You are on page 1of 7

*m..

Society of Petroleum Engineere

lADC/SPE 39305

The First Coiled Tubing Sidetrack in Norway, Gullfaks Field


R. Gaas@ (SPE), K.Gjerde, B. Samsonsen, Statoil Norway.
IADC Members
Copyright 1998, Society of Petroleum Engineers
identiled. Most of these pockets were unlikely to be economi-
This paper was prepared for preeenlalion at the 1S96 IANSPE Drilling confer~ce held in cally recovered using conventional drilling methods. In the pro-
Dallas, Texas 3-6 March 1998.
ject named “Let Hundred Wells Flow” (LHWF), methods for
This paper was selected for presentation by an SPE Program Committee following review of
information contained in an abstract submitted by the author(s), Contenk of the paper, as draining these pockets were also described. The LHWF-project
presented, have not been reviewed by the Scciety of Petroleum Engineers and are subject to
correction by the author(s), ~e material, as presented, does not necessarily reflect any position of
proposed 34 reservoir targets/ pockets, representing about 10
the Society of Petroleum Engineers, ib officers, or membem Papers presented at SPE meetings mill. Sm3 of recoverable oil, 800/0 of which was Increased Oil
are subject to publication review by Editorial Committees of the Society of Petroleum Engineers
Permission to copy is restricted to an abstract of not more than 300 words, Illustrations may not be Recovery-oil (IOR-oil). Four different drainage methods were
copied, The abstract should contain conspicuous acknowledgment of where and by whom the
paper was presented, Write Librarian, SPE, PO, Box 8333836, Richardson, TX 75083-3636 identi]ed:
● sidetracks through 5 1/2” tubing by coiled tubing drilling
U.S.A., faX 01.972-952-9435,

● sidetracks through 7“ tubing

Abstract ● conventional sidetracks (recovering the tubing first)

● new wells including multilateral wells

Statoil has recently completed a sidetrack drilled with coiled tub-


ing. The sidetrack, the first on the Norwegian Continental SheU Through tubing sidetracks were established as the predominant
of its type, is 254 m and was drilled from the Gtilfaks A method.
plafform. A pilot project was defined to establish whether or not the
The objectives of the project were to drain a small reservoir coiled tubing drilling (Cm) method was viable for the Gf.dK&s
pocket and to qualifi the coiled tubing drilling technique. Stak- field.
ing out a course for further development of the CTD technolo~
was also part of the job. Project Objectives
This paper will describe how Statoil successfully achieved
these objectives with a small project team, intensive experience The CTD project was given two main objectives:
gathering, dedicated contracting strategy, short project planning
phase, continuos dialogue with the authorities and a drilling pro- Reserves. To drain unswept oil in a Brent sandstone (Rannoch).
gram based on simple and field proven solutions. Further to enhance the reservoir understanding of the area.
The sequence of operations started with removing the comple-
tion string tail-pipe with D-restrictions. This was followed by Strategic. To establish the feasibility of through tubing side-
isolating the existing perforations in the mothenvell and install- tracking technology with coiled tubing, from a practical and eco-
ing a through tubing retrievable whipstock. A window was nomical point of view.
milled in the 7“ liner and a 3 3/4” hole drilled to TD with a The CTD technology is applicable for several of Statoils fields,
build-up rate of 25 degrees pcr 30 m and a tangent section at 93 and the proving of the technoloW was given high priority.
degrees. The resemoir was logged using coiled tubing. A 2 7/8”
liner was run to TD and cemented. The reservoir was perforated Experience Gathering
in underbalance. At the outset, no previous experience with CTD was available
The well has produced at a rate of 400 Sm3/day (>50 YO water- within Statoils own organisation.
cut) from one of many oil bearing reservoir pockets in the GulI- The project proceeded to investigate the CTD technology state
f&s field. of the art. In this process, several fields, operators and contrac-
tors in Europe and America were visited. The findings estab-
Introduction lished the base for the planning and design of the first well.

In 1995/96, a concentratedeffort was made on locating remain- Project Organisation


ing oil in the Gullfaks reservoir. Pockets of unswept reservoir, at-
tics etc. with recoverable volumes of more than 50,000 Sm3 were

123
2 The First Coiled Tubing Sidetrack in Norway, Gullfaks Field SPE 39305

Project team. A dedicated team was formed with a defined ● Rigging up


mandate: ● Mud Mixing with portable Mud Processing Unit
Q build CTD competence ● Handling and running of Liner
● candidate wells selection

● select contractors/contractual strategy The RA sessions generated a total of 92 recommendations,


● build project organisation programme amendments and other action points, all of which
● define technology strategy were processed and “closed out” prior to starting the
● project execution operation.

