You are on page 1of 58

PRICE EST NO:BR/2019/7248

DATA ANALYSIS

BRIDGE PROPER

1. Specification Code : 2.4.2.A

SUBHEAD : 2.0

Site Clearence
Dismantling of existing structures like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood work, steel work, including T&P and
2.4.2.A scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable
material and stacking the serviceable material with all lifts and lead of 1000 metres
Cement Concrete Grade M-15 & M-20 - By Mechanical Means

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

unit=cum
202 Taking output = 1.25 cum
a) Labour

L-12 Mate Day 0.02 407.00 8.14

Mazdoor
Public Works Department
L-13 for loading and unloading Day 0.25 368.00 92.00

L-14
PRICE
Mazdoor/Dresser (Semi Skilled)
with Pneumatic breaker
Day 0.25 368.00 92.00
b) Machinery

Air Compressor
250 cfm with 2 leads of pneumatic
P&M-001 hour 0.67 322.00 215.74 MR200
breaker @ 1.5 cum per hour

P&M-095 Tractor - trolley hour 0.27 365.00 98.55 MR294

TOTAL 506.43

Cost of 1.25 cum 506.43

Cost of 1 cum 405.14

1. The excavation of earth, dismantling of stone masonry work in head walls and protection works is
Note not included which is to be measured and paid separately. 2. Credit for retrieved stone from masonry
work may be taken as per actual availability.

printed on 11-10-2019 22:25:09 page 1


PRICE EST NO:BR/2019/7248

Add Overhead @ 20.0% 81.02

Add Contractors Profit @ 10.0% 48.61

Cost index 32.04% 65.00

Total with Cost index 599.79

Say 599.79

2. Specification Code : 2.4.2.B

SUBHEAD : 2.0

Site Clearence
Dismantling of existing structures like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood work, steel work, including T&P and
2.4.2.B scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable
material and stacking the serviceable material with all lifts and lead of 1000 metres
Prestressed / reinforced cement concrete grade M-20 & above - By Mechanical Means

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. Public Works Department ref.

L-12
202

Mate
PRICE
unit=cum
Taking output = 1.25 cum
a) Labour

Day 0.05 407.00 20.35

Mazdoor/Dresser (Semi Skilled)


L-14 with Pneumatic breaker Day 0.66 368.00 242.88

L-02 Blacksmith Day 0.25 487.00 121.75

Mazdoor
for loading and unloading
L-13 b) Machinery Day 0.25 368.00 92.00

Air Compressor
250 cfm with 2 leads of pneumatic
P&M-001 hour 1.0 322.00 322.00 MR200
breaker @ 1.00 cum per hour

P&M-095 Tractor - trolley hour 0.27 365.00 98.55 MR294

printed on 11-10-2019 22:25:09 page 2


PRICE EST NO:BR/2019/7248

TOTAL 897.53

Cost of 1.25 cum 897.53

Cost of 1 cum 718.02

1. The excavation of earth, dismantling of stone masonry work in head walls and protection works is
Note not included which is to be measured and paid separately. 2. Credit for retrieved stone from masonry
work may be taken as per actual availability.

Add Overhead @ 20.0% 143.60

Add Contractors Profit @ 10.0% 86.16

Cost index 32.04% 161.38

Total with Cost index 1109.17

Say 1109.17

3. Specification Code : 2.2

SUBHEAD : 2.0

Site Clearence
Public Works Department
Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery of
2.2

Morth
SOR
Ref. to
MoRTH
the area

PRICEDescription Unit Quantity Rate Rs Cost Rs


Remarks
/Input
Code Spec. ref.

Unit = Hectate
201 Taking output = 1 Heatare
a) Labour

L-12 Mate Day 2.0 407.00 814.00

L-13 Mazdoor Day 50.0 368.00 18400.00

TOTAL 19214.00

Cost of 1.0 Hecter 19214.00

Add Overhead @ 20.0% 3842.80

Add Contractors Profit @ 10.0% 2305.67

Cost index 32.04% 8126.13

printed on 11-10-2019 22:25:09 page 3


PRICE EST NO:BR/2019/7248

Total with Cost index 33488.62

Say 33488.62

4. Specification Code : 12.1.B.1

SUBHEAD : 12.0

Foundations
Earth work in excavation of foundation of structures as per drawing and technical
specification, including setting out, construction of shoring and bracing, removal of stumps
12.1.B.1 and other deleterious matter, dressing of sides and bottom and backfilling with approved
material.
Ordinary Soil - Depth upto 3m - Mechanical Means

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = cum
304 Taking output =240 cum
a) Labour

L-12 Mate Public Works Department


Day 0.32 407.00 130.24

PRICE
Mazdoor
L-13 Day 8.0 368.00 2944.00
b) Machinery

Hydraulic Excavator of 1 cum


P&M-026 hour 6.0 1312.00 7872.00 MR225
bucket

TOTAL 10946.24

Cost of 240.0 cum 10946.24

Cost of 1 cum 45.61

Labour provided for excavation by mechanical means includes that required for trimming of bottom
Note
and side slopes.

Add Overhead @ 20.0% 9.12

Add Contractors Profit @ 10.0% 5.47

Cost index 32.04% 5.41

Total with Cost index 65.62

Say 65.62

printed on 11-10-2019 22:25:09 page 4


PRICE EST NO:BR/2019/7248

5. Specification Code : 12.1.B.2

SUBHEAD : 12.0

Foundations
Earth work in excavation of foundation of structures as per drawing and technical
specification, including setting out, removal of stumps and other deleterious matter, only for
12.1.B.2
dressing of sides and bottom and backfilling with approved material.
Ordinary Soil - Depth 3 M to 6 M- Mechanical Means

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = cum
304 Taking output = 210 cum
a)Labour

L-12 Mate Day 0.32 407.00 130.24

Mazdoor
L-13 Day 8.0 368.00 2944.00
b) Machinery

Hydraulic Excavator of 1 cum


P&M-026 hour 6.0 1312.00 7872.00 MR225
bucket

Public Works Department TOTAL 10946.24

PRICE Cost of 210.0 cum 10946.24

Cost of 1 cum 52.12

Add Overhead @ 20.0% 10.42

Add Contractors Profit @ 10.0% 6.25

Cost index 32.04% 6.19

Total with Cost index 74.99

Say 74.99

6. Specification Code : 12.1.4.A

SUBHEAD : 12.0

Foundations

printed on 11-10-2019 22:25:09 page 5


PRICE EST NO:BR/2019/7248

Earth work in excavation of foundation of structures as per drawing and technical


specification, including setting out, construction of shoring and bracing, removal of stumps
12.1.4.A and other deleterious matter, dressing of sides and bottom and backfilling with approved
material.
Hard Rock ( blasting prohibited) - Mechanical Means

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit= cum
Taking output= 10 cum
304
Mechanical Means
a) Labour

L-12 Mate Day 0.2 407.00 81.40

Mazdoor
L-13 Day 5.0 368.00 1840.00
b) Machinery

Air Compressor
250 cfm with 2 leads of pneumatic
P&M-001 hour 6.0 322.00 1932.00 MR200
breaker

TOTAL 3853.40
Public Works Department
Cost of 10.0 cum 3853.40

Note
PRICE Cost of 1 cum 385.34

In case of rock, foundation beyound 3 m is not dug and hence not included.

Add Overhead @ 20.0% 77.06

Add Contractors Profit @ 10.0% 46.24

Cost index 32.04% 81.26

Total with Cost index 589.91

Say 589.91

7. Specification Code : od18544/2019_2020

od18544/2019_2020 :Providing dowel bars using 25mm dia rods, 3.00m long at about 1.0m c/c, keeping 1.50m
length within concrete and 1.50m into the rock, after drilling holes in granite rock including cost and coneyance of
all materials cutting ros in position with grout 1:2 etc complete with all incidental charges etc.

printed on 11-10-2019 22:25:09 page 6


PRICE EST NO:BR/2019/7248

Code Description Unit Quantity Rate Amount

M-126 Mild Steel bars tonne 0.01155 36842.24 425.53

0128 Mate Day 0.01 407.0 4.07

0134 Rock Hole Driller Day 0.1 368.0 36.8

0102 Blacksmith 1st class Day 0.1 487.0 48.7

0115 Coolie Day 0.2 368.0 73.6

0367 Portland Cement tonne 0.0015 5700.0 8.55

0058 Air Compressor hour 0.1 200.0 20.0

TOTAL 617.25

cost for one no 617.25

say 617.25

Add Overhead @ 20.0% 123.45

Add Contractors Profit @ 10.0% 74.06

SAY 814.77

Cost index 32.04 % 261.05

Total with Cost index 1075.82

Say 1075.82
Public Works Department
8. Specification Code : od18545/2019_2020

PRICE
od18545/2019_2020 :Pumping or Bailing out water and removing slush etc by using pump set including cost of
labour, oil hire charges of pumpset, etc complete

Code Description Unit Quantity Rate Amount

Hire charges of Pump set of capacity 4000


0011 Day 0.027 650.0 17.55
litres/hour

0114 Beldar Day 0.29 368.0 106.72

MR Add 1% water charges L.S 1.0 1.12 1.12

TOTAL 125.39

cost for one hour 125.39

say 125.39

Add Overhead @ 20.0% 25.07

Add Contractors Profit @ 10.0% 15.04

SAY 165.51

printed on 11-10-2019 22:25:09 page 7


PRICE EST NO:BR/2019/7248

Cost index 32.04 % 52.55

Total with Cost index 218.07

Say 218.07

9. Specification Code : 12.8.1.C

SUBHEAD : 12.0

Foundations
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and
12.8.1.C Technical Specifications
RCC Grade M20 - Using Concrete Mixer - (Without formwork)

