Activity ID Activity Name Original Start Finish S O N D J F M A M J J A S O N D J F M A M J J A S O

1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 20
Duration
623 23-Sep-13 19-Sep-15 19-Sep-15, BLSF Bulk
BLSF Bulk Liquid Storage Facility- Salah, Oman
BLSF.1 Pre-Construction 28 23-Sep-13 24-Oct-13 24-Oct-13, BLSF.1 Pre-Construction

BLSF.1.1 Pre-Construction Meeting 4 23-Sep-13 27-Sep-13 27-Sep-13, BLSF.1.1 Pre-Construction Meeting


Pre-Construction Meetings 5 23-Sep-13 27-Sep-13 Pre-Construction Meetings
BLSF.1.2 Pre-Construction Submittals 22 30-Sep-13 24-Oct-13 24-Oct-13, BLSF.1.2 Pre-Construction Submittals
BLSF.1.2.1 Submittals 4 30-Sep-13 04-Oct-13 04-Oct-13, BLSF.1.2.1 Submittals
QC Plan 5 30-Sep-13 04-Oct-13 QC Plan
Baseline Schedule 5 30-Sep-13 04-Oct-13 Baseline Schedule
Safety and AP Plan 5 30-Sep-13 04-Oct-13 Safety and AP Plan
Area Use Plan 5 30-Sep-13 04-Oct-13 Area Use Plan
Geo Technical Investigation Plan 5 30-Sep-13 04-Oct-13 Geo Technical Investigation Plan
BLSF.1.2.2 Review and Approval 16 07-Oct-13 24-Oct-13 24-Oct-13, BLSF.1.2.2 Review and Approval
Review and Approval of QC Plan 14 07-Oct-13 24-Oct-13 Review and Approval of QC Plan
Review and Appoval of Baseline Schedule 14 07-Oct-13 24-Oct-13 Review and Appoval of Baseline Schedule
Review and Appoval of Safety and AP Plan 14 07-Oct-13 24-Oct-13 Review and Appoval of Safety and AP Plan
Review and Appoval of Area Use Plan 14 07-Oct-13 24-Oct-13 Review and Appoval of Area Use Plan
Review and Appoval of Geo Tech. Investigation Plan 14 07-Oct-13 24-Oct-13 Review and Appoval of Geo Tech. Investigation Plan

BLSF.2 Design 106 25-Oct-13 25-Feb-14 25-Feb-14, BLSF.2 Design

BLSF.2.1 Site Survey 5 25-Oct-13 30-Oct-13 30-Oct-13, BLSF.2.1 Site Survey


Site Survey 4 25-Oct-13 30-Oct-13 Site Survey
BLSF.2.2 10% Design Submittal 24 31-Oct-13 27-Nov-13 27-Nov-13, BLSF.2.2 10% Design Submittal
10% Design Submittal 5 31-Oct-13 06-Nov-13 10% Design Submittal
10% Design Review 14 07-Nov-13 26-Nov-13 10% Design Review
10% Design Approval 1 27-Nov-13 27-Nov-13 10% Design Approval
BLSF.2.3 65% Design Submittal 25 28-Nov-13 27-Dec-13 27-Dec-13, BLSF.2.3 65% Design Submittal
65% Design Submittal 7 28-Nov-13 06-Dec-13 65% Design Submittal
65% Design Review 14 09-Dec-13 26-Dec-13 65% Design Review
65% Design Approval 1 27-Dec-13 27-Dec-13 65% Design Approval
BLSF.2.4 95% Design Submittal 26 30-Dec-13 28-Jan-14 28-Jan-14, BLSF.2.4 95% Design Submittal
95% Design Submittal 7 30-Dec-13 07-Jan-14 95% Design Submittal
95% Design Review 14 08-Jan-14 27-Jan-14 95% Design Review
95% Design Approval 1 28-Jan-14 28-Jan-14 95% Design Approval
BLSF.2.5 100% Design Submittal 24 29-Jan-14 25-Feb-14 25-Feb-14, BLSF.2.5 100% Design Submittal
100% Design Submittal 5 29-Jan-14 04-Feb-14 100% Design Submittal
100% Design Review 14 05-Feb-14 24-Feb-14 100% Design Review
100% Design Approval 1 25-Feb-14 25-Feb-14 100% Design Approval

BLSF.3 Procurement 226 30-Dec-13 18-Sep-14 18-Sep-14, BLSF.3 Procurement

BLSF.3.1 Civil / Structural 58 30-Dec-13 06-Mar-14 06-Mar-14, BLSF.3.1 Civil / Structural


Submitals of Civil & Structurle Meterials 35 30-Dec-13 14-Feb-14 Submitals of Civil & Structurle Meterials
Review and Approval of Civil & Structurle Materials 14 17-Feb-14 06-Mar-14 Review and Approval of Civil & Structurle Materials
BLSF.3.2 Architectural 58 17-Feb-14 24-Apr-14 24-Apr-14, BLSF.3.2 Architectural
Submitals of Architectural Meterials 35 17-Feb-14 04-Apr-14 Submitals of Architectural Meterials
Review and Approval of Architectural Materials 14 07-Apr-14 24-Apr-14 Review and Approval of Architectural Materials
BLSF.3.3 Electrical 58 07-Apr-14 12-Jun-14 12-Jun-14, BLSF.3.3 Electrical
Submitals of Electrical Meterials 35 07-Apr-14 23-May-14 Submitals of Electrical Meterials
Review and Approval of Electrical Materials 14 26-May-14 12-Jun-14 Review and Approval of Electrical Materials
BLSF.3.4 Mechanical 58 26-May-14 31-Jul-14 31-Jul-14, BLSF.3.4 Mechanical
Submitals of Mechnical Meterials 35 26-May-14 11-Jul-14 Submitals of Mechnical Meterials
Govt. Review and Approval of Mechanical Materials 14 14-Jul-14 31-Jul-14 Govt. Review and Approval of Mechanical Materials
BLSF.3.5 Plumbing 58 14-Jul-14 18-Sep-14 18-Sep-14, BLSF.3.5 Plumbing
Submitals of Plumbing Meterials 35 14-Jul-14 29-Aug-14 Submitals of Plumbing Meterials

Actual Work Critical Remaining Work Summary Page 1 of 10 TASK filter: All Activities

Remaining Work Milestone (c) Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish S O N D J F M A M J J A S O N D J F M A M J J A S O
1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 20
Duration
Review and Approval of Plumbing Materials 14 01-Sep-14 18-Sep-14 Review and Approval of Plumbing Materials

