LOCATION PHASE 1B. BLOCK 21, LOT 25 PRAMANA RESIDENTIAL PARK, STA. ROSA , LAGUNA
OWNER : ATTY. RICARDO VICTOR RAMOS
SUBJECT COST ESTIMATES
MATERIAL
ITEM DESCRIPTION UNIT QTY
UNIT COST
I. PRE CONSTRUCTION REQUIREMENTS
A Government Permit & Fees
1. Admin fee to process government fees
2. Barangay Permit
3. LGU Permit and Fees
B Contractor's All Risk Insurance
C Covid 19 Protocol
D Safety Officer
E Secuirty Deposit
SUB-TOTAL
II. CONSTRUCTION REQUIREMENTS
A GENERAL REQUIREMENTS
Mobilization/ Demobilization
Barracks/Transportation
Temporary Utilities (Power /Water) Consumables
Safety & Housekeeping
Equipment Rentals/Purchases
Gate Fees
SUB-TOTAL
B EXCAVATION WORKS/CIVIL-EARTHWORKS
Site Clearing
Structural Excavation (Basement/Footing/Tie Beam/Wall
- Wall Footing/Septic Vault/Cistern)
Backfill & Compaction
Construction Debris disposal
Gravel Bed
Soil Poisoning (Chemical soil Treatment-Anti Termite)
SUB-TOTAL
C FORM WORKS (Concrete Forming Accessories)
Column Footing
Shearwall
Cistern tank
Stairs
Grade Beams
Columns
Beams
Suspended Slabs
SUB-TOTAL
D REBAR WORKS
SUB-TOTAL
E CONCRETE WORKS (Ready Mix
SUB-TOTAL
F MASONRY WORKS
CHB walls
Exterior walls
Interior walls
Perimeter walls
Stairs
Plastering
SUB-TOTAL
G TINSMITHRY & STEEL FRAMING WORKS
Roofing Works
Stone coated roof tiles Feroof by Kawara
0.6mm Thk Rib Type Color Roof for substrate.
10mm Thk Insulation Foam Double sided Aluminum
Consumables
Roof Structural Steel framing
SUB-TOTAL
H FLOOR FINISH WORKS lot 1.00 OSM
TILES
Tile works at garage, lanai, living/dining, service areas)
Tile works bathrooms
Wood tiles at bedrooms
Trench drains
WOOD
Solid narra steps and handrail for stairs
Handrail solid narra
METAL
Gate at garage
Ballusters - tubular frame in metal painted finish
Railing for balconies
SUB-TOTAL
I WALL FINISHES
Ground Floor
Painting works Interiors lot 1.00 OSM
Painting work exterior
Painting work perimeter wall
Stone wall finishes at exterior
SUB-TOTAL
J WATER PROOFING WORKS
6 Mils Polyethelene-Dam Proofing
Hot process waterproofing
3 Ply Morta Seal-T&B/Balcony and concrete ledges
SUB-TOTAL
K CEILING FINISHES
Ground Floor
Toilets - 4'x8' Moisture Resistance Gypsum Bd Incl. Metal Frame
Other Interior areas - 4'x8' Ordinary Gypsum Board Incl. Metal Frame
2nd Floor
Toilets - 4'x8' Moisture Resistance Gypsum Bd Incl. Metal Frame
Other Interior Areas - 4'x8' Ordinary Gypsum Board Incl. Metal Frame
Exterior Area - Ficem board / hardiflex eaves and vent slats
-
L DOORS AND JAMBS
Solid Wood
Doors and Jambs
Solid Narra wooden door
Sliding Glass door at kitchen OSM
SUB-TOTAL
M WINDOWS
Windows lot 1.00 OSM
SUB-TOTAL
N FINISHING HARDWARE
Door Lockset hafele
3½" x 3½" Ball Bearing Stainless Door Hinge - Yale
SUB-TOTAL
O PAINTING WORKS
Walls
Ceiling and eaves
Doors and Door Frame in ducco finish
Cistern - in food grade epoxy finish
SUB-TOTAL
P CABINETRY WORKS lot 1.00 by others
SUB-TOTAL
R GLASS & GLAZING
Shower Enclosure
Facial Mirror OSM
SUB-TOTAL
S PLUMBING WORKS
Plumbing Fixtures (By Owner)
Water Closet OSM
Lavatory OSM
