GREEN 

WORLD CONSTRUCTION 
Poblacion, Trinidad, Bohol 
 
 
July 27, 2022 
 
 
 
HON. JUDITH DEL ROSARIO CAJES 
Municipal Mayor 
Municipality of Trinidad 
 
 
Through:   ENGR. TEODOMIRO BALONGA 
    Municipal Engineer 
    Municipality of Trinidad 
 
 
Sir: 
 
 
Greetings! 
 
We are submitting to your office our TIME SUSPENSION REPORT for the period of June 23, 2022 to July 20, 2022 
for our Project REHABILITATION (CONCRETING) of M. CABIHUGAN – STO TOMAS ROAD, BEYOND KASILIOAN 
BRIDGE at M. Cabihugan, Trinidad, Bohol. 
 
 
Thank you. 
 
 
Truly, 
 
GREEN WORLD CONSTRUCTION 
By: 
 
 
__________________________ 
Contractor’s Authorized Officer 
 
 
 
RECEIVED BY  :________________________________________ 
DATE    :________________________________________ 
TIME SUSPENSION REPORT
For the Month of June 2022

Project Name: Rehabilitation (Concreting) of M.Cabihugan ‐ Sto Tomas Road, Beyond Kasilioan Bridge
Location: M Cabihugan, Trinidad Bohol

WEATHER TIME SUSPENDED 
DATE REMARKS
A.M P.M RECOMMENDED

June 23, 2022 Fair Fair Resume/Workable


June 24, 2022 Fair Fair Resume/Workable
June 25, 2022 Fair Fair Resume/Workable
June 26, 2022 Rainy Rainy Suspended 1
June 27, 2022 Rainy Rainy Suspended 1
June 28, 2022 Rainy Rainy Suspended 1
June 29, 2022 Rainy Rainy Suspended 1
June 30, 2022 Rainy Rainy Suspended 1

NOTE:
Subject to the condition that no additional claim shall be made by the contractor 
against the Project as a result of this time suspension.

1. Total Suspension of time recommended for this month 5 days
2. Total Suspension of time recommended previously 34 days
3. Grand Total to Date 39 days
4. Original Contract Time (Calendar Days) 90 days
5. Revised Contract Time (Calendar Days) ‐ days
6. Date of Effectivity of Contract March 30, 2022
7.Total Time Used this Month 3 days
8. Total Time Used Previously / Grand Total 52 days
9. Original Expiry Date June 28, 2022
10. Revised Expiry Date August 06, 2022

PREPARED BY: CHECKED AND REVIEWED BY:

____________________________ ENGR. TEODOMIRO BALONGA
Contractor Municipal Engineer
Green World Construction

APPROVED BY:

HON JUDITH DEL ROSARIO CAJES
Municipal Mayor
TIME SUSPENSION REPORT
For the Month of July 2022

Project Name: Rehabilitation (Concreting) of M.Cabihugan ‐ Sto Tomas Road, Beyond Kasilioan Bridge
Location: M Cabihugan, Trinidad Bohol

WEATHER TIME SUSPENDED 
DATE REMARKS
A.M P.M RECOMMENDED
July 01, 2022 Rainy Rainy Suspended 1
July 02, 2022 Cloudy Cloudy Suspended/Wet Soil ground 1
July 03, 2022 Rainy Rainy Suspended 1
July 04, 2022 Rainy Rainy Suspended 1
July 05, 2022 Rainy Rainy Suspended 1
July 06, 2022 Cloudy Cloudy Suspended/Wet Soil ground 1
July 07, 2022 Rainy Rainy Suspended 1
July 08, 2022 Rainy Rainy Suspended 1
July 09, 2022 Cloudy Cloudy Suspended/Wet Soil ground 1
July 10, 2022 Rainy Rainy Suspended 1
July 11, 2022 Cloudy Cloudy Suspended/Wet Soil ground 1
July 12, 2022 Rainy Rainy Suspended 1
July 13, 2022 Rainy Rainy Suspended 1
July 14, 2022 Rainy Rainy Suspended 1
July 15, 2022 Rainy Rainy Suspended 1
July 16, 2022 Rainy Rainy Suspended 1
July 17, 2022 Rainy Rainy Suspended 1
July 18, 2022 Rainy Rainy Suspended 1
July 19, 2022 Rainy Rainy Suspended 1
July 20, 2022 Rainy Rainy Suspended 1

NOTE:
Subject to the condition that no additional claim shall be made by the contractor 
against the Project as a result of this time suspension.

1. Total Suspension of time recommended for this month  20 days
2. Total Suspension of time recommended previously 39 days
3. Grand Total to Date 59 days
4. Original Contract Time (Calendar Days) 90 days
5. Revised Contract Time (Calendar Days) ‐ days
6. Date of Effectivity of Contract March 30, 2022
7.Total Time Used this Month 0 days
8. Total Time Used Previously / Grand Total 52 days
9. Original Expiry Date June 28, 2022
10. Revised Expiry Date August 26, 2022

PREPARED BY: CHECKED AND REVIEWED BY:

____________________________ ENGR. TEODOMIRO BALONGA
Contractor Municipal Engineer
Green World Construction

APPROVED BY:

HON JUDITH DEL ROSARIO CAJES
Municipal Mayor