Sindalah Cluster 3 Hotel Steel Structure Works (WO.

09) Cluster 03 - Internal Schedule 22-Mar-23 09:13 AM


Activity ID Activity Name Remaining Start Finish Total Float3 March 2023 April 2023 May 2023 June 2023 July 2023 023
Duration
7 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28

Sindalah Cluster 3 Hotel Steel


S Structure Works (WO.09) 146.00 21-Feb-23 12:00 AM 17-Jul-23 12:00 AM 0.00 17-Jul-23 12:00 A

Milestones 146.00 21-Feb-23 12:00 AM 17-Jul-23 12:00 AM 0.00 17-Jul-23 12:00 A

Milestones 146.00 21-Feb-23 12:00 AM 17-Jul-23 12:00 AM 0.00 17-Jul-23 12:00 A


Milestones 146.00 21-Feb-23 12:00 AM 17-Jul-23 12:00 AM 0.00 17-Jul-23 12:00 A
Contractual Milestones 146.00 21-Feb-23 12:00 AM 17-Jul-23 12:00 AM 0.00 17-Jul-23 12:00 A
09-C3-ML-CM-000 Commencement Date for Work Order 09 0.00 21-Feb-23 12:00 AM* 0.00 Commencement Date for Work Order 09
09-C3-ML-CM-002 Completion Date for Work Order 09 0.00 17-Jul-23 12:00 AM* 0.00 Completion Date

Engineering 49.00 21-Feb-23 12:00 AM 11-Apr-23 12:00 AM 0.00 11-Apr-23 12:00 AM, Engineering

