Melkasa-Sodere-Nuraera-
2 Yencomad 1,440,812,001.09 4.0 1-Jan-18 56.1 70.1 54.0 61.99 50.01 47.4 41.3 3 2 43.29 No Pass
Metehara
3 Adiarkay - Telmet 1,981,378,049.64 4.0 17-Jan-19 36.0 45.0 41.4 20.27 80.1 No
4 Koshe-Mito-Werabe Road Project 1,850,695,155.03 4.0 23-Oct-20 36.0 45.0 20.2 24.11 20.4 No
5 Degolo - Kelela Road Project 1,469,861,944.62 3.0 8-Apr-17 70.0 87.5 62.8 84.99 42.9 No
6 Debrebirhan - Ankober Sunshine 1,623,194,217.85 6.0 23-Oct-18 36.7 45.9 44.3 70.85 39.51 91.0 35.7 4 3 38.73 No Pass
9 Kong-Begondi-Wenbera 1,587,200,899.42 3.0 11-Jan-13 85.6 107.0 113.7 100.91 100.0 Yes
16 Gishen Junction 1,316,700,000.00 4.0 27-May-20 30.0 37.6 25.1 3.57 38.7
Construction Works of
19 Alemketema - Degolo Road 1,280,770,840.15 3.0 28-Apr-17 66.7 83.4 62.1 52.29 45.2 No
Project
Gemeshu
Ginchi - Kachise -Chuleti; 58.86 45.0 2.0 - 44.96 Pass
20 Beyene GC 1,267,054,518.94 3.0 31-Dec-19 32.6 40.7 30.0 15.23 44.6 No
Contract 2: Shikute - Chuleti
Nekemte-Soge-Kamashe-Koncho;
21 1,923,629,581.78 6.0 24-Mar-21 36.0 45.0 15.2 - 11.6 No
Lot 2: Km 105-km 160
Engineering Procurement Directorate
Summary of Local Contractors' Performance Evaluation
Reporting Period End of June 2022
Reporting Period 30-Jun-22
1.25
Total contract Actual Aggregated Total Time elapsed
Revised Contract times Time No. of Additional
Mobilization period cumulative actual Average average is beyond 5/4 Pass/
I. Contractor's Price contract Elapsed Expected Contracts expected
Contract Name Period Commence considered progress to performance Expected expected of the Non
No. name (ETB) period (Months) Progress under progress
(months) ment Date for this date (%) (%) progress progress Contract Performing
(1.25* A) ( C) consideration (%)
Evaluation (A) (G) (in %) period
(B)
Nekemte-Soge-Kamashe-Koncho;
22 2,359,484,513.18 4.0 22-Feb-21 36.0 45.0 16.2 - 13.4 No
Lot 1: Nekemte - Km 105
Engineering Procurement Directorate
Summary of Local Contractors' Performance Evaluation
Reporting Period End of June 2022
Reporting Period 30-Jun-22
1.25
Total contract Actual Aggregated Total Time elapsed
Revised Contract times Time No. of Additional
Mobilization period cumulative actual Average average is beyond 5/4 Pass/
I. Contractor's Price contract Elapsed Expected Contracts expected
Contract Name Period Commence considered progress to performance Expected expected of the Non
No. name (ETB) period (Months) Progress under progress
(months) ment Date for this date (%) (%) progress progress Contract Performing
(1.25* A) ( C) consideration (%)
Evaluation (A) (G) (in %) period
(B)
23 Fik-Hamero Lot I Road Project 849,129,220.55 3.00 2-May-17 55.8 69.7 62.0 97.91 72.2 No
