PT. OSAII committed to develop and execute the project execution plan for the bid
Valve Maintenance Repair Services STC-0603 to achieve the excellent valve
maintenance and repair result with safely completion of the job to the client of
Pertamina PHE ONWJ Ltd.
The project execution plan will be ready to start within 1 (one) month after the bid
awarded to our company, the commitment of readiness operations of valve
maintenance repair services will cover the following items:
Administration
Performance bond
HSE Plan
Please refer to HSE Plan of PT. OSAII for Valve Maintenance Repair Services Bid
STC-0603.
The main target of PT. OSAII HSE Plan and Execution are:
0 (Zero) Target of Incident
0 (Zero) Target of Accident
0 (Zero) Target of Equipment Damage
Planning of 50% from the total valves will be the base of maintenance management
plan for this project execution planning as the winner will be 2 (two) contractors.
Manpower Allocation
Man- Total
No. Description Hour Manpower/ Detail
Loading Month
Offshore Man-Hour Calculation
1. Database 237 1 1-Technician
2 On-line Maintenance 1,422 5 1 Supv.+2 Tech.+2 Helper
Insitu-Repair (10% from 288 2 1 Supv. + 1 Helper
Total)
3. Install & Dismantle 2,380 10 2 Supv.+4 Tech.+4 Helper
PT. OSAII has prepared the plan and ready to start the work for valve maintenance
repair services with completion of the following items:
HSE Management System Commitment with fully support from Top
Management to achieve excellent work and complete the job safely.
Availability of Competent Manpower Resources.
Availability of Professional Workshop Equipment Facilities, Offshore Tools
and Valve Management Performance to support the contract.
Manufacturer support from Dresser for the PSV and Control Valve.
Windrojo