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = cum
1500,170
Taking output = 15 cum
0 & 2100
a) Material

M-081 Cement tonne 5.21 5792.24 30177.57

M-005 Public Works Department


Coarse sand at Site cum 6.75 1303.77 8800.45

PRICE
M-053 Aggregates 20mm nominal size cum 8.1 1403.77 11370.54

10mm nominal size


M-051 cum 5.4 1403.77 7580.36
b) Labour

L-12 Mate Day 0.86 407.00 350.02

L-11 Mason (1st class) Day 1.5 487.00 730.50

Mazdoor
L-13 Day 20.0 368.00 7360.00
c) Machinery

Concrete Mixer (cap 0.4/0.28


P&M-009 hour 6.0 234.00 1404.00 MR208
cum)

P&M-079 Generator 33 KVA hour 6.0 374.00 2244.00 MR278

TOTAL 70017.44

Cost of 15.0 cum 70017.44

Cost of 1 cum 4667.83

Add Overhead @ 20.0% 933.56

printed on 11-10-2019 22:25:09 page 8


PRICE EST NO:BR/2019/7248

Add Contractors Profit @ 10.0% 560.13

Cost index 32.04% 1871.29

Total with Cost index 8032.84

Say 8032.84

10. Specification Code : 12.8.H.2.1

SUBHEAD : 12.0

FOUNDATIONS
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and
12.8.H.2.1 Technical Specifications.
RCC Grade M35 - Using Batching Plant, Transit Mixer and Concrete Pump

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

1500,170
0 & 2100

Rate as per item Number of SH:


Public Works Department
Foundations
cum 1.0 4682.94 4682.94(B)
12.8.H.2

PRICE
T RCC Grade M35
Formwork @ 3 per cent on cost of
concrete of 12.8.H.2
B*3/100 140.488(T)

Cost of 1.0 cum 4823.43

Add Overhead @ 20.0% 964.68

Add Contractors Profit @ 10.0% 578.81

Cost index 32.04% 1901.30

Total with Cost index 8268.23

Say 8268.23

11. Specification Code : 12.40

SUBHEAD : 12.0

printed on 11-10-2019 22:25:09 page 9


PRICE EST NO:BR/2019/7248

Foundations

Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as
12.40
per Drawing and Technical Specifications

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = 1 MT
1600 Taking output = 1 MT
a) Material

Cold twisted bars (HYSD Bars)


including5 per cent overlaps and
M-082 tonne 1.05 37392.24 39261.85
wastage

Binding wire
b) Labour for cutting, bending,
M-072 kg 6.0 48.09 288.54
shifting to site, tying and placing
in position

L-12 Mate Day 0.4 407.00 162.80

L-02 Blacksmith Day 2.0 487.00 974.00


Public Works Department
L-13 Mazdoor Day 6.0 368.00 2208.00

PRICE TOTAL 42895.19

Cost of 1.0 MT 42895.19

Cost of 1 MT 42895.19

Add Overhead @ 20.0% 8579.03

Add Contractors Profit @ 10.0% 5147.42

Cost index 32.04% 18141.57

Total with Cost index 74763.23

Say 74763.23

12. Specification Code : 13.5.H.P.1

SUBHEAD : 13.0

SUB-STRUCTURE

printed on 11-10-2019 22:25:09 page 10


PRICE EST NO:BR/2019/7248

Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical


13.5.H.P.1 Specifications
RCC Grade M35 - Using concrete Mixer - Height upto 5m

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

1500,170
0 & 2200

Rate as per item Number of SH:


Foundations cum 1.0 5100.32 5100.32(A)
12.8.H.1
RCC Grade M35

Add 10 per cent for Formwork


A*10/100 510.032(T)

Cost of 1.0 cum 5610.35

Cost of 1 cum 5610.35

The basic components of this analysis are the same as those of items 12.8 (A to H). The only
changes are as under:
a) Ramps/Stairs: Extra expenditure on structures which are more than 5 m high @ 2 per cent of cost
for height upto 10 m and 4 per cent for heights above 10 m will be involved for approaching the work
Note Public Works Department
spot by providing higher ramp/stair case for use by the working parties.
b) The above mentioned percentages have been suitably modified for different categories as cost for

PRICE
various categories varies, whereas effort for access for same height will be similar. As the cost of
richer concrete is comparatively more, the percentage to be added has been reduced to maintain the
same cost for extra efforts.

Add Overhead @ 20.0% 1122.07

Add Contractors Profit @ 10.0% 673.24

Cost index 32.04% 2259.63

Total with Cost index 9665.29

Say 9665.29

13. Specification Code : 13.6

SUBHEAD : 13.0

Sub-Structure

printed on 11-10-2019 22:25:09 page 11


PRICE EST NO:BR/2019/7248

Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per
13.6
drawing and Technical Specifications

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Output: MT
1600 &
Taking output = 1 MT
2200
a) Material

Cold twisted bars (HYSD Bars)


M-082 HYSD bars including 5 per cent tonne 1.05 37392.24 39261.85
overlaps and wastage

Binding wire
b) Labour for cutting, bending,
shifting to site, tying and placing
M-072 kg 6.0 48.09 288.54
in position

L-12 Mate Day 0.34 407.00 138.38

L-02 Blacksmith Day 2.0 487.00 974.00

L-13 Mazdoor Public Works Department


Day 6.5 368.00 2392.00

PRICE TOTAL 43054.77

Cost of 1.0 MT 43054.77

Cost of 1 MT 43054.77

Add Overhead @ 20.0% 8610.95

Add Contractors Profit @ 10.0% 5166.57

Cost index 32.04% 18209.06

Total with Cost index 75041.36

Say 75041.36

14. Specification Code : 14.1E.1.2.A

SUBHEAD : 14.0

SUPER-STRUCTURE

printed on 11-10-2019 22:25:09 page 12


PRICE EST NO:BR/2019/7248

"Furnishing and Placing PSC Grade M40 Using Concrete Mixer as per drawing and Technical
14.1E.1.2.A Specification.
For T-beam & slab - Height upto 5m"

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

1500,160
0 & 1700

Rate as per item Number of SH:


cum 1.0 5280.03 5280.03(B)
14.1.E.1 Super-Structure

Formwork and staging 25% of


Labour, Material, Machinery of
B*25/100 1320.01(T)
14.1.A.1

Cost of 1.0 cum 6600.04

1.Where ever concrete is carried out using batching plant, transit mixer, concrete pump, admixers
conforming IS: 9103 @ 0.4 per cent of weight of cement may be added for achieving desired slump of
concrete.2. Cement provided for various components of the super structure is for estimating purpose
Note only. Actual quantity of cement will be as per approved mix design. Similarly, the provision for coarse
Public Works Department
and fine aggregates is for estimating purpose and the exact quantity shall be as per the mix design.3.
The items like needle and surface vibrators are part of minor T & P which is already covered under

PRICE
the overhead charges. As such these items have not been added separately in the rate analysis.

Add Overhead @ 20.0% 1320.00

Add Contractors Profit @ 10.0% 792.00

Cost index 32.04% 2662.77

Total with Cost index 11374.82

Say 11374.82

15. Specification Code : 14.1F.1.A

SUBHEAD : 14.0

SUPER-STRUCTURE
"Furnishing and Placing PSC Grade M45 Using Batching Plant, Transit Mixer and Concrete
14.1F.1.A Pump as per drawing and Technical Specification.
For solid slab/voided slab super-structure - Height upto 5m"

printed on 11-10-2019 22:25:09 page 13


PRICE EST NO:BR/2019/7248

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

1500,160
0 & 1700

Rate as per item Number of SH:


cum 1.0 5011.19 5011.19(B)
14.1.F.1 Super-Structure

Formwork and staging 16% of


Labour, Material, Machinery of
B*16/100 801.79(T)
14.1.F.1

Cost of 1.0 cum 5812.98

1.Where ever concrete is carried out using batching plant, transit mixer, concrete pump, admixers
conforming IS: 9103 @ 0.4 per cent of weight of cement may be added for achieving desired slump of
concrete.2. Cement provided for various components of the super structure is for estimating purpose
Note only. Actual quantity of cement will be as per approved mix design. Similarly, the provision for coarse
and fine aggregates is for estimating purpose and the exact quantity shall be as per the mix design.3.
The items like needle and surface vibrators are part of minor T & P which is already covered under
the overhead charges. As such these items have not been added separately in the rate analysis.

