Professional Documents
Culture Documents
FLOOR TILES (Dry area) Completed Completed Completed Completed Completed Completed
FLOOR TILES (Wet area) Completed Completed Completed Completed Completed Completed
WALL TILE (Wet&Dry area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
FLOOR TILES (Dry area) Completed Completed Completed Completed Completed Completed
FLOOR TILES (Wet area) Completed Completed Completed Completed Completed Completed
WALL TILE (Wet&Dry area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
Level-2 FALSE WORK (Dry area)
Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
WOODEN DOORS Completed Completed Completed Completed Completed Completed
WARDROBES Completed Completed Completed Completed Completed Completed
KITCHEN CABINETS Completed Completed Completed Completed Completed Completed
CURTAIN WALL WINDOWS Completed Completed Completed Completed Completed Completed
ALUMINUM LOUVER DOORS Completed Completed Completed Completed Completed Completed
FIRE RATED DOORS N/A N/A N/A N/A N/A N/A
FLOOR TILES (Dry area) Completed Completed Completed Completed Completed Completed
FLOOR TILES (Wet area) Completed Completed Completed Completed Completed Completed
WALL TILE (Wet&Dry area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
Level-3
FALSE WORK (Dry area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
WOODEN DOORS Completed Completed Completed Completed Completed Completed
WARDROBES Completed Completed Completed Completed Completed Completed
KITCHEN CABINETS Completed Completed Completed Completed Completed Completed
CURTAIN WALL WINDOWS Completed Completed Completed Completed Completed Completed
ALUMINUM LOUVER DOORS Completed Completed Completed Completed Completed Completed
FIRE RATED DOORS N/A N/A N/A N/A N/A N/A
FLOOR TILES (Dry area) Completed Completed Completed Completed Completed Completed
FLOOR TILES (Wet area) Completed Completed Completed Completed Completed Completed
WALL TILE (Wet&Dry area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
Level-4 FALSE WORK (Dry area)
Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
WOODEN DOORS Completed Completed Completed Completed Completed Completed
WARDROBES Completed Completed Completed Completed Completed Completed
KITCHEN CABINETS Completed Completed Completed Completed Completed Completed
CURTAIN WALL WINDOWS Completed Completed Completed Completed Completed Completed
ALUMINUM LOUVER DOORS Completed Completed Completed Completed Completed Completed
FIRE RATED DOORS N/A N/A N/A N/A N/A N/A
FLOOR TILES (Dry area) Completed Completed Completed Completed Completed Completed
FLOOR TILES (Wet area) Completed Completed Completed Completed Completed Completed
WALL TILE (Wet&Dry area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
Level-5 FALSE WORK (Dry area)
Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
WOODEN DOORS Completed Completed Completed Completed Completed Completed
WARDROBES Completed Completed Completed Completed Completed Completed
KITCHEN CABINETS Completed Completed Completed Completed Completed Completed
CURTAIN WALL WINDOWS Completed Completed Completed Completed Completed Completed
ALUMINUM LOUVER DOORS N/A N/A N/A N/A N/A N/A
FIRE RATED DOORS N/A N/A N/A N/A N/A N/A
FLOOR TILES (Dry area) Completed Completed Completed Completed Completed Completed
FLOOR TILES (Wet area) Completed Completed Completed Completed Completed Completed
WALL TILE (Wet&Dry area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
Level-6 FALSE WORK (Dry area)
Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
WOODEN DOORS Completed Completed Completed Completed Completed Completed
WARDROBES Completed Completed Completed Completed Completed Completed
KITCHEN CABINETS Completed Completed Completed Completed Completed Completed
CURTAIN WALL WINDOWS Completed Completed Completed Completed Completed Completed
ALUMINUM LOUVER DOORS N/A N/A N/A N/A N/A N/A
FIRE RATED DOORS N/A N/A N/A N/A N/A N/A
FLOOR TILES (Dry area) Completed Completed Completed Completed Completed Completed
FLOOR TILES (Wet area) Completed Completed Completed Completed Completed Completed
WALL TILE (Wet&Dry area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
Level-7 FALSE WORK (Dry area)
Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
WOODEN DOORS Completed Completed Completed Completed Completed Completed
WARDROBES Completed Completed Completed Completed Completed Completed
KITCHEN CABINETS Completed Completed Completed Completed Completed Completed
CURTAIN WALL WINDOWS Completed Completed Completed Completed Completed Completed
ALUMINUM LOUVER DOORS N/A N/A N/A N/A N/A N/A
