Construction of Tech Tower 2 – SRM KTR

Project Review Meeting – 30.01.2022


Project Status as on 30.01.2023
Time Status Project Completion Date:
Financial Status
28-Apr-24
Contractual Project Start Date 15-Sep-2022
Contract Value Today Date: 30-Jan-23
Duration in Months 18 Months (Revised BOQ 75 Cr 75 Cr Only
Waiting for approval)

454
Contractual Project Completion Date 14-Mar-2024
Revised Project Start Date 22-Sep-2022
Completed Value 11.37 Cr
Revised Project Completion Date
28-Apr-2024

Contractual Duration in Days 538 Balance Value 63.63 Cr


Time Elapsed in Days 75 Work Completion % days left to
15 complete project
Time Elapsed in % 8

Project Progress as on 30.01.2023 – 11.5%


Financial Summary of Tech Tower Project

Claimed Value up
Work Order Work Done Value up To Be Billed as on
S. No Works to 02.01.2023 (RAB Work in Progress
Value to jan 2023 25.01.2023
01)

Construction of Tech Tower 2 – SRM KTR


1 Civil 75,17,98,644 11,37,85,864 9,42,58,645 1,05,90,309 3,01,17,528
Grand Total 75,17,98,644 11,37,85,864.00 9,42,58,645.00 1,05,90,309.00 3,01,17,528.00

TARGET FOR FEB 2023


S. No Works Work Order Value Plan Value up to FEB 2023

Construction of Tech Tower 2 – SRM KTR


1 Civil 75,17,98,644 94,49,300.00

Grand Total 75,17,98,644 94,49,300.00


January Planned vs Actual Tech Tower Project
Total Completed Balance
Sl.No Description
Qty Unit Amount Qty Amount Qty Amount
1 Raft Pour 2 balance
Reinforcement steel laying 242 MT 23092608 190 18130560 52 4962048
Shuttering works 109 SQM 59187 109 59187
RCC Raft 603.45 CUM 4982687 603 4982687
Back filling 5850 Cum 1327950 4680 1062360 1170 265590
2 NGL Plinth beam
M.Sand Filling 2 Cum 5883 13 44616
PCC 2 Cum 12936 13 91091
Reinforcement steel laying 2 Mt 145522 0 36380 1 109141
Shuttering works 55 Sqm 29865 14 7466 41 22399
RCC 11 Cum 94328 4 34901 7 59427
3 Basement Brick work
NGL Plinth beam above 25 Cum 249675 12 119844 13 129831

TOTAL AMOUNT 30000641 19527219 10590309


Reasons for Non Achievement
16 13.96 Cumulative Financial Progress

12 11.37 Cumulative Planned


1.15 13.96
1.1 Value up to Jan’23
1.1
8
1.05 Achieved Value up
4 2.59 11.37
1 to Jan’23
0 0.95 0.94
2.59
Cumulative Achieved Non Achieved Non Achieved Value
0.9
Planned Value Value up to Value Value
up to Jan’23 Jan’23 0.85
Feb Mar Target Completion % 81%

Reasons for Non Achievement for Civil Targets


Description of the Work Scope Completed Justifications for Not Achieved Present Status
Note :
Footing 3014 Cum 2284 Cum 75 % Completed
Drawing changes
Maximum delay and due to heavy
Column upto pedastal 38 nos 14 Nos rain and cyclone 2 times . After rain 75 % Completed
minimum 5 days regular works
affected due to wet soil condition
and dewatering works.
Plinth Beam at NGL 440 M 340 M 25 % Completed

Brick work 25 Cum 12 Cum 50 % Completed


For Jan target
       
JAN 23 Month Financial Target & Hindrances

Planned
S.No Description of work Value in Hindrance Responsible
Cr

Drawing Revised 3times


(Revised Drawing
1 Plinth beam and Grade slab 3.00 received on 19.01.2023) CLIENT SRM
Still Grid 2 is on Hold

Reinforcement steel On
2 Raft works 19.01.2023 and
26.01.2023
Labour/ Material Requirements – Feb ’23

Available at site Balance to be


S.No83 Description Uom Required required

1 Carpender & Helper Nos 15 15 0

2 Barbender & Helper Nos 30 24 6

3 Unskilled Nos 25 25 0

S.No Description Uom Required Remarks

Senior Site Engineer


1 Minimum 5 years 01 Nos
experience

2 Fresher 01 Nos
DRAWING REQUIREMENTS
• 1)Section BB Slab Grade of concrete
• 2)Is there any M sand Filling, LDPE Sheet and PCC needed below the escalator base slab
• 3)Is there any Plinth beam at FFL for duct ,Shaft,Toilet outer walls ,In electrical
rooms,Service area ?
• 4)Service area floor level is (+)0.00 , whether FFL plinth beam is need or not,If needed
kindly give Section details
• 5)Inner plastering for brick walls at basement level is need or not
• 7)NGL Plinth beam top to FFL is 1.25 m only,but in the above drawing it was mentioned
as 1.35 m
• 8)RCW 1 Grade of concrete
• 9)Lift opening details
• 10)Staircase details
• 11)Section Details X1,X2,X4,Y1
• 12)Ground floor and typical floor roof beam and slab drawings
• 13)Arch Beam reinforcement lapping arrangement approval
Project Supply Requirements for Upcoming Month (Feb ’ 23 )

S.No Description Uom Required Remarks

1 Cement Bags 600

2 Steel Mt 0

3 M Sand Unit 100

4 RMC Cum 603

5 Bricks for basement works Nos -

6 Plywood Nos -

7 Runner Cft -
SRM KTR Delay Hindrance details
Tech Tower 2 Building
No of
Sl.N Work status as on
Description As per schedule Actual days Remarks
o delay 24.01.2023