BLSF.4 Mobilization 89 07-Dec-13 19-Mar-14 19-Mar-14, BLSF.4 Mobilization

BLSF.4.1 Machinary & Staff 25 07-Dec-13 04-Jan-14 04-Jan-14, BLSF.4.1 Machinary & Staff
Mobilization to Site 25 07-Dec-13 04-Jan-14 Mobilization to Site
63 06-Jan-14 19-Mar-14
BLSF.4.3 Construction of Site Offices / Staff Residence 19-Mar-14, BLSF.4.3 Construction of Site Offices / Staff Residence
BLSF.4.3.1 Foundations 22 06-Jan-14 31-Jan-14 31-Jan-14, BLSF.4.3.1 Foundations
Layout and Excavation 1 06-Jan-14 06-Jan-14 Layout and Excavation
Prepare Sub-Grade 1 07-Jan-14 07-Jan-14 Prepare Sub-Grade
Rebar Cutting, Bending and Fixing of Footings 2 08-Jan-14 09-Jan-14 Rebar Cutting, Bending and Fixing of Footings
Form Works Fixing of Footings 2 09-Jan-14 10-Jan-14 Form Works Fixing of Footings
Concrete Pouring of Footings 1 13-Jan-14 13-Jan-14 Concrete Pouring of Footings
Concrete Curing of Footings 7 14-Jan-14 22-Jan-14 Concrete Curing of Footings
Remove Form Work of Footings 1 14-Jan-14 14-Jan-14 Remove Form Work of Footings
Block Masonary (CMU) 2 15-Jan-14 16-Jan-14 Block Masonary (CMU)
Back Fill 2 16-Jan-14 17-Jan-14 Back Fill
Prepare Sub-Grade of SOG 1 17-Jan-14 17-Jan-14 Prepare Sub-Grade of SOG
Capillary Water Barrier 2 17-Jan-14 20-Jan-14 Capillary Water Barrier
Rebar Cutting, Bending and Fixing of SOG 2 20-Jan-14 21-Jan-14 Rebar Cutting, Bending and Fixing of SOG
Concrete Pouring of SOG 1 22-Jan-14 22-Jan-14 Concrete Pouring of SOG
Concrete Curing of SOG 7 23-Jan-14 31-Jan-14 Concrete Curing of SOG
BLSF.4.3.2 Supertructure 28 23-Jan-14 24-Feb-14 24-Feb-14, BLSF.4.3.2 Supertructure
Concrete Masonary unit (CMU) Wall 3 23-Jan-14 27-Jan-14 Concrete Masonary unit (CMU) Wall
Lintle Beams 1 27-Jan-14 27-Jan-14 Lintle Beams
Bond Beams 2 28-Jan-14 29-Jan-14 Bond Beams
Form Work Roof Slab 2 30-Jan-14 31-Jan-14 Form Work Roof Slab
Rebar Cutting, Bending & Fixing Roof Slab 2 31-Jan-14 03-Feb-14 Rebar Cutting, Bending & Fixing Roof Slab
Concrete Pouring Roof Slab 1 04-Feb-14 04-Feb-14 Concrete Pouring Roof Slab
Concrete Curing Roof Slab 7 05-Feb-14 13-Feb-14 Concrete Curing Roof Slab
Remove Form Work 14 05-Feb-14 24-Feb-14 Remove Form Work
CMU Work Above Roof Slab 1 05-Feb-14 05-Feb-14 CMU Work Above Roof Slab
BLSF.4.3.3 Atchitectural 7 25-Feb-14 04-Mar-14 04-Mar-14, BLSF.4.3.3 Atchitectural
Plaster Work Internal Walls & Ceiling 2 25-Feb-14 26-Feb-14 Plaster Work Internal Walls & Ceiling
Rigid Insulation 2 25-Feb-14 26-Feb-14 Rigid Insulation
Stucco on External Wall 2 27-Feb-14 28-Feb-14 Stucco on External Wall
Paint Internal Walls and Ceiling 2 03-Mar-14 04-Mar-14 Paint Internal Walls and Ceiling
BLSF.4.3.4 Mechanical 20 17-Feb-14 11-Mar-14 11-Mar-14, BLSF.4.3.4 Mechanical
Fixing of Roof Truss 10 17-Feb-14 28-Feb-14 Fixing of Roof Truss
Fixing of sheets & Insulation 2 03-Mar-14 04-Mar-14 Fixing of sheets & Insulation
Fixing of Gutter and Down Spout 1 04-Mar-14 04-Mar-14 Fixing of Gutter and Down Spout
Fixing of Doors 2 05-Mar-14 06-Mar-14 Fixing of Doors
Fixing of Windows 2 07-Mar-14 10-Mar-14 Fixing of Windows
Fixing fo Roof Hatch & Laouvers 1 11-Mar-14 11-Mar-14 Fixing fo Roof Hatch & Laouvers
BLSF.4.3.5 Plumbing 12 05-Mar-14 18-Mar-14 18-Mar-14, BLSF.4.3.5 Plumbing
Clorination System 5 05-Mar-14 11-Mar-14 Clorination System
Water Disribution System 5 12-Mar-14 18-Mar-14 Water Disribution System
BLSF.4.3.6 Electrical 38 04-Feb-14 19-Mar-14 19-Mar-14, BLSF.4.3.6 Electrical
Installation of Conduits 2 04-Feb-14 05-Feb-14 Installation of Conduits
Wiring System 2 06-Mar-14 07-Mar-14 Wiring System
Installation fo Outlets and Switches 2 10-Mar-14 11-Mar-14 Installation fo Outlets and Switches
Installation of Exhuast Fan and Heater 1 12-Mar-14 12-Mar-14 Installation of Exhuast Fan and Heater
Installation of Lightening Protection System 5 13-Mar-14 19-Mar-14 Installation of Lightening Protection System

BLSF.5 Construction 477 07-Jan-14 17-Jul-15 17-Jul-15, BLSF.5 Construction

Actual Work Critical Remaining Work Summary Page 2 of 10 TASK filter: All Activities

Remaining Work Milestone (c) Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish S O N D J F M A M J J A S O N D J F M A M J J A S O
1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 20
Duration
BLSF.5.1 Site Develoments anf Improvements 422 07-Jan-14 13-May-15 13-May-15, BLSF.5.1 Site Develoments anf Improvements
Demolition / Clearing and Grubbing 30 07-Jan-14 17-Feb-14 Demolition / Clearing and Grubbing
Earth Work (Cutting and Filling) 100 21-Jan-14 09-Jun-14 Earth Work (Cutting and Filling)

