S. No. Description of Item Nos. Length Unit Quantity CSR Rate CP %age Total Rate Cost
Ia Materials
CC 1:2:4 as per CSR 10.12
1x0.10x0.1x1.22 = 0.012 cum cum 0.012 2799.75 26% 3527.69 42.33
Reinforcement Steel as per CSR 18.17
8mm dia, length= (1.18+.06)= 1.24 mtr kg 0.48 49.83 16% 57.8 27.74
Formwork as per CSR 9.14
2x(0.1+1.22)x0.1 sqm 0.264 153.46 35% 207.17 54.69
Total - I 124.76
II Labour (For transportation and fixing)
Taking output 57 no.
(i) Mate Day 0.57 293.72 0% 293.72 167.42
(ii) Mazdoor Unskilled (Semi Skilled Lower) Day 14.25 263.72 0% 263.72 3758.01
Machinery
(iv) Tractor Trolly as per CSR 2.59 hour 6 250 13% 282.5 1695
5620.43
Sundries such as traffic management during construction, watch and ward, minor T&P, rehandling
of materials etc. @ 2% i.e. on Total - II 112.41
Add contractor's profit & Overhead Charges @ 21.5% i.e. on Rs. 5732.84 1232.56
6965.4
Labour for 57 no. 6965.4
Labour for 1 no. Total - II 122.2
Certificate
1.) The rate of the material are the lowest market rates.
2.) The rate of labour are as per CSR/Labour commissioner rates.
3.) The lead taken for carriage is as per shortest possible route.