Cluster 3 49.00 21-Feb-23 12:00 AM 11-Apr-23 12:00 AM 0.00 11-Apr-23 12:00 AM, Cluster 3
Connection Modeling 39.00 21-Feb-23 12:00 AM 01-Apr-23 12:00 AM 1.00 01-Apr-23 12:00 AM, Connection Modeling
Zone 1 20.00 21-Feb-23 12:00 AM 13-Mar-23 12:00 AM 0.00 13-Mar-23 12:00 AM, Zone 1
09-C3-EN-CM-Z1-000 Prepare and Submit Calculation Sheets for Connection Modeling 10.00 21-Feb-23 12:00 AM 03-Mar-23 12:00 AM 0.00 Prepare and Submit Calculation Sheets for Connection Modeling
09-C3-EN-CM-Z1-002 Review and Approve Calculation Sheets for Connection Modeling 10.00 03-Mar-23 12:00 AM 13-Mar-23 12:00 AM 0.00 Review and Approve Calculation Sheets for Connection Modeling
Zone 2 20.00 21-Feb-23 12:00 AM 13-Mar-23 12:00 AM 10.00 13-Mar-23 12:00 AM, Zone 2
09-C3-EN-CM-Z2-000 Prepare and Submit Calculation Sheets for Connection Modeling 10.00 21-Feb-23 12:00 AM 03-Mar-23 12:00 AM 0.00 Prepare and Submit Calculation Sheets for Connection Modeling
09-C3-EN-CM-Z2-002 Review and Approve Calculation Sheets for Connection Modeling 10.00 03-Mar-23 12:00 AM 13-Mar-23 12:00 AM 10.00 Review and Approve Calculation Sheets for Connection Modeling
Zone 3 20.00 03-Mar-23 12:00 AM 23-Mar-23 12:00 AM 10.00 23-Mar-23 12:00 AM, Zone 3
09-C3-EN-CM-Z3-000 Prepare and Submit Calculation Sheets for Connection Modeling 10.00 03-Mar-23 12:00 AM 13-Mar-23 12:00 AM 0.00 Prepare and Submit Calculation Sheets for Connection Modeling
09-C3-EN-CM-Z3-002 Review and Approve Calculation Sheets for Connection Modeling 10.00 13-Mar-23 12:00 AM 23-Mar-23 12:00 AM 10.00 Review and Approve Calculation Sheets for Connection Modeling
Central Part 20.00 12-Mar-23 12:00 AM 01-Apr-23 12:00 AM 0.00 01-Apr-23 12:00 AM, Central Part
09-C3-EN-CM-CP-000 Prepare and Submit Calculation Sheets for Connection Modeling 10.00 12-Mar-23 12:00 AM 22-Mar-23 12:00 AM 0.00 Prepare and Submit Calculation Sheets for Connection Modeling
09-C3-EN-CM-CP-002 Review and Approve Calculation Sheets for Connection Modeling 10.00 22-Mar-23 12:00 AM 01-Apr-23 12:00 AM 0.00 Review and Approve Calculation Sheets for Connection Modeling
Shop Drawings 39.00 03-Mar-23 12:00 AM 11-Apr-23 12:00 AM 0.00 11-Apr-23 12:00 AM, Shop Drawings
Zone 1 20.00 13-Mar-23 12:00 AM 02-Apr-23 12:00 AM 0.00 02-Apr-23 12:00 AM, Zone 1
09-C3-EN-SD-Z1-000 Prepare and Submit DWGs for Steel Structure Works 10.00 13-Mar-23 12:00 AM 23-Mar-23 12:00 AM 0.00 Prepare and Submit DWGs for Steel Structure Works
09-C3-EN-SD-Z1-002 Review and Approve DWGs for Steel Structure Works 10.00 23-Mar-23 12:00 AM 02-Apr-23 12:00 AM 0.00 Review and Approve DWGs for Steel Structure Works
Zone 2 20.00 03-Mar-23 12:00 AM 23-Mar-23 12:00 AM 0.00 23-Mar-23 12:00 AM, Zone 2
09-C3-EN-SD-Z2-000 Prepare and Submit DWGs for Steel Structure Works 10.00 03-Mar-23 12:00 AM 13-Mar-23 12:00 AM 0.00 Prepare and Submit DWGs for Steel Structure Works
09-C3-EN-SD-Z2-002 Review and Approve DWGs for Steel Structure Works 10.00 13-Mar-23 12:00 AM 23-Mar-23 12:00 AM 0.00 Review and Approve DWGs for Steel Structure Works
Zone 3 20.00 13-Mar-23 12:00 AM 02-Apr-23 12:00 AM 0.00 02-Apr-23 12:00 AM, Zone 3
09-C3-EN-SD-Z3-000 Prepare and Submit DWGs for Steel Structure Works 10.00 13-Mar-23 12:00 AM 23-Mar-23 12:00 AM 0.00 Prepare and Submit DWGs for Steel Structure Works
09-C3-EN-SD-Z3-002 Review and Approve DWGs for Steel Structure Works 10.00 23-Mar-23 12:00 AM 02-Apr-23 12:00 AM 0.00 Review and Approve DWGs for Steel Structure Works
Central Part 20.00 22-Mar-23 12:00 AM 11-Apr-23 12:00 AM 0.00 11-Apr-23 12:00 AM, Central Part
09-C3-EN-SD-CP-000 Prepare and Submit DWGs for Steel Structure Works 10.00 22-Mar-23 12:00 AM 01-Apr-23 12:00 AM 0.00 Prepare and Submit DWGs for Steel Structure Works
09-C3-EN-SD-CP-002 Review and Approve DWGs for Steel Structure Works 10.00 01-Apr-23 12:00 AM 11-Apr-23 12:00 AM 0.00 Review and Approve DWGs for Steel Structure Works

Procurement 75.00 01-Mar-23 12:00 AM 15-May-23 12:00 AM 0.00 15-May-23 12:00 AM, Procurement