The team consisted of a project manager, a completions en- Authorities


gineer and a drilling engineer. After contract award, a repre- A direct communication line was established with Oljedirek-
sentative from the lead contractor, Schlurnberger Dowell, was toratet (OD, Norwegian Petroleum Directorate). The OD was
incorporated in the project team, working directly from Sta- kept informed of all the cential considerations with reference
toils oftice. to well control, barriers etc. The OD made a review of the pro-
ject operation onshore and offshore, with no major findings.
Project Strategies. The group was given 6 months to plan A considerable work was performed by the team to bridge
and execute the project. Three major strategies were stipulated the apparent gap between roles & regulations pertaining to
shortly after project start: standard drilling operations and rules & regulations pertain-
● use only field-proven, simple solutions ing to well maintenance operations. This applied both to inter-
● mobile, stand-alone operation nal and governmental regulations,
● perfoml the operation as an established, standard drilling

operation with reference to lines of commantireporting Well Selection


lines The LHWF-project defined a range of wells as candidates for
CTD sidetracks. The final selection was based on:
Contracts. Four companies were evaluated initially as the s production potential
● motherwell production status
CTD contractor. Only the Schlumberger Dowell/Anadrill
● motherwell completions desigtistatus
group was approached for bid submittal, and the contract was
● sidetrack completions requirements
awarded to Dowell as the lead contractor. In addition, existing
● slot access (other drilling or workover activities)
contracts on the Gullfaks Field were used for window estab-
lishment technology, liner and TCP perforation (Baker Oil
Tools) and logging operations maritime Western Atlas). Three wells were included in the final evaluations. Two
were selected for final design. For these two wells, Drilling
Risk Analysis. Risk Analysis Methods (RA) were intensively and Completions Programmed were produced and submitted
used in the planning phase. The major objective of the RA to the Norwegian Petroleum Directorate ND) for approval.
was to ensure that Safety, Health and Environmental Issues
A IOA Well Design
were dealt with in a professional manner. Having the opera-
tional crew members participate in RA-sessions also provided
the added benefit of ownership, both to the highest HSE stan- Reservoir Target. The A1OA well was designed to access and
dards and to the technical challenges. The National Authori- produce a pocket of unswept oil trapped between a tight fault
ties (NPD) has requiretnents to risk analysis in the Rules & and the A lO motherwell (see figure 1).
Regulations.
The HAZID (Hazard Identification) and the HAZOP (Haz- Completion requirement. The lower Brent sands typically do
ardous Operation) methods was extensively used on the Drill- not require sand control, as it is well cemented and has me-
ing and Completions Programme, and on special critical dium to low permeability and porosity. Further, zonal isola-
operations. tion was a requirement as part of the wellbore would penetrate
HAZOPS addressing the following topics were performed: gasbearing and waterflooded sands. Thus a conventional ce-
● Cutting tailpipe
mented liner was chosen as a completion string.
s Installing whipstock Perforation method selected was coiled tubing deployed
● Differential sticking
guns in underbalance.
c Handling of influx
Ezit point. The governing criterion for the exit point was that
Safe Job Analysis were conducted for the following it had to be positioned so that window milling avoided casing
operations: collars or casing centralizers. Further, the exit point shodd
give a reasonable build rate and it shodd be in the same’

124
SPE 39305 R. Gaas@, K.Gjerde, B.Samsonsen 3

pressure regime as the rest of the sidetrack. And finally, adequate 1. The inclusion of a jar/accellerator in the milling BHA was
space had to be available for a back up window above the pri- discovered to be detrimental to the milling operations. When
mary whipstock, pressure was applied to the system (pumping), the jar gradually
stroked out, causing too much weight on mill and consequential
Well Trajectory. The mothewell has an inclination of 40 de- Stallout.
grees at the exit point. A rapid build to horizontal was desirable 2. With excessive hours of milling/stallout the whipstock was
to avoid the waterzonc. An azimuthal change of 35 degrees was probably severely worn and the exit point was measured to be 30
needed to line up the tangent section. The dogleg severity was degrees right of high side. It is recommended that the whipstock
limited to 25 degrees per 30 meters, to allow the installation of a is set left of high side to compensate for the natural tendency of
conventional liner, the mill to “walk” off to the right.
3. Depth control was poor. Conventional flagging technique
Drilling& Completions Programme. A “standard” Drilling& did not prove adequate. There was no intelligence (GR or CCL)
Completions Programme was prepared and submitted to the NPD in the milling BHA for this purpose. Depth correlating devices
for approval. should be included in milling BHA.

