1 Mobilization to Site
2 Temporary Office Set Up
3 Pre Site Assement Induction
4 Setting Out of Fence line
5 Clearing & Grubbing
6 Excavation
8 Boxing/formwork
10 Fence Post Alignment Fixation
11 Concrete Mix & Pour
12 Fixing of Mesh panels
13 Installment Of Gates
14 Rasor Wire Installation
15 Demobilization
16 Commissioning
LS LS LS
17 Project Supervision Cost LS
18 Labor Cost LS
19 Material Cost LS
20 Equipment Cost LS
Subtotal Cost
10% Contingency
Total Construction Cost Estimate 827,900.52 PGK
Notes.
a Timeframe of expected TWL Fencing Project completion date to be end of November & provided theres sufficeint funding, work is expected to be completed before end of November 2020 as stipulated in the provided scheduale
b Work to start as soon as possible. Number of labor is dependent on time factor and funds availability and shall be andorsed & approved by General Mamanger Kemele Construction.
c Any changes of scope of works and matters affecting the progress of the Project shall be settled, adviced, endorsed & approved by Management for further elaboration.