: AWE-FCCL-2022-08Rev00
Former Al-Hadeed Constructors Rev. No.: 00
Date : December 08, 2022
Kiln Shell Replacement Services for Cement Plant Line 1 Duration: 20 Days
Page : 1 of 1
Sequence of Activities & Estimation of Time Schedule Clint : Fauji Cement Ltd
Duration
S.No Description Strat Date End Date Remarks
Day
Dismantling
1 Installation of Bracing 8-Dec 12-Dec 4
2 Marking of Existing Shell for Cutting 12-Dec 12-Dec 0.5
3 Dismantling of Existing Shell 12-Dec 14-Dec 2
Installation
4 Beveling of existing shell & New Kiln Shell 14-Dec 15-Dec 0.5
7 Welding & Radio Graphic Test of New Kiln Shell 21-Dec 25-Dec 4
Commissioning
Total Days 21
AL-WAREED Engineering Privet Limited Doc. No.: AWE-FCCL-2022-08Rev00
Rev. No.: 00
Former Al-Hadeed Constructors
Date : December 08, 2022
Duration: 20 Days
Kiln Shell Replacement Services for Cement Plant Line 1 Page : 1 of 1
Clint : Fauji Cement Ltd
Dismantling
Installation of Bracing
Installation
Alignment and adjustment of the new Kiln shell with existing shell
Commissioning
Commissioning of Kiln