Project Execution Plan

Valve Maintenance Repair Services Bid STC-0603

PT. OSAII committed to develop and execute the project execution plan for the bid
Valve Maintenance Repair Services STC-0603 to achieve the excellent valve
maintenance and repair result with safely completion of the job to the client of
Pertamina PHE ONWJ Ltd.

The project execution plan will be ready to start within 1 (one) month after the bid
awarded to our company, the commitment of readiness operations of valve
maintenance repair services will cover the following items:

Administration
Performance bond

HSE Plan
Please refer to HSE Plan of PT. OSAII for Valve Maintenance Repair Services Bid
STC-0603.

The main target of PT. OSAII HSE Plan and Execution are:
0 (Zero) Target of Incident
0 (Zero) Target of Accident
0 (Zero) Target of Equipment Damage

Maintenance Repair Services Plan


Information data obtained from the pre-bid meeting and bid document, the total active
valves in Pertamina PHE ONWJ Ltd. as follows:
Total Valves : 14,000 Ea
PSV : 3,000 Ea

Planning of 50% from the total valves will be the base of maintenance management
plan for this project execution planning as the winner will be 2 (two) contractors.

No. Description Total Qty 1 Year Plan Monthly Plan (Ea)


(Ea)
1. Valve 7,000 2,334 195
2. PSV 1,500 500 42
Total 237
Work Load Activity Plan of Maintenance Repair Services
Man-
Man-
No. Description Location Total/Month Hour
Hour/Qty
Loading
Offshore Man-Hour Calculation
1. Database Field 237 1 237
2 On-line Maintenance Field 237 6 1,422
Insitu-Repair (10% from Field 24 12 288
Total)
3. Install & Dismantle Field 119 20 2,380
Total 4,327
Onshore Man-Hour Calculation
4. Workshop Repair (50% Workshop 119 180 21,420
from Total)
5. Reporting:
On-line Maintenance Workshop 237 2 474
Workshop Repair Workshop 119 4 476
6. PSV Testing and Workshop 42 24 1,008
Certification
Total 23,378

Manpower Allocation
Man- Total
No. Description Hour Manpower/ Detail
Loading Month
Offshore Man-Hour Calculation
1. Database 237 1 1-Technician
2 On-line Maintenance 1,422 5 1 Supv.+2 Tech.+2 Helper
Insitu-Repair (10% from 288 2 1 Supv. + 1 Helper
Total)
3. Install & Dismantle 2,380 10 2 Supv.+4 Tech.+4 Helper

Onshore Man-Hour Calculation


4. Workshop Repair (50% 21,420 89 89 Workshop Personnel
from Total) with 12 hour work
5. Reporting:
On-line Maintenance 474 2 2 Assistant Valve Engineer
Workshop Repair 476 2 2 Valve Engineer
6. PSV Testing and 1,008 4 1 Supv. + 3 Helper
Certification
Note:
Manpower loading is based on 12 hours offshore work with schedule 2:1 and 2 shift
working schedule at our valve workshop Cikarang.

PT. OSAII has prepared the plan and ready to start the work for valve maintenance
repair services with completion of the following items:
 HSE Management System Commitment with fully support from Top
Management to achieve excellent work and complete the job safely.
 Availability of Competent Manpower Resources.
 Availability of Professional Workshop Equipment Facilities, Offshore Tools
and Valve Management Performance to support the contract.
 Manufacturer support from Dresser for the PSV and Control Valve.

Jakarta 15 April 2011

Windrojo
Director