16 17 18 19 20 21 22 23 24 25 26 27 28 29
SCOPE OF WORK PROGRESS START END
M T W T F S S M T W T F S S
PRELIMINARIES
Disassemble work and install a new tiling works and other accessories 0% 23/10/2023 23/10/2023
Soundproofing indicator in every partition wall at the old wing 0% 23/10/2023 23/10/2023
Replace the existing exhaust fan and install new exhaust fan 0% 23/10/2023 23/10/2023
CARPENTRY WORKS
Dissassemble replace to new wood 16mm thickness ramp entrance 0% 23/10/2023 23/10/2023
Feature wall at reception wall area, beige fluted panel 0% 31/10/2023 03/11/2023
Spray paint gun with expoxy filler 1k at reception table area 0% 04/11/2023 06/11/2023
Custom acrylic golden paint alphabet; 7pcs (DR CHONG) 0% 06/11/2023 08/11/2023
FLOORING WORKS
AWNING ROOF
Replace fabric to existing awning and install new awning; 35ft x 2.5m 0%
03/11/2023 07/11/2023
NOTE: This Master Work Program is based on the overall planning of the design and construction phase. Any delays or changes to the masterwork program dateline, we will update and inform to the client.
END 24/10/2023