FIRE RATED DOORS N/A N/A N/A N/A N/A N/A
FLOOR TILES (Dry area) Completed Completed Completed Completed Completed Completed
FLOOR TILES (Wet area) Completed Completed Completed Completed Completed Completed
WALL TILE (Wet&Dry area) Completed Completed Completed Completed Completed Completed
Level-8
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
Level-8
FALSE WORK (Dry area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
WOODEN DOORS Completed Completed Completed Completed Completed Completed
WARDROBES Completed Completed Completed Completed Completed Completed
KITCHEN CABINETS Completed Completed Completed Completed Completed Completed
CURTAIN WALL WINDOWS Completed Completed Completed Completed Completed Completed
ALUMINUM LOUVER DOORS N/A N/A N/A N/A N/A N/A
FIRE RATED DOORS N/A N/A N/A N/A N/A N/A
FLOOR TILES (Dry area) Completed Completed Completed Completed Completed Completed
FLOOR TILES (Wet area) Completed Completed Completed Completed Completed Completed
WALL TILE (Wet&Dry area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
Level-9 FALSE WORK (Dry area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
WOODEN DOORS Completed Completed Completed Completed Completed Completed
WARDROBES Completed Completed Completed Completed Completed Completed
KITCHEN CABINETS Completed Completed Completed Completed Completed Completed
CURTAIN WALL WINDOWS Completed Completed Completed Completed Completed Completed
ALUMINUM LOUVER DOORS N/A N/A N/A N/A N/A N/A
FIRE RATED DOORS N/A N/A N/A N/A N/A N/A
FLOOR TILES (Dry area) Completed Completed Completed Completed Completed Completed
FLOOR TILES (Wet area) Completed Completed Completed Completed Completed Completed
WALL TILE (Wet&Dry area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
COUNTER TOPS(wet area) Completed Completed Completed Completed Completed Completed
Level-10 FALSE WORK (Dry area) Completed Completed Completed Completed Completed Completed
FALSE WORK (Wet area) Completed Completed Completed Completed Completed Completed
WOODEN DOORS Completed Completed Completed Completed Completed Completed
WARDROBES Completed Completed Completed Completed Completed Completed
KITCHEN CABINETS Completed Completed Completed Completed Completed Completed
CURTAIN WALL WINDOWS Completed Completed Completed Completed Completed Completed
ALUMINUM LOUVER DOORS N/A N/A N/A N/A N/A N/A
FIRE RATED DOORS N/A N/A N/A N/A N/A N/A
RAL FINISHES WORKS)
Date: 31-Oct-20
LIFT LOBBY REMARKS
Completed
Completed
Completed
N/A
N/A
N/A
Completed
N/A
N/A
N/A
N/A Light Pelmet
N/A
Completed
Completed
Completed
Completed
Completed
N/A
N/A
N/A
Completed
N/A
N/A
N/A
N/A
N/A
Completed
Completed
Completed
Completed
N/A
N/A
N/A
Completed
N/A
N/A
N/A
N/A
N/A
N/A
Completed
Completed
Air Devices Complete Complete Complete Complete Complete Complete N/A complete
A/C Installation Complete Complete Complete Complete Complete Complete N/A complete
Motorized Fire Damper N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
BMS System N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
Mulitgas Detector Complete Complete Complete Complete Complete Complete N/A N/A
Push Button Complete Complete Complete Complete Complete Complete N/A N/A
solenoid connection with FACP Complete Complete Complete Complete Complete Complete N/A N/A
Gas Meter Installation N/A N/A N/A N/A N/A N/A 20-Nov-20 N/A Material at site
Sprinkler Installation Not in Our Scope
Level-1
ZCV Installation Not in Our Scope
Fire Hose Cabinet Installation Not in Our Scope
Gas Water Heater Complete Complete Complete Complete Complete Complete N/A N/A
Fixture Installation Complete Complete Complete Complete Complete Complete N/A N/A
Faucits Installation Complete Complete Complete Complete Complete Complete N/A N/A
water meter Installation N/A N/A N/A N/A N/A N/A Complete N/A
PRV Installation N/A N/A N/A N/A N/A N/A Complete N/A
Garbage Chute Doors Installation N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
Garbage Chute sprinkler & jet Spray N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
FLOOR ITEM Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Meter Room LIFT LOBBY REMARKS
Air Devices Complete Complete Complete Complete Complete Complete N/A complete
A/C Installation Complete Complete Complete Complete Complete Complete N/A complete
Motorized Fire Damper N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
BMS System N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
Mulitgas Detector Complete Complete Complete Complete Complete Complete N/A N/A
Push Button Complete Complete Complete Complete Complete Complete N/A N/A