Public Works Department


Add Overhead @ 20.0% 1162.59

PRICE Add Contractors Profit @ 10.0%

Cost index
697.55

32.04% 2302.31

Total with Cost index 9975.45

Say 9975.45

16. Specification Code : 14.2

SUBHEAD : 14.0

Super-Structure
Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per
14.2
drawing and technical specifications

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

printed on 11-10-2019 22:25:09 page 14


PRICE EST NO:BR/2019/7248

Unit = 1 MT
1600 Taking output = 1 MT
a) Material

Cold twisted bars (HYSD Bars)

M-082 tonne 1.05 37392.24 39261.85


including 5 % for laps and
wastage

Binding wire
M-072 b) Labour for cutting, bending, kg 8.0 48.09 384.72
typing and placing in position

L-12 Mate Day 0.44 407.00 179.08

L-02 Blacksmith Day 3.0 487.00 1461.00

L-13 Mazdoor Day 8.0 368.00 2944.00

TOTAL 44230.65

Cost of 1.0 MT 44230.65

Add Overhead @ 20.0% 8846.12

Add Contractors Profit @ 10.0% 5307.67


Public Works Department
Cost index 32.04% 18706.38

PRICE Total with Cost index 77090.84

Say 77090.84

17. Specification Code : 14.3

SUBHEAD : 14.0

SUPER-STRUCTURE
High tensile steel wires/strands including all accessories for stressing, stressing operations
14.3
and grouting complete as per drawing and Technical Specifications

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

printed on 11-10-2019 22:25:09 page 15


PRICE EST NO:BR/2019/7248

Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand
40 m long cable (weight = 0.377
MT)
a) Material

1800

HTS Strand
@ 9.42 kg/m including 2 per cent 22620.00(
tonne 0.39 58000.00 MR134
M-119 for wastage and extra length for B)
jacking

Sheathing duct
M-165 ID 66 mm along with 5 per cent metre 42.0 180.00 7560.00(C) MR163
extra length 40 x 1.05 = 42 m.

Tube anchorage set complete


with bearing plate, permanent
M-257 each 2.0 2900.00 5800.00(D) MR437
wedges etc

Cement
b) Labour
M-081 i) For making and fixing cables, tonne 0.125 5792.24 724.03(E)
anchorages
Public Works Department

PRICE
Add 0.50 per cent cost of material
for Spacers, Insulation tape and
miscellaneous items
(B+C+D+E
)*0.5/100
183.52(T)

Mate
L-12 Day 0.16 407.00 65.12

Blacksmith
L-02 Day 1.0 487.00 487.00

Mazdoor
L-13 ii) For prestressing Day 3.0 368.00 1104.00

Mate
L-12 Day 0.05 407.00 20.35

Fitter
L-08 Day 0.25 487.00 121.75

Mazdoor
L-13 iii) For grouting Day 1.0 368.00 368.00

printed on 11-10-2019 22:25:09 page 16


PRICE EST NO:BR/2019/7248

Mate
L-12 Day 0.05 407.00 20.35

Mason (1st class)


L-11 Day 0.25 487.00 121.75

Mazdoor
L-13 Day 1.0 368.00 368.00
c) Machinery

Prestressing Jack with Pump &


P&M-040 access hour 2.5 130.00 325.00 MR239

Grouting pump with agitator


M-111 hour 1.0 714.00 714.00 MR126

Generator 33 KVA
P&M-079 hour 3.5 374.00 1309.00 MR278

Cost of 0.377 MT 41911.87

Cost of 1 MT 111172.07

Note Cost of HT steel has been taken for delivery at site. Hence carriage has not been considered.

Add Overhead @ 20.0% 22234.41


Public WorksAddDepartment
Contractors Profit @ 10.0% 13340.64

PRICE Cost index 32.04% 3818.65

Total with Cost index 150565.79

Say 150565.79

18. Specification Code : 14.7

SUBHEAD : 14.0

SUPER-STRUCTURE
Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post not to exceed 1 in 500, center to center spacing
14.7
between vertical post not to exceed 2000 mm, leaving adequate space between vertical post
for expansion, complete as per approved drawings and technical specifications.

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

printed on 11-10-2019 22:25:09 page 17


PRICE EST NO:BR/2019/7248

Unit = 1 RM
Taking output = 2 x 24 m span =
48 m.
a) Material

2703

Rate as per item Number of SH:


Super-Structure
No. of vertical posts = (12 + 2)2 =
28 Nos., External area of vertical
post 0.25x0.275 = 0.069sqm,
Concrete in vehicle posts = 0.069
18836.95(
x 28 = 1.932 cum, Hand rail in 3 cum 4.092 4603.36
14.1C.2 B)
tiers = 3 x 24 = 72 m, External
area = 0.170 x 0.175 = 0.03 sqm,
Concrete in hand rails = 0.03 x 72
= 2.16 cum, Total Concrete =
1.932 + 2.16 = 4.092 cum. (Refer
MoRTH SD / 202).

Add 12 per cent of above cost for


form work. B*12/100 2260.43(T)

Rate as per item Number of SH:


14.2 Public Works Department
Super-Structure MT 0.865 44230.65 38259.51

PRICE Cost of 48.0 RM

Cost of 1 RM
59356.80

1236.60

1. Quantities of material have been adopted from standard plans of MoRTH vide drawing no.
Note
SD/202.2. 48 m length is the total linear length adding both sides of 24 m span.

Add Overhead @ 20.0% 247.32

Add Contractors Profit @ 10.0% 148.39

Cost index 32.04% 510.13

Total with Cost index 2142.45

Say 2142.45

19. Specification Code : 14.4

SUBHEAD : 14.0

printed on 11-10-2019 22:25:09 page 18


PRICE EST NO:BR/2019/7248

Super-Structure

Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
14.4
complete as per drawing and Technical Specifications.

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = 1 cum
Taking output = 1 cum
2702
a) Material

Rate as per item Number of SH:


14.1.C.1 Super-Structure cum 1.0 5037.12 5037.12
Cement concrete M30 Grade

Rate as per item Number of SH:


Super-Structure
14.2 (HYSD bar reinforcement) MT 0.075 44230.65 3317.30
b) Labour

Mazdoor
L-13 Public Works Department
for cleaning deck slab concrete
Day 0.15 368.00 55.20
surface.

PRICE TOTAL 8409.62

Cost of 1.0 cum 8409.62

Add Overhead @ 20.0% 1681.92

Add Contractors Profit @ 10.0% 1009.15

Cost index 32.04% 3453.80

Total with Cost index 14554.51

Say 14554.51

20. Specification Code : 14.10

SUBHEAD : 14.0

Super-Structure

printed on 11-10-2019 22:25:09 page 19


PRICE EST NO:BR/2019/7248

PCC M15 Grade leveling course below approach slab complete as per drawing and Technical
14.10
specification.

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = 1 cum
Taking output = 1 cum
2700
Material

Rate as per item Number of SH:


12.8.A Foundations cum 1.0 4228.66 4228.66
excluding formworks

TOTAL 4228.66

Cost of 1.0 cum 4228.66

Add Overhead @ 20.0% 845.73

Add Contractors Profit @ 10.0% 507.43

Cost index 32.04% 1685.56


Public Works Department
Total with Cost index 7267.39

21. Specification Code : 14.11


PRICE Say 7267.39

SUBHEAD : 14.0

SUPER-STRUCTURE
Reinforced cement concrete approach slab including reinforcement and formwork complete
14.11
as per drawing and Technical specification.

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = 1 cum
Taking output = 1 cum
a) Material

printed on 11-10-2019 22:25:09 page 20


PRICE EST NO:BR/2019/7248

1500,160
0,1700,27
04

Rate as per item Number of SH:


Foundations
Cement concrete M30 Grade by cum 1.0 4594.12 4594.12(B)
12.8.G.2
using batching plant, excluding
formwork

Add 2 per cent for formwork


B*2/100 91.8824(T)

Rate as per item Number of SH:


14.2 Super-Structure MT 0.05 44230.65 2211.53
HYSD bar reinforcement

Cost of 1.0 cum 6897.53

Cost of 1 cum 6897.53

The grade of reinforced cement concrete may be adopted as M30 for severe conditions and M25 for
Note
moderate conditions.

Add Overhead @ 20.0% 1379.50


Public WorksAddDepartment
Contractors Profit @ 10.0% 827.70

PRICE Cost index 32.04% 2779.85

Total with Cost index 11884.59

Say 11884.59

22. Specification Code : 14.9

SUBHEAD : 14.0

SUPER-STRUCTURE
14.9 Drainage Spouts complete as per drawing and Technical specification

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = 1 No.
Taking output = 1 No.
a) Material

printed on 11-10-2019 22:25:09 page 21


PRICE EST NO:BR/2019/7248

2705

Corrosion resistant Structural


steel kg 4.0 37.84 151.36(B)
M-229
including 5 per cent wastage

G.I Pipe - 100 m dia


M-244 metre 6.0 460.00 2760.00(C) MR189

Gl Bolt 10mm dia


M-110 no 6.0 11.00 66.00(D)

Galvanised MS flat clamp


M-101 b) Labour each 2.0 35.00 70.00(E) MR118
for fabrication

Mate
L-12 Day 0.02 407.00 8.14(F)

Blacksmith
L-02 Day 0.02 487.00 9.74(G)

Mazdoor
L-13 Day 0.02 368.00 7.36(H)
For fixing in position

Mate
L-12 Day 0.01 407.00 4.07(I)

Mason (1st class)


L-11 Day 0.01 487.00 4.87(J)
Public Works Department

PRICE
Mazdoor
L-13 Day 0.2 368.00 73.60(K)

Add @ 5 per cent of cost of


material and labour for electrodes, (B+C+D+E
cutting gas, sealant, anti-corrosive +F+G+H+I
157.757(T)
bituminous paint, mild steel +J+K)*5/10
grating etc. 0

Cost of 1.0 no 3312.90

Cost of each 3312.90

1. In case of viaducts in urban areas, the drainage spouts should be connected with suitably located
pipelines to discharge the surface run-off to drains provided at ground level.2. In case of bridges,
Note
sufficient length of G.I Pipe shall be provided to ensure that there is no splashing of water from the
drainage spout on the structure.