24 Adaba-Angetu Road Project 1,441,107,219.65 4.0 18-Nov-14 74.3 92.9 91.4 81.90 96.1 No
25 Warder - Kebridehar Road Project 1,814,123,577.90 4.0 10-Jun-19 48.0 60.0 36.7 40.42 33.7 No
Macro General
Not qualified
Contractor and 42.30 41.0 5.0 4.50 45.45
Fik - Segeg - Gerbo - Denan; Lot for tendering
Trading
26 II; Segeg - Gerbo - Yoale (Km 1,232,011,537.11 4.0 7-Jun-21 42.0 52.5 12.8 5.15 5.3 No
90+000 - Km 191+000)
Dubti - Arrisa - Adigala -
Biyokebob; Lot II: KM 72+000 -
27 1,482,000,000.00 4.0 27-May-21 36.0 45.0 13.1 5.12 8.0 No
KM150+000 Design and Build
Road Project
28 Dalol/Musli-Bada Road Project 1,249,624,731.89 3.00 28-Jan-16 49.8 62.3 77.1 89.05 100.0 Yes
Taremaber-Meleya-Molale' Defence
30 1,906,200,296.75 4.00 24-Dec-18 47.7 59.7 42.2 18.28 42.0 No Not qualified
Molale-Sefemeda Road Project Construction 31.01 48.4 5.0 4.50 52.87
for tendering
Enterprise (DCE)
Continuation of Ambo - Wolliso
31 1,264,907,396.11 3.00 26-Nov-19 32.2 40.3 31.1 29.73 47.7 No
Road Project
39 Dabat - Ajire Road Project 931,304,149.54 4.0 10-Oct-16 77.3 96.6 68.7 85.66 42.3 No
40 Ajire - Keraker Road Project 1,158,659,797.00 4.0 21-Sep-18 50.3 62.9 45.3 59.05 43.1 No
Powercon 41.21 24.8 4.0 3.00 27.85 Pass
Haik - Bitsma - Chifra Road
41 2,138,481,835.73 4.0 22-Dec-20 51.5 64.4 18.2 12.18 7.3
Project
Sodo Junction )Dimtu)-Bilate
42 2,375,680,864.47 4.0 14-Apr-22 36.0 45.0 2.5 0.16 - No
Military Training Center
43 Babille-Fik Lot I 432,482,654.80 4.0 2-May-17 63.3 79.1 62.0 79.04 48.6 No
44 Debre Markos - Debre Elias 1,299,644,371.61 4.0 18-Sep-19 40.3 50.3 33.4 47.92 38.2 No
Gode – Hargele, Lot 1: Gode – FAL General
45 1,893,759,386.74 4.0 6-Oct-20 48.0 60.0 20.8 21.98 33.95 12.3 23.1 4.0 3.00 26.08 No Pass
Km 100 Road Project Construction PLC
Engineering Procurement Directorate
Summary of Local Contractors' Performance Evaluation
Reporting Period End of June 2022
Reporting Period 30-Jun-22
1.25
Total contract Actual Aggregated Total Time elapsed
Revised Contract times Time No. of Additional
Mobilization period cumulative actual Average average is beyond 5/4 Pass/
I. Contractor's Price contract Elapsed Expected Contracts expected
Contract Name Period Commence considered progress to performance Expected expected of the Non
No. name (ETB) period (Months) Progress under progress
(months) ment Date for this date (%) (%) progress progress Contract Performing
(1.25* A) ( C) consideration (%)
Evaluation (A) (G) (in %) period
(B)
47 Babille-Fik Lot II Road Project 461,423,813.70 4.0 2-May-17 55.4 69.3 62.0 79.76 73.6 No
54 Assosa-Daleti Lot 1 228,630,902.66 3.0 7-Mar-17 60.8 76.0 63.8 77.11 60.0 No
Senan
19.97 14.9 2.0 - 14.93 Pass
Construction Plc.
