Approved Cost: Rs: 15.969 (M) dated 17.01.2023.
T.S Cost: Rs: 15.969 (M) dated 18.01.2023.
Contractor: Muhammad Ijaz Asghar
Agreement Amount: Rs. 13.013 (M).
Time Limit: 6-Months

Date of Start:- 22.06.2023.

Date of Compl: 21.12.2023.

Scope of work:

1 Litigant shed 2795 Sft


2 Steel Banches 30- Nos
3 External Development

Financial Progress:
Year Allocation Allotment Expdr. % Age

2023-24 15.969 9.410 6.168 66%


Total 15.969 9.410 6.168 66%

Physical Progress:

Litigant shed : Brick work upto roof level.


PROJECT BRIEF

CONSTRUCTION OF MOSQUE IN JUDICIAL COMPLEX


SARGODHA.
Approved Cost: Rs: 29.704 (M) dated 07.09.2022.
T.S Cost: Rs: 36.286 (M) dated 21.09.2022.
Contractor: AR Builders & Developers
Agreement Amount: Rs.30.084 (M).
Time Limit: 12-Months

Date of Start:- 27.10.2022.

Date of Compl: 26.10.2023.

Scope of work:

1 Mosque Building 2993 Sft


2 Prayer yard
3 Minar
4 Ablution Area 1142 Sft

Financial Progress:
Year Allocation Allotment Expdr. % Age

2022-23 29.704 29.704 29.704 100%


Total 29.704 29.704 29.704 100%

Physical Progress:

Mosque Building Flooring in progress


Prayer yard Flooring in progress
Minar Finishing in progress
Ablution Area Flooring in progress