Weekly Progress Report - PK08

Time
From 18-April-2020 to 23-April-2020
Span:

3.4 Narrative Project Status


3.3.1 The Engineering and Submissions Status
This week shop drawings of basement floor columns have finished and submitted.

4 Progress Outline
4.1 Engineering
4.1.1 Drawing Submittals Status

Period (Week) Cumulative

Planned Actual Planned Actual to date

4 4 355 355

4.1.3 Shop Drawings process Status

Work Submitted Outstanding Responds Approved Revised and


Approved Rejected
Package to DAR with DAR by DAR as Noted Resubmit
1=2+3 2 3=4+5+6+7 4 5 6 7
Structure 10 1 9 4 3 2 0
Total 10 1 9 4 3 2 0

7 Quality Control
7.1 Engineering
7.1.1 Design Shop Drawing Submittals & Approval Log

Submittal Return
S/N Drawing Ref: No. Drawing Title Revision Status Remarks
Date Date

COLUMN C50 RFT DETAILS FROM


SHD-CSCEC-08-G00-
FOUNDATION LEVEL TO LOWER Approved as
1 ST-SC-13-BF-00-0035- 00 2020/4/13 2020/4/14 N/A
GROUND Noted
0000-00
LEVEL AT TOWER AREA

SHD-CSCEC-08-G00- COLUMINS DETAILS FROM


Approved as
2 ST-SC-13-BF-00-0034- FOUNDATION TO LOWER 00 2020/4/13 N/A N/A
Noted
0000-00 GROUND C29,C30

SHD-CSCEC-08-G00- COLUMINS DETAILS FROM


Approved as
3 ST-SC-13-BF-00-0036- FOUNDATION TO LOWER 00 2020/4/13 N/A N/A
Noted
0000-00 GROUND C31,C32,C33
SHD-CSCEC-08-G00- COLUMINS DETAILS FROM
Approved as
4 ST-SC-13-BF-00-0037- FOUNDATION TO LOWER 00 2020/4/13 N/A N/A
Noted
0000-00 GROUND C35,C36

12. Weekly Look Ahead Shop Drawing Submittals

S/N Drawing Title Nos of Drawing Revision Submit Date

1 CORE WALL DIMENSIONS FROM XX TO XX 12 00 2020/4/22

2 CORE WALL RFT FROM XX TO XX 8 00 2020/4/22

3 COLUMINS AND AXIS LOWER GROUND FLOOR 6 00 2020/4/23

4 LOWER GROUND FLOOR SLAB DIM. 4 00 2020/4/24