You are on page 1of 4

RENOVATION WORKS AT DR CHONG CLINIC, BANGSAR KL

PROJECT START: 13/10/2023 RENOVATION START 16/10/2023 RENOVATION END 24/10/2023


WEEK & DATE Oct 16, 2023 Oct 23, 2023

16 17 18 19 20 21 22 23 24 25 26 27 28 29
SCOPE OF WORK PROGRESS START END
M T W T F S S M T W T F S S

PRELIMINARIES

Site Mobalisation 0% 23/10/2023 23/10/2023

TOILET AREA AND TREATMENT ROOM AT OLD WING

Disassemble work and install a new tiling works and other accessories 0% 23/10/2023 23/10/2023

Soundproofing indicator in every partition wall at the old wing 0% 23/10/2023 23/10/2023

Diassemble existing waterpump and install new waterpump 0% 23/10/2023 23/10/2023

Replace the existing exhaust fan and install new exhaust fan 0% 23/10/2023 23/10/2023

CARPENTRY WORKS

Dissassemble replace to new wood 16mm thickness ramp entrance 0% 23/10/2023 23/10/2023

Feature wall at reception wall area, beige fluted panel 0% 31/10/2023 03/11/2023

Spray paint gun with expoxy filler 1k at reception table area 0% 04/11/2023 06/11/2023

Custom acrylic golden paint alphabet; 7pcs (DR CHONG) 0% 06/11/2023 08/11/2023

Cleaning works with high grade detergent and waterjet 0% 09/11/2023


13/11/2023

Signage; DR CHONG CLINIC PREMIUM 0% 10/11/2023 13/11/2023

FLOORING WORKS

Remove cracked laminate floor and install a new laminate fooring

AWNING ROOF
Replace fabric to existing awning and install new awning; 35ft x 2.5m 0%
03/11/2023 07/11/2023

NOTE: This Master Work Program is based on the overall planning of the design and construction phase. Any delays or changes to the masterwork program dateline, we will update and inform to the client.
END 24/10/2023

You might also like