees)
from well tests varies widely, from 10 to over 700
• KOP- +/- 1645' (off of cement plug in openhole)
millidarcies. Reservoir temperature is 73 degrees Fahrenheit.
The well path was planned to intercept and traverse
the Basal porosity in the 100' Sand as described by the LDT-
Candidate Selection/Well Planning CNL.
The well path (azimuthal direction) was supported by
The objectives of this project were two-fold.
FMI analysis of current direction and bedding profiles, and
1) To demonstrate that an existing storage well could be
was confirmed and supported by CNG’s in-house Isopotential
successfully side-tracked and drilled horizontally with Coiled
and Isopach maps.
Tubing
2) To use available mapping data and State of the Art
Candidate Preparation-Phase 1
openhole logging technology and analysis to plan a horizontal
well course to effect a high-deliverability openhole completion
The Candidate well underwent conventional Coiled Tubing
in the Storage horizon.
cleanout (CTCO) operations, openhole logging, and cement
In order to enhance the chances for success of the
plugback on May 26-28,1999. The well was cleaned out to a
South Bend Project, efficient and economic CTD methods had
depth of 1760’ with 1 ¾” coil tubing, a 4 ¾” mill, 2 7/8”
to be modeled in order to proceed. It was decided that more motor, and 70 Quality foam as the drilling medium. The well
petrophysical information was needed in order to properly
was then killed with 9.3 ppg brine water, and logging
model the drillability of the 100 Foot Sand with CTD
operations commenced. A logging suite consisting of a
Technology, and to refine the target interval. Since most wells
Gamma-Ray (GR) Caliper (CAL) Slimhole Lithodensity
in the field were “open hole completed”, the first objective
(SLDT) Compensated Neutron (CNL) Dual Laterallog (DLL)
was to clean out the existing wellbore allowing the geologic
Slimhole FMS (SFMS) and Array Sonic was run from TD to
target to be re-evaluated with newer and state-of-the-art casing point. Logging tools were broken down and run
technology. An openhole wireline Suite consisting of Hi-
separately to compensate for the inadequate amount of rathole
Resolution Litho-Density, Digital Array Sonic, Formation
in the existing openhole completion. Coil tubing was then
MicroImager, and Dual Laterallog were implemented to
rigged back up on the well, and plugback operations were
determine the target zone for directional drilling as well as
effected through the coil. A cement plug consisting of a 16.0
mechanical properties for drillability and proper azimuthal
ppg Class A slurry with 0.75% Fluid loss additive and 3% KCl
coordinates for well path direction and build rate. was spotted from 1760’ to 1573’. Phase 1 operations were
The information derived from logging was utilized to
complete at this point, and equipment was rigged down and
model the project and drill the well on paper. The regional
demobilized from location.
dip of the 100 Foot Sand was 3 – 4 degrees dipping to the
SSW at approximately 205 degrees azimuth. The Hi-Res
Well Plan-Phase 2-Directional Drilling
Density information coupled with the FMI Image data
determined the target porosity to be 14’ thick. The plan was
The well plan for the KW-34 was designed to achieve the
then to steer the BHA into the targeted zone, traversing the
objective of landing a lateral in the defined porosity interval of
targeted porosity layer at high angle until a 500’ lateral section
the 100’ sand, with the objective of increasing the
had been achieved.
SPE 57459 Coiled Tubing Ultrashort-Radius Horizontal Drilling in a Gas Storage Reservoir: A Case Study 3
deliverability and injectivity indices of the well. The selection Steering/BHA Specifications/Drilling Parameters
of the interval was determined by evaluation of the logs
obtained in phase one of the operation. This process was This well was drilled with double articulated steerable mud
described in the preceding candidate selection/well planning motors, a wired MWD telemetry system, and 2 3/8” wired
section. Bearing in mind that the KW-34 well was drilled and coiled tubing. The proposed well path included an openhole
cased in 1922, rotation of a drill string in a well of this vintage sidetrack at 1627’ TVD (true vertical depth). A build rate of
was less than desirable, further validating the selection of the 65 degrees per 100'’to 87 degrees inclination was planned to
CTD process. The well plan for the actual drilling of the intercept the target top at 1714' TVD.
sidetrack section was as follows: Performance of the articulated system was
exceptional and the desired build rates were exceeded. The
• Move in and rig up. highest build rates achieved were 100 degrees/100’ over a five
• Test BOP foot interval. Formation hardness, abrasiveness, and sand to
• Dress cement plug from 1575’ to the KOP of 1627’ (5’ shale laminations affected the actual build rates achieved. The
outside the casing shoe.) hardness and abrasiveness of the formation also adversely
• Run Gyro at 1627’ to determination direction if any. affected bit life. Insert type rock bits were used to drill the
• Drill +/- 30’ until Directional tools were out of the curve and the lateral, and a total of 7 rock bits were used to
original wellbore. Build angle at 75 degrees/100’. drill 290’ of 4 ¾” hole.