solenoid connection with FACP Complete Complete Complete Complete Complete Complete N/A N/A
Gas Meter Installation N/A N/A N/A N/A N/A N/A 20-Nov-20 N/A Material at site
Sprinkler Installation Not in Our Scope
Level-2 ZCV Installation Not in Our Scope
Fire Hose Cabinet Installation Not in Our Scope
Gas Water Heater Complete Complete Complete Complete Complete Complete N/A N/A
Fixture Installation Complete Complete Complete Complete Complete Complete N/A N/A
water meter Installation N/A N/A N/A N/A N/A N/A Complete N/A
PRV Installation N/A N/A N/A N/A N/A N/A Complete N/A
Garbage Chute Doors Installation N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
Garbage Chute sprinkler & jet Spray N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
FLOOR ITEM Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Meter Room LIFT LOBBY REMARKS
Air Devices Complete Complete Complete Complete Complete Complete N/A complete
A/C Installation Complete Complete Complete Complete Complete Complete N/A complete
Motorized Fire Damper N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
BMS System N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
Mulitgas Detector Complete Complete Complete Complete Complete Complete N/A N/A
Push Button Complete Complete Complete Complete Complete Complete N/A N/A
solenoid connection with FACP Complete Complete Complete Complete Complete Complete N/A N/A 18-Oct-20
Gas Meter Installation N/A N/A N/A N/A N/A N/A 20-Nov-20 N/A Material at site
Sprinkler Installation Not in Our Scope
Level-3 ZCV Installation Not in Our Scope
Fire Hose Cabinet Installation Not in Our Scope
Gas Water Heater Complete Complete Complete Complete Complete Complete N/A N/A
Fixture Installation Complete Complete Complete Complete Complete Complete N/A N/A
water meter Installation N/A N/A N/A N/A N/A N/A Complete N/A
PRV Installation N/A N/A N/A N/A N/A N/A Complete N/A
Garbage Chute Doors Installation N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
Garbage Chute sprinkler & jet Spray N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
FLOOR ITEM Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Meter Room LIFT LOBBY REMARKS
Air Devices Complete Complete Complete Complete Complete Complete N/A Complete
A/C Installation Complete Complete Complete Complete Complete Complete N/A Complete
Motorized Fire Damper N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
BMS System N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
Mulitgas Detector Complete Complete Complete Complete Complete Complete N/A N/A
Push Button Complete Complete Complete Complete Complete Complete N/A N/A
Level-4
solenoid connection with FACP Complete Complete Complete Complete Complete Complete N/A N/A
Gas Meter Installation N/A N/A N/A N/A N/A N/A 20-Nov-20 N/A Material at site
Sprinkler Installation Not in Our Scope
Level-4 ZCV Installation Not in Our Scope
Fire Hose Cabinet Installation Not in Our Scope
Gas Water Heater Complete Complete Complete Complete Complete Complete N/A N/A
Fixture Installation Complete Complete Complete Complete Complete Complete N/A N/A
water meter Installation N/A N/A N/A N/A N/A N/A Complete N/A
PRV Installation N/A N/A N/A N/A N/A N/A Complete N/A
Garbage Chute Doors Installation N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
Garbage Chute sprinkler & jet Spray N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
FLOOR ITEM Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Meter Room LIFT LOBBY REMARKS
Air Devices Complete Complete Complete Complete Complete Complete N/A complete
A/C Installation Complete Complete Complete Complete Complete Complete N/A complete
Motorized Fire Damper N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
BMS System N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
Mulitgas Detector Complete Complete Complete Complete Complete Complete N/A N/A
Push Button Complete Complete Complete Complete Complete Complete N/A N/A
solenoid connection with FACP Complete Complete Complete Complete Complete Complete N/A N/A
Gas Meter Installation N/A N/A N/A N/A N/A N/A 20-Nov-20 N/A Material at site
Sprinkler Installation Not in Our Scope
Level-5 ZCV Installation Not in Our Scope
Fire Hose Cabinet Installation Not in Our Scope
Gas Water Heater Complete Complete Complete Complete Complete Complete N/A N/A
Fixture Installation Complete Complete Complete Complete Complete Complete N/A N/A
FLOOR ITEM Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Meter Room LIFT LOBBY REMARKS
Air Devices Complete Complete Complete Complete Complete Complete N/A complete
A/C Installation Complete Complete Complete Complete Complete Complete N/A complete
