Professional Documents
Culture Documents
CORRECTIVE MAINTENANCE
PROCEDURE
Document No. : EWP-PRO-SOP-002
Validity. : 25 Juni 2024
SUBJECT :
PURPOSE : Describes the work steps for Corrective Maintenance for HVAC in offshore platform and
various hazardous area.
PERSON(S) IN CHARGE :
1. 2.
3. 4.
5. 6.
DISTRIBUTION :
This document is subject to annual review for each revision (1 year validity from latest revision).
0 25/06/2021 Issued for Use Destian Wicaksana Yohanes Bryan Martini Lim
(Production Lead) (Project Manager) (President Director)
Page 1 of 7
Corrective Maintenance Procedure
25, June 2021
Table of Contents
1 Introduction .....................................................................................................................3
2 Abbreviations ..................................................................................................................3
3 Scope of Work .................................................................................................................3
3.1 Pre-Work Scope ................................................................................................................................... 4
3.2 Work Scope .......................................................................................................................................... 4
4 Reference, Drawings and Relevant Technical Data .....................................................6
5 Specific Issues, Safety and Concerns ..........................................................................7
6 Special Concern and Instruction ...................................................................................7
7 Testing Commissioning Procedure and Acceptance ..................................................7
8 QA/QC and Certification .................................................................................................7
9 Waste Disposal Plan .......................................................................................................7
10 Attachment ......................................................................................................................7
10.1 Performance test unit system Form ...................................................................................................... 7
10.2 BOQ (Bill of Quantity) Materials for Next Job .................................................................................... 7
Page 2 of 7
Corrective Maintenance Procedure
25, June 2021
1 Introduction
Based on the information from the Mubadala Petroleum team and the Eskimo team's
recommendations preventative maintenance is to be done on every Heating, Ventilation, and
Air Conditioning (HVAC) units and assets on PHE WMO platform including:
1. HVAC PPP
2. HVAC LQ PHE-5
3. HVAC MCC CPP1
4. HVAC TCP
5. HVAC MCC CPP2
2 Abbreviations
CM : Corrective Maintenance
PTW : Permit to Work
EER : Electronic Equipment Room
HVAC : Heating, Ventilation, and Air Conditioning
LQ : Living Quarter
3 Scope of Work
Page 3 of 7
Corrective Maintenance Procedure
25, June 2021
c. Clean and tidy work area is mandatory required during work to minimize any potential
risk.
d. Engineer should reffer and brief the team on the Standard Operating Procedure (SOP)
and Standard Task List for the activity about to be done on that day.
• Mobilization
a. All materials unable to be hand-carried will be mobilized to site via ORF Gresik using
commercial boat.
b. Contractor and Responsible Engineer should ensure all material and equipment
required to be delivered on site.
• General Pre-Caution
a. Perform Job Risk Assessment meeting to define the hazard and adequate precaution
to minimize the risk.
b. Ensure all Permit to Work (PTW) required to be approved by authorized party.
c. Ensure all precaution to be followed by all workers and all concerning party.
• Corrective Maintenance
1. HVAC Compressor.
2. Condenser.
3. Evaporator.
4. Electric Motor.
5. Oil Separator.
6. Fan and Blower.
7. Transmitter and Transducer also Switch.
8. Control Panel Parts and Accessories.
9. Electrical Parts and Accessories.
10. Damper parts and Accessories.
11. Ducting Parts and accessories.
12. Software.
Page 5 of 7
Corrective Maintenance Procedure
25, June 2021
The following reference, drawings and relevant technical data will be part of the SOP
attachments [if any].
The following documents [if any] are referred and used as reference:
Document No Description
N/A N/A
N/A N/A
The following technical data [if any] are referred and used as reference:
Parameter[s] Description
N/A N/A
N/A N/A
N/A N/A
Page 6 of 7
Corrective Maintenance Procedure
25, June 2021
All works to be carried out under guidance of PHE WMO Permit to Work (PTW) system.
Control the following risks when performing the work if applicable:
Personnel Exposures [Moving Parts, Hot surfaces, High Noise Levels, Dropped
Objects, Slips, Trips, Falls, odors, gases, toxic materials].
10 Attachment
Page 7 of 7