You are on page 1of 1

June 08.

2021

EDWARD C. ALBARACIN
Director III
Philippine Science High School-MIMAROPA Region Campus
Brgy Rizal, Odiongan, Romblon

Project: Design and Build Scheme Infrastructure Project: Elevated Water Tank

Subject: Consolidation of Time Extension Request - 2

Sir;

Reference to the above and further to our all submitted letters, please find below summary report of our
total requested time extension and its corresponding status for your review and approval.

No. of No. of days to


S/N Date Description days be approved Remarks
requested
1 October 7, 2020 Consolidation of Time 156 days 156 days Dec 2019 to July 30, 2020
Extension Request 1
2 Jan 25, 2020 Due to Bad Weather 85 days 85 days Sep 8, 2020 to Dec 24, 2020
3 March 17, 2021 Due to Bad Weather 35 days 35 days Jan 1, 2021 to Mar 13, 2021
4 March 17, 2021 Site Instruction no. 07 Time duration to complete S.I.
5 June 4, 2021 Due to Bad Weather 26 days 26 days Mar 23, 2021 to June 4, 2021

Submission of revised construction schedule will be submitted in the soonest.

Thank you for your kind consideration.

Very truly yours, Approved and Conformed by:

DOMINIC NINO Y. CABRAL


Project Manager PSHS - MRC