Pilling works 90 18-Mar-14 30-Jun-14 Pilling works


Weigh Bridge 45 27-May-14 28-Jul-14 Weigh Bridge
Uploading and Dowloading Bay Foundations 75 15-Jul-14 09-Oct-14 Uploading and Dowloading Bay Foundations
Septic Tank and Sewerage System 50 06-Sep-14 02-Nov-14 Septic Tank and Sewerage System
Perimeter Wall all around the premises 85 29-Sep-14 23-Jan-15 Perimeter Wall all around the premises
Road and Drainage works 95 08-Dec-14 28-Mar-15 Road and Drainage works
Site Electrical Works 90 29-Jan-15 13-May-15 Site Electrical Works
BLSF.5.2 Storage Tanks 382 17-Mar-14 04-Jun-15 04-Jun-15, BLSF.5.2 Storage Tanks
BLSF.5.2.1 Product Tanks (39.5 m dia meter) 304 17-Mar-14 05-Mar-15 05-Mar-15, BLSF.5.2.1 Product Tanks (39.5 m dia meter)
BLSF.5.2.1.1 Foundations 110 12-May-14 16-Sep-14 16-Sep-14, BLSF.5.2.1.1 Foundations
Layout and Excavation 22 12-May-14 10-Jun-14 Layout and Excavation
Prepare Sub-Grade 22 14-May-14 12-Jun-14 Prepare Sub-Grade
Rebar Cutting, Bending and Fixing of Footings 22 30-May-14 30-Jun-14 Rebar Cutting, Bending and Fixing of Footings
Form Works Fixing of Footings 22 10-Jun-14 09-Jul-14 Form Works Fixing of Footings
Concrete Pouring of Footings 7 10-Jul-14 18-Jul-14 Concrete Pouring of Footings
Concrete Curing of Footings 15 11-Jul-14 31-Jul-14 Concrete Curing of Footings
Remove Form Work of Footings 7 11-Jul-14 21-Jul-14 Remove Form Work of Footings
Back Fill 21 22-Jul-14 19-Aug-14 Back Fill
Rebar Cutting, Bending and Fixing of Ring Beam 14 11-Aug-14 28-Aug-14 Rebar Cutting, Bending and Fixing of Ring Beam
Concrete Pouring of Ring Beam 10 26-Aug-14 08-Sep-14 Concrete Pouring of Ring Beam
Concrete Curing of Ring Beam 15 27-Aug-14 16-Sep-14 Concrete Curing of Ring Beam
Form Work Removing of Ring Beam 10 30-Aug-14 09-Sep-14 Form Work Removing of Ring Beam
BLSF.5.2.1.2 Supertructure 42 28-Aug-14 15-Oct-14 15-Oct-14, BLSF.5.2.1.2 Supertructure
Rebar Cutting, Bending and Fixing of External Wall 7 09-Sep-14 17-Sep-14 Rebar Cutting, Bending and Fixing of External Wall
Form Works Fixing of External Wall 7 28-Aug-14 05-Sep-14 Form Works Fixing of External Wall
Concrete Pouring of External Wall 7 08-Sep-14 16-Sep-14 Concrete Pouring of External Wall
Concrete Curing of External Wall 15 09-Sep-14 29-Sep-14 Concrete Curing of External Wall
Remove Form Work of External Wall 7 09-Sep-14 17-Sep-14 Remove Form Work of External Wall
Rebar Cutting, Bending and Fixing of Internal Wall 14 09-Sep-14 26-Sep-14 Rebar Cutting, Bending and Fixing of Internal Wall
Concrete Pouring of Internal Wall 10 24-Sep-14 07-Oct-14 Concrete Pouring of Internal Wall
Concrete Curing of Internal Wall 15 25-Sep-14 15-Oct-14 Concrete Curing of Internal Wall
Form Work Removing of Internal Wall 10 29-Sep-14 09-Oct-14 Form Work Removing of Internal Wall
BLSF.5.2.1.4 Mechanical 301 17-Mar-14 02-Mar-15 02-Mar-15, BLSF.5.2.1.4 Mechanical
Fabrication of Tanks and Transport to site 150 17-Mar-14 10-Oct-14 Fabrication of Tanks and Transport to site
Errection of Tanks 50 29-Sep-14 05-Dec-14 Errection of Tanks
Fabrication and Errection of Stail Case 27 24-Nov-14 30-Dec-14 Fabrication and Errection of Stail Case
Installation of Level guage and Nozzels 15 17-Dec-14 06-Jan-15 Installation of Level guage and Nozzels
Installation of Pipes 42 10-Dec-14 05-Feb-15 Installation of Pipes
Applying Paint on Tanks 21 07-Feb-15 02-Mar-15 Applying Paint on Tanks
BLSF.5.2.1.6 Electrical & Fire Fighting 156 05-Sep-14 05-Mar-15 05-Mar-15, BLSF.5.2.1.6 Electrical & Fire Fighting
Installation of Conduits 5 06-Feb-15 12-Feb-15 Installation of Conduits
Wiring System 5 13-Feb-15 19-Feb-15 Wiring System
Installation of Outlets and Switches 5 20-Feb-15 26-Feb-15 Installation of Outlets and Switches
Procurement and Installation of Pumps 125 05-Sep-14 26-Feb-15 Procurement and Installation of Pumps
Installation of Lightening Protection System 5 27-Feb-15 05-Mar-15 Installation of Lightening Protection System
BLSF.5.2.2 Product Tanks (33 & 25 m dia meter) 134 17-Nov-14 21-Apr-15 21-Apr-15, BLSF.5.2.2 Product Tanks (33 & 25 m dia meter)
BLSF.5.2.2.1 Foundations 54 03-Dec-14 03-Feb-15 03-Feb-15, BLSF.5.2.2.1 Foundations
Layout and Excavation 7 03-Dec-14 11-Dec-14 Layout and Excavation
Prepare Sub-Grade 7 10-Dec-14 18-Dec-14 Prepare Sub-Grade

Actual Work Critical Remaining Work Summary Page 3 of 10 TASK filter: All Activities

Remaining Work Milestone (c) Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish S O N D J F M A M J J A S O N D J F M A M J J A S O
1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 20
Duration
Rebar Cutting, Bending and Fixing of Footings 7 17-Dec-14 25-Dec-14 Rebar Cutting, Bending and Fixing of Footings
Form Works Fixing of Footings 7 24-Dec-14 01-Jan-15 Form Works Fixing of Footings
Concrete Pouring of Footings 2 02-Jan-15 05-Jan-15 Concrete Pouring of Footings
Concrete Curing of Footings 8 05-Jan-15 14-Jan-15 Concrete Curing of Footings
Remove Form Work of Footings 2 05-Jan-15 06-Jan-15 Remove Form Work of Footings
Back Fill 7 07-Jan-15 15-Jan-15 Back Fill
Rebar Cutting, Bending and Fixing of Ring Beam 5 15-Jan-15 21-Jan-15 Rebar Cutting, Bending and Fixing of Ring Beam
Concrete Pouring of Ring Beam 2 21-Jan-15 22-Jan-15 Concrete Pouring of Ring Beam
Concrete Curing of Ring Beam 9 22-Jan-15 03-Feb-15 Concrete Curing of Ring Beam
Form Work Removing of Ring Beam 5 22-Jan-15 27-Jan-15 Form Work Removing of Ring Beam
BLSF.5.2.2.2 Supertructure 17 23-Jan-15 11-Feb-15 11-Feb-15, BLSF.5.2.2.2 Supertructure
Rebar Cutting, Bending and Fixing of External Wall 2 23-Jan-15 26-Jan-15 Rebar Cutting, Bending and Fixing of External Wall
Form Works Fixing of External Wall 2 27-Jan-15 28-Jan-15 Form Works Fixing of External Wall
Concrete Pouring of External Wall 2 29-Jan-15 30-Jan-15 Concrete Pouring of External Wall
Concrete Curing of External Wall 9 30-Jan-15 11-Feb-15 Concrete Curing of External Wall
Remove Form Work of External Wall 2 30-Jan-15 02-Feb-15 Remove Form Work of External Wall
Rebar Cutting, Bending and Fixing of Internal Wall 2 23-Jan-15 26-Jan-15 Rebar Cutting, Bending and Fixing of Internal Wall
Concrete Pouring of Internal Wall 2 26-Jan-15 27-Jan-15 Concrete Pouring of Internal Wall
Concrete Curing of Internal Wall 9 27-Jan-15 06-Feb-15 Concrete Curing of Internal Wall
Form Work Removing of Internal Wall 2 27-Jan-15 28-Jan-15 Form Work Removing of Internal Wall
BLSF.5.2.2.4 Mechanical 121 17-Nov-14 06-Apr-15 06-Apr-15, BLSF.5.2.2.4 Mechanical
Fabrication of Tanks & Transport to site 75 17-Nov-14 27-Feb-15 Fabrication of Tanks & Transport to site
Errection of Tanks 15 16-Feb-15 06-Mar-15 Errection of Tanks
Fabrication and Errection of Stail Case 10 02-Mar-15 13-Mar-15 Fabrication and Errection of Stail Case
Installation of Level guage and Nozzels 7 09-Mar-15 17-Mar-15 Installation of Level guage and Nozzels
Installation of Pipes 15 11-Mar-15 31-Mar-15 Installation of Pipes
Applying Paint on Tanks 5 01-Apr-15 06-Apr-15 Applying Paint on Tanks
BLSF.5.2.2.6 Electrical & Fire Fighting 18 01-Apr-15 21-Apr-15 21-Apr-15, BLSF.5.2.2.6 Electrical & Fire Fighting
Installation of Conduits 3 01-Apr-15 03-Apr-15 Installation of Conduits
Wiring System 3 06-Apr-15 08-Apr-15 Wiring System
Installation fo Outlets and Switches 3 09-Apr-15 13-Apr-15 Installation fo Outlets and Switches
Installation of Exhuast Fan and Heater 3 14-Apr-15 16-Apr-15 Installation of Exhuast Fan and Heater
Installation of Lightening Protection System 3 17-Apr-15 21-Apr-15 Installation of Lightening Protection System
BLSF.5.2.3 Fire Water Tank (9 m dia meter) 127 27-Nov-14 23-Apr-15 23-Apr-15, BLSF.5.2.3 Fire Water Tank (9 m dia meter)
BLSF.5.2.3.1 Foundations 37 02-Feb-15 16-Mar-15 16-Mar-15, BLSF.5.2.3.1 Foundations
Layout and Excavation 5 02-Feb-15 06-Feb-15 Layout and Excavation
Prepare Sub-Grade 5 05-Feb-15 11-Feb-15 Prepare Sub-Grade
Rebar Cutting, Bending and Fixing of Footings 5 10-Feb-15 16-Feb-15 Rebar Cutting, Bending and Fixing of Footings
Form Works Fixing of Footings 5 13-Feb-15 19-Feb-15 Form Works Fixing of Footings
Concrete Pouring of Footings 2 20-Feb-15 23-Feb-15 Concrete Pouring of Footings
Concrete Curing of Footings 8 23-Feb-15 04-Mar-15 Concrete Curing of Footings
Remove Form Work of Footings 2 23-Feb-15 24-Feb-15 Remove Form Work of Footings
Back Fill 5 25-Feb-15 03-Mar-15 Back Fill
Rebar Cutting, Bending and Fixing of Ring Beam 2 03-Mar-15 04-Mar-15 Rebar Cutting, Bending and Fixing of Ring Beam
Concrete Pouring of Ring Beam 2 04-Mar-15 05-Mar-15 Concrete Pouring of Ring Beam
Concrete Curing of Ring Beam 8 05-Mar-15 16-Mar-15 Concrete Curing of Ring Beam
Form Work Removing of Ring Beam 2 05-Mar-15 07-Mar-15 Form Work Removing of Ring Beam
BLSF.5.2.3.2 Supertructure 17 06-Mar-15 25-Mar-15 25-Mar-15, BLSF.5.2.3.2 Supertructure
Rebar Cutting, Bending and Fixing of External Wall 2 06-Mar-15 09-Mar-15 Rebar Cutting, Bending and Fixing of External Wall
Form Works Fixing of External Wall 2 10-Mar-15 11-Mar-15 Form Works Fixing of External Wall
Concrete Pouring of External Wall 2 12-Mar-15 13-Mar-15 Concrete Pouring of External Wall
Concrete Curing of External Wall 9 13-Mar-15 25-Mar-15 Concrete Curing of External Wall