Operational Phase Open Hole Drilling

Mobilisation. The equipment mobilisation was a critical factor, Drilling. The build section was drilled problem free, with opti-
considering the start-up date was early in the month of February, mal penetration rate and a smooth dogleg severi~.
often a time of extreme weather conditions in the North Sea Re- The drilling of the tangent gave a near perfectly straight hole.
gion. The maximum unit weight (2 3/8” CT reel) was around 40 The..Vipertool h~ .W otien~gx. sub..M?l.rn?YlQ@t?_?PV[inWus!Y
t. The operation waited for almost two weeks on favorable at approximately 1 RPM. The tool was rotated continuously in
weather conditions for this single lifi. the tangent section resulting in a completely straight hole. The
snakelike wellpath created by conventional steerable systems was
thus avoided and a more desirable wellpath profile for subsequent
Rig Up. The conventional drilling rig was out of service at the completions operations was created.
time. The equipment was rigged up in the main drilling tower. Differential sticking became a considerable problem. Sliding
The safety aspects of operating within the environmentally well while pumping gradually became impossible, and TD was set 15
protected drillfloor was highly valued. The access to the rigging m high due to lack of progress.
winches etc. that this location offered was an added bonus. The
injector head and the strippers was placed over the drillfloor, Drilling Fluid Performance. The Visplex drilling fluid system
leaving the BOPS below the floor (see enclosed figure 2). pe~omed well. Hole cleaning was excellent. Cuttings return was
monitored continuously, as well as torque and drag.
Well Preparation. Tailpipe cutting was necessary as the tailpipe The mud weight was designed to be statically in overbalance.
had a nipple profile with 3,687” ID. The required dfi diameter With a maximum flow rate of 2,5 bbl/min, the overbalance was
was 3,8”. The tailpipe was successfully cut and dropped using a 3 observed to increase with 15-20 bar (220-300 psi). This overbal-
5/8” JRC explosive tool. ance was enough to cause differential sticking, probably due to
Isolation of the motherwell perforations was done with a high the high solids content of the mud and the properties of the filter
expansion ratio slips-type PES plug. cake.
Due to the presence of H2S, two complete hole volumes of
seawater was bull-headed back into the motherwell reservoir Logging. Though operationally successful, the logs needed con-
prior to setting the isolating plug. Visplex weighted mud (1,42 siderable reprocessing (several days) onshore before they codd
s.g.) was displaced into the well after the plug setting. be interpreted. The logging tools were of outdated technology.
However, subject to availability, the only choice.
Window Establishment. Installation of the Baker Retrievable
Through Tubing Whipstock was done utilising the Anadrill Vi- Liner installation and cementing. The shoulders of the external
per BHA. The whipstock was oriented high side. Accurate depth couplings of the liner was bevelled to 45 degrees to prevent the
correlation for setting depth was enabled by utilising the GR- shoulders to hang up.
sensor in the Viper assembly Centralisers were not installed, to avoid creating too much drag.
Baker Oil tools one trip milling system was utilised. Seven The external couplings were considered to provide a certain de-
trips were necessary to establish the window, and the following gree of centralisation in the 3 3/4” hole. The liner was installed
learning points were identified: and cemented with standard plug/dart liner running system.

125
..... .— .— .-—

4 The First Coiled Tubing Sidetrack in Norway, Gullfaks Field SPE 39305

Perforation. Two zones of 20 m each was perforated with 2“


4 shots per foot, 7 g charge guns in underbalance.

Production. The well was initially produced at the expected


rate of 400 Sm3/D, but with more than 50°/0watercut. The
watercut has, despite of ill expectations, remained at this
level. The well has produced about 50.000 Sm3 to date
(nov.97) and continues to produce around the given rate.

