Professional Documents
Culture Documents
1 2 3 4 1 2 3 4 5 6 1 2 3 4 5 6 7
RS232C/485 POWER
3 1
DC+ F.G
DC- F.G
4 2
STATUS
7 1
DI1(O) DI2(C)
DI 3 DI 4
DI 5 DI 6
RS232C COM1 DI 7
DI 8 DI 9
DI 10 COM2
12 6
TCP/IP CONTROL
9 1
DO1 +
DO1 -
DO2 +
DO2 -
DO3+ DO4+
DO3- DO4-
PO1+ PO2+
PO1- PO2-
CAN 16 8
H
VOLTAGE
VA
VB
VC
V ABC COM
VR
VS
VT
V RST COM
CURRENT
IA
IB
TD IC
I COM
TD1+
3I 0+
TD1-
3I 0-
TD2+
TD2-
13.8 KV AUTO RECLOSING SYSTEM
TEST PROCEDURE
Project: Berri Gas Plant
Contents:
1. Preparation prior to testing activities .............................................................................................................. 3
2. Reference standard .......................................................................................................................................... 3
3. Tests Procedures .............................................................................................................................................. 3
3.1 Auto recloser controller testing. .................................................................................................................. 3
3.2 Current Transformers testing. ...................................................................................................................... 3
3.3 Voltage Transformers Testing. ...................................................................................................................... 3
3.4 Load Break Switch Testing. ........................................................................................................................... 3
3.1 Auto recloser controller Relay: .................................................................................................................... 3
3.1.1 Measurement Check: ............................................................................................................................... 4
3.1.2 Protection Characteristics: ....................................................................................................................... 4
3.1.2.1 Fault Detection..................................................................................................................................... 4
3.1.2.2 Over current protection ....................................................................................................................... 4
3.1.2.3 Ground protection ............................................................................................................................... 7
3.1.2.4 Auto Reclosing Function: ..................................................................................................................... 8
3.1.2.5 General Specification for Protection and control functions: ............................................................... 9
3.2 Current Transformers: ................................................................................................................................ 10
3.2.1 Visual Check ........................................................................................................................................... 10
3.2.2 Electrical Test ......................................................................................................................................... 10
3.2.2.1 Insulation Resistance Test .................................................................................................................. 10
3.2.2.2 Ratio and Polarity Test: ...................................................................................................................... 10
3.2.2.3 Winding Resistance Test..................................................................................................................... 11
3.2.2.4 Saturation/Knee Point Test ................................................................................................................ 11
3.2.2.5 CT Burden Test ................................................................................................................................... 12
3.3 Voltage Transformer ................................................................................................................................... 13
3.3.1 Visual Check: .......................................................................................................................................... 13
3.3.2 Electrical Test ......................................................................................................................................... 13
3.3.2.1 Insulation Resistance Test: ................................................................................................................. 13
3.3.2.2 Ratio and Polarity Test: .................................................................................................................. 14
3.3.2.3 Winding Resistance Test..................................................................................................................... 14
3.4 Medium Voltage Load Break Switch (LBS): ............................................................................................ 15
2. Reference standard
• IEC 61869 Standard for Current & Voltage Transformers testing.
• IEC 60352-5 Standard for contact resistance test.
3. Tests Procedures
3.1 Auto recloser controller testing.
3.2 Current Transformers testing.
3.3 Voltage Transformers Testing.
3.4 Load Break Switch Testing.
o Operation curves
• Relay Event Recorder should be configured.
• Make Sure that Relay LED’s Configured per each desired function
3.1.1 Measurement Check:
• Below mentioned quantities shall be calculated/ measured.
a) r.m.s phase to phase and phase to neutral voltage of all three phase.
b) r.m.s current per phase
c) Three phase active power in kW
d) Three phase reactive power in kVAR
e) Total three phase active energy in kWh
f) Power factor
g) Maximum demand
• AR and control element shall have the facility to record the number and time of outages.
The information shall be accessible locally or remotely and the following parameters shall be
recorded:
a) Cumulative total number of outages
b) Cumulative total outage duration
c) Time and duration of each outage
Cold Load:
In Cold Load Pickup mode, without changing operational characteristics, pickup level is changed
by the times of Cold Load Multiplier (0~10) and the characteristics of time-delayed element
operate even if the setting is in the Instantaneous element. If the transient current goes down
and retrains below the pickup level within Cold Load Duration, then the normal sequence mode
is restored after Cold Load Restore Time. The Cold Load Restore Time is fixed value of 30msec.
These setting exist for both phase fault and earth fault separately, and the value ‘0’ of Cold Load
Multiplier means Cold Load Pickup Function disabled. Normaly Reclosing Sequence mode is
applied.
2- Fast Curve
Setting:
TCC Curve: VI Min Response Time: 0
Time Multiplier: 1 Reset type: RDMT
Time Adder: 0 Reset Definite Time
• Inject current to phase A and start by value more than Pickup Value and slowly increase until
Overcurrent trip occur.
• Stop injection by operation of output contact with injected current must be greater than Pickup
Current.
• Trip Time is should equal to Expected Time from the Above Equation.
• Repeat the same for phase B & phase C
3- Delay Curve
Setting:
TCC Curve: NI Min Response Time: 0
Time Multiplier: 1 Reset type: RDMT
Time Adder: 0 Reset Definite Time
• Inject current to phase A and start by value more than Pickup Value and slowly increase until
Overcurrent trip occur.
• Stop injection by operation of output contact with injected current must be greater than Pickup
Current.
• Trip Time is should equal to Expected Time from the Above Equation.
• Repeat the same for phase B & phase C
4- Definite Time OC
Setting:
Pickup Current I>>: 1000 A Response Time: 0
• Inject current to phase A and start by value less than the Pickup Value and slowly increase until
Overcurrent trip occur.
• Stop injection by operation of output contact with injected current must be greater than or equals
Pickup Current Setting.
• Repeat the same for phase B & phase C
Apply Voltage in Accordance with the manufacturer’s data. In the absence of manufacturer’s data,
Use Table 1. The ambient temperature shall be noted down during test.
Test Value shall be compared with the table 1
Fig 8.4