Motorized Fire Damper N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
BMS System N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
Mulitgas Detector Complete Complete Complete Complete Complete Complete N/A N/A
Push Button Complete Complete Complete Complete Complete Complete N/A N/A
solenoid connection with FACP Complete Complete Complete Complete Complete Complete N/A N/A
Gas Meter Installation N/A N/A N/A N/A N/A N/A 20-Nov-20 N/A Material at site
Sprinkler Installation Not in Our Scope
Level-6 ZCV Installation Not in Our Scope
Fire Hose Cabinet Installation Not in Our Scope
Gas Water Heater Complete Complete Complete Complete Complete Complete N/A N/A
Fixture Installation Complete Complete Complete Complete Complete Complete N/A N/A
FLOOR ITEM Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Meter Room LIFT LOBBY REMARKS
Air Devices Complete Complete Complete Complete Complete Complete N/A complete
A/C Installation Complete Complete Complete Complete Complete Complete N/A complete
Motorized Fire Damper N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
BMS System N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
Mulitgas Detector Complete Complete Complete Complete Complete Complete N/A N/A
Push Button Complete Complete Complete Complete Complete Complete N/A N/A
solenoid connection with FACP Complete Complete Complete Complete Complete Complete N/A N/A
Gas Meter Installation N/A N/A N/A N/A N/A N/A 20-Nov-20 N/A Material at site
Sprinkler Installation Not in Our Scope
Level-7 ZCV Installation Not in Our Scope
Fire Hose Cabinet Installation Not in Our Scope
Gas Water Heater Complete Complete Complete Complete Complete Complete N/A N/A
Fixture Installation Complete Complete Complete Complete Complete Complete N/A N/A
Will be Done at the Time of Customer Hand over
Faucits Installation
water meter Installation N/A N/A N/A N/A N/A N/A Complete N/A
PRV Installation N/A N/A N/A N/A N/A N/A Complete N/A
Garbage Chute Doors Installation N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
Garbage Chute sprinkler & jet Spray N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
FLOOR ITEM Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Meter Room LIFT LOBBY REMARKS
Air Devices Complete Complete Complete Complete Complete Complete N/A complete
A/C Installation Complete Complete Complete Complete Complete Complete N/A complete
Motorized Fire Damper N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
BMS System N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
Mulitgas Detector Complete Complete Complete Complete Complete Complete N/A N/A
Push Button Complete Complete Complete Complete Complete Complete N/A N/A
solenoid connection with FACP Complete Complete Complete Complete Complete Complete N/A N/A
Gas Meter Installation N/A N/A N/A N/A N/A N/A 20-Nov-20 N/A Material at site
Sprinkler Installation Not in Our Scope
Level-8 ZCV Installation Not in Our Scope
Fire Hose Cabinet Installation Not in Our Scope
Gas Water Heater Complete Complete Complete Complete Complete Complete N/A N/A
Fixture Installation Complete Complete Complete Complete Complete Complete N/A N/A
Will be Done at the Time of Customer Hand over
Faucits Installation
water meter Installation N/A N/A N/A N/A N/A N/A Complete N/A
PRV Installation N/A N/A N/A N/A N/A N/A Complete N/A
Garbage Chute Doors Installation N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
Garbage Chute sprinkler & jet Spray N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
FLOOR ITEM Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Meter Room LIFT LOBBY REMARKS
Air Devices Complete Complete Complete Complete Complete Complete N/A complete
A/C Installation Complete Complete Complete Complete Complete Complete N/A complete
Motorized Fire Damper N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
BMS System N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
Mulitgas Detector Complete Complete 2-Nov-20 2-Nov-20 Complete 2-Nov-20 N/A N/A
Push Button Complete Complete Complete Complete Complete Complete N/A N/A
solenoid connection with FACP Complete Complete Complete Complete Complete Complete N/A N/A
Gas Meter Installation N/A N/A N/A N/A N/A N/A 20-Nov-20 N/A Material at site
Sprinkler Installation Not in Our Scope
Level-9 ZCV Installation Not in Our Scope
Fire Hose Cabinet Installation Not in Our Scope
Gas Water Heater Complete Complete Complete Complete Complete Complete N/A N/A
Fixture Installation Complete Complete Complete Complete Complete Complete N/A N/A
FLOOR ITEM Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Meter Room LIFT LOBBY REMARKS