Actual Work Critical Remaining Work Summary Page 4 of 10 TASK filter: All Activities

Remaining Work Milestone (c) Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish S O N D J F M A M J J A S O N D J F M A M J J A S O
1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 20
Duration
Remove Form Work of External Wall 2 13-Mar-15 16-Mar-15 Remove Form Work of External Wall
Rebar Cutting, Bending and Fixing of Internal Wall 2 06-Mar-15 09-Mar-15 Rebar Cutting, Bending and Fixing of Internal Wall
Concrete Pouring of Internal Wall 2 09-Mar-15 10-Mar-15 Concrete Pouring of Internal Wall
Concrete Curing of Internal Wall 9 10-Mar-15 20-Mar-15 Concrete Curing of Internal Wall
Form Work Removing of Internal Wall 2 10-Mar-15 11-Mar-15 Form Work Removing of Internal Wall
BLSF.5.2.3.4 Mechanical 79 05-Jan-15 06-Apr-15 06-Apr-15, BLSF.5.2.3.4 Mechanical
Fabrication of Tanks & Transport to site 50 05-Jan-15 13-Mar-15 Fabrication of Tanks & Transport to site
Errection of Tanks 10 09-Mar-15 20-Mar-15 Errection of Tanks
Fabrication and Errection of Stail Case 5 18-Mar-15 24-Mar-15 Fabrication and Errection of Stail Case
Installation of Level guage and Nozzels 5 20-Mar-15 26-Mar-15 Installation of Level guage and Nozzels
Installation of Pipes 10 20-Mar-15 02-Apr-15 Installation of Pipes
Applying Paint on Tanks 3 04-Apr-15 06-Apr-15 Applying Paint on Tanks
BLSF.5.2.3.6 Electrical & Fire Fighting 127 27-Nov-14 23-Apr-15 23-Apr-15, BLSF.5.2.3.6 Electrical & Fire Fighting
Installation of Conduits 3 03-Apr-15 07-Apr-15 Installation of Conduits
Wiring System 3 08-Apr-15 10-Apr-15 Wiring System
Installation fo Outlets and Switches 3 13-Apr-15 15-Apr-15 Installation fo Outlets and Switches
Procurement and Installation of Pumps 103 27-Nov-14 20-Apr-15 Procurement and Installation of Pumps
Installation of Lightening Protection System 3 21-Apr-15 23-Apr-15 Installation of Lightening Protection System
BLSF.5.2.4 Slope Tank (3.8 m dia meter) 127 08-Jan-15 04-Jun-15 04-Jun-15, BLSF.5.2.4 Slope Tank (3.8 m dia meter)
BLSF.5.2.4.1 Foundations 37 16-Mar-15 27-Apr-15 27-Apr-15, BLSF.5.2.4.1 Foundations
Layout and Excavation 5 16-Mar-15 20-Mar-15 Layout and Excavation
Prepare Sub-Grade 5 19-Mar-15 25-Mar-15 Prepare Sub-Grade
Rebar Cutting, Bending and Fixing of Footings 5 24-Mar-15 30-Mar-15 Rebar Cutting, Bending and Fixing of Footings
Form Works Fixing of Footings 5 27-Mar-15 02-Apr-15 Form Works Fixing of Footings
Concrete Pouring of Footings 2 03-Apr-15 06-Apr-15 Concrete Pouring of Footings
Concrete Curing of Footings 8 06-Apr-15 15-Apr-15 Concrete Curing of Footings
Remove Form Work of Footings 2 06-Apr-15 07-Apr-15 Remove Form Work of Footings
Back Fill 5 08-Apr-15 14-Apr-15 Back Fill
Rebar Cutting, Bending and Fixing of Ring Beam 2 14-Apr-15 15-Apr-15 Rebar Cutting, Bending and Fixing of Ring Beam
Concrete Pouring of Ring Beam 2 15-Apr-15 16-Apr-15 Concrete Pouring of Ring Beam
Concrete Curing of Ring Beam 8 16-Apr-15 27-Apr-15 Concrete Curing of Ring Beam
Form Work Removing of Ring Beam 2 16-Apr-15 18-Apr-15 Form Work Removing of Ring Beam
BLSF.5.2.4.2 Supertructure 17 17-Apr-15 06-May-15 06-May-15, BLSF.5.2.4.2 Supertructure
Rebar Cutting, Bending and Fixing of External Wall 2 17-Apr-15 20-Apr-15 Rebar Cutting, Bending and Fixing of External Wall
Form Works Fixing of External Wall 2 21-Apr-15 22-Apr-15 Form Works Fixing of External Wall
Concrete Pouring of External Wall 2 23-Apr-15 24-Apr-15 Concrete Pouring of External Wall
Concrete Curing of External Wall 9 24-Apr-15 06-May-15 Concrete Curing of External Wall
Remove Form Work of External Wall 2 24-Apr-15 27-Apr-15 Remove Form Work of External Wall
Rebar Cutting, Bending and Fixing of Internal Wall 2 17-Apr-15 20-Apr-15 Rebar Cutting, Bending and Fixing of Internal Wall
Concrete Pouring of Internal Wall 2 20-Apr-15 21-Apr-15 Concrete Pouring of Internal Wall
Concrete Curing of Internal Wall 9 21-Apr-15 01-May-15 Concrete Curing of Internal Wall
Form Work Removing of Internal Wall 2 21-Apr-15 22-Apr-15 Form Work Removing of Internal Wall
BLSF.5.2.4.4 Mechanical 79 16-Feb-15 18-May-15 18-May-15, BLSF.5.2.4.4 Mechanical
Fabrication of Tanks & Tranport to site 50 16-Feb-15 24-Apr-15 Fabrication of Tanks & Tranport to site
Errection of Tanks 10 20-Apr-15 01-May-15 Errection of Tanks
Fabrication and Errection of Stail Case 5 29-Apr-15 05-May-15 Fabrication and Errection of Stail Case
Installation of Level guage and Nozzels 5 01-May-15 07-May-15 Installation of Level guage and Nozzels
Installation of Pipes 10 01-May-15 14-May-15 Installation of Pipes
Applying Paint on Tanks 3 16-May-15 18-May-15 Applying Paint on Tanks
BLSF.5.2.4.6 Electrical & Fire Fighting 127 08-Jan-15 04-Jun-15 04-Jun-15, BLSF.5.2.4.6 Electrical & Fire Fighting
Installation of Conduits 3 15-May-15 19-May-15 Installation of Conduits
Wiring System 3 20-May-15 22-May-15 Wiring System

