For
The construction of Obicha River Bridge
Construction PROJECT
of existing condition of Project area, to have first hand information of the actual
condition of the site, local material source, Access of the road of the project and
other relevant information which is helpful for preparation of the technical
proposal and price quotation that will be undertaking after this pre qualification.
Accordingly, the findings and data collected during the exciting project visit are
summarized in further.
2. Project Location
And dire dawa availability and other related information including availability of
water for intended works to use the project efficiently.
The major part of the project area in the vicinity was grass land, Moderate Air
and part of one is forest area and others.
3.1.2 Geology
There are construction stone source that will be used for masonry works, at
nearby vicinities of Ambo sites.
b. Sand
There is sand source suitable for water work construction Obicha River in the
project areas.
The technical proposal we are adopting for the project is fully based on detail
examination of the sites and through understanding of the given Qualification
documents and Information we obtain. Our proposed method for the efficient
execution of the project is as described hereunder;
Up on receiving the Notice to commence the works the project activity will be
commenced by collecting complete set of Project Documents and project
Information, followed by organizing and equipping of the project team with the
necessary manpower & construction equipment within mobilization period of 5
days.
Within the time of project commencement period which takes place within 5 days
after site hand over of the project, the core project staff including General
Manager, Project Manager, Construction Forman & Chief Plumber will mobilize to
the project site for assessment of the project, site preparation and other
preliminary activities.
At this stage, the Project Manager and his core staff will meet with the local
respective authorities to conduct Community awareness pertaining to the project
area such as land acquisition and locating campsite and locally available
construction material utilization. Based on this information, the Project team will
prepare the practical work schedule, which eventually submitted to your
organization as a Final work schedule.
Surveying Crew of the project will start surveying works immediately after site
handover of the project, such as: set Control Points and adequate bench marks
for all structures at the first place and finally supervise the designed level and
layout of the project components.