# Activity ID Activity Name Original Start Finish 2023 2024 2025 2026 2027 2028 2029 2030 2031

Duration
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
1 Kg Jebat Hilir Kuala Bintulu 2343 01-Sep-23 29-Jan-30 29-Jan-30, Kg Jebat Hilir Kua
2 Kg Jebat Hilir.Phase
H 1 Earthworks 488 01-Sep-23 31-Dec-24 31-Dec-24, Kg Jebat Hilir.Phase 1 Earthworks
3 A1000 Site survey work, site analysis, SI, Prelim Design, Council submission, P 30 01-Sep-23* 30-Sep-23 Sep-23* 30-Sep-23,
4 A1010 Tender stage 92 01-Oct-23* 31-Dec-23 1-Oct-23* 31-Dec-23,
5 A1020 Construction Period 182 01-Jan-24* 30-Jun-24 01-Jan-24* 30-Jun-24,
6 A1030 Settlement Period 184 01-Jul-24* 31-Dec-24 01-Jul-24* 31-Dec-24,
7 Kg Jebat Hilir.Phase
H 2 Building Works 1855 01-Jan-25 29-Jan-30 29-Jan-30, Kg Jebat Hilir.Pha
8 A1040 Site Survey, site analysis, SI work 31 01-Jan-25* 31-Jan-25 01-Jan-25* 31-Jan-25,
9 A1050 Preliminary design, council submission, preparation of detail design and 365 01-Feb-25* 31-Jan-26 01-Feb-25* 31-Jan-26,
10 A1060 Tender stage 90 01-Feb-26* 01-May-26 01-Feb-26* 01-May-26,
11 A1070 Construction Period 913 02-May-26* 30-Oct-28 02-May-26* 30-Oct-28,
12 A1080 Defect Libiality Period 365 31-Oct-28* 30-Oct-29 31-Oct-28* 30-Oct-29,
13 A1090 Allowance for unforseen delay 91 31-Oct-29* 29-Jan-30 31-Oct-29* 29-Jan-30,