Kitchen Sink OSM
Floor Drain/Gutter Drain OSM
Water Heater - Ecotherm OSM
Shower Head & Valve OSM
Lavatory Faucet OSM
SUB-TOTAL
Roughing - In
Sanitary Waste & Vent (Emerald)
Cistern
Potable Water Distribution System (Fusion Type P.P.R)
Area Drain / Catch Basin
Grease Traps / Septic Tanks / etc
Grease Trap - 5 gpm
Septic Tank Including Manhole Cover
Aircon drains - 2" pipe
SUB-TOTAL
T ELECTRICAL WORKS
1 Rougn-in
2 Devices
3 Ceiling exhaust fans
4 Panel boards
U MECHANICAL WORKS
ACU's OSM
V ELECTRONIC WORKS
TOTAL
IV OVERHEAD AND SUPERVISION FEE
TOTAL COST, E-VAT EXCLUSIVE
IV EXCLUSIONS:
MATERIAL LABOR OTHERS
TOTAL
AMOUNT UNIT COST AMOUNT
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - - -
- -
- - -
- - -
- - - -
- - - -
- - -
- - -
- - -
- - -
- -
Notes:
FOR CONFIRMATION RESPONSIBLE
MECHANICAL WORKS
2 Confirmation ACCU/FCU inclung ding hangers, supports, miscellaneeous materials and labor by others Owner
Wiring from ACCU ECB to FCU by vendor.? Owner
Is the ECB of the ACCU is part of AC vendor ? Or part of electrical works? Owner
8 Exhaust and Kitechen is PVC duct based on layout while on detailed drawing duct sheet. Owner
Please confirm what to use? If duct sheet please provide size and specs.
Owner
9 Storage exhaust fan not reflected on theequipment schedule. Please povide the capacity. Owner
ELECTRCAL WORKS
5 Is the the water heater directly connected to the equipment? Do we need to provide outlet/GFCI/ breaker? Owner
If we need please specify what to use.
7 The back up pump has no prower supply , Please provide. Not reflected on the electrical plan. Owner
8 Is the ECB for the pumps included in the electrical? Not included in the plan Owner
PLUMBING WORKS
1 Exact distance of tapping point for the drainage pipe INFO. Cia to check actual
3 Civil works for plumbing not included . Estimate is fully piping only INFO. Cia to do take off
MATERIAL LABOR
ITEM DESCRIPTION UNIT QTY OTHERS TOTAL
UNIT COST AMOUNT UNIT COST AMOUNT
1 DRAINAGE LINE
150mm Ø lm 59
150mm Ø coupling No 20
200mm dia ( assume 5 meters tapping point) lm 35
Perforated Pipe
75mm Ø lm 55
75mm coupling Ø No 19
End Cap 75mm Ø No 9
100mm Ø lm 20
100mm Ø coupling No 7
Wye 100 mm x 75mm No 12
Elbow 75mm-90 deg No 11
Clean Out 100mm No 3
75mm Ø lm 98
100mm Ø lm 33
150mm Ø lm 30
75 mm Ø coupling No 33
100mm Ø coupling No 11
150mm Ø coupling No 10
75mm Ø Elbow- 90 Deg No 42
100mm Ø Elbow-90 Deg No 30
150mm Ø Elbow-90 Deg No 14
75mm Ø Wye No 12
100mm Ø x 75mm Ø Wye No 6
100mm Ø P Trap No 5
2 VENT LINE
50mm Ø lm 80
50mm Ø coupling No 27
50mm elbow Ø -90 Deg No 45
50mm Ø Tee No 27
50mm Ø lm 32
100mm Ø lm 53
150mm Ø lm 11
100mm Ø coupling No 18
150mm Ø coupling No 4
100mm Ø FCO No 9
150mm Ø FCO No 3
50mm Ø -45 Deg Elbow No 43
100mm Ø -45 Deg Elbow No 40
150 mm Ø -45 Deg Elbow No 7
50mm Ø -90 Deg Elbow No 8
100mm Ø -90Deg Elbow No 33
50mm Ø - Tee No 12
100mm Ø - Tee No 6
100x50mm Tee Reducer No 5
50mm Wye No 10
100mm Wye No 21
150mm Wye No 4
100 x 50mm Wyre Reducer No 13
150 x 100mm Wyre Reducer No 10
50mm P Trap No 8