Structure 75.00 01-Mar-23 12:00 AM 15-May-23 12:00 AM 0.00 15-May-23 12:00 AM, Structure
Short Lead Items 75.00 01-Mar-23 12:00 AM 15-May-23 12:00 AM 0.00 15-May-23 12:00 AM, Short Lead Items
Zone 1 70.00 03-Mar-23 12:00 AM 12-May-23 12:00 AM 0.00 12-May-23 12:00 AM, Zone 1
09-C3-PR-SS-000 Issue Purchase Order [PO] and Procure Raw Material [Z1] [C3] 30.00 03-Mar-23 12:00 AM 02-Apr-23 12:00 AM 10.00 Issue Purchase Order [PO] and Procure Raw Material [Z1] [C3]
09-C3-PR-SS-002 Prepare Fabrication Drawings/ Sheets [Z1] [C3] 10.00 02-Apr-23 12:00 AM 12-Apr-23 12:00 AM 0.00 Prepare Fabrication Drawings/ Sheets [Z1] [C3]
09-C3-PR-Z1-000 Fabricate and Delivery [Z1] [C3] 30.00 12-Apr-23 12:00 AM 12-May-23 12:00 AM 0.00 Fabricate and Delivery [Z1] [C3]
Zone 2 42.00 01-Mar-23 12:00 AM 12-Apr-23 12:00 AM 0.00 12-Apr-23 12:00 AM, Zone 2
09-C3-PR-Z2-2 Issue Purchase Order [PO] and Procure Raw Material [Z1] [C3] 30.00 01-Mar-23 12:00 AM 31-Mar-23 12:00 AM 2.00 Issue Purchase Order [PO] and Procure Raw Material [Z1] [C3]
09-C3-PR-Z2-4 Prepare Fabrication Drawings/ Sheets [Z1] [C3] 10.00 23-Mar-23 12:00 AM 02-Apr-23 12:00 AM 0.00 Prepare Fabrication Drawings/ Sheets [Z1] [C3]
09-C3-PR-Z2-000 Fabricate and Delivery [Z2] [C3] 10.00 02-Apr-23 12:00 AM 12-Apr-23 12:00 AM 0.00 Fabricate and Delivery [Z2] [C3]
Zone 3 70.00 03-Mar-23 12:00 AM 12-May-23 12:00 AM 0.00 12-May-23 12:00 AM, Zone 3
08-C4-1000 Issue Purchase Order [PO] and Procure Raw Material [Z3] [C3] 30.00 03-Mar-23 12:00 AM 02-Apr-23 12:00 AM 10.00 Issue Purchase Order [PO] and Procure Raw Material [Z3] [C3]
08-C4-1002 Prepare Fabrication Drawings/ Sheets [Z3] [C3] 10.00 02-Apr-23 12:00 AM 12-Apr-23 12:00 AM 0.00 Prepare Fabrication Drawings/ Sheets [Z3] [C3]
09-C3-PR-Z3-000 Fabricate and Delivery [Z3] [C3] 30.00 12-Apr-23 12:00 AM 12-May-23 12:00 AM 0.00 Fabricate and Delivery [Z3] [C3]
Central Part 63.00 13-Mar-23 12:00 AM 15-May-23 12:00 AM 0.00 15-May-23 12:00 AM, Central Part
08-C4-1004 Issue Purchase Order [PO] and Procure Raw Material [CP] [C3] 30.00 13-Mar-23 12:00 AM 12-Apr-23 12:00 AM 3.00 Issue Purchase Order [PO] and Procure Raw Material [CP] [C3]
08-C4-1006 Prepare Fabrication Drawings/ Sheets [CP] [C3] 10.00 05-Apr-23 12:00 AM 15-Apr-23 12:00 AM 0.00 Prepare Fabrication Drawings/ Sheets [CP] [C3]
09-C3-PR-CP-000 Fabricate and Delivery [CP] [C3] 30.00 15-Apr-23 12:00 AM 15-May-23 12:00 AM 0.00 Fabricate and Delivery [CP] [C3]

Construction 100.00 08-Apr-23 12:00 AM 17-Jul-23 12:00 AM 0.00 17-Jul-23 12:00 A

Cluster 3 100.00 08-Apr-23 12:00 AM 17-Jul-23 12:00 AM 0.00 17-Jul-23 12:00 A


Steel Structure Works 100.00 08-Apr-23 12:00 AM 17-Jul-23 12:00 AM 0.00 17-Jul-23 12:00 A