Add Overhead @ 20.0% 662.58

printed on 11-10-2019 22:25:09 page 22


PRICE EST NO:BR/2019/7248

Add Contractors Profit @ 10.0% 397.54

Cost index 32.04% 144.38

Total with Cost index 4517.42

Say 4517.42

23. Specification Code : 14.16

SUBHEAD : 14.0

Super-Structure
Providing and applying 2 coats of water based cement paint to unplastered concrete surface
14.16 after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1
litre for 2 sqm.

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit: sqm
800 Taking output = 10 sqm
a) Labour

L-12 Mate
Public Works Department
Day 0.01 407.00 4.07

L-18

L-15
PRICE
Painter 1 class

Mazdoor/Dresser/Sinker (skilled)
b) Material
Day

Day
0.25

0.25
448.00

407.00
112.00

101.75

M-190 Water based cement paint Litre 5.0 200.00 1000.00

TOTAL 1217.82

Cost of 10.0 sqm 1217.82

Cost of 1 sqm 121.78

Add Overhead @ 20.0% 24.35

Add Contractors Profit @ 10.0% 14.61

Cost index 32.04% 51.50

Total with Cost index 212.25

Say 212.25

Approach road
printed on 11-10-2019 22:25:09 page 23
PRICE EST NO:BR/2019/7248

1. Specification Code : 12.1.2.B

SUBHEAD : 12.0

Foundations
Earth work in excavation of foundation of structures as per drawing and technical
specification, including setting out, construction of shoring and bracing, removal of stumps
12.1.2.B and other deleterious matter, dressing of sides and bottom and backfilling with approved
material.
Ordinary Rock (not requiring blasting ) - Depth up to 3 m - Mechanical Means

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Mechanical Means
Unit = cum
304
Taking output= 180 cum
a) Laour

L-12 Mate Day 0.24 407.00 97.68

Mazdoor
L-13 Day 6.0 368.00 2208.00
b) Machinery
Public Works Department
Hydraulic Excavator of 1 cum

PRICE
P&M-026 hour 6.0 1312.00 7872.00 MR225
bucket

TOTAL 10177.68

Cost of 180.0 cum 10177.68

Cost of 1 cum 56.54

Note In case of rock, foundation beyond 3 m is not dug and hence not included

Add Overhead @ 10.0% 5.65

Add Contractors Profit @ 10.0% 6.21

Cost index 32.04% 4.96

Total with Cost index 73.38

Say 73.38

2. Specification Code : 12.8.A

SUBHEAD : 12.0

printed on 11-10-2019 22:25:09 page 24


PRICE EST NO:BR/2019/7248

Foundations

Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and


12.8.A Technical Specifications
PCC Grade M15 ( Without formwork)

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = cum
1500,170
Taking output = 15 cum
0 & 2100
a) Material

M-081 Cement tonne 4.13 5792.24 23921.95

M-005 Coarse sand at Site cum 6.75 1303.77 8800.45

M-055 Aggregate 40mm nominal size cum 8.1 1362.79 11038.60

M-053 Aggregates 20mm nominal size cum 4.05 1403.77 5685.27

10mm nominal size


M-051 cum 1.35 1403.77 1895.09
b) Labour

L-12 Mate Day 0.86 407.00 350.02

L-11 Mason (1st class) Day 1.5 487.00 730.50


Public Works Department
Mazdoor
L-13

P&M-009
PRICE
c) Machinery

Concrete Mixer (cap 0.4/0.28


cum)
Day

hour
20.0

6.0
368.00

234.00
7360.00

1404.00 MR208

Generator (b) 63 KVA


P&M-019 hour 6.0 374.00 2244.00 MR218

TOTAL 63429.88

Cost of 15.0 cum 63429.88

Cost of 1 cum 4228.66

Needle Vibrator is an item of minor T & P which is already included in overhead charges. Hence not
Note
added in rate analysis of cement concrete works.

Add Overhead @ 10.0% 422.86

Add Contractors Profit @ 10.0% 465.15

Cost index 32.04% 1545.09

printed on 11-10-2019 22:25:09 page 25


PRICE EST NO:BR/2019/7248

Total with Cost index 6661.78

Say 6661.78

3. Specification Code : 15.9

SUBHEAD : 15.0

RIVER TRAINING & PROTECTION WORKS


15.9 Construction of dry rubble flooring at cross drainage works for relatively less important works.

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = cum
Taking output = 1 cum
a) Material

2506

Boulder with minimum size of 300


cum 1.0 987.08 987.08
M-003 mm for Pitching at Site

Gravel/Quarry spall at Site


M-008 Public Works Department
cum 0.2 822.08 164.42
b) Labour

L-12

L-11
Mate
PRICE
Mason (1st class)
Day

Day
0.1

0.5
407.00

487.00
40.70(A)

243.50(B)

Mazdoor
L-13 Day 1.5 368.00 552.00(C)

Add 1 per cent of (b) for trimming


(A+B+C)*1/
and preparation of base 8.362(T)
100

Cost of 1.0 cum 1996.06

Cost of 1 cum 1996.06

Add Overhead @ 10.0% 199.60

Add Contractors Profit @ 10.0% 219.56

Cost index 32.04% 773.84

printed on 11-10-2019 22:25:09 page 26


PRICE EST NO:BR/2019/7248

Total with Cost index 3189.07

Say 3189.07

4. Specification Code : 12.8.G.1.1

SUBHEAD : 12.0

FOUNDATIONS
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and
12.8.G.1.1 Technical Specifications.
RCC Grade M30 - Using Concrete Mixer

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

1500,170
0 & 2100

Rate as per item Number of SH:


cum 1.0 5011.50 5011.50(B)
12.8.G.1 Foundations

Using Concrete Mixer


Public Works Department
Formwork @ 3.5 per cent on cost
B*3.5/100 175.402(T)

PRICE
of concrete of 12.8.G.1

Cost of 1.0 cum 5186.90

Add Overhead @ 10.0% 518.69

Add Contractors Profit @ 10.0% 570.55

Cost index 32.04% 1913.29

Total with Cost index 8189.44

Say 8189.44

5. Specification Code : 12.40

SUBHEAD : 12.0

Foundations

printed on 11-10-2019 22:25:09 page 27


PRICE EST NO:BR/2019/7248

Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as
12.40
per Drawing and Technical Specifications

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = 1 MT
1600 Taking output = 1 MT
a) Material

Cold twisted bars (HYSD Bars)


including5 per cent overlaps and
M-082 tonne 1.05 37392.24 39261.85
wastage

Binding wire
b) Labour for cutting, bending,
M-072 kg 6.0 48.09 288.54
shifting to site, tying and placing
in position

L-12 Mate Day 0.4 407.00 162.80

L-02 Blacksmith Day 2.0 487.00 974.00

L-13 Mazdoor Day 6.0 368.00 2208.00


Public Works Department TOTAL 42895.19

PRICE Cost of 1.0 MT 42895.19

Cost of 1 MT 42895.19

Add Overhead @ 10.0% 4289.51

Add Contractors Profit @ 10.0% 4718.47

Cost index 32.04% 16629.77

Total with Cost index 68532.96

Say 68532.96

6. Specification Code : 12.8.B.1

SUBHEAD : 12.0

FOUNDATIONS

printed on 11-10-2019 22:25:09 page 28


PRICE EST NO:BR/2019/7248

Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and


12.8.B.1 Technical Specifications
PCC Grade M20

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

1500,170
0 & 2100

Rate as per item Number of SH:


cm 1.0 4633.77 4633.77(B)
12.8.B Foundations

PCC Grade M20

Formwork @ 4 per cent on cost of


concrete i.e. cost of material, B*4/100 185.351(T)
labour and machinery of 12.8.B

Cost of 1.0 cum 4819.12

Public Works Department


Add Overhead @ 10.0% 481.91

PRICE Add Contractors Profit @ 10.0%

Cost index
530.10

32.04% 1770.23

Total with Cost index 7601.37

Say 7601.37

7. Specification Code : 13.5.G.P.1

SUBHEAD : 13.0

SUB-STRUCTURE
Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical
13.5.G.P.1 Specifications
RCC Grade M30 - Using concrete Mixer - Height upto 5m

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

printed on 11-10-2019 22:25:09 page 29


PRICE EST NO:BR/2019/7248

1500,170
0 & 2200

Rate as per item Number of SH:


Foundations cum 1.0 5011.50 5011.50(A)
12.8.G.1
RCC Grade M30

Add 10 per cent for Formwork


A*10/100 501.15(T)

Cost of 1.0 cum 5512.65

Cost of 1 cum 5512.65

The basic components of this analysis are the same as those of items 13.8 (A to H). The only
changes are as under
:a) Ramps/Stairs: Extra expenditure on structures which are more than 5 m high @ 2 per cent of cost
for height upto 10 m and 4 per cent for heights above 10 m will be involved for approaching the work
Note spot by providing higher ramp/stair case for use by the working parties.
b) The above mentioned percentages have been suitably modified for different categories as cost for
various categories varies, whereas effort for access for same height will be similar. As the cost of
richer concrete is comparatively more, the percentage to be added has been reduced to maintain the
same cost for extra efforts.