55 Eliya - Makuye 1,083,400,000.00 4.0 23-Jul-21 36.0 45.0 11.2 7.91 5.4 No
Assosa-Daleti-Baruda, Contract 2:
56 772,048,982.83 4.0 1-May-17 63.7 79.7 62.0 63.96 48.1 No
Km 36+000 - Dabus - Baruda
Dangla - Jawi Design and Build Enyi
57 2,247,404,541.84 4.0 3-Jun-21 42.0 52.5 12.9 9.05 15.93 5.3 11.49 3.0 2.00 13.49 No Pass
Road Project Construction
Homosha – Hidassie Dam; Lot-1:
58 2,081,401,426.09 4.0 13-Jul-21 42.0 52.5 11.6 5.55 4.5 No
Homosha – Km 70
60 Azezo - Gonder Road Project 871,565,791.41 2.0 27-Oct-17 59.3 74.1 56.1 55.27 46.3 No
64 Weyito - Turmi Road Project 2,843,185,710.00 4.0 27-May-21 48.0 60.0 13.1 11.34 4.6 No
70 Continuation of Werabe - Bojaber 795,000,000.00 4.0 1-Oct-19 43.5 54.4 33.0 40.73 33.3 No
Powercon Plc in
JV with Tesfaye
73 Ajire -Keraker 1,158,659,797.00 4.0 21-Sep-18 50.3 62.9 45.3 59.05 59.05 43.1 43.1 1.0 - 43.15 No Pass
Legesse
Construction
78 Edo-Serofta-Warqa Road Project 1,687,343,877.25 4.0 24-Jan-19 50.7 63.4 41.2 57.93 37.0 No
Alemayehu
Negele Borena - Doloado - 40.15 25.5 2.0 - 25.49 Pass
Ketema GC
79 Melkasuftu, Lot 1 : Negele 1,371,325,369.08 4.0 30-Mar-21 36.0 45.0 15.0 18.27 11.3 No
Borena - Km 60
MCG
Negele Borena - Doloado - Construction PLC
80 Melkasuftu, Lot 1 : Negele in JV with 1,371,325,369.08 4.0 30-Mar-21 36.0 45.0 15.0 18.27 18.27 11.3 11.3 1.0 - 11.29 No Pass
Borena - Km 60 Alemayehu
Ketema GC
Omorate-Omo Bridge-Gynayom-
81 972,658,698.71 3.0 7-Feb-19 44.4 55.5 40.7 69.02 44.3 No
Kangaken
Gog-Jore-Akobo Raod Project
82 Contract 1 Lot I; km 0+000- 1,497,465,276.22 6.0 6-Aug-21 42.0 52.5 10.8 13.22 3.59 No
NKH Constrction
36+000 (Goge-Jore-Angella) 25.77 13.1 3.0 2.00 15.08 Pass
Plc.
Gambela –Abobo-Gog-Dima/Radd;
Lot III Km 72-Akuila-Achagna-
83 1,574,746,965.24 4.0 8-Oct-21 42.0 52.5 8.7 11.00 2.83 No
Dima/Radd Junction Design and
Build Road Project
Engineering Procurement Directorate
Summary of Local Contractors' Performance Evaluation
Reporting Period End of June 2022
Reporting Period 30-Jun-22
1.25
Total contract Actual Aggregated Total Time elapsed
Revised Contract times Time No. of Additional
Mobilization period cumulative actual Average average is beyond 5/4 Pass/
I. Contractor's Price contract Elapsed Expected Contracts expected
Contract Name Period Commence considered progress to performance Expected expected of the Non
No. name (ETB) period (Months) Progress under progress
(months) ment Date for this date (%) (%) progress progress Contract Performing
(1.25* A) ( C) consideration (%)
Evaluation (A) (G) (in %) period
(B)
95 Metu By-Pass Road Project 661,753,584.55 3.0 11-Feb-21 24.0 30.0 16.6 35.52 28.6 No
Oromia
Ambo town-Guder town Road Not qualified
96 Construction 1,038,722,506.06 4.0 16-Mar-21 24.0 30.0 15.5 27.58 11.77 25.6 10.9 3.0 2.00 12.89 No
Project for tendering
Corporation
97 Chanka - Gidami Road Project 3,206,772,589.87 3.0 20-Oct-21 48.0 60.0 8.3 1.75 2.5 No
Kibish
98 Bulbula - Alage Road Project 686,000,000.00 4.0 12-Nov-20 36.0 45.0 19.6 46.85 46.85 19.23 19.2 1.0 - 19.23 No Pass
Construction Plc.
