Monthly Progress Report – PK08

Time
From 01-April-2020 to 30-April-2020
Span:

3.4 Narrative Project Status


3.3.1 The Engineering and Submissions Status
This month shop drawings of basement floor columns have finished and submitted.

4 Progress Outline
4.1 Engineering
4.1.1 Drawing Submittals Status

Period (Month) Cumulative

Planned Actual Planned Actual to date

79 79 314 314

4.1.3 Shop Drawings process Status

Work Submitted Outstanding Responds Approved Revised and


Approved Rejected
Package to DAR with DAR by DAR as Noted Resubmit
1=2+3 2 3=4+5+6+7 4 5 6 7
Structure 10 1 9 4 3 2 0
Total 10 1 9 4 3 2 0

7 Quality Control
7.1 Engineering
7.1.1 Design Shop Drawing Submittals & Approval Log

Submittal Return
S/N Drawing Ref: No. Drawing Title Revision Status Remarks
Date Date

COLUMN C50 RFT DETAILS FROM


SHD-CSCEC-08-G00-
FOUNDATION LEVEL TO LOWER Approved as
1 ST-SC-13-BF-00-0035- 00 2020/4/13 2020/4/14 N/A
GROUND Noted
0000-00
LEVEL AT TOWER AREA

SHD-CSCEC-08-G00- COLUMINS DETAILS FROM


Approved as
2 ST-SC-13-BF-00-0034- FOUNDATION TO LOWER 00 2020/4/13 N/A N/A
Noted
0000-00 GROUND C29,C30

SHD-CSCEC-08-G00- COLUMINS DETAILS FROM


Approved as
3 ST-SC-13-BF-00-0036- FOUNDATION TO LOWER 00 2020/4/13 N/A N/A
Noted
0000-00 GROUND C31,C32,C33
SHD-CSCEC-08-G00- COLUMINS DETAILS FROM
Approved as
4 ST-SC-13-BF-00-0037- FOUNDATION TO LOWER 00 2020/4/13 N/A N/A
Noted
0000-00 GROUND C35,C36

12. Monthly Look Ahead Shop Drawing Submittals

S/N Drawing Title Nos of Drawing Revision Submit Date

1 CORE WALL DIMENSIONS FROM XX TO XX 12 00 2020/4/22

2 CORE WALL RFT FROM XX TO XX 8 00 2020/4/22

3 COLUMINS AND AXIS LOWER GROUND FLOOR 6 00 2020/4/23

4 LOWER GROUND FLOOR SLAB DIM. 4 00 2020/4/24