RIVER KING AYEYAR CONSTRUCTION CO., LTD.

Weekly Site Walk Report (No.025)

Project - R-8A
Date / Time of Observations: 06.10.2022 ( 16:43 hrs )
Recorded By – RKA Staff & Sub Contractor Doc No : 025

Item Action
No. Location Description of findings Required Action Target Complete Closure Photos Remark
By Date Date

01. In Front
of Need to do Myo
Site proper Lwin 06.10.2022 07.10.2022 Done It.
Entrance. housekeeping Oo

Near The
02. labour Need to do Myo
Shutter. proper Lwin 06.10.2022 07.10.2022 Done It.
housekeeping. Oo
RIVER KING AYEYAR CONSTRUCTION CO., LTD.

Weekly Site Walk Report (No.025)

Project - R-8A
Date / Time of Observations: 06.10.2022 ( 16:43 hrs )
Recorded By – RKA Staff & Sub Contractor Doc No : 025

Action Action Target Complete


Item Location Description of findings Required By Date Date Closure Photos Remark
No.

Need to keep Myo


03. Corner Properly. Lwin 06.10.2022 06.10.2022
Of show Don’t put on Oo Done It.
Gallery. the walk way.

Need to keep Myo


04. Corner of back scaffold Lwin 07.10.2022 07.10.2022
Show pipe to the Oo Done It.
gallery rack.
RIVER KING AYEYAR CONSTRUCTION CO., LTD.

Weekly Site Walk Report (No.025)

Project - R-8A
Date / Time of Observations: 06.10.2022 ( 16:43 hrs )
Recorded By – RKA Staff & Sub Contractor Doc No : 025

05. Near the Need to do Myo 07.10.2022 07.10.2022


Security housekeeping. Lwin Done It.
Gate. Oo.

Need to keep Myo


06. Near the back rebar to Lwin 07.10.2022 07.10.2022 Done It.
Corner of the rebar yard. Oo.
Show
gallery.