Tiks Construction
Mankusa - Birsheleko (Defense
99 In Joint Ventury 972,716,279.92 4.0 8-Mar-21 36.0 45.0 15.7 18.54 18.54 12.56 12.6 1.0 - 12.56 No Pass
Camp) - 145 Kebele Road Project
with FAL GC
Engineering Procurement Directorate
Summary of Local Contractors' Performance Evaluation
Reporting Period End of June 2022
Reporting Period 30-Jun-22
1.25
Total contract Actual Aggregated Total Time elapsed
Revised Contract times Time No. of Additional
Mobilization period cumulative actual Average average is beyond 5/4 Pass/
I. Contractor's Price contract Elapsed Expected Contracts expected
Contract Name Period Commence considered progress to performance Expected expected of the Non
No. name (ETB) period (Months) Progress under progress
(months) ment Date for this date (%) (%) progress progress Contract Performing
(1.25* A) ( C) consideration (%)
Evaluation (A) (G) (in %) period
(B)
100 Combolcha Bypass 806,164,023.72 3.0 23-Jun-21 24.0 30.0 4.3 1.64 1.53 No
Yonab
Awash – Kulbi – Dire Dawa/Harar 6.63 5.0 2.0 - 5.04 Pass
Construction Plc.
Overlay Road Project; Contract 1:
101 478,385,156.18 3.0 5-Apr-21 36.0 45.0 14.8 15.05 10.95 No
Awash – Meiso (Km 0+000 –
70+500)
102 Jigjiga Bypass Road Project 672,098,730.28 4.0 14-May-21 18.0 22.5 13.5 11.60 32.92 No
Yirgalem Not qualified
15.88 27.0 2.0 - 27.00
Construction Plc. for tendering
103 Bonosha - Achamo Road Project 682,155,064.23 4.0 7-May-21 24.0 30.0 13.8 20.09 21.16 No
104 Shebele - Imi Road Project 249,613,616.05 1.5 15-Jul-21 10.0 12.5 11.5 - 80.14 No
Somali Roads Not qualified
- 80.1 1.0 - 80.14
Enterprise for tendering
105 Kubi River Bridge 113,055,906.20 3.0 8-Apr-22 12.0 15.0 2.7 - - No
DOGUSAN
Gode - Kelafo - Ferfer Lot 2: INSAAT TIC. A.S Not qualified
106 2,497,881,730.00 4.0 24-Aug-21 42.0 46.7 10.2 - - 3.72 3.7 1.0 - 3.72 No
Kelafo - Ferfer in JV with Rabah for tendering
and Sons PLC
Bure – Gomer Road Project, (Km
Midroc
0+000 – Km 41.30) and Bure Not qualified
107 Construction 1,365,798,491.89 3.0 21-Sep-21 36.0 40.0 9.3 2.46 2.46 4.18 4.2 1.0 - 4.18 No
Industrial Park Spur Road, for tendering
Ethiopia PLC
1.74km
Mankusa - Birsheleko(Defense
108 972,716,279.92 4.0 8-Mar-21 36.0 45.0 15.7 18.54 12.56 No
Camp) - 145 Kebele Road Project
Tiks Construction 8.30 7.8 2.0 - 7.79 Pass
Addis – Gibe River Road Overlay
109 1,651,808,351.17 4.0 10-Aug-21 36.0 45.0 10.7 2.27 4.99 No
Project; Lot III: Kore – Gibe River
Negele Borena - Doloado -
110 Melkasuftu, Lot 1 : Negele 1,371,325,369.08 4.0 30-Mar-21 36.0 45.0 15.0 18.27 11.29 No
Borena - Km 60 MCG
9.53 7.8 2.0 - 7.85 Pass
Construction PLC
Addis – Gibe River Road Overlay
111 1,651,808,351.17 4.0 10-Aug-21 36.0 45.0 10.7 2.27 4.99 No
Project; Lot III: Kore – Gibe River
Hafcon
Abay River Bridge and
Construction in
Approach Road Design & Build
112 JV with Cross 825,659,857.57 4.0 15-Sep-21 30.0 37.5 9.5 6.97 6.97 5.47 5.5 1.0 - 5.47 No Pass
Project, Lot 2: Abay River Bridge
Land
Approach Road
Construction
1 2
Formula to be
Category of Contract Period Contractors who failed to complete projects after one fourth of the
used
contract period elapsed beyond the Contract period will be
First (1/3)rd 6(t1)
disqualified
Second(1/3)rd 6+21(t2)
last (1/3)rd 27+23(t3)
Beyond Contract period 50+50(t4)