1. SITE CLEARING
Starting the construction, we mitigate the process and approach to be used for
the site clearing. Amidst the operation our team didn’t anticipate the large land profile of
the site that needed to be cleared. Schedule-wise, the item of earthworks such as
clearing, excavation and layout / stacking lasted for two weeks. With this expense we
decide to have additional heavy equipment (Backhoe) on the second week of the
operation. With this action the additional equipment sufficed the delay.
2. WEATHER CONDITIONS
The successive rainfall that was experienced at the construction site was shown below:
2021
MAY JUNE JULY
5 1 1
18 2 2
21 7 3
22 8 5
23 9 6
24 12
20
21
22
23
24
25
This showed that the amount of rainfall was a disadvantage in our operation
during that time and given the fact that continuation of the manpower deployment will
result to inevitable waste of materials and substandard end result. It is unfortunate that
the latter come up to the decision to delay the operation. With that being said, the whole
team is humbly asking for a schedule extension of the Construction of One-Storey
Commercial Building Project.
Thank you.
Respectfully yours,