Air Devices Complete Complete Complete Complete Complete Complete N/A complete
A/C Installation Complete Complete Complete Complete Complete Complete N/A complete
Motorized Fire Damper N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
BMS System N/A N/A N/A N/A N/A N/A N/A 20-Nov-20 Material not Procured
Mulitgas Detector 2-Nov-20 2-Nov-20 2-Nov-20 2-Nov-20 2-Nov-20 2-Nov-20 N/A N/A
Push Button Complete Complete Complete Complete Complete Complete N/A N/A
solenoid connection with FACP Complete Complete Complete 2-Nov-20 2-Nov-20 2-Nov-20 N/A N/A
Gas Meter Installation N/A N/A N/A N/A N/A N/A 20-Nov-20 N/A Material at site
Sprinkler Installation Not in Our Scope
Level-10 ZCV Installation Not in Our Scope
Fire Hose Cabinet Installation Not in Our Scope
Gas Water Heater Complete Complete Complete Complete Complete Complete N/A N/A
Fixture Installation Complete Complete Complete Complete Complete Complete N/A N/A
Faucits Installation Will be Done at the Time of Customer Hand over
water meter Installation N/A N/A N/A N/A N/A N/A Complete N/A
PRV Installation N/A N/A N/A N/A N/A N/A Complete N/A
Garbage Chute Doors Installation N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
Garbage Chute sprinkler & jet Spray N/A N/A N/A N/A N/A N/A N/A 30-Nov-20
31-Oct-20
REMARKS
Material at site
REMARKS
Material at site
REMARKS
Material at site
REMARKS
REMARKS
Material at site
REMARKS
Material at site
REMARKS
Material at site
REMARKS
Material at site
REMARKS
Material at site
REMARKS
Material at site
ITEM WISE COMPLETION STATUS OF TOWER 3 (ELECTRICAL & COMMUNICATION WORKS)
Floor Item Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Lift Lobby Date of
Completion
Electrical Power Completed Completed Completed Completed Completed Completed
Electrical Lighting Completed Completed Completed Completed Completed Completed
Fire Alarm System Completed Completed Completed Completed Completed Completed
Gas Detection System Completed Completed Completed Completed Site office for Completed N/A
Structured Cabling Completed Completed Completed Completed
contractor Completed Completed
Level-1 Will be Install at the time of
Audio Intercom Will be Install at the time of Handing over Handing over
Will be Install at
CCTV N/A N/A N/A N/A N/A N/A the time of
Handing over
Floor Item Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Lift Lobby
Electrical Power Completed Completed Completed Completed Completed Completed Completed
Electrical Lighting Completed Completed Completed Completed Completed Completed Completed
Fire Alarm System Completed Completed Completed Completed Completed Completed Completed
Gas Detection System Completed Completed Completed Completed Completed Completed N/A
Structured Cabling Completed Completed Completed Completed Completed Completed Completed
Level-2
Audio Intercom Will be Install at the time of Handing over
CATV Completed Completed Completed Completed Completed Completed Completed
Will be Install at
CCTV N/A N/A N/A N/A N/A N/A the time of
Handing over
Floor Item Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Lift Lobby
Electrical Power Completed Completed Completed Completed Completed Completed Completed
Electrical Lighting Completed Completed Completed Completed Completed Completed Completed
Fire Alarm System Completed Completed Completed Completed Completed Completed Completed
Gas Detection System Completed Completed Completed Completed Completed Completed N/A
Structured Cabling Completed Completed Completed Completed Completed Completed Completed
Level-3
Audio Intercom Will be Install at the time of Handing over
CATV Completed Completed Completed Completed Completed Completed Completed
Will be Install at
CCTV the time of
Handing over
N/A N/A N/A N/A N/A N/A
Floor Item Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Lift Lobby
Electrical Power Completed Completed Completed Completed Completed Completed Completed
Electrical Lighting Completed Completed Completed Completed Completed Completed Completed
Fire Alarm System Completed Completed Completed Completed Completed Completed Completed
Gas Detection System Completed Completed Completed Completed Completed Completed N/A
Structured Cabling Completed Completed Completed Completed Completed Completed Completed
Level-4
Audio Intercom Will be Install at the time of Handing over
CATV Completed Completed Completed Completed Completed Completed Completed
Will be Install at
CCTV N/A N/A N/A N/A N/A N/A the time of
Handing over
Floor Item Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Lift Lobby
Electrical Power Completed Completed Completed Completed Completed Completed Completed