50mm End Cap No 1
Kitchen Drain 50mm No 1
4 PLUMBING FIXTURES
Water Closet No 5
Lavatory No 5
Toilet Floor Drain 50mm No 8
Shower complete with Accessories No 4
Water Heater No 4
Grease Trap No 1
Kitchen Sink No 1
Bladder Tank 50 gallons No 1
PUMPS
PPR
20mm Ø lm 6
25mm Ø lm 50
40mm Ø lm 70
20mm Ø coupling No 2
25mm Ø coupling No 17
40mm Ø coupling No 24
20mm Ø Elbow No 10
25mm Ø Elbow No 30
40mm Ø Elbow No 20
40mm x 20mm Ø Tee No 5
40mm x 25mm Ø Tee No 12
Hose Bibb No 3
25mm Ø Gate Valve No 1
25mm Ø Check Valve No 1
15mm Ø lm 45
15mm Ø coulpling No 15
15mm Ø Elbow No 40
15mm Ø Tee No 10
15mm Ø End Cap No 3
25mm Ø lm 185
25mm Ø coulpling No 62
25mm Ø Elbow No 120
25mm Ø Tee No 25
25mm Ø End Cap No 10
25mm Ø Gate Valve No 7
25mm Angle Valve No 10
Note:
Assumption only;
MATERIAL LABOR
ITEM DESCRIPTION UNIT QTY OTHERS TOTAL
UNIT COST AMOUNT UNIT COST AMOUNT
KW-HR meter Base ( Kilo Watt Hour Meter by Meralco. Base by owner.) Set 1
4 GROUNDING SYSTEM
5 PIPES
50mm IMC lm 3
50mm IMC coupling No 1
50mm IMC Locknut and Bushing No 2
65mm IMC lm 25
65mm IMC coupling No 9
50mm IMC Locknut and Bushing No 4
6 BOXES
Pull Box ( 250mm x 250mm ) No 2
Square Box No 20
Junction Box No 20
25mm PVC Locknut and Bushing No 30
7 POWER OUTLETS
Duplex Outlet No 31
Duplex Outlet, WP No 10
Ref Outlet No 1
Range Outlet No 1
Rangehood Outlet No 1
GFCI No 4
Water Heater Outler, 30A No 4
Washing machine outlet , GFCI No 1
WAC Outlet, 20A No 1
Duplex outlet, ceiling mounted No 3
Doorbell No 1
Doorbel Buzzer 1
3.5mm2 lm 1062
5.5 mm2 lm 150
Utility Box No 59
Junction Box No 10
Square Box No 10
20mm dia PVC lm 354
25mm dia PVC lm 50
20mm Locknut and Bushing No 70
25mm Locknut and Bushing No 10
8 SWITCHES
3.5mm2 lm 832
Utility Box No 26
Junction Box No 8
Square Box No 5
20mm dia PVC lm 108
25mm dia PVC lm 80
20mm Locknut and Bushing No 26
25mm Locknut and Bushing No 10
9 LIGHTING FIXTURES
3.5mm2 lm 1230
Utility Box No 12
Octagonal Box No 70
Square Box No 10
20mm dia PVC lm 410
20mm Locknut and Bushing No 92
15mm Flexible metallic Conduit No 77
15mm Flexible metallic Connector No 154
AUXILIARY SYSTEM
Telephone Outlet No 5
Data Outlet No 5
Utility Box No 10
Square Box No 10
Telephone Pull Box No 1
Telephone Terminal Cabinet complete 100 pairs terminal Block No 1
CAT 5e UTP CABLE lm 150
25mm dia PVC lm 140
25mm Locknut and Bushing No 20
38mm dia IMC lm 21
38mm coupling No 7
38mm Service Entrance Cap No 1
2 CATV SYSTEM
CATV Outlet No 5
Utility Box No 5
Square Box No 5
CATV Pull Box No 1
RG59 Coaxial Cable lm 75
25 mm PVC pipe lm 70
25mm Locknut and Bushing No 10
38mm dia IMC lm 21
38mm coupling No 7
38mm Service Entrance Cap No 1
Note:
Assumption only;
1. For the Auxiliary works, just follow the layout. No single diagram
provided.
4. We used the spare breaker on the Panel PP for the back up pumps. No
more spare breakers
5. Assume outlet for Water Heater, is 30A. Normal outlet only. Not
indicated in the plan.
MECHANICAL WORKS
3 FLEXIBLE DUCT
150mm dia lm 9
200mm dia with insulation lm 2
4 EXHAUST FAN
Note:
Assumption only;