Contractor : FF CRUZ & CO., INC. Variance -43.72% A.P.13.02 Original Contract Value for Construction 612,023,852
Approved Variation Orders -
Contractual Milestones Var 25.52
Revised Contract Value for Construction 612,023,852
0 50 100
Effective Date : 26 Nov 2018 3.0 Resources Status 4.0 Health, Safety & Environment
Proj Completion : 25 April 2019
Proj Duration : 150 DAYS Indirect Manpower 24 Nos. Man-hours Worked (Feb 1 -28, 2019) 43,640 Hrs
Project Elapsed : 94days Direct Manpower 46 Nos. Man-hours Worked (since Proj Start) 101,675 Hrs
Proj Days to Go : 56 days Nos. Lost Time Incidents (Since Proj Start) - Nos
Nos. Near Misses/Incidents Reported ( for this Month) 1 Nos
Total Resources Involved 70 Nos.
Description of Works 5.0 Monthly Progress Highlights 7.0 Monthly Progress Photos
Mobilization
The activities on this project covers the
● moblization 100% done
following activities:
Section 2 : Reclamation
It includes sandfilling works, installation
Engineering / Procurement
of primary and secondary rock armour,
PVDs And Geotextile
Section3: Monitoring And Instrumentation
Section 4: Paving and Fencing
Construction
It includes Temporary Terminal Fencing,
pavement works and truckpave ● As of Feb 28, 2019, 49,788 cumulative cu.m of sand were unload to the offshore
(Required cu.m 371,205.84, progress is 13.41%)
● 1008 m / 1008 m length of H -Piles were driven for TIPSI Temporary Load- out
Facility at Pier 3, 100% complete Unloading of Sandfill materials
(Cumulative Volume = 49,788 cu.m) on February 28, 2019
● Tire Fender is 100% installed, horizontal support flanges are partially fully weld
and Walkway and Stairs & Railings are on-going
Page 1of 1