Public Works Department


Add Overhead @ 10.0% 551.26

PRICE
Add Contractors Profit @ 10.0% 606.39

Cost index 32.04% 2033.45

Total with Cost index 8703.76

Say 8703.76

8. Specification Code : 13.6

SUBHEAD : 13.0

Sub-Structure
Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per
13.6
drawing and Technical Specifications

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

printed on 11-10-2019 22:25:09 page 30


PRICE EST NO:BR/2019/7248

Output: MT
1600 &
Taking output = 1 MT
2200
a) Material

Cold twisted bars (HYSD Bars)


M-082 HYSD bars including 5 per cent tonne 1.05 37392.24 39261.85
overlaps and wastage

Binding wire
b) Labour for cutting, bending,
shifting to site, tying and placing
M-072 kg 6.0 48.09 288.54
in position

L-12 Mate Day 0.34 407.00 138.38

L-02 Blacksmith Day 2.0 487.00 974.00

L-13 Mazdoor Day 6.5 368.00 2392.00

TOTAL 43054.77

Cost of 1.0 MT 43054.77

Cost of 1 MT 43054.77

Public Works Department


Add Overhead @ 10.0% 4305.47

PRICE Add Contractors Profit @ 10.0%

Cost index
4736.02

32.04% 16691.64

Total with Cost index 68787.92

Say 68787.92

9. Specification Code : 13.5.B

SUBHEAD : 13.0

SUB-STRUCTURE
Plain/Reinforced Cement Concrete in sub-structure complete as per drawing and Technical
13.5.B Specifications
PCC Grade M20 - Height upto 5m

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

printed on 11-10-2019 22:25:09 page 31


PRICE EST NO:BR/2019/7248

1500,170
0 & 2200

Rate as per item Number of SH:


Foundations cm 1.0 4633.77 4633.77(A)
12.8.B
PCC M20

Add 10 per cent of cost of


material, labour and machinery (a
b c) for Formwork
A*10/100 463.377(T)

Cost of 1.0 cum 5097.15

Cost of 1 cum 5097.15

The basic components of this analysis are the same as those of items 12.8 (A to H). The only
changes are as under:
a) Ramps/Stairs: Extra expenditure on structures which are more than 5 m high @ 2 per cent of cost
for height upto 10 m and 4 per cent for heights above 10 m will be involved for approaching the work
Note spot by providing higher ramp/stair case for use by the working parties.
b) The above mentioned percentages have been suitably modified for different categories as cost for
various categories varies, whereas effort for access for same height will be similar. As the cost of
Public Works Department
richer concrete is comparatively more, the percentage to be added has been reduced to maintain the

PRICE
same cost for extra efforts.

Add Overhead @ 10.0% 509.71

Add Contractors Profit @ 10.0% 560.68

Cost index 32.04% 1872.37

Total with Cost index 8039.92

Say 8039.92

10. Specification Code : 13.10

SUBHEAD : 13.0

Sub-Structure

printed on 11-10-2019 22:25:09 page 32


PRICE EST NO:BR/2019/7248

Providing and laying of Filter media with granular materials/stone crushed aggregates
satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a
thickness of not less than 600 mm with smaller size towards the soil and bigger size towards
13.10
the wall and provided over the entire surface behind abutment, wing wall and return wall to
the full height compacted to a firm condition complete as per drawing and Technical
Specification.

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = cum
2200 Taking output = 10 cum.
a) Labour

L-12 Mate Day 0.32 407.00 130.24

Mazdoor
L-13 for filling, watering, ramming etc. Day 7.0 368.00 2576.00

Mazdoor/Dresser/Sinker (skilled)
L-15 Day 1.0 407.00 407.00
b) Material

Filter media/Filter Material as per


Table 300-3
Public Works Department
Filter media of stone aggregate

M-012
PRICE
conforming to clause 2504.2.2. of
MoRTH specifications.

c) Machinery
cum 12.0 1241.54 14898.48

Water Tanker
P&M-060 6 KL Capacity hour 0.06 250.00 15.00 MR259

TOTAL 18026.72

Cost of 10.0 cum 18026.72

Cost of 1 cum 1802.67

Add Overhead @ 10.0% 180.26

Add Contractors Profit @ 10.0% 198.29

Cost index 32.04% 698.28

Total with Cost index 2879.52

printed on 11-10-2019 22:25:09 page 33


PRICE EST NO:BR/2019/7248

Say 2879.52

11. Specification Code : od23183/2019_2020

od23183/2019_2020 :Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing


wall/return wall with 100 mm dia PVC pipe, extending through the full width of the structure with slope of 1V :
20H towards drawing foce.Complete as per drawing and Technical Specifications

Code Description Unit Quantity Rate Amount

MR PVC pipe 100 mm dia metre 31.15 300.0 9345.0 ()

Rate as per item number 12.6.A of SH:


12.6.A cum 0.05 4943.7 247.19 ()
Foundations

L-12 Mate Day 0.03 363.0 10.89 ()

L-13 Mazdoor Day 0.25 329.0 82.25 ()

L-11 Mason (1st class) Day 0.5 435.0 217.5 ()

TOTAL 9902.83

cost for 30.0 no 9902.83

cost for one no 330.09

Public Works Department say 330.09

PRICE
Add Overhead @ 10.0% 33.00

Add Contractors Profit @ 10.0% 36.30

SAY 399.40

Cost index 32.04 % 7.20

Total with Cost index 406.62

Say 406.62

12. Specification Code : 3.16

SUBHEAD : 3.0

EARTH WORK,EROSION CONTROL AND DRAINAGE


Construction of embankment with approved material obtained from borrow pits with all lifts
3.16 and leads, transporting to site, spreading, grading to required slope and compacting to meet
requirement of table 300-2.

printed on 11-10-2019 22:25:09 page 34


PRICE EST NO:BR/2019/7248

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = cum
Taking output = 100 cum
a) Labour

305

Mate Day 0.04 407.00 16.28


L-12

Mazdoor
L-13 Day 1.0 368.00 368.00
b) Machinery

Hydraulic Excavator of 1 cum


P&M-026 bucket hour 1.67 1312.00 2191.04 MR225
capacity @ 60 cum per hour

Tipper 10 tonne
P&M-102 tonne km 160.0 3.00 480.00(A) MR384
capacity

Add 10 per cent of cost of


carriage to cover cost of loading
A*10/100 48.0(T)
and unloading

Dozer D - 80 - A 12
P&M-014
Public Works Department
for spreading @ 200 cum per
hour 0.5 3748.00 1874.00 MR213

P&M-140
hour

PRICE
Motor Grader for grading
@ 100 cum per hour

Water Tanker
hour 1.0 2413.00 2413.00 MR471

P&M-060 hour 4.0 250.00 1000.00 MR259


6 KL Capacity

Vibratory Roller 8 tonne


P&M-059 @ 100 cum per hour hour 1.0 1553.00 1553.00 MR258
c) Material

Water
M-189 Kilo litre 24.0 13.00 312.00 MR177

Compensation for earth taken


M-092 from private land cum 100.0 159.71 15971.00

Cost of 100.0 cum 26226.00

Cost of 1 cum 262.26

printed on 11-10-2019 22:25:09 page 35


PRICE EST NO:BR/2019/7248

Compensation for earth will vary from place to place and will have to be assessed realistically as per
Note particular ground situation. In case earth is available from Govt. land, compensation for earth will not
be required. The position is required to be clearly stated in the cost estimate.

Add Overhead @ 10.0% 26.22

Add Contractors Profit @ 10.0% 28.84

Cost index 32.04% 63.40

Total with Cost index 380.74

Say 380.74

13. Specification Code : 3.3

SUBHEAD : 3.0

Earth Work,Erosion Control and Drainage


Excavation for road way in soil with Dozer including cutting and pushing the earth to site of
3.3 embankment upto a distance of 100 metres (average lead 50 metres), including trimming
bottom and side slopes in accordance with requirements of lines, grades and cross sections.

Public Works Department


Morth Ref. to Remarks
SOR
Code
MoRTH
Spec.

301
PRICE
Unit= cum
Description

Taking output= 180 cum


Unit Quantity Rate Rs Cost Rs /Input
ref.

a) Labour

L-12 Mate Day 0.08 407.00 32.56

Mazdoor
L-13 Day 2.0 368.00 736.00
b)Machinery

Dozer D - 80 - A 12
P&M-014 @ 30 cum per hour hour 6.0 3748.00 22488.00 MR213

TOTAL 23256.56

Cost of 180.0 cum 23256.56

Cost of 1 cum 129.20

Add Overhead @ 10.0% 12.92

printed on 11-10-2019 22:25:09 page 36


PRICE EST NO:BR/2019/7248

Add Contractors Profit @ 10.0% 14.21

Cost index 32.04% 1.65

Total with Cost index 157.99

Say 157.99

14. Specification Code : 3.4

SUBHEAD : 3.0

Earth Work,Erosion Control and Drainage


Excavation for roadway in ordinary rock by deploying a dozer, 80 HP including cutting and
pushing the cut earth to site of embankment upto a distance of 100 metres ( average lead 50
3.4
metres ), trimming bottom and side slopes in accordance with the requirements of lines,
grades and cross sections.

