Contractor : FF CRUZ & CO., INC. Variance This Month -25.52% 6.02
A.P. Original Contract Value for Construction 612,023,852
Approved Variation Orders -
Contractual Milestones Var 25.52
Revised Contract Value for Construction 612,023,852
0 50 100
Effective Date : 26 Nov 2018 3.0 Resources Status 4.0 Health, Safety & Environment
Proj Completion : 25 April 2019
Proj Duration : 150 DAYS Indirect Manpower 24 Nos. Man-hours Worked (Jan 1 - 31, 2019) 2,710 Hrs
Project Elapsed : 66 days Direct Manpower 45 Nos. Man-hours Worked (cumulative since Nov 56,841 Hrs
Proj Days to Go : 84 days Nos. Lost Time Incidents (cumulative) - Nos
Nos. Near Misses/Incidents Reported (cumulative) 1 Nos
Total Resources Involved 69 Nos.
Description of Works 5.0 Monthly Progress Highlights 7.0 Monthly Progress Photos
Mobilization
The activities on this project covers the
● moblization 100% done
following activities:
Section 2 : Reclamation
It includes sandfilling works, installation
Engineering / Procurement
of primary and secondary rock armour,
PVDs And Geotextile
Section3: Monitoring And Instrumentation
Section 4: Paving and Fencing
Construction
It includes Temporary Terminal Fencing,
pavement works and truckpave ● 10,290 cu.m of sand were unload to the offshore on marked areas of : "A6", "A9",
"A8", "A12", "A15", "A16", "A19" (Required cu.m 371,205.84, % progress is
2.77%)
Page 1of 1
Driven H-Pile (16 sets - 324 x 611 x36m), 576 m of 1008 m length of piles driven
Identification of Long Lead Items=
CONTRACTOR to submit deliverables lists including all materials whose delivery
period is 5 weeks or more.
COMPANY RAISE CONCERN ABOUT SLOW PROGRESS FOR SUBMITTALS
AS PER EOT & ACTION PLAN the new dates for SHOP DRAWINGS on 21 APRIL
2015 And MATERIAL 28 MAR 2015
COMPANY inform CONTRACTOR that existing villa dismantling items list (with
GSD signature) should be submitted to GSD