Actual Work Critical Remaining Work Summary Page 5 of 10 TASK filter: All Activities

Remaining Work Milestone (c) Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish S O N D J F M A M J J A S O N D J F M A M J J A S O
1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 20
Duration
Installation fo Outlets and Switches 3 25-May-15 27-May-15 Installation fo Outlets and Switches
Procurement and Installation of Pumps 103 08-Jan-15 01-Jun-15 Procurement and Installation of Pumps
Installation of Lightening Protection System 3 02-Jun-15 04-Jun-15 Installation of Lightening Protection System
BLSF.5.3 Facilities 415 20-Mar-14 17-Jul-15 17-Jul-15, BLSF.5.3 Facilities
BLSF.5.3.1 Administration Block 119 20-Mar-14 05-Aug-14 05-Aug-14, BLSF.5.3.1 Administration Block
BLSF.5.3.1.1 Foundations 55 20-Mar-14 23-May-14 23-May-14, BLSF.5.3.1.1 Foundations
Layout and Excavation 7 20-Mar-14 28-Mar-14 Layout and Excavation
Prepare Sub-Grade 2 31-Mar-14 01-Apr-14 Prepare Sub-Grade
Rebar Cutting, Bending and Fixing of Footings 7 02-Apr-14 10-Apr-14 Rebar Cutting, Bending and Fixing of Footings
Form Works Fixing of Footings 5 10-Apr-14 16-Apr-14 Form Works Fixing of Footings
Concrete Pouring of Footings 2 17-Apr-14 18-Apr-14 Concrete Pouring of Footings
Concrete Curing of Footings 9 21-Apr-14 01-May-14 Concrete Curing of Footings
Remove Form Work of Footings 2 21-Apr-14 22-Apr-14 Remove Form Work of Footings
Block Masonary (CMU) 3 23-Apr-14 25-Apr-14 Block Masonary (CMU)
Back Fill 4 25-Apr-14 30-Apr-14 Back Fill
Prepare Sub-Grade of SOG 2 30-Apr-14 01-May-14 Prepare Sub-Grade of SOG
Capillary Water Barrier 3 01-May-14 05-May-14 Capillary Water Barrier
Rebar Cutting, Bending and Fixing of SOG 5 05-May-14 09-May-14 Rebar Cutting, Bending and Fixing of SOG
Concrete Pouring of SOG 2 12-May-14 13-May-14 Concrete Pouring of SOG
Concrete Curing of SOG 8 14-May-14 23-May-14 Concrete Curing of SOG
BLSF.5.3.1.2 Supertructure 26 14-May-14 13-Jun-14 13-Jun-14, BLSF.5.3.1.2 Supertructure
Concrete Masonary unit (CMU) Wall 3 14-May-14 16-May-14 Concrete Masonary unit (CMU) Wall
Lintle Beams 1 16-May-14 16-May-14 Lintle Beams
Bond Beams 2 19-May-14 20-May-14 Bond Beams
Form Work Roof Slab 2 21-May-14 22-May-14 Form Work Roof Slab
Rebar Cutting, Bending & Fixing Roof Slab 2 22-May-14 23-May-14 Rebar Cutting, Bending & Fixing Roof Slab
Concrete Pouring Roof Slab 1 26-May-14 26-May-14 Concrete Pouring Roof Slab
Concrete Curing Roof Slab 7 27-May-14 04-Jun-14 Concrete Curing Roof Slab
Remove Form Work 14 27-May-14 13-Jun-14 Remove Form Work
CMU Work Above Roof Slab 1 27-May-14 27-May-14 CMU Work Above Roof Slab
BLSF.5.3.1.3 Atchitectural 39 16-Jun-14 30-Jul-14 30-Jul-14, BLSF.5.3.1.3 Atchitectural
Plaster Work Internal Walls & Ceiling 10 16-Jun-14 27-Jun-14 Plaster Work Internal Walls & Ceiling
Rigid Insulation 5 26-Jun-14 02-Jul-14 Rigid Insulation
Stucco on External Wall 5 03-Jul-14 09-Jul-14 Stucco on External Wall
Paint Internal Walls and Ceiling 15 10-Jul-14 30-Jul-14 Paint Internal Walls and Ceiling
BLSF.5.3.1.4 Mechanical 34 06-Jun-14 15-Jul-14 15-Jul-14, BLSF.5.3.1.4 Mechanical
Fixing of Roof Truss 10 06-Jun-14 19-Jun-14 Fixing of Roof Truss
Fixing of sheets & Insulation 5 20-Jun-14 26-Jun-14 Fixing of sheets & Insulation
Fixing of Gutter and Down Spout 2 26-Jun-14 27-Jun-14 Fixing of Gutter and Down Spout
Fixing of Doors 5 30-Jun-14 04-Jul-14 Fixing of Doors
Fixing of Windows 5 07-Jul-14 11-Jul-14 Fixing of Windows
Fixing fo Roof Hatch & Laouvers 2 14-Jul-14 15-Jul-14 Fixing fo Roof Hatch & Laouvers
BLSF.5.3.1.5 Plumbing 24 09-Jul-14 05-Aug-14 05-Aug-14, BLSF.5.3.1.5 Plumbing
Internal Plumbing Works 10 09-Jul-14 22-Jul-14 Internal Plumbing Works
External Plumbing Works 10 23-Jul-14 05-Aug-14 External Plumbing Works
BLSF.5.3.1.6 Electrical 38 26-May-14 08-Jul-14 08-Jul-14, BLSF.5.3.1.6 Electrical
Installation of Conduits 2 26-May-14 27-May-14 Installation of Conduits
Wiring System 2 25-Jun-14 26-Jun-14 Wiring System
Installation fo Outlets and Switches 2 27-Jun-14 30-Jun-14 Installation fo Outlets and Switches
Installation of Exhuast Fan and Heater 1 01-Jul-14 01-Jul-14 Installation of Exhuast Fan and Heater
Installation of Lightening Protection System 5 02-Jul-14 08-Jul-14 Installation of Lightening Protection System
BLSF.5.3.2 Power House 106 14-Aug-14 15-Dec-14 15-Dec-14, BLSF.5.3.2 Power House
BLSF.5.3.2.1 Foundations 43 14-Aug-14 02-Oct-14 02-Oct-14, BLSF.5.3.2.1 Foundations