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit=cum
301 Taking output=108cum
a) Labour Public Works Department
L-12

L-13
Mate

Mazdoor
PRICE
b) Machinery

Dozer D - 80 - A 12
Day

Day
0.12

3.0
407.00

368.00
48.84

1104.00

P&M-014 @ 20 cum per hour hour 6.0 3748.00 22488.00 MR213

TOTAL 23640.84

Cost of 108.0 cum 23640.84

Cost of 1 cum 218.90

Add Overhead @ 10.0% 21.89

Add Contractors Profit @ 10.0% 24.07

Cost index 32.04% 4.13

Total with Cost index 269.01

Say 269.01

printed on 11-10-2019 22:25:09 page 37


PRICE EST NO:BR/2019/7248

15. Specification Code : 4.1.A.2

SUBHEAD : 4.0

SUB-BASES,BASES AND SHOULDERS


Construction of granular sub-base by providing graded Material, mixing in a mechanical mix
plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor
4.1.A.2 grader on prepared surface and compacting with vibratory power roller to achieve the desired
density, complete as per clause 401
Grading-II - Plant Mix Method

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = cum
Taking output = 225 cum (450
tonne)
a) Labour

401

Mate Day 0.4 407.00 162.80


L-12
Public Works Department
Mazdoor/Dresser/Sinker (skilled)

PRICE
L-15 Day 2.0 407.00 814.00

Mazdoor
L-13 Day 8.0 368.00 2944.00
b) Machinery

Wet mix plant @75 tonne capacity


P&M-101 per hour hour 6.0 1213.00 7278.00 MR383

Generator (a) 125 KVA


P&M-018 hour 6.0 702.00 4212.00 MR217

Water Tanker
P&M-060 6 KL capacity 5 km lead with one hour 4.5 250.00 1125.00 MR259
trip per hour

Front End loader 1 cum bucket


P&M-017 capacity hour 6.0 812.00 4872.00 MR216

Tipper 10 tonne
P&M-102 tonne km 450.0 3.00 1350.00(A) MR384

printed on 11-10-2019 22:25:09 page 38


PRICE EST NO:BR/2019/7248

Add 10 per cent of cost of


carriage to cover loading and
A*10/100 135.0(T)
unloading

Motor Grader 110HP@ 50 cum


P&M-106 per hour hour 6.0 2413.00 14478.00 MR389

Vibratory Roller 8 tonne

c) Material
Granular sub-base Material as per
P&M-059 table 400-1 hour 6.0 1553.00 9318.00 MR258
For Grading-II Material

26.5 mm to 9.5 mm
M-015 cum 100.8 1383.77 139484.02
@ 35 per cent

9.5 mm to 2.36 mm
M-017 cum 72.0 1343.77 96751.44
@ 25 per cent

2.36 mm below
M-020 cum 115.2 1303.77 150194.30
@ 40 per cent

Water
Public Works Department
M-189 Kilo litre 27.0 13.00 351.00 MR177

PRICE Cost of 225.0 cum 433469.25

Cost of 1 cum 1926.53

Add Overhead @ 10.0% 192.65

Add Contractors Profit @ 10.0% 211.91

Cost index 32.04% 672.58

Total with Cost index 3003.69

Say 3003.69

16. Specification Code : 4.12

SUBHEAD : 4.0

SUB-BASES,BASES AND SHOULDERS

printed on 11-10-2019 22:25:09 page 39


PRICE EST NO:BR/2019/7248

Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam
specification including premixing the Material with water at OMC in mechanical mix plant
4.12 carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base /
base course on well prepared surface and compacting with vibratory roller to achieve the
desired density.

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit=cum
Taking output=225 cum (495
tonnes)
Labour

406

Mate Day 0.48 407.00 195.36


L-12

Mazdoor/Dresser/Sinker (skilled)
L-15 Day 2.0 407.00 814.00

Mazdoor

L-13 Machinery Public Works Department


Day 10.0 368.00 3680.00

P&M-094 PRICE
Wet Mix plant 75 TPH
capacity
hour 6.6 1213.00 8005.80 MR293

Generator (a) 125 KVA


P&M-018 hour 6.0 702.00 4212.00 MR217

Front End loader 1 cum bucket


P&M-017 capacity hour 6.0 812.00 4872.00 MR216

Paver Finisher Mechanical


P&M-035 100TPH hour 6.0 983.00 5898.00 MR234

Vibratory Roller 8 tonne


P&M-059 hour 3.9 1553.00 6056.70 MR258

Water Tanker
P&M-060 hour 3.0 250.00 750.00 MR259
6 KL capacity

Truck 5.5 cum per 10 tonnes


P&M-058 tonne km 495.0 3.00 1485.00(A) MR257

printed on 11-10-2019 22:25:09 page 40


PRICE EST NO:BR/2019/7248

Add 10 percent of cost of carriage


to cover cost of loading and
A*10/100 148.5(T)
unloading
Material ( Table 400-13)

Aggregate 45mm to 22.4mm


M-034 cum 89.1 1349.22 120215.50
@ 30 per cent

Aggregate 22.4mm to 2.36mm


M-031 cum 118.8 1303.77 154887.88
@ 40 per cent

2.36 mm & below


M-022 cum 89.1 1136.27 101241.66
@ 30 per cent

Water
M-189 Kilo litre 18.0 13.00 234.00 MR177

Cost of 225.0 cum 412697.25

Cost of 1 cum 1834.21

1. Though vibratory roller is required only for 3 hours as per norms, the same is required to be
available at site for 6 hours to match with other machines. The usage rates of vibratory roller may be
Note multiplied with a factor of 0.652. As three wheeled smooth steel rollers are commonly in use, the
same has been provided as an alternative which can be used if the thickness of individual layer does
not exceed 100 mm..

Public Works Department

PRICE Add Overhead @ 10.0%

Add Contractors Profit @ 10.0%

Cost index
183.42

201.76

32.04% 656.53

Total with Cost index 2875.93

Say 2875.93

17. Specification Code : 5.1.a

SUBHEAD : 5.0

Bases and Surface courses


Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of
5.1.a granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0
kg/sqm using mechanical means.

printed on 11-10-2019 22:25:09 page 41


PRICE EST NO:BR/2019/7248

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = sqm
Taking output = 3500 sqm
502
a) Labour

L-12 Mate Day 0.08 407.00 32.56

Mazdoor
L-13 Day 2.0 368.00 736.00
b) Machinery

Mechanical Broom Hydraulic


P&M-031 hour 2.8 358.00 1002.40 MR230
@ 1250 sqm per hour

P&M-001 Air Compressor hour 2.8 322.00 901.60 MR200

Bitumen Pressure Distributor


P&M-004 hour 2.0 1080.00 2160.00 MR203
@ 1750 sqm per hour

Water Tanker
P&M-060 6 KL capacity @ 1 trip per hour hour 1.0 250.00 250.00 MR259
c) Material

Bitumen Emulsion (SS)


M-404 tonne 2.45 51658.00 126562.10 MR123
@ 0.7 kg per sqm
Public Works Department
M-197 carriage code of Bitumen tonne 2.45 103.77 254.24

M-189 Water
PRICE Kilo litre 6.0 13.00 78.00

TOTAL 131976.90
MR177

Cost of 3500.0 sqm 131976.90

Cost of 1 sqm 37.71

Bitumen primer has been provided @ 0.70 kg per sqm as per clause 502.8. Payment shall be made
Note with adjustment, plus or minus, for the variation between this quantity and the actual quantity
approved by the Engineer after the preliminary trials referred to in clause No. 502.4.3.

Add Overhead @ 10.0% 3.77

Add Contractors Profit @ 10.0% 4.14

Cost index 32.04% 0.11

Total with Cost index 45.74

Say 45.74

printed on 11-10-2019 22:25:09 page 42


PRICE EST NO:BR/2019/7248

18. Specification Code : 5.2.a

SUBHEAD : 5.0

Bases and Surface courses


Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure
5.2.a distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned
with mechanical broom.

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = sqm
Taking output = 3500 sqm
503
a) Labour

L-12 Mate Day 0.08 407.00 32.56

Mazdoor
L-13 Day 2.0 368.00 736.00
b) Manchinery

Mechanical Broom Hydraulic


P&M-031 Public Works Department
@ 1250 sqm per hour
hour 2.8 358.00 1002.40 MR230

P&M-001
250cfm
PRICE
Air Compressor

Emulsion Pressure Distributor


hour 2.8 322.00 901.60 MR200

P&M-016 hour 2.0 806.00 1612.00 MR215


c) Material

Bitumen Emulsion (RS)


M-403 tonne 0.7 30100.00 21070.00 MR121
@ 0.2 kgper sqm

M-197 carriage code of Bitumen tonne 0.7 103.77 72.64

TOTAL 25427.20

Cost of 3500.0 sqm 25427.20

Cost of 1 sqm 7.26

1. Bitumen emulsion has been provided @ 0.20 kg per sqm as per clause 503.8. Payment shall be
made with adjustment, plus or minus, for the variation between this quantity and actual quantity
Note approved by the Engineer after preliminary trials referred to in clause No. 503.4.3
2. An output of 3500 sqm has been considered in case of prime coat and tack coat which can be
covered by bituminous courses on the same day.

printed on 11-10-2019 22:25:09 page 43


PRICE EST NO:BR/2019/7248

Add Overhead @ 10.0% 0.72

Add Contractors Profit @ 10.0% 0.79

Cost index 32.04% 0.09

Total with Cost index 8.88

Say 8.88

19. Specification Code : 5.3.2.b

SUBHEAD : 5.0

BASES AND SURFACE COURSES


Providing and laying bituminous macadam with 100-120 TPH batch type hot mix plant
producing an average output of 75 tonnes per hour using bitumen VG 30 crushed aggregates
of specified grading premixed with bituminous binder, transported to site, laid over a
5.3.2.b
previously prepared surface with paver finisher to the required grade, level and alignment and
rolled as per clauses 501.6 and 501.7 to achieve the desired compaction.
Grading II - (19 mm nominal size )

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. Public Works Department ref.

