You are on page 1of 3

Sr. No.

1
(i)

II

(i)
(ii)
Item

CSR Item - 10.28


Damp proof course 4 cm thick of cement concrete 1: 2: 4 over toe wall (without Bitumen).

Unit
MATERIALS
Cement concrete 1:2:4
Rate as per item No. 10.12 (i)
Total-1
Add contractor's profit @ 10% i.e. on Rs.87.47
Labour cess on cost of material @ 1% i.e. on Rs. 87.47
Total-1
LABOUR
Taking output
Brick Mason Layer (1st Class)
Mazdoor (Un-Skilled)/Chowkidar/Cleaner
Total-11
Sunderies such as water @ 3% i.e. on Rs.360.05
Add Overhead charges & contractor profit @ 21.50% i.e on Rs.370.85
Labour cess on cost of labour @ 1% i.e. on Rs.450.58
Labour for
Labour for
Add Submountainous Region @ 10% i.e. on Rs. 37.92

cost per sqm


Quantity
Rate Cost Total

1 sqm

cum 0.040 2186.75 87.47


87.47
8.75
96.22 0.96
97.18 97.18

12 sqm
each 1.00 223.36 223.36
each 1.00 136.69 136.69
360.05
10.80
370.85 79.73
450.58 4.51
12 sqm, 455.09
1 sqm 37.92 37.92

135.10