Actual Work Critical Remaining Work Summary Page 6 of 10 TASK filter: All Activities

Remaining Work Milestone (c) Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish S O N D J F M A M J J A S O N D J F M A M J J A S O
1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 20
Duration
Layout and Excavation 5 14-Aug-14 20-Aug-14 Layout and Excavation
Prepare Sub-Grade 2 21-Aug-14 22-Aug-14 Prepare Sub-Grade
Rebar Cutting, Bending and Fixing of Footings 3 25-Aug-14 27-Aug-14 Rebar Cutting, Bending and Fixing of Footings
Form Works Fixing of Footings 3 27-Aug-14 29-Aug-14 Form Works Fixing of Footings
Concrete Pouring of Footings 2 01-Sep-14 02-Sep-14 Concrete Pouring of Footings
Concrete Curing of Footings 8 03-Sep-14 12-Sep-14 Concrete Curing of Footings
Remove Form Work of Footings 2 03-Sep-14 04-Sep-14 Remove Form Work of Footings
Back Fill 3 09-Sep-14 11-Sep-14 Back Fill
Prepare Sub-Grade of SOG 2 11-Sep-14 12-Sep-14 Prepare Sub-Grade of SOG
Capillary Water Barrier 3 12-Sep-14 16-Sep-14 Capillary Water Barrier
Rebar Cutting, Bending and Fixing of SOG 3 16-Sep-14 18-Sep-14 Rebar Cutting, Bending and Fixing of SOG
Concrete Pouring of SOG 2 19-Sep-14 22-Sep-14 Concrete Pouring of SOG
Concrete Curing of SOG 8 23-Sep-14 02-Oct-14 Concrete Curing of SOG
Block Masonary (CMU) 3 05-Sep-14 09-Sep-14 Block Masonary (CMU)
BLSF.5.3.2.2 Supertructure 30 23-Sep-14 27-Oct-14 27-Oct-14, BLSF.5.3.2.2 Supertructure
Concrete Masonary unit (CMU) Wall 5 23-Sep-14 29-Sep-14 Concrete Masonary unit (CMU) Wall
Lintle Beams 2 29-Sep-14 30-Sep-14 Lintle Beams
Bond Beams 2 30-Sep-14 01-Oct-14 Bond Beams
Form Work Roof Slab 2 02-Oct-14 03-Oct-14 Form Work Roof Slab
Rebar Cutting, Bending & Fixing Roof Slab 2 03-Oct-14 06-Oct-14 Rebar Cutting, Bending & Fixing Roof Slab
Concrete Pouring Roof Slab 1 07-Oct-14 07-Oct-14 Concrete Pouring Roof Slab
Concrete Curing Roof Slab 7 08-Oct-14 16-Oct-14 Concrete Curing Roof Slab
Remove Form Work 14 08-Oct-14 27-Oct-14 Remove Form Work
CMU Work Above Roof Slab 1 08-Oct-14 08-Oct-14 CMU Work Above Roof Slab
BLSF.5.3.2.3 Atchitectural 19 28-Oct-14 18-Nov-14 18-Nov-14, BLSF.5.3.2.3 Atchitectural
Plaster Work Internal Walls & Ceiling 5 28-Oct-14 03-Nov-14 Plaster Work Internal Walls & Ceiling
Rigid Insulation 3 31-Oct-14 04-Nov-14 Rigid Insulation
Stucco on External Wall 3 05-Nov-14 07-Nov-14 Stucco on External Wall
Paint Internal Walls and Ceiling 7 10-Nov-14 18-Nov-14 Paint Internal Walls and Ceiling
BLSF.5.3.2.4 Mechanical 22 20-Oct-14 13-Nov-14 13-Nov-14, BLSF.5.3.2.4 Mechanical
Fixing of Roof Truss 7 20-Oct-14 28-Oct-14 Fixing of Roof Truss
Fixing of sheets & Insulation 4 29-Oct-14 03-Nov-14 Fixing of sheets & Insulation
Fixing of Gutter and Down Spout 1 03-Nov-14 03-Nov-14 Fixing of Gutter and Down Spout
Fixing of Doors 3 04-Nov-14 06-Nov-14 Fixing of Doors
Fixing of Windows 3 07-Nov-14 11-Nov-14 Fixing of Windows
Fixing fo Roof Hatch & Laouvers 2 12-Nov-14 13-Nov-14 Fixing fo Roof Hatch & Laouvers
BLSF.5.3.2.6 Electrical 60 07-Oct-14 15-Dec-14 15-Dec-14, BLSF.5.3.2.6 Electrical
Installation of Conduits 5 07-Oct-14 13-Oct-14 Installation of Conduits
Wiring System 5 11-Nov-14 17-Nov-14 Wiring System
Installation fo Outlets and Switches 5 18-Nov-14 24-Nov-14 Installation fo Outlets and Switches
Installation of Exhuast Fan and Heater 5 25-Nov-14 01-Dec-14 Installation of Exhuast Fan and Heater
Installation of Lightening Protection System 10 02-Dec-14 15-Dec-14 Installation of Lightening Protection System
BLSF.5.3.3 Pump Station 62 19-Nov-14 30-Jan-15 30-Jan-15, BLSF.5.3.3 Pump Station
BLSF.5.3.3.1 Foundations 24 19-Nov-14 16-Dec-14 16-Dec-14, BLSF.5.3.3.1 Foundations
Layout and Excavation 1 19-Nov-14 19-Nov-14 Layout and Excavation
Prepare Sub-Grade 1 20-Nov-14 20-Nov-14 Prepare Sub-Grade
Rebar Cutting, Bending and Fixing of Footings 2 21-Nov-14 24-Nov-14 Rebar Cutting, Bending and Fixing of Footings
Form Works Fixing of Footings 2 24-Nov-14 25-Nov-14 Form Works Fixing of Footings
Concrete Pouring of Footings 1 26-Nov-14 26-Nov-14 Concrete Pouring of Footings
Concrete Curing of Footings 7 27-Nov-14 05-Dec-14 Concrete Curing of Footings
Remove Form Work of Footings 1 27-Nov-14 27-Nov-14 Remove Form Work of Footings
Back Fill 2 01-Dec-14 02-Dec-14 Back Fill

Actual Work Critical Remaining Work Summary Page 7 of 10 TASK filter: All Activities