Learning Points

Risk analysis. Using risk analysis to assess the project from


an Health, Safety, Environmental and Economical side is
critical to success.
Drilling Fluid. The drilling fluid needs to be optimised from a
Werential sticking point of view.
BHA for Milling. Accelerator and jar should not be included
in the milling assembly.
Stand alone operation. The stand alone operation was
successfid.
Separate Drilling fluids Module. This module was a chal-
lenge with respect to health and working environment. Using
the platforms existing system should be evaluated,

Conclusions
The CTD project met all the given objectives within the given
timeframe.
The CTD technology is qualified for the Gullfaks field and
for Statoil.
Coiled tubing drilling in underbalance is the natural direc-
tion to go to be able to fully utilise the potential of the method.
The method can then really become an inexpensive alternative
to conventional drilling.

Future Plans
On the Gullfaks Field, two wells will be side-tracked with
CTD end 1997/early 1998. Late 1998 another two wells will
be side-tracked with CTD.
From the middle of 1999, a permanent CTD-operation will
be started with a level of 5-7 sidetracks per year.
On the Statfjord and Yme Fields, each have plans for 1-3
CTD sidetracks per year from 1998.

Acknowledgements
The authors would like to thank Den norske stats oljeselskap
AS (STATOIL) and the Gullfaks License Group for permis-
sion to publish this paper.

References

1. Vikane, E., Samsonsen, B. and Lorentzen, K.E.: Through


Tubing IMIII Drilling as a Method for Increased Oil Recovery
on the GullfAs Field” SPE 39358, IADC/SPE Dallas 1998.

126
I
5
sPE 39305 R. Gaasa, K.Gjerde, B.Samsonsen

PRELIMINARY INTERPRETATIONAFTER DRILLING/LOGGINGA-1OA

1750
9750
. ..— —

?800
$800

1850
1850

1$00
<900

OP!PE E kiA Bm04, I

Fig. 1. Reservoir interpretation


~

127
6 The Firat Coiled Tubing Sidetrack in Norway, Gullfaks Field SPE 39305
~

Client LHBS CTD


Coiled Tubing Drilling Sewices - NORWAY Installation: Gullfaks A
Well: GFA-10
WELL CONTROL STACK - STATOIL Gullfaks A
Date: 24 Jan. 1997
Created by: T.W. Staal

$ Radial Stripper 5118”-IOK


Radial Stripper 5 l/8”-10K
1 X-over :Bowan CC44 Box to 5118” 10K
t X-over :Bowen CC44 Pin to 5 1/8” 10K
rl~
t
1,3 m

m
Triple BOP 5 l/8w-10K
1
Pmre FlowCress 51/8”-1OK
$
0.4 *
Drill
—-—.
RKa
Fbor- .-- —_- ~r~----------

Riser 5 1/8”-1 OK

Riser 5 l/8”-10K

II

Riser 5 1/8”-1 OK

9/
X-0v8r31/16’ -2l/l6’
i’
Annular BOP 5 1/8”-1 OK
x-over 2111a--2”
1,0
1s02
/

0,8

0.7

283m RK8
.-—_— .--—
5
—— BOP_____
H _ __-__– ~------
Riser 7 l/16”-10K
X-Over 7 l/16*-5K to 7 l/16”-10K
( 6 3/6” tapered bore)
32,* RKS 3.4
-— --
--——-

Tree 7 l/l f3”-5K top flange

I Fig.2. Well Rig up on A-IOA

128
I SPE 39305 R. Gaas@, K.Gierde, B.Samsonsen 7

PRINSIPP KOMPLETTERING 34/10-A-10


STATUS PR, 2G. Of. 97
m

1
-

I I . I
6.OM 4,778 5 1/2- Pm hk 17 * 20 b/ft

.
3
}
6.535
4.770
+,8a7 cm-
Flow CW91M0
5 1/2- T& Wc.nk *W.
I
~

-
~

Jl~l 102 I 4 ?7b


4.
x
.W
.m w
x
X-Q%
)

I 1

l’~,1 i Iaw.0 I 5,.945 I 4,1700 I +0 Cunco s 7*< w- 20’ st,tie I


I I
,I I !
I
,--- ---- 1
1 !

1 I I --- I —-. I

I
..
—..
I I I I ! I
I , I I
r t
. ....
-.-. — . .. 1
-+ I ! 1 I

I
,
.—.
I

. ..-
I
1
1

I
I I
.,--L I
)

4 s
.. . . . . . ..-. —-..
>~ I

k [ !

I , 1
4~—’1———
I MERKNADER,

I I eRONN 34/10-A-10
0s b Trmmmu I

I . l’”In

I Fig. 3. Well schematic, A-10 motherwell

129

You might also like