Professional Documents
Culture Documents
lADC/SPE 39305
123
2 The First Coiled Tubing Sidetrack in Norway, Gullfaks Field SPE 39305
124
SPE 39305 R. Gaas@, K.Gjerde, B.Samsonsen 3
pressure regime as the rest of the sidetrack. And finally, adequate 1. The inclusion of a jar/accellerator in the milling BHA was
space had to be available for a back up window above the pri- discovered to be detrimental to the milling operations. When
mary whipstock, pressure was applied to the system (pumping), the jar gradually
stroked out, causing too much weight on mill and consequential
Well Trajectory. The mothewell has an inclination of 40 de- Stallout.
grees at the exit point. A rapid build to horizontal was desirable 2. With excessive hours of milling/stallout the whipstock was
to avoid the waterzonc. An azimuthal change of 35 degrees was probably severely worn and the exit point was measured to be 30
needed to line up the tangent section. The dogleg severity was degrees right of high side. It is recommended that the whipstock
limited to 25 degrees per 30 meters, to allow the installation of a is set left of high side to compensate for the natural tendency of
conventional liner, the mill to “walk” off to the right.
3. Depth control was poor. Conventional flagging technique
Drilling& Completions Programme. A “standard” Drilling& did not prove adequate. There was no intelligence (GR or CCL)
Completions Programme was prepared and submitted to the NPD in the milling BHA for this purpose. Depth correlating devices
for approval. should be included in milling BHA.
Mobilisation. The equipment mobilisation was a critical factor, Drilling. The build section was drilled problem free, with opti-
considering the start-up date was early in the month of February, mal penetration rate and a smooth dogleg severi~.
often a time of extreme weather conditions in the North Sea Re- The drilling of the tangent gave a near perfectly straight hole.
gion. The maximum unit weight (2 3/8” CT reel) was around 40 The..Vipertool h~ .W otien~gx. sub..M?l.rn?YlQ@t?_?PV[inWus!Y
t. The operation waited for almost two weeks on favorable at approximately 1 RPM. The tool was rotated continuously in
weather conditions for this single lifi. the tangent section resulting in a completely straight hole. The
snakelike wellpath created by conventional steerable systems was
thus avoided and a more desirable wellpath profile for subsequent
Rig Up. The conventional drilling rig was out of service at the completions operations was created.
time. The equipment was rigged up in the main drilling tower. Differential sticking became a considerable problem. Sliding
The safety aspects of operating within the environmentally well while pumping gradually became impossible, and TD was set 15
protected drillfloor was highly valued. The access to the rigging m high due to lack of progress.
winches etc. that this location offered was an added bonus. The
injector head and the strippers was placed over the drillfloor, Drilling Fluid Performance. The Visplex drilling fluid system
leaving the BOPS below the floor (see enclosed figure 2). pe~omed well. Hole cleaning was excellent. Cuttings return was
monitored continuously, as well as torque and drag.
Well Preparation. Tailpipe cutting was necessary as the tailpipe The mud weight was designed to be statically in overbalance.
had a nipple profile with 3,687” ID. The required dfi diameter With a maximum flow rate of 2,5 bbl/min, the overbalance was
was 3,8”. The tailpipe was successfully cut and dropped using a 3 observed to increase with 15-20 bar (220-300 psi). This overbal-
5/8” JRC explosive tool. ance was enough to cause differential sticking, probably due to
Isolation of the motherwell perforations was done with a high the high solids content of the mud and the properties of the filter
expansion ratio slips-type PES plug. cake.
Due to the presence of H2S, two complete hole volumes of
seawater was bull-headed back into the motherwell reservoir Logging. Though operationally successful, the logs needed con-
prior to setting the isolating plug. Visplex weighted mud (1,42 siderable reprocessing (several days) onshore before they codd
s.g.) was displaced into the well after the plug setting. be interpreted. The logging tools were of outdated technology.
However, subject to availability, the only choice.
Window Establishment. Installation of the Baker Retrievable
Through Tubing Whipstock was done utilising the Anadrill Vi- Liner installation and cementing. The shoulders of the external
per BHA. The whipstock was oriented high side. Accurate depth couplings of the liner was bevelled to 45 degrees to prevent the
correlation for setting depth was enabled by utilising the GR- shoulders to hang up.
sensor in the Viper assembly Centralisers were not installed, to avoid creating too much drag.
Baker Oil tools one trip milling system was utilised. Seven The external couplings were considered to provide a certain de-
trips were necessary to establish the window, and the following gree of centralisation in the 3 3/4” hole. The liner was installed
learning points were identified: and cemented with standard plug/dart liner running system.
125
..... .— .— .-—
4 The First Coiled Tubing Sidetrack in Norway, Gullfaks Field SPE 39305
Learning Points
Conclusions
The CTD project met all the given objectives within the given
timeframe.
The CTD technology is qualified for the Gullfaks field and
for Statoil.
Coiled tubing drilling in underbalance is the natural direc-
tion to go to be able to fully utilise the potential of the method.
The method can then really become an inexpensive alternative
to conventional drilling.
Future Plans
On the Gullfaks Field, two wells will be side-tracked with
CTD end 1997/early 1998. Late 1998 another two wells will
be side-tracked with CTD.
From the middle of 1999, a permanent CTD-operation will
be started with a level of 5-7 sidetracks per year.
On the Statfjord and Yme Fields, each have plans for 1-3
CTD sidetracks per year from 1998.
Acknowledgements
The authors would like to thank Den norske stats oljeselskap
AS (STATOIL) and the Gullfaks License Group for permis-
sion to publish this paper.
References
126
I
5
sPE 39305 R. Gaasa, K.Gjerde, B.Samsonsen
1750
9750
. ..— —
?800
$800
1850
1850
1$00
<900
127
6 The Firat Coiled Tubing Sidetrack in Norway, Gullfaks Field SPE 39305
~
m
Triple BOP 5 l/8w-10K
1
Pmre FlowCress 51/8”-1OK
$
0.4 *
Drill
—-—.
RKa
Fbor- .-- —_- ~r~----------
Riser 5 1/8”-1 OK
Riser 5 l/8”-10K
II
Riser 5 1/8”-1 OK
9/
X-0v8r31/16’ -2l/l6’
i’
Annular BOP 5 1/8”-1 OK
x-over 2111a--2”
1,0
1s02
/
0,8
0.7
283m RK8
.-—_— .--—
5
—— BOP_____
H _ __-__– ~------
Riser 7 l/16”-10K
X-Over 7 l/16*-5K to 7 l/16”-10K
( 6 3/6” tapered bore)
32,* RKS 3.4
-— --
--——-
128
I SPE 39305 R. Gaas@, K.Gierde, B.Samsonsen 7
1
-
I I . I
6.OM 4,778 5 1/2- Pm hk 17 * 20 b/ft
.
3
}
6.535
4.770
+,8a7 cm-
Flow CW91M0
5 1/2- T& Wc.nk *W.
I
~
-
~
I 1
1 I I --- I —-. I
I
..
—..
I I I I ! I
I , I I
r t
. ....
-.-. — . .. 1
-+ I ! 1 I
I
,
.—.
I
. ..-
I
1
1
I
I I
.,--L I
)
—
4 s
.. . . . . . ..-. —-..
>~ I
k [ !
I , 1
4~—’1———
I MERKNADER,
I I eRONN 34/10-A-10
0s b Trmmmu I
I . l’”In
129