June 09.

2021

EDWARD C. ALBARACIN
Director III
Philippine Science High School-MIMAROPA Region Campus
Brgy Rizal, Odiongan, Romblon

Project: Design and Build Scheme Infrastructure Project: Completion of School Canteen &
Students Activity Center

Subject: Revised Completion Date

Sir;

Reference to the above and further to our letters regarding request for time extension dated
June 08, 2021, we would like to submit the revised completion date with the following computation:

Date of Contract: January 13, 2020


Project Started: January 15, 2020
Project Duration: 220 Calendar Days
Original Project Completion Date: August 22, 2020
EOT June 08, 2021 373 Calendar Days
Revised Project Completion Date: August 30, 2021

Thank you for your kind consideration.

Very truly yours, Approved and Conformed by:

DOMINIC NINO Y. CABRAL


Project Manager PSHS - MRC