PHASE 2

date w.o.n description remarks


19/3/2023-20/3/2023 To perform gamma ray 18” phase 2
(one day valid) area
17/3/2023-18/3/2023 To perform gamma ray 18” phase 2
(one day valid) area
18/3/2023-20/3/2023 Welding fabrication,installation of 18”new pipe Attach isolation cert,TRA,TRA
line for water injection phase 2 line project work sheet,TPT,TPT name form

22/3/2023-28/3/2023 To perform sand blasting,pipe wrapping of 18” Attach isolation cert,TRA,TRA


new pipeline for water injection Phase2 project work sheet,TPT,TPT name form

19/3/23-25/3/2023 Excavation work at phase 2 area


21/3/23-27/3/23 Form works /shuttering block works,concreting
at water injection Phase-2 line project

MANIFOLD AREA/OIL CENTER


23/3/2023-29/3/2023 C.22/23 To excavate by hand at manifold area/oil
center for water injection phase 2,part 2

POWER STATION AREA


19/3/2023-25/3/2023 To lift and remove PSV for calibration at power
station area /skid/S5/compressor area(re install after
calibration)
19/3/2023-25/3/2023 To install end flange/blind flange and isolate PSV/TSV Attach isolation cert,TRA,TRA
for removal located at skid/S5 tank/power station work sheet,TPT,TPT name
compressor area form

20/3/2023-22/3/2023 To remove scaffolding at S5 tank/power


station area
20/3/23-26/3/23 To repair damaged road between oil center
Gas heater area and power station

WATER INJECTION
17/3/2023-23/3/2023 To install end flange/blind flange to PSV/TSV for
isolation and removal located at water injection area
17/3/2023-23/3/2023 To remove PSV/TSV for maintenance and
recalibration at water injection area(re install after
calibration)
11/3/23-17/3/23 To install insulation on 8”&6”water
(7 days)(done) injection flow line near phase2
11/3/23-13/3/23 To erect scaffolding at water injection (tool box talk&name
well 2 list)

GAS HEATER
To repair damaged road between oil
20/3/2023-26/3/2023 center Gas heater area and power station
area

M2 A-8 AND A41


Welding ,repair, installation New 16 “ M2 Attach isolation cert,TRA,TRA
9/3/2023-11/3/2023 work sheet,TPT,TPT name list
(3 days) (done) flowline location between A-8&A41
11/3/23-17/3/23 Backfilling at 16” new flow line of M2
between A8 & A41
done To perform excavation on 16” leak M2
flow line pipe location A8 & A41

M1 MANIFOLD
16/3/2023-18/3/2023 Welding repair installation of new 8” Attach TRA,TRAwork
sheet,TPTR,TPTR name list
A27 flow line M1 manifold area
Attach isolation cert,TRA,TRA
10/3/2023-16/3/2023 Cold cutting Of 8” leak flow line M1 work sheet,TPT,TPT name
(done) manifold area A-29 form
Welding and connection of new 8” pipe for Attach isolation cert,TRA,TRA
12/3/2023-14/3/2023 work sheet,TPT,TPT name
(done) A29 flow line at M1 manifold area form
17/3/2023-18/3/2023 To Perform Gamma ray on 8” new weld
(one day valid) joint for A27 line at M1 manifold area

17/3/23-23/3/23 To pipe wrapping at M1 manifold area for


A27 line 8”pipe
MTCE&GESE OIL CENTER,SEPARETOR,
19/3/23-25/3/23 Ceramic tile installation,concreting at
oil center,rest room area
5/3/23-11/3/23 Demolise floor,discover leak
(done) line,replace new one at oil center

SEPARETOR
603
Attach isolation
6/3/2023-12/3/23 013/2023 Remove blind disc,de isolate cert,TRA,TRA work sheet,
(7days) (done) closing manhole s.603
6/3/2023-12/3/23 Closing of man hole,remove blind disk
(done) and deisolate seperetor S 603
8/3/2023-to 15 days Seperator S 603
18/3/23-24/3/23 Pipe install&insulation pipe in
(done) installation work at separator S.603
area
18/3/23-24/3/23 Water filling at separator S.603
Attach isolation
14/3/2023-20/3/2023 To remove blind disc and de cert,TRA,TRA work sheet,
(done) isolate separators S603 name list
17/3/2023-19/3/2023 To remove scaffolding at meter
(done) prover area/oil center

MTCE A50
Attach isolation cert,TRA,TRA
11/3/2023-13/3/2023 Welding connection of 8”flow line for work sheet,TPT,TPT name
(done) oil well A50 form

11/3/23-17/3/23 To perform excavation at oil well A50 Attach in(excavation


Map)
(7days) (done) area
9/3/23-15/3/2023 Transport & lay down of pips &materials for Tool box talk&name
oil well A50 /bolt&installation list attach
14/3/2023-16/3/2023 Welding and repair at new 8”flow line pipe TPT,TRA attach
(done) for A50
15/3/2023-15/3/2023 To perform gamma ray for 8” new pipe weld
(done) joint located at oil well A50
14/3/23-20/3/23 Pipe wrapping and backfilling of new 8”
(done) flowline pipe located at oil well A50

NGL ,WAREHOUSE,MTCE&GESE
19/3/2023-25/3/2023 Water mixing of caliche,ground leveling new
warehouse beside NGL plant
5/3/2023-11/3/2023 Ground leveling mixing calichie new ware
(done) house beside ngl plant area
13/3/2023-19/3/2023 To lift remove and transport old container
(done) located near R.O trailers /NGL plant area (For Attach TRA&TPT
transport to rai camp for repair)
15/3/23-21/3/23 To put sealant/epoxy on plastic RO tank TRA&TPT
located at NGL