Remaining Work Milestone (c) Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish S O N D J F M A M J J A S O N D J F M A M J J A S O
1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 20
Duration
Prepare Sub-Grade of SOG 1 02-Dec-14 02-Dec-14 Prepare Sub-Grade of SOG
Capillary Water Barrier 2 02-Dec-14 03-Dec-14 Capillary Water Barrier
Rebar Cutting, Bending and Fixing of SOG 2 03-Dec-14 04-Dec-14 Rebar Cutting, Bending and Fixing of SOG
Concrete Pouring of SOG 1 05-Dec-14 05-Dec-14 Concrete Pouring of SOG
Concrete Curing of SOG 7 08-Dec-14 16-Dec-14 Concrete Curing of SOG
Block Masonary (CMU) 2 28-Nov-14 01-Dec-14 Block Masonary (CMU)
BLSF.5.3.3.2 Supertructure 27 08-Dec-14 07-Jan-15 07-Jan-15, BLSF.5.3.3.2 Supertructure
Concrete Masonary unit (CMU) Wall 3 08-Dec-14 10-Dec-14 Concrete Masonary unit (CMU) Wall
Lintle Beams 1 10-Dec-14 10-Dec-14 Lintle Beams
Bond Beams 2 11-Dec-14 12-Dec-14 Bond Beams
Form Work Roof Slab 2 15-Dec-14 16-Dec-14 Form Work Roof Slab
Rebar Cutting, Bending & Fixing Roof Slab 2 16-Dec-14 17-Dec-14 Rebar Cutting, Bending & Fixing Roof Slab
Concrete Pouring Roof Slab 1 18-Dec-14 18-Dec-14 Concrete Pouring Roof Slab
Concrete Curing Roof Slab 7 19-Dec-14 29-Dec-14 Concrete Curing Roof Slab
Remove Form Work 14 19-Dec-14 07-Jan-15 Remove Form Work
CMU Work Above Roof Slab 1 19-Dec-14 19-Dec-14 CMU Work Above Roof Slab
BLSF.5.3.3.3 Atchitectural 7 08-Jan-15 15-Jan-15 15-Jan-15, BLSF.5.3.3.3 Atchitectural
Plaster Work Internal Walls & Ceiling 2 08-Jan-15 09-Jan-15 Plaster Work Internal Walls & Ceiling
Rigid Insulation 2 08-Jan-15 09-Jan-15 Rigid Insulation
Stucco on External Wall 2 12-Jan-15 13-Jan-15 Stucco on External Wall
Paint Internal Walls and Ceiling 2 14-Jan-15 15-Jan-15 Paint Internal Walls and Ceiling
BLSF.5.3.3.4 Mechanical 20 31-Dec-14 22-Jan-15 22-Jan-15, BLSF.5.3.3.4 Mechanical
Fixing of Roof Truss 10 31-Dec-14 13-Jan-15 Fixing of Roof Truss
Fixing of sheets & Insulation 2 14-Jan-15 15-Jan-15 Fixing of sheets & Insulation
Fixing of Gutter and Down Spout 1 15-Jan-15 15-Jan-15 Fixing of Gutter and Down Spout
Fixing of Doors 2 16-Jan-15 19-Jan-15 Fixing of Doors
Fixing of Windows 2 20-Jan-15 21-Jan-15 Fixing of Windows
Fixing fo Roof Hatch & Laouvers 1 22-Jan-15 22-Jan-15 Fixing fo Roof Hatch & Laouvers
BLSF.5.3.3.6 Electrical 37 18-Dec-14 30-Jan-15 30-Jan-15, BLSF.5.3.3.6 Electrical
Installation of Conduits 2 18-Dec-14 19-Dec-14 Installation of Conduits
Wiring System 2 19-Jan-15 20-Jan-15 Wiring System
Installation fo Outlets and Switches 2 21-Jan-15 22-Jan-15 Installation fo Outlets and Switches
Installation of Pumps 1 23-Jan-15 23-Jan-15 Installation of Pumps
Installation of Lightening Protection System 5 26-Jan-15 30-Jan-15 Installation of Lightening Protection System
BLSF.5.3.4 Well House 64 16-Jan-15 31-Mar-15 31-Mar-15, BLSF.5.3.4 Well House
BLSF.5.3.4.1 Foundations 24 16-Jan-15 12-Feb-15 12-Feb-15, BLSF.5.3.4.1 Foundations
Layout and Excavation 1 16-Jan-15 16-Jan-15 Layout and Excavation
Prepare Sub-Grade 1 19-Jan-15 19-Jan-15 Prepare Sub-Grade
Rebar Cutting, Bending and Fixing of Footings 2 20-Jan-15 21-Jan-15 Rebar Cutting, Bending and Fixing of Footings
Form Works Fixing of Footings 2 21-Jan-15 22-Jan-15 Form Works Fixing of Footings
Concrete Pouring of Footings 1 23-Jan-15 23-Jan-15 Concrete Pouring of Footings
Concrete Curing of Footings 7 26-Jan-15 03-Feb-15 Concrete Curing of Footings
Remove Form Work of Footings 1 26-Jan-15 26-Jan-15 Remove Form Work of Footings
Back Fill 2 28-Jan-15 29-Jan-15 Back Fill
Prepare Sub-Grade of SOG 1 29-Jan-15 29-Jan-15 Prepare Sub-Grade of SOG
Capillary Water Barrier 2 29-Jan-15 30-Jan-15 Capillary Water Barrier
Rebar Cutting, Bending and Fixing of SOG 2 30-Jan-15 02-Feb-15 Rebar Cutting, Bending and Fixing of SOG
Concrete Pouring of SOG 1 03-Feb-15 03-Feb-15 Concrete Pouring of SOG
Concrete Curing of SOG 7 04-Feb-15 12-Feb-15 Concrete Curing of SOG
Block Masonary (CMU) 2 27-Jan-15 28-Jan-15 Block Masonary (CMU)
BLSF.5.3.4.2 Supertructure 26 04-Feb-15 06-Mar-15 06-Mar-15, BLSF.5.3.4.2 Supertructure
Concrete Masonary unit (CMU) Wall 3 04-Feb-15 06-Feb-15 Concrete Masonary unit (CMU) Wall

Actual Work Critical Remaining Work Summary Page 8 of 10 TASK filter: All Activities