TECH TOWER Start date Finish date Start date Finish date
1 Earth work 26-Sep-22 13-Oct-22 22-Sep-22 19-Nov-22 37
2 PCC for Raft 10-Oct-22 15-Oct-22 10-Oct-22 22-Nov-22 38

3 Raft steel 12-Oct-22 26-Oct-22 18-Oct-22 85% work


completed
60% work
4 Raft shuttering 18-Oct-22 26-Oct-22 29-Nov-22
completed
Pour 1 and Pour
5 Raft RCC 27-Oct-22 31-Oct-22 16-Dec-22 75% completed 2 ( 1st part)
completed
Pedestal upto Drawing Revised
6 Plinth beam 28-Oct-22 09-Nov-22 06-Jan-23 75% completed on 05/01/2023

7 Plinth beam 05-Nov-22 12-Nov-22 18-Jan-23 25% completed Drawing Revised


on 11/01/2023

8 Basement 12-Nov-22 17-Nov-22 25-Jan-23


Masonry works

Pedastal and
Plinth beam final
GFC drawing
9 Back filling 15-Nov-22 20-Nov-22 05-Jan-23
Received on 05
jan and 11 jan
respectively

GFC Drawing
10 Grade slab 19-Nov-22 25-Nov-22 04-Mar-23 received on
19.01.2023
SRM KTR Delay Hindrance details
Tech Tower 2 Building
No of days Delay due to drawing
Sl.No Description Start Finish Drawing issue date Rain Client clearance Remarks
delay issue

Earth work excavation clearance


1 delay

Auditirium function 23-Sep-22 25-Sep-22 3 3


Auditorium power line clearance 01-Oct-22 06-Oct-22 6 6
Chiller line clearance 16-Oct-22 26-Oct-22 11 11
Wet soil condition vehicle not not
30-Oct-22 14-Nov-22 16 16
entered in site due to Heavy rain
2 PCC for Raft
Chiller line clearance &
16-Oct-22 26-Oct-22 10 10
Auditorium power line clearance

3 Raft RCC 27-Oct-22 24-Nov-22 28 28

4 Plinth beam 05-Nov-22 24-Nov-22 19 19


Drawing not
5 Grade slab flooring 19-Nov-22 received 38

6 Ground floor roof slab

Column lifting 23-Nov-22 Drawing not 34


received
Drawing not
Roof slab 26-Nov-22 31
received
1 Rain delay
01-Nov-22 to 25 dec 22 10 days
Total 10
SRM KTR Site - Program
Tech Tower 2 Building
Sl.No Description Duration Start Finish
1 Raft Pour 2 balance
Reinforcement steel laying 6 23-Jan-23 29-Jan-23
Shuttering works 3 26-Jan-23 29-Jan-23
RCC Raft 1 30-Jan-23 31-Jan-23
Raft beam & Drop shuttering 1 31-Jan-23 01-Feb-23
Raft beam & Drop RCC 1 01-Feb-23 01-Feb-23
Back filling 3 24-Jan-23 27-Jan-23
2 NGL Plinth beam
M.Sand Filling 20 17-Jan-23 06-Feb-23
PCC 20 18-Jan-23 06-Feb-23
Reinforcement steel laying 20 19-Jan-23 08-Feb-23
Shuttering works 20 19-Jan-23 08-Feb-23
RCC 20 20-Jan-23 09-Feb-23
3 Basement Brick work
NGL Plinth beam above 19 27-Jan-23 15-Feb-23
Back filling with consolidation 15 03-Feb-23 18-Feb-23
4 Grade slab beam
M.Sand Filling 11 08-Feb-23 19-Feb-23
PCC 13 09-Feb-23 22-Feb-23
Reinforcement steel laying 15 10-Feb-23 25-Feb-23
Shuttering works 15 11-Feb-23 26-Feb-23
RCC 12 15-Feb-23 27-Feb-23
Backfilling and Consolidation 10 18-Feb-23 28-Feb-23
Project Progress Images
TOP VIEW TECH TOWER -2

ON 12.01.2023 ON 30.01.2023
PROGRESS STATUS

STATUS
South west corner Pour 1

ON 12.01.2023 ON 30.01.2023
North WEST

On 12.01.2023 On 30.01.2023
•.
NORTH EAST corner

ON 12.01.2023 ON 30.01.2023
South East corner

ON 12.01.2023 ON 30.01.2023
QA&QC – Slide presentation
Quality Tracker – NC open Vs Closed
S.No Description Total NC Closed Opened

1 Total No.of NC - - -
Cube Register
S.No Description Total Set Passed Failed Balance to
of cube be tested
1 M40 Trial Mix 1 1 - -
2 M40 SCC Trial Mix 1 1 - -
3 M40 Grade        
  7 days 65 65 - 0
  14 days 65 48 - 17
  28 Days 65 30 - 35
4 M40 SCC Grade        
  7 days 15 15 - -
  14 days 15 15 - -
  28 Days 15 15 - -
  Total Nos 240 188 - 52
QC– Slide presentation
SAFETY SLIDE
TECH TOWER 2
Tactive – status

• Material Receipt entry


• Local purchase – 18.01.2023
• SPR RMC,Bulk materials etc – 18.01.2023

• Material Issue Register – Upto Nov 22 completed, Dec 22 entry in


progress
• Labour/ Sub contract bill status – 15.01.2023
• Shuttering hire - Tactive status – In progress (HO)
• Machinery Hire – Tactive status - In progress (HO)
• Client bill entry - – Tactive status - In progress (HO)
Thank You