You are on page 1of 1

Project Ampara I Road ( AM-02 )

Sub Contractor SJT Engineering Pvt.Ltd pag -1


Supplier NEM Construction Pvt Ltd
Date 25.06.2020
Period Ending 31st March 2020

SECOND INTEGRATED ROAD INVESTMENT PROGRAM


Contract Package - RDA/ADB/iROAD-2(EP)/NCB/AM-02

Project Escalation Adjustment


Price Escalation
Escalation
Description Unit Rate (A) (A x B x 0.966 / Qty (D) Amount (C x D ) Sub Total Remark
Percentage (B)
100) = C

Payment Certificate NO-01 Amount

Feb-2020 Revised Amount Asphalt Concrete wearing course (Ex-Plant) MT 7100 6.5248 447.51 590.02 264,039.85 264,039.85

Feb 2020 Claimed Amount Asphalt Concrete wearing course (Ex-Plant) MT 7100 5.4184 372.00 590.02 219,487.44 219,487.44 Bill No-01

Project Escalation Adjustment Amount 44,552.41 A

Payment Certificate NO-02 Amount

Mar-2020 Asphalt Concrete wearing course (Ex-Plant) MT 7100 6.5248 447.51 1,012.12 452,933.82

Mar-2020 Asphalt Concrete Binder course (Ex-Plant) MT 6725 6.5248 423.87 246.68 104,560.25 557,494.07 B

Total Amount (A+B) 602,046.48 Bill No-02

Payment Certificate NO-02 A Amount


Mar-2020 Asphalt Concrete wearing course (Ex-Plant) MT 7100 6.5248 447.51 (403.00) (180,346.53) (180,346.53) Bill No-02 A

Payment Certificate NO-03 Amount


Mar-2020 Asphalt Concrete wearing course (Ex-Plant) MT 7100 3.9405 270.26 2,049.56 553,914.09 553,914.09 Bill No-03

You might also like