Remaining Work Milestone (c) Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish S O N D J F M A M J J A S O N D J F M A M J J A S O
1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 20
Duration
Lintle Beams 1 06-Feb-15 06-Feb-15 Lintle Beams
Bond Beams 2 09-Feb-15 10-Feb-15 Bond Beams
Form Work Roof Slab 2 11-Feb-15 12-Feb-15 Form Work Roof Slab
Rebar Cutting, Bending & Fixing Roof Slab 2 12-Feb-15 13-Feb-15 Rebar Cutting, Bending & Fixing Roof Slab
Concrete Pouring Roof Slab 1 16-Feb-15 16-Feb-15 Concrete Pouring Roof Slab
Concrete Curing Roof Slab 7 17-Feb-15 25-Feb-15 Concrete Curing Roof Slab
Remove Form Work 14 17-Feb-15 06-Mar-15 Remove Form Work
CMU Work Above Roof Slab 1 17-Feb-15 17-Feb-15 CMU Work Above Roof Slab
BLSF.5.3.4.3 Atchitectural 7 09-Mar-15 16-Mar-15 16-Mar-15, BLSF.5.3.4.3 Atchitectural
Plaster Work Internal Walls & Ceiling 2 09-Mar-15 10-Mar-15 Plaster Work Internal Walls & Ceiling
Rigid Insulation 2 09-Mar-15 10-Mar-15 Rigid Insulation
Stucco on External Wall 2 11-Mar-15 12-Mar-15 Stucco on External Wall
Paint Internal Walls and Ceiling 2 13-Mar-15 16-Mar-15 Paint Internal Walls and Ceiling
BLSF.5.3.4.4 Mechanical 21 27-Feb-15 23-Mar-15 23-Mar-15, BLSF.5.3.4.4 Mechanical
Fixing of Roof Truss 10 27-Feb-15 12-Mar-15 Fixing of Roof Truss
Fixing of sheets & Insulation 2 13-Mar-15 16-Mar-15 Fixing of sheets & Insulation
Fixing of Gutter and Down Spout 1 16-Mar-15 16-Mar-15 Fixing of Gutter and Down Spout
Fixing of Doors 2 17-Mar-15 18-Mar-15 Fixing of Doors
Fixing of Windows 2 19-Mar-15 20-Mar-15 Fixing of Windows
Fixing fo Roof Hatch & Laouvers 1 23-Mar-15 23-Mar-15 Fixing fo Roof Hatch & Laouvers
BLSF.5.3.4.5 Plumbing 12 17-Mar-15 30-Mar-15 30-Mar-15, BLSF.5.3.4.5 Plumbing
Clorination System 5 17-Mar-15 23-Mar-15 Clorination System
Water Disribution System 5 24-Mar-15 30-Mar-15 Water Disribution System
BLSF.5.3.4.6 Electrical 38 16-Feb-15 31-Mar-15 31-Mar-15, BLSF.5.3.4.6 Electrical
Installation of Conduits 2 16-Feb-15 17-Feb-15 Installation of Conduits
Wiring System 2 18-Mar-15 19-Mar-15 Wiring System
Installation fo Outlets and Switches 2 20-Mar-15 23-Mar-15 Installation fo Outlets and Switches
Installation of Exhuast Fan and Heater 1 24-Mar-15 24-Mar-15 Installation of Exhuast Fan and Heater
Installation of Lightening Protection System 5 25-Mar-15 31-Mar-15 Installation of Lightening Protection System
BLSF.5.3.5 Bunk Pit 99 24-Mar-15 17-Jul-15 17-Jul-15, BLSF.5.3.5 Bunk Pit
BLSF.5.3.5.1 Foundations 24 24-Mar-15 20-Apr-15 20-Apr-15, BLSF.5.3.5.1 Foundations
Layout and Excavation 1 24-Mar-15 24-Mar-15 Layout and Excavation
Prepare Sub-Grade 1 25-Mar-15 25-Mar-15 Prepare Sub-Grade
Rebar Cutting, Bending and Fixing of Footings 2 26-Mar-15 27-Mar-15 Rebar Cutting, Bending and Fixing of Footings
Form Works Fixing of Footings 2 27-Mar-15 30-Mar-15 Form Works Fixing of Footings
Concrete Pouring of Footings 1 31-Mar-15 31-Mar-15 Concrete Pouring of Footings
Concrete Curing of Footings 7 01-Apr-15 09-Apr-15 Concrete Curing of Footings
Remove Form Work of Footings 1 01-Apr-15 01-Apr-15 Remove Form Work of Footings
Back Fill 2 03-Apr-15 06-Apr-15 Back Fill
Prepare Sub-Grade of SOG 1 06-Apr-15 06-Apr-15 Prepare Sub-Grade of SOG
Capillary Water Barrier 2 06-Apr-15 07-Apr-15 Capillary Water Barrier
Rebar Cutting, Bending and Fixing of SOG 2 07-Apr-15 08-Apr-15 Rebar Cutting, Bending and Fixing of SOG
Concrete Pouring of SOG 1 09-Apr-15 09-Apr-15 Concrete Pouring of SOG
Concrete Curing of SOG 7 10-Apr-15 20-Apr-15 Concrete Curing of SOG
Block Masonary (CMU) 2 02-Apr-15 03-Apr-15 Block Masonary (CMU)
BLSF.5.3.5.2 Supertructure 28 10-Apr-15 12-May-15 12-May-15, BLSF.5.3.5.2 Supertructure
Concrete Masonary unit (CMU) Wall 3 10-Apr-15 14-Apr-15 Concrete Masonary unit (CMU) Wall
Lintle Beams 1 14-Apr-15 14-Apr-15 Lintle Beams
Bond Beams 2 15-Apr-15 16-Apr-15 Bond Beams
Form Work Roof Slab 2 17-Apr-15 20-Apr-15 Form Work Roof Slab
Rebar Cutting, Bending & Fixing Roof Slab 2 20-Apr-15 21-Apr-15 Rebar Cutting, Bending & Fixing Roof Slab
Concrete Pouring Roof Slab 1 22-Apr-15 22-Apr-15 Concrete Pouring Roof Slab

Actual Work Critical Remaining Work Summary Page 9 of 10 TASK filter: All Activities

Remaining Work Milestone (c) Primavera Systems, Inc.


Activity ID Activity Name Original Start Finish S O N D J F M A M J J A S O N D J F M A M J J A S O
1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 20
Duration
Concrete Curing Roof Slab 7 23-Apr-15 01-May-15 Concrete Curing Roof Slab
Remove Form Work 14 23-Apr-15 12-May-15 Remove Form Work
CMU Work Above Roof Slab 1 23-Apr-15 23-Apr-15 CMU Work Above Roof Slab
BLSF.5.3.5.3 Atchitectural 7 13-May-15 20-May-15 20-May-15, BLSF.5.3.5.3 Atchitectural
Plaster Work Internal Walls & Ceiling 2 13-May-15 14-May-15 Plaster Work Internal Walls & Ceiling
Rigid Insulation 2 13-May-15 14-May-15 Rigid Insulation
Stucco on External Wall 2 15-May-15 18-May-15 Stucco on External Wall
Paint Internal Walls and Ceiling 2 19-May-15 20-May-15 Paint Internal Walls and Ceiling
BLSF.5.3.5.4 Mechanical 20 05-May-15 27-May-15 27-May-15, BLSF.5.3.5.4 Mechanical
Fixing of Roof Truss 10 05-May-15 18-May-15 Fixing of Roof Truss
Fixing of sheets & Insulation 2 19-May-15 20-May-15 Fixing of sheets & Insulation
Fixing of Gutter and Down Spout 1 20-May-15 20-May-15 Fixing of Gutter and Down Spout
Fixing of Doors 2 21-May-15 22-May-15 Fixing of Doors
Fixing of Windows 2 25-May-15 26-May-15 Fixing of Windows
Fixing fo Roof Hatch & Laouvers 1 27-May-15 27-May-15 Fixing fo Roof Hatch & Laouvers
BLSF.5.3.5.5 Plumbing 12 21-May-15 03-Jun-15 03-Jun-15, BLSF.5.3.5.5 Plumbing
Clorination System 5 21-May-15 27-May-15 Clorination System
Water Disribution System 5 28-May-15 03-Jun-15 Water Disribution System
BLSF.5.3.5.6 Electrical 37 04-Jun-15 17-Jul-15 17-Jul-15, BLSF.5.3.5.6 Electrical
Installation of Conduits 2 04-Jun-15 05-Jun-15 Installation of Conduits
Wiring System 2 06-Jul-15 07-Jul-15 Wiring System
Installation fo Outlets and Switches 2 08-Jul-15 09-Jul-15 Installation fo Outlets and Switches
Installation of Exhuast Fan and Heater 1 10-Jul-15 10-Jul-15 Installation of Exhuast Fan and Heater
Installation of Lightening Protection System 5 13-Jul-15 17-Jul-15 Installation of Lightening Protection System

BLSF.6 Close Out 55 18-Jul-15 19-Sep-15 19-Sep-15, BLSF.6 Cl

BLSF.6.1 Close out Inspections 10 18-Jul-15 28-Jul-15 28-Jul-15, BLSF.6.1 Close out Inspec
Close out Inspection 10 18-Jul-15 28-Jul-15 Close out Inspection
BLSF.6.2 Inspection and Punch List 20 29-Jul-15 20-Aug-15 20-Aug-15, BLSF.6.2 Inspectio
Inspection and Punch List 20 29-Jul-15 20-Aug-15 Inspection and Punch List
BLSF.6.3 As Built Drawings 10 22-Aug-15 01-Sep-15 01-Sep-15, BLSF.6.3 As Bu
As-Built Drawings 10 22-Aug-15 01-Sep-15 As-Built Drawings
BLSF.6.4 Demobilization 15 02-Sep-15 19-Sep-15 19-Sep-15, BLSF.6.4
De-Mobilization form Site 15 02-Sep-15 19-Sep-15 De-Mobilization form S

Actual Work Critical Remaining Work Summary Page 10 of 10 TASK filter: All Activities

Remaining Work Milestone (c) Primavera Systems, Inc.