• Run Gyro. Continue to build angle until landed in 100’ Hydraulic hole cleaning was efficient, and due to the
sand. Build angle at 75 degrees/100’ and maintain 215 frequent bit trips, short tripping was not required. The well
degree azimuth. was drilled at a 200 psi overbalance pressure (due to lower
• POOH for lateral drilling BHA assembly. than anticipated reservoir inventory), but drilling fluid losses
to the formation were minimal.
• Drill +/- 500’ of lateral.
Due to lower than anticipated ROP (rate of
After the lateral was drilled the plan was to
penetration) and a tight economic ceiling on the project, the
immediately conduct completion operations. This was to be
directional plan was revised mid-well and a lateral length of
accomplished with nitrogen and a smaller (1 ¾”) CT reel.
173.5’ was drilled in the target porosity (1714’-1728’ TVD).
A total of 4.125 days elapsed from the dressing of the cement
CT Drilling Equipment Specifications
plug to the TD and final trip out with the drilling assembly,
prior to CT completion operations. A total of 290’ of 4 ¾”
The coiled tubing used to drill the well was 2 3/8” (2.375”)
hole was drilled (curve plus lateral) with 173.5’ in the target
OD with a 7-conductor cable installed within, the cable
interval.
supplied power to the down hole steering BHA as well as sent
data in “real time” back to surface. The large-pipe reel was
mobilized from the Gulf Coast region with the 2.375” coiled
Completion/Well Testing
tubing aboard and set along side a “bobtail” coiled tubing unit
which powered the hydraulics on the drilling reel. A reel of
Immediately after drilling of the lateral section was concluded,
1.75” “non-wired” coiled tubing was also loaded on the
the CT drilling reel was swapped out for a 1 ¾” CT reel,
“bobtail” unit to be used for other runs where the wired reel
affixed with a jetting nozzle, and run into the well. Nitrogen
was not needed. The coiled tubing unit had an injector head
was pumped at varying rates from 1500 to 3000 standard
capable of pulling /pushing 80,000 lbs (force) and was
cubic-feet per minute (SCFM) while three passes were made
mounted on an elevated substructure / drilling platform which
with the coil tubing and nozzle through the lateral section. The
served as a working platform above the BOP stack and
well was flowed on a 32/64” and 48/64” choke during this
allowed the injector head to be hydraulically moved from over
operation, and flowback/cleanup operations continued after
the well so that the down hole tools could be quickly
the coil was pulled from the well. Drilling equipment was
deployed.
rigged down and demobilized from the site at this point, and
The coiled tubing forces and pipe life were carefully
site reclamation/well reconnect operations were undertaken.
monitored using computer software that tracked pipe life and
Two months subsequent to the drilling operations, a
tubing forces in “real time” by constantly monitoring
multi-point isochronal test was conducted on the KW-34 well.
differential pressure, pipe weight, and past tubing cycles,
Analysis of the data indicated that the well had increased in
electronic devices were also installed on the coiled tubing reel
performance from 0.337 MMcfd to 2.83 MMcfd at a delta-
that actually measured the pipe diameter at several different
pressure squared of 100,000, translating to an 840% increase
axis and calculated the ovality of the coil so that any possible
in performance.
damage to the coil could be detected. This software also
allowed prediction of the tubing forces required to deploy the
steering BHA and motor and set limits for the operating range
of the coil. (see plot 1)
4 E.K. Stiles, M.W. DeRoeun, I.J. Terry, S.P. Cornell, S.J. DuPuy SPE 57459
Conclusions
Nomenclature
BCF= billion cubic feet
BOP= blowout preventer
BUR= build rate
BHA= bottomhole assembly
Figure 2
CT= Coil Tubing Cost Distribution by Activity
CTD= Coil tubing drilling
KCl= Potassium Chloride
KOP= kickoff point
Mmcfd= million cubic feet per day
MD= measured depth
MWD= measurement while drilling
OD= outside diameter Demob. Previous
PBTD= plugged back total depth 8% Activities
PPG= pounds per gallon
25%
TVD= true vertical depth
Acknowledgements
The authors wish to thank CNG Transmission and the
Schlumberger Companies. A special thanks is also offered to Drilling Mobilization
Devin Rock, Schlumberger IPM, for his assistance in 14%
53%
preparation of this paper, and his tireless efforts as the Project
Engineer for the 1999 CTD Program at CNG Transmission.
SPE 57459 Coiled Tubing Ultrashort-Radius Horizontal Drilling in a Gas Storage Reservoir: A Case Study 5
Total Displacement
257 ft
6 E.K. Stiles, M.W. DeRoeun, I.J. Terry, S.P. Cornell, S.J. DuPuy SPE 57459
-400 -200 0
Surface Location: North:186405.61 ft, East:1517700.87 ft NAD83 Pennsylvania State Planes, Northern Zone, US Feet
-200
Grid Coord Local Cooord
Target Name N(+)/S(-) E(+)/W(-) TVD VSEC N(+)/S(-) E(+)/W(-) Shape Major Axis
ft ft ft ft ft ft
End of Build 186326.94 1517662.60 1714.00 -79.37 - 79.37 - 36.79 Point
End of Well 185606.48 1517310.03 1728.00 -806.28 - 806.28 - 375.76 Point
-400
1600
Proposal
Survey
-800
1700