GAS PLANT
Open bolts ,lift and P7 tank located at gas
13/3/2023-14/3/2023 plant area ,transport to rai camp for cleaning Attach TRA&TPT
inspection
(done)
14/3/2023-20/3/2023 To remove liquid contents of P7 tank by
(done) vaccum
17/3/23-23/3/2023 Lifting and installation of condensate tank P7
gas plant area

ACCOMENDATION MELLITAH,MILITTARY(CAMP)
MTCE Welding fabrication ,installation of new
20/3/2023-22/3/2023 23/26 inlet/outlet 8”water pipe flow line at staff Attach TRA&TPT
1&staff2
9/3/2023/-15/3/23 To install water heater for MOG mess
(done) hall &accomontation area
10/03/2023-16/3/2023 New concrete floor between bathroom
(done) &mess hall for military camp
17/3/2023-23/3/2023 To perform block works and concreting at
Staff2 area/accomendation
20/3/23-22/3/23 To erect scaffolding at football field
(3 days) area/accomendation

18/3/23-24/3/23 To insert blind disc and isolate 6”&4” water


line at staff-2 area(accomendation)
21/3/23-27/3/23 Water line,plumbing repair at MOG-mess
hall/accomendation(for washer equipment
21/3/23-27/3/23 Sand leveling,block works,concreting for new
trailer located back of swimming
pool/accomendation area
17/3/2023-23/3/2023 To constract new concrete floor between
bathroom&mess hall for military camp

PRODUCED WATER ,FT2,API AREA


12/3/2023-18/3/2023 Painting inside filter tank-A/produced
(done) water area
14/3/23-20/3/23 To reinstall sight glass/level
(done) class,instruements PSV,closing of man hole
for filter Tank-A/producd water area
14/3/23-20/3/23 To reinstall pipes and systems,loading of
(done) media filters for nutshell filter Tank
A/produced water area
22/3/23-24/3/23 To remove scaffolding at inside /outside filter
Tank-A located at produced water area
19/3/23-25/3/23 To remove insulation on 3”&4”leak steam
pipe back of API area/near filter tank A
produced water area
21/3/23-27/3/23 To lift and remove PSV/TSV for calibration at
produced water area
21/3/23-27/3/23 To install end flange/blind flange onPSV/TSV TRA,TPT,
for calibration at produced water
22/3/23-28/3/23 Cleaning,inspection & closing manhole

FT2
14/3/23-20/3/23 MTCE To install insulation on 3/4 &1/2 steam
done 23-022 line for FT2 line near API area TRA,TPT attach
19/3/23-25/3/23 To remove insulation on 8” leak pipe at
FT 2 near API area

AUXILARY AREA
23/3/2023-29/3/2023 To re install metal sheet walling for fire
fighting/auxiliary area
23/3/2023-25/3/2023 To erect scaffolding at fire
(scaffold)3 days fighting/auxiliary area(after remove)

RO PLANT ,WATER TREATMENT


15/3/23-21/3/23 Mtce To remove media filters,bed layers and Attach confined
23/025 systems of media filter MM10 at RO space,isolation
plant/auxilury plant area-water treatment
15/3/2023-21/3/2023 To perform internal cleaning and inspection of
media filter MM10 located at RO
plant/auxilury plant area
18/3/23-24/3/21 To install blind disc and isolate media filter
MM11&12 at RO plant/opening of manhole for
ventilation located at internal treatment area
20/3/23-26/3/23 To remove media filter,internal cleaning and
inspection of media filter tank MM12/water
treatment area-RO plant
18/3/23-20/3/21 Welding & repair work at media filtter
MM11&MM12 tank at RO plant area
TPS NGL
18/3/23-24/3/23 To install end flange /blind flange&isolate Attach isolation
PSV/TSV for removal at TPS 11&12 near NGL
plant
18/3/23-24/3/23 To lift and remove PSV/TSV at TPS 11&12 for isolation ,TRA,TPT
calibration /located near NGL plant(Re install attach
after calibration)
21/4/23-23/3/23 To erect at scaffold TPS 11&12 near NGL plant
area(remove after Psv/Tsv installation)

BOILER#3 WATER TREATMENT


20/3/23-22/3/23 23/035 To erect scaffolding at boiler*3/water
treatment area
20/3/23-22/3/23 To remove insulation at boiler *3/water
treatment area (pipe and system)reinstall after
20/3/23-22/3/23 To insert blind disc and isolate boiler *3/water
treatment area opening of manhole for
ventilation(front and back)
21/3/23-27/3/23 To remove PSV of boiler *3 for calibration and TRA,TPT
repair re install after calibration
21/3/23-27/3/23 Internal cleaning and inspection of boiler*3 TRA,TPT
located at water treatment area
21/3/23-27/3/23 To lift and remove PSV/TSV for calibration at TRA
produced water area re install after calipration
21/3/23-27/3/23 To install end flange/blind flange on PSV/TSV
for calibration at produced water area
21/3/23-27/3/23 To remove pave.
. valvs and pipe systems of boiler *3 for
calibration,inspection and repair(include
burner)

A75 WELL PIPE


23/3/23-29/3/23 To perform excavation on 8”
(Excavation) leak flow line of oil well