Proposed 85 Henley Drive Waterfalls Clusters

Indicative Program of Works


Task Name Duration Start Date End Date

Project Initiation 2 Month 15 September 23 November


2023 2023
 Obtaining Project Data
 Commercial Offer to Land Owner
 Land Owner Formal Acceptance
 Draft Development Agreement &
Negotiations
 Signing of Development Agreements

Permits & Project Preparation 3 months 7 November 2023 26 January 2024


 Project Legal, marketing, financial, technical
Feasibility Studies
 Permits and approvals

Design Development & Cost Budgeting 3 months 20 November 2023 14 February


 Concept designs 2024
 Engineering designs
 Approval of drawings by Harare City Council
 Costings based on approved designs

Fund raising – Provisional To Be determined by 3 Months 06 November 2023 26 January 2024


market response

Main Construction Works 12 Months 11 March 2024 07 February


2025

NB: This program is indicative because there are factors beyond our control that may affect
timelines. These include Development Permit processes and real estate market conditions.