Actual Work Critical Remaining Work Summary Page 1 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Sindalah Cluster 3 Hotel Steel Structure Works (WO.09) Metal Building Factory 22-Mar-23 09:13 AM
Activity ID Activity Name Remaining Start Finish Total Float3 March 2023 April 2023 May 2023 June 2023 July 2023 023
Duration
7 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28
Zone 1 32.00 21-Apr-23 12:00 AM 23-May-23 12:00 AM 0.00 23-May-23 12:00 AM, Zone 1
09-C3-CO-Z1-000 Erect Steel Structure Columns [Z1] [C3] 24.00 21-Apr-23 12:00 AM 15-May-23 12:00 AM 0.00 Erect Steel Structure Columns [Z1] [C3]
09-C3-CO-Z1-002 Erect Steel Structure Frame [Z1] [C3] 24.00 25-Apr-23 12:00 AM 19-May-23 12:00 AM 0.00 Erect Steel Structure Frame [Z1] [C3]
09-C3-CO-Z1-004 Erect Steel Structure Bracing [Z1] [C3] 24.00 29-Apr-23 12:00 AM 23-May-23 12:00 AM 0.00 Erect Steel Structure Bracing [Z1] [C3]
Zone 2 15.00 08-Apr-23 12:00 AM 23-Apr-23 12:00 AM 0.00 23-Apr-23 12:00 AM, Zone 2
09-C3-CO-Z2-000 Erect Steel Structure Columns [Z2] [C3] 10.00 08-Apr-23 12:00 AM 18-Apr-23 12:00 AM 0.00 Erect Steel Structure Columns [Z2] [C3]
09-C3-CO-Z2-002 Erect Steel Structure Frame [Z2] [C3] 10.00 10-Apr-23 12:00 AM 20-Apr-23 12:00 AM 0.00 Erect Steel Structure Frame [Z2] [C3]
09-C3-CO-Z2-004 Erect Steel Structure Bracing [Z2] [C3] 10.00 13-Apr-23 12:00 AM 23-Apr-23 12:00 AM* 0.00 Erect Steel Structure Bracing [Z2] [C3]
Zone 3 29.00 24-Apr-23 12:00 AM 23-May-23 12:00 AM 0.00 23-May-23 12:00 AM, Zone 3
09-C3-CO-Z3-000 Erect Steel Structure Columns [Z3] [C3] 24.00 24-Apr-23 12:00 AM 18-May-23 12:00 AM 0.00 Erect Steel Structure Columns [Z3] [C3]
09-C3-CO-Z3-002 Erect Steel Structure Frame [Z3] [C3] 24.00 27-Apr-23 12:00 AM 21-May-23 12:00 AM 0.00 Erect Steel Structure Frame [Z3] [C3]
09-C3-CO-Z3-004 Erect Steel Structure Bracing [Z3] [C3] 24.00 29-Apr-23 12:00 AM 23-May-23 12:00 AM* 0.00 Erect Steel Structure Bracing [Z3] [C3]
Central Part 80.00 28-Apr-23 12:00 AM 17-Jul-23 12:00 AM 0.00 17-Jul-23 12:00 A
09-C3-CO-CP-000 Erect Steel Structure Columns [CP] [C3] 40.00 28-Apr-23 12:00 AM 07-Jun-23 12:00 AM 0.00 Erect Steel Structure Columns [CP] [C3]
09-C3-CO-CP-002 Erect Steel Structure Frame [CP] [C3] 40.00 18-May-23 12:00 AM 27-Jun-23 12:00 AM 0.00 Erect Steel Structure Frame [CP] [C3]
09-C3-CO-CP-004 Erect Steel Structure Bracing [CP] [C3] 40.00 07-Jun-23 12:00 AM 17-Jul-23 12:00 AM* 0.00 Erect Steel Struct

Actual Work Critical Remaining Work Summary Page 2 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation