You are on page 1of 2

3 DURATION

3.1 TIMELINE

A 2-Storey Residential Building project schedule provides a comprehensive overview of the complete
effort. The given visuals were to present for the clients to foresee the going project in chronological
order with a specific timeline.

Survey Developed detailed Construction


Instructed drawings and final begins
materials

Technical
Initial
Client Brief Measured Design
Concept Identification of Contractor Post
design/ Initial Design & budget Budget Evaluation
meeting Survey Development needed Mobalisation occupancy
design Specification for the project evaluation

3.2 EXECUTIVE MILESTONES

MILESTONE COMPLETION DATE


Meeting with the client September 2022
Designing and Planning October 2022
Building permit application October 2022
Finalization of design and planning November 2022
Securing financing, equipment or resources November 2022
Site preparation December 2022
Site work December 2022
Construction Mobilization January 2023
Foundation construction January 2023
Rough Framing February 2023
Major components and dry wall February 2023
Interior Finishes March 2023
Final Finishes March 2023
8 PROJECT CHARTER APPROVAL

The undersigned authorize and fund the Project: Two-Storey Residential Building and confirm that they
have read the project charter. The signatories or their chosen representatives will collaborate with any
changes to this project charter and provide their approval.

Signature: Date: 17/09/2022

Name: Ronalyn Y. Comendador

Title: Project Leader

Signature Date: 17/09/2022

Name: Andre R. Consul

Title: Project Manager

Signature: Date: 17/09/2022

Name: Jun Rey Cuysona

Title: Project Officer

Signature: Date: 17/09/2022

Name: Carlos Miguel A. Dauz

Title: Project Officer

Signature: Date: 17/09/2022

Name: Sheena Fe C. Dente

Title: Project Officer

You might also like