Electrical Lighting Completed Completed Completed Completed Completed Completed Completed
Fire Alarm System Completed Completed Completed Completed Completed Completed Completed
Gas Detection System Completed Completed Completed Completed Completed Completed N/A
Structured Cabling Completed Completed Completed Completed Completed Completed Completed
Level-5
Audio Intercom Will be Install at the time of Handing over
CATV Completed Completed Completed Completed Completed Completed Completed
Will be Install at
CCTV N/A N/A N/A N/A N/A N/A the time of
Handing over
Floor Item Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Lift Lobby
Electrical Power Completed Completed Completed Completed Completed Completed Completed
Electrical Lighting Completed Completed Completed Completed Completed Completed Completed
Fire Alarm System Completed Completed Completed Completed Completed Completed Completed
Gas Detection System Completed Completed Completed Completed Completed Completed N/A
Structured Cabling Completed Completed Completed Completed Completed Completed Completed
Level-6
Audio Intercom Will be Install at the time of Handing over
CATV Completed Completed Completed Completed Completed Completed 25-Oct-20
Will be Install at
CCTV N/A N/A N/A N/A N/A N/A the time of
Handing over
Floor Item Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Lift Lobby
Electrical Power Completed Completed Completed Completed Completed Completed Completed
Electrical Lighting Completed Completed Completed Completed Completed Completed Completed
Fire Alarm System Completed Completed Completed Completed Completed Completed Completed
Gas Detection System Completed Completed Completed Completed Completed Completed N/A
Structured Cabling Completed Completed Completed Completed Completed Completed Completed
Level-7
Audio Intercom Will be Install at the time of Handing over
CATV Completed Completed Completed Completed Completed Completed 25-Oct-20
Will be Install at
CCTV N/A N/A N/A N/A N/A N/A the time of
Handing over
Floor Item Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Lift Lobby
Electrical Power Completed Completed Completed Completed Completed Completed Completed
Electrical Lighting 25-Oct-20 25-Oct-20 25-Oct-20 25-Oct-20 25-Oct-20 25-Oct-20 25-Oct-20
Fire Alarm System Completed Completed Completed Completed Completed Completed Completed
Gas Detection System Completed Completed Completed Completed Completed Completed N/A
Structured Cabling Completed Completed Completed Completed Completed Completed Completed
Level-8
Audio Intercom Will be Install at the time of Handing over
CATV Completed Completed Completed Completed Completed Completed 25-Oct-20
Will be Install at
CCTV N/A N/A N/A N/A N/A N/A the time of
Handing over
Floor Item Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Lift Lobby
Electrical Power Completed Completed Completed Completed Completed Completed Completed
Electrical Lighting 24-Oct-20 24-Oct-20 24-Oct-20 24-Oct-20 24-Oct-20 24-Oct-20 24-Oct-20
Fire Alarm System Completed Completed Completed Completed Completed Completed Completed
Gas Detection System Completed Completed Completed Completed Completed Completed N/A
Structured Cabling Completed Completed Completed Completed Completed Completed Completed
Level-9
Audio Intercom Will be Install at the time of Handing over
CATV Completed Completed Completed Completed Completed Completed 25-Oct-20
Will be Install at
CCTV N/A N/A N/A N/A N/A N/A the time of
Handing over
Floor Item Aprtment-B Aprtment-C Aprtment-D Aprtment-E Aprtment-F Aprtment-G Lift Lobby
Electrical Power Completed Completed Completed Completed Completed Completed 25-Oct-20
Electrical Lighting 25-Oct-20 25-Oct-20 25-Oct-20 25-Oct-20 25-Oct-20 25-Oct-20 25-Oct-20
Fire Alarm System Completed Completed Completed Completed Completed Completed Completed
Gas Detection System 23-Oct-20 23-Oct-20 23-Oct-20 23-Oct-20 23-Oct-20 23-Oct-20 N/A
Structured Cabling Completed Completed Completed Completed Completed Completed Completed
Level-10
Audio Intercom Will be Install at the time of Handing over
CATV Completed Completed Completed Completed Completed Completed 25-Oct-20
Will be Install at
CCTV N/A N/A N/A N/A N/A N/A the time of
Handing over
CATION WORKS)
Date: 31-Oct-2020
Remarks
Remarks
Remarks
Remarks
Remarks
Termination of incoming cables for DBs in El. Room not done
Mirror Light Not Install
Remarks
Termination of incoming cables for DBs in El. Room not done
Mirror Light Not Install
Remarks
Remarks
Termination of incoming cables for DBs in El. Room not done
Remarks
Termination of incoming cables for DBs in El. Room not done