Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


REGIONAL OFFICE IV-A
QUEZON 1ST DISTRICT ENGINEERING OFFICE
Barangay Abang, Lucban, Quezon

EXECUTIVE SUMMARY
(MONTHLY TIME SUSPENSION REPORT)
-For the month of OCTOBER to DECEMBER 2021-

A. SUBJECT : Request for Monthly Time Suspension Report for 21DK0180 –


Concreting of Barangay May-it FMR, Barangay May-it,
Lucban, Quezon

B. ACTION RECOMMENDED : For Approval

C. IMPLEMENTING OFFICE : DPWH-QUEZON 1st DISTRICT ENGINEERING OFFICE

D. REVIEWING OFFICE : Construction Section

E. REASON ON THIS SUSPENSION TIME :

We are presenting herewith the Monthly Time Suspension Report (MTSR) issued by this
office in tabulated form in connection with the Request for Monthly Time Suspension Report
(MTSR) for the month of October 03, 2021 to December 31, 2021 for the project 21DK0180
- Concreting of Barangay May-it FMR, Barangay May-it, Lucban, Quezon, under contract with
JEAN MARIE CONSTRUCTION AND SUPPLY. During the actual implementation of the
project, it could not be avoided that the project will be suspended due to unfavorable
weather which rendered unworkable condition at the project site. Often rain slows down
construction works and causes delay to the project.

DATE No. of Days Remarks


Suspended not
(Suspension Start (Date of Resume) including
Date) Sun/Hol
a October 03, 2021 October 06, 2021 2 Suspended due
b October 08, 2021 October 09, 2021 1 to bad weather
c October 12, 2021 October 19, 2021 6
d October 22, 2021 November 08, 2021 13
e November 12, 2021 November 18, 2021 5
f November 20, 2021 November 21, 2021 1
g November 23, 2021 December 01, 2021 6
h December 04, 2021 December 06, 2021 1
i December 07, 2021 December 09, 2021 1
j December 11, 2021 December 20, 2021 7
k December 25, 2021 January 01, 2022 4
Total 47

MTSR Requested (Oct. to Dec. 2021) ------------------------------ 47 Calendar Days

Total Monthly Time Suspension Report (If Approved) ----------- 47 Calendar Days

Page 1 of 2
F. CONTRACTUAL DATA:

Original Contract Amount : Php11,344,762.49


Revised Contract Amount due to Variation 1 : Php11,939,998.26
Original Contract Time : 105 Calendar Days
Effectivity of Contract : September 06, 2021
Original Expiry Date : December 19, 2021
Additional Calendar Days due to Variation 1 : 30 Calendar Days
Revised Expiry Date due to Variation 1 : January 18, 2022
Total Suspension Requested (due to MTSR) : 47 Calendar Days
Revised Expiry Date (If Approved) : March 06, 2022

In view of the favorable recommendation of the Project Engineer concerned and


further evaluation made by this office, approval of the request for the Time Suspension with
forty-seven (47) calendar days relative to the subject project is respectfully recommended
pursuant to D.O. No. 42, Series of 2020.

Notwithstanding the approval of the Time Suspension of forty-seven (47) calendar


days, the project is still subject to liquidated damages if the completion will be further
delayed.

We will not file any claims against the


Government due to this Time Suspension.

JEAN MARIE CONSTRUCTION


AND SUPPLY
Contractor

Prepared by : By : PATRICK A. POBEDA


Proprietor/Manager

BERNADETH D. HORA
Project Engineer

Noted : Recommending Approval :

EUFRONIA S. CABAYSA MELINDA E. STO. DOMINGO


Chief, Construction Section Assistant District Engineer
Approved:

For approval effective October 03, 2021 provided that the contractor
will not file any claims against the Government due to this Time Suspension.

MA. CHYMBELIN D. IBAL


District Engineer