PRICE
Unit = cum
Taking output = 205 cum (450
tonnes)

a) Labour

504

Mate Day 0.84 407.00 341.88


L-12

Mazdoor
working with HMP, mechanical
broom, paver, roller, asphalt
L-13 Day 14.0 368.00 5152.00
cutter and assistance for setting
out lines, levels and layout of
construction

Mazdoor/Dresser/Sinker (skilled)
for checking line & levels
L-15 Day 5.0 407.00 2035.00

b) Machinery

printed on 11-10-2019 22:25:09 page 44


PRICE EST NO:BR/2019/7248

Hotmix Plant - 120 TPH capacity


P&M-021 @ 75 tonne per hour actual hour 6.0 23579.00 141474.00 MR220
output

Air Compressor
P&M-001 hour 2.2 322.00 708.40 MR200
250 cfm

Paver finisher hydrostactic with


P&M-105 sensor control @ 75 cum per hour hour 6.0 2694.00 16164.00 MR388

Generator 250 KVA


P&M-081 hour 6.0 702.00 4212.00 MR280

Front End loader 1 cum bucket


P&M-017 capacity hour 6.0 812.00 4872.00 MR216

Tipper 10 tonne
P&M-102 tonne km 450.0 3.00 1350.00(B) MR384

Add 10 per cent of cost of


carriage to cover cost of loading
B*10/100 135.0(T)
and unloading

Smooth Wheeled Roller 8 tonne


P&M-044 hour 3.9 464.00 1809.60 MR243
for initial break down rolling.
Public Works Department
Vibratory Roller 8 tonne
P&M-059 hour 3.9 1553.00 6056.70 MR258

PRICE
for intermediate rolling.

Tandem Road Roller


Finish rolling with 6-8 tonnes
smooth wheeled tandem roller.

c) Material
i) Bitumen
P&M-045 hour 3.9 1152.00 4492.80 MR244
weight of mix = 205 x 2.2 = 450
tonne
Total weight of mix = 450 tonnes
Weight of bitumen = 450 x3.4
/100 = 15.30 tonnes

Bitumen VG-30
M-401 tonne 15.3 30820.00 471546.00 MR101
@ 3.4 per cent of mix

printed on 11-10-2019 22:25:09 page 45


PRICE EST NO:BR/2019/7248

carriage code of Bitumen

ii) Aggregate
Weight of aggregate = 450 -15.30
M-197 = 434.70 tonnes tonne 15.3 103.77 1587.68
Taking density of aggregate = 1.5
ton/cum
Volume of aggregate = ( 434.70
/1.50) = 289.80 cum

Aggregate 25mm to 10mm


M-046 cum 115.92 1318.77 152871.82
40 per cent

Aggregates 10 mm to 5 mm
M-040 cum 115.92 1403.77 162725.02
40 per cent

5 mm and below
M-208 cum 57.96 1353.77 78464.51
20 per cent

Cost of 205.0 cum 1055998.05

Cost of 1 cum 5151.21

1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be
available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving
the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
Public Works Department
2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job
Note
mix formula.

PRICE
3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries
have been included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of Mechanical broom and 2 mazdoors for
the same shall be deleted as the same has been included in the cost of tack coat.

Add Overhead @ 10.0% 515.12

Add Contractors Profit @ 10.0% 566.63

Cost index 32.04% 762.46

Total with Cost index 6995.43

Say 6995.43

20. Specification Code : 5.6.2.b

SUBHEAD : 5.0

BASES AND SURFACE COURSES

printed on 11-10-2019 22:25:09 page 46


PRICE EST NO:BR/2019/7248

Providing and laying bituminous concrete with 100-120 TPH hot mix plant producing an
average output of 75 tonnes per hour using crushed aggregates of specified grading,
premixed with bituminous binder (NRMB) @ 5.4 per cent of mix and filler, transporting the hot
mix to work site, laying with a hydrostatic paver finisher with sensor control to the required
5.6.2.b
grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MORTH specification clause No. 507 complete in all
respects
For Grading -II (13.2 mm Nominal size).

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = cum
Taking output = 191 cum (450
tonnes)

a) Labour

507

Mate Day 0.84 407.00 341.88


L-12

Mazdoor
Public Works Department
working with HMP, mechanical

L-13

PRICE
broom, paver, roller, asphalt
cutter and assistance for setting
out lines, levels and layout of
construction
Day 14.0 368.00 5152.00

Mazdoor/Dresser/Sinker (skilled)
for checking line & levels
L-15 Day 5.0 407.00 2035.00
b) Machinery

Hotmix Plant - 120 TPH capacity


P&M-021 hour 6.0 23579.00 141474.00 MR220
@ 75 tonne per hour

Paver finisher hydrostactic with


P&M-105 sensor control @ 75 cum per hour hour 6.0 2694.00 16164.00 MR388

Generator 250 KVA


P&M-081 hour 6.0 702.00 4212.00 MR280

Front End loader 1 cum bucket


P&M-017 capacity hour 6.0 812.00 4872.00 MR216

printed on 11-10-2019 22:25:09 page 47


PRICE EST NO:BR/2019/7248

Tipper 10 tonne
P&M-102 tonne km 450.0 3.00 1350.00(B) MR384

Add 10 per cent of cost of


carriage to cover cost of loading
B*10/100 135.0(T)
and unloading

Smooth Wheeled Roller 8 tonne


P&M-044 hour 3.9 464.00 1809.60 MR243
for initial break down rolling.

Vibratory Roller 8 tonne


P&M-059 hour 3.9 1553.00 6056.70 MR258
for intermediate rolling.

Tandem Road Roller


Finish rolling with 6-8 tonnes
smooth wheeled tandem roller.

c) Material
P&M-045 hour 3.9 1152.00 4492.80 MR244
i) Bitumen

Total weight of mix = 450 tonnes


Weight of bitumen =450 x 5.4
/100 = 24.30 tonnes

Bitumen (NRMB)
M-402 tonne 24.3 35370.00 859491.00 MR102
Public Works Department
@ 5.4 per cent of weight of mix

PRICE
carriage code of Bitumen

ii) Aggregate

Weight of aggregate = 450 -24.30


M-197 tonne 24.3 103.77 2521.61
= 427.50 tonnes
Taking density of aggregate = 1.5
ton/cum
Volume of aggregate = 427.5/1.5
= 283.80 cum

Aggregate 20mm to 10mm


M-045 cum 85.14 1403.77 119516.98
30 per cent

Aggregates 10 mm to 5 mm
M-040D cum 70.95 1403.77 99597.48
25 per cent

5 mm and below
M-208 cum 122.034 1353.77 165205.97
43 per cent

Filler @ 2 per cent of weight of


M-203 aggregates. cum 5.676 968.77 5498.74

printed on 11-10-2019 22:25:09 page 48


PRICE EST NO:BR/2019/7248

Cost of 191.0 cum 1439926.08

Cost of 1 cum 7538.88

1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be
available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving
the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65
2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job
mix formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries
have been included in administrative overheads of the contractor.
Note
4. In case BC is laid over freshly laid tack coat, provision of mechanical broom and 2 mazdoors shall
be deleted as the same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be used for construction i.e. 37.5-25 mm, 25-
10 mm etc. should be found in the laboratory and accordingly the quantities should be ammended for
use in field. The average density of 1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be calculated from the total weight of dry
aggregates i.e.. excluding the weight of bitumen. The weight of filler will also be 2 per cent by weight
of dry aggregates.

Add Overhead @ 10.0% 753.88

Public WorksAddDepartment
Contractors Profit @ 10.0% 829.27

PRICE
Cost index 32.04% 811.63

Total with Cost index 9933.68

Say 9933.68

21. Specification Code : 8.4.5

SUBHEAD : 8.0

TRAFFIC SIGNS,MARKINGS & OTHER ROAD APPURTENANCES


Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign with
7years warranty manufactured as per IRC :67 made of Type IV micro prismatic grade
sheeting vide clause 801.3.3 fixed over aluminium sheeting, 2 mm thick/ aluminium composit
material sheeting 4 mm thick with suitable back supporting frame of MS angle 25x25x3 and
supported on GI pipe pole 50mm NB confirming to IS 1239 firmly fixed to the ground by
8.4.5
means of properly designed foundation with M 15 grade cement concrete min size 45 cm x 45
cm x 60 cm, 60 cm below ground level including painting all exposed surface with 2 coats of
epoxy painting over epoxy primer and as per approved drawing and clause 801 including
lettering symbols etc.
60 cm x 45 cm rectangular

printed on 11-10-2019 22:25:09 page 49


PRICE EST NO:BR/2019/7248

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = Each
Taking output = one traffic sign

801

Rate as per item Number of SH:


Foundations cum 0.216 134.50 29.05
12.1.A.1
Excavation for foundation

Rate as per item Number of SH:


Foundations
12.8.A cum 0.12 4228.66 507.44
Cement concrete M15 grade

Rate as per item Number of SH:


Traffic signs,Markings & Other
Road Appurtenances
Painting angle iron post two
8.9.A sqm 0.827 63.91 52.85
coats

a) Labour (For fixing at site)

Mate
Public Works Department
L-12 Day 0.01 407.00 4.07

L-13
Mazdoor
PRICE
b) Material Day 0.25 368.00 92.00

GI pipe 50 mm dia
M-210 metre 3.1 220.00 682.00(A)
3.1 m long

Structural Steel
M-179 Mild steel angle 25 x 25 x 3 - tonne 0.00264 37842.24 99.90(B)
2.4m @ 1.10Kg/m

Aluminium sheeting fixed with


ASTM Type IV retroreflective
M-212 sqm 0.27 3495.00 943.65(C) MR419
sheeting

printed on 11-10-2019 22:25:09 page 50


PRICE EST NO:BR/2019/7248

Add 2 per cent of cost of material


towards cost of drilling holes,
(A+B+C)*2/
nuts, bolts etc. 34.511(T)
100

c) Machinery

Tractor
P&M-053 hour 0.01 365.00 3.65 MR252

Cost of 1.0 each 2449.13

1.Rate for excavation, cement concrete M-15 may be taken from respective chapters 2. The depth of
foundation and quantity of cement concrete in the foundation are indicative. These may be increased
Note
for areas having higher wind velocities like in coastal areas. This is applicable to all road signs and
directions boards. 3. Price of Aluminium sheeting is inclusive of cost for lettering.

Add Overhead @ 10.0% 244.91

Add Contractors Profit @ 10.0% 269.40

Cost index 32.04% 563.60

Total with Cost index 3527.05

Say 3527.05

Public Works Department


22. Specification Code : 8.6

PRICE SUBHEAD : 8.0

TRAFFIC SIGNS,MARKINGS & OTHER ROAD APPURTENANCES


Providing and fixing of direction and place identification retro-reflectorised sign with 7 years
warranty manufactured as per IRC :67 High Intensity Micro Prismatic (Type IV) grade
sheeting fixed over aluminium sheeting, 2 mm thick/ aluminium composit material sheeting 4
mm thick with area exceeding 0.9 sqm, with suitable back supporting frame of MS angle
8.6 40x40x6 and supported on suitably designed GI pipe pole not less than 50mm NB , 2 Nos.
confirming to IS 1239, firmly fixed to the ground by means of properly designed foundation
with M 15 grade cement concrete min size 45 cm x 45 cm x 60 cm, 60 cm below ground level
including painting all exposed surface with 2 coats of epoxy painting over epoxy primer and as
per approved drawing and clause 801 including lettering symbols etc.

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = sqm
Taking output = 1.50 sqm

printed on 11-10-2019 22:25:09 page 51


PRICE EST NO:BR/2019/7248

801

Rate as per item Number of SH:


Foundations cum 0.432 134.50 58.10
12.1.A.1
Earthwork excavation

Rate as per item Number of SH:


12.8.A Foundations cum 0.24 4228.66 1014.88
Cement concrete M15 grade

Rate as per item Number of SH:


Traffic signs,Markings & Other
Road Appurtenances
8.9.A sqm 2.35 63.91 150.19
Painting angle & post 2 coats

a) Labour (For fixing at site)

Mate
L-12 Day 0.01 407.00 4.07

Mazdoor
L-13 Day 0.3 368.00 110.40
b) Material

GI pipe 50 mm dia
M-210 metre 7.0 220.00 1540.00(A)
3.5m long,2nos

Structural Steel

M-179
Public Works Department
Mild steel angle iron 40mm x 40
tonne 0.02239 37842.24 847.29(B)
mm x 6 mm,6.4metres long @

M-212
PRICE
3.498 kg/m

Aluminium sheeting fixed with


ASTM Type IV retroreflective
sheeting
sqm 1.5 3495.00 5242.50(C) MR419

Add 2 per cent of cost of post &


back support frame for drilling
holes, nuts, bolts, fabrication etc. (A+B+C)*2/
152.596(T)
100
c) Machinery

Tractor
P&M-053 hour 0.02 365.00 7.30 MR252

Cost of 1.5 sqm 9127.32

Cost of 1 sqm 6084.88

i) Rate for excavation, cement concrete M-15 and painting may be taken from respective chapters ii)
Note
For large sign boards size of supporting pole may be increased suitably as the case may be.

printed on 11-10-2019 22:25:09 page 52


PRICE EST NO:BR/2019/7248

Add Overhead @ 10.0% 608.48

Add Contractors Profit @ 10.0% 669.33

Cost index 32.04% 959.98

Total with Cost index 8322.69

Say 8322.69

23. Specification Code : 55.10.1

SUBHEAD : 55.0

OD MORTH
Providing and erecting retro-reflectorised Object Hazard Marker 300mm x 900mm
Providing and erecting retro-reflectorised Object Hazard Marker sign with 07 years warranty,
manufactured as per IRC 67 USING Type IV ASTM D 4956-09 micro prismatic retro reflective
sheeting fixed over aluminium sheetig, 2 mm thick / aluminium composit material sheeting 4
mm thick with suitable back support frame and supported on a mild steel angle iron post
55.10.1
75mmx75mmx6mm, firmly fixed 30cm above ground level by means of properly designed
foundation with M 15 grade cement concrete 30cmx30x45cm, 45cm below ground level
including painting all non-reflective faces with epoxy paint 2 coats over epoxy primer as per
Public Works Department
approved drawing and clause 801.
300 mm x 900 mm

Morth
SOR
Code
Ref. to
MoRTH
Spec.
PRICEDescription Unit Quantity Rate Rs Cost Rs
Remarks
/Input
ref.

Taking output = one traffic sign

Rate as per item Number of SH:


Foundations cum 0.091 134.50 12.24
12.1.A.1
Excavation for foundation

Rate as per item Number of SH:


Foundations
12.8.A.1 cum 0.04 4397.81 175.91
Cement concrete M15 grade

Rate as per item Number of SH:


Traffic signs,Markings & Other
8.9.A Road Appurtenances sqm 0.72 63.91 46.02
Cement concrete M15 grade

printed on 11-10-2019 22:25:09 page 53


PRICE EST NO:BR/2019/7248

Mate
Painting angle iron post and
frame two coats

L-12 Day 0.01 407.00 4.07


a) Labour (For fixing at site)

Mazdoor
L-13 Day 0.25 368.00 92.00

Structural Steel

M-179 tonne 0.01088 37842.24 411.72(B)


b) Material

Structural Steel
Mild steel angle iron 75 x 75 x 6
M-179 tonne 0.00264 37842.24 99.90(C)
mm -1.6m @6.8m/kg

Add 2 per cent of cost of angle


iron towards cost of drilling holes,
(B+C)*2/10
nuts, bolts etc. 10.2324(T)
0
Mild steel angle 25 x 25 x 3 -
2.4m @1.1kg/m Public Works Department

PRICE
Aluminium sheeting fixed with
ASTM Type IV retroreflective
M-212 sqm 0.27 3495.00 943.65 MR419
sheeting

Tractor
of size including lettering and
signs as applicable
P&M-053 hour 0.01 365.00 3.65 MR252
c) Machinery

Cost of 1.0 each 1799.40

Cost of 1 each 1799.40

1.Rate for excavation, cement concrete M-15 and painting may be taken from respective chapters
2. The depth of foundation and quantity of cement concrete in the foundation are indicative. These
Note
may be increased for areas having higher wind velocities like in coastal areas. This is applicable to all
road signs and directions boards.

printed on 11-10-2019 22:25:09 page 54


PRICE EST NO:BR/2019/7248

Add Overhead @ 10.0% 179.94

Add Contractors Profit @ 10.0% 197.93

Cost index 32.04% 326.42

Total with Cost index 2503.70

Say 2503.70

24. Specification Code : 8.13

SUBHEAD : 8.0

Traffic signs,Markings & Other Road Appurtenances


Providing and laying of hot applied thermoplastic compound 2.5 mm thick including
reflectorising glass beads on Bituminous Surface @ 250 gms per sqm area, thickness of 2.5
8.13
mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be
level, uniform and free from streaks and holes.

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit=sqm
803
Public Works Department
Taking output= 600 sqm

L-12

L-13
Mate

Mazdoor
PRICE
a) Labour

b) Machinery
Day

Day
0.03

0.75
407.00

368.00
12.21

276.00

P&M-043 Road marking machine hour 10.0 93.00 930.00 MR242

Tractor
P&M-053 hour 0.5 365.00 182.50 MR252
c) Material

Hot applied thermoplastic


M-118 Litre 1500.0 120.00 180000.00
compound

M-152 Refllectiorising glass beads kg 150.0 60.00 9000.00

TOTAL 190400.71

Cost of 600.0 sqm 190400.71

Cost of 1 sqm 317.33

1. A sealing primer may be applied in advance on cement concrete pavement to ensure proper
Note bonding. Any laitance and/or curing compound to be removed where paint is required to be applied
on concrete surface.2. Cost of painter is already included in hire cjharges of road marking