ATI MANILA SOUTH HARBOUR EXPANSION PROJECT : EIB RECLAMATION

Monthly Report No. 1 - January 2019, MPR -001


Project Month No. 3
Projects Details 1.0 Progress/Schedule Status & Trend 2.0 Financial Status Php

Owner : ATI, DP WORLD Planned 31.54% Plan 31.5


PMC : AECOM Actual 6.02%

Contractor : FF CRUZ & CO., INC. Variance This Month -25.52% 6.02
A.P. Original Contract Value for Construction 612,023,852
Approved Variation Orders -
Contractual Milestones Var 25.52
Revised Contract Value for Construction 612,023,852
0 50 100
Effective Date : 26 Nov 2018 3.0 Resources Status 4.0 Health, Safety & Environment
Proj Completion : 25 April 2019
Proj Duration : 150 DAYS Indirect Manpower 24 Nos. Man-hours Worked (Jan 1 - 31, 2019) 2,710 Hrs
Project Elapsed : 66 days Direct Manpower 45 Nos. Man-hours Worked (cumulative since Nov 56,841 Hrs
Proj Days to Go : 84 days Nos. Lost Time Incidents (cumulative) - Nos
Nos. Near Misses/Incidents Reported (cumulative) 1 Nos
Total Resources Involved 69 Nos.

Description of Works 5.0 Monthly Progress Highlights 7.0 Monthly Progress Photos
Mobilization
The activities on this project covers the
● moblization 100% done
following activities:
Section 2 : Reclamation
It includes sandfilling works, installation
Engineering / Procurement
of primary and secondary rock armour,
PVDs And Geotextile
Section3: Monitoring And Instrumentation
Section 4: Paving and Fencing
Construction
It includes Temporary Terminal Fencing,
pavement works and truckpave ● 10,290 cu.m of sand were unload to the offshore on marked areas of : "A6", "A9",
"A8", "A12", "A15", "A16", "A19" (Required cu.m 371,205.84, % progress is
2.77%)

● 576 m / 1008 m length of H -Piles were driven, 57% complete


Unloading of Sandfill materials by Barge Urbiztondo at Reclamation Area, A8 and A9
(Estimated Volume = 3,108 cu.m) on January 31, 2019

6.0 Areas of Concern

Page 1of 1
Driven H-Pile (16 sets - 324 x 611 x36m), 576 m of 1008 m length of piles driven
Identification of Long Lead Items=
CONTRACTOR to submit deliverables lists including all materials whose delivery
period is 5 weeks or more.
COMPANY RAISE CONCERN ABOUT SLOW PROGRESS FOR SUBMITTALS
AS PER EOT & ACTION PLAN the new dates for SHOP DRAWINGS on 21 APRIL
2015 And MATERIAL 28 MAR 2015
COMPANY inform CONTRACTOR that existing villa dismantling items list (with
GSD signature) should be submitted to GSD

COMPANY RAISED concern about delays in subcontractor approvals drawings &


materials approvals for swimming pool ,PQ submitted by DTF no 0272 on 23-2-
2015 also for ANTITERMITE its approved and LANDSCAPING to be done by EDICO

BOUNDARY WALL drawings submitted via DTF no 332 on 11-3-2015 approved B


on 18-3-2015,Design calculation submitted on 18-3-2015 via DTF 348. It was
resubmitted via DTF 433, DATED 07-04-2015 with received status C dated 12-
04-2015
Approved Senior Structural Engineer should attend the Progress Meeting
EDICO pointed outh that SPECIFICATION being used by the COMPANY
ENGINEERING TEAM is different for those issued to EDICO as part of CONTRACT
DOCUMENT DOSSIER and shall be provided to COMPANY ENGINEERING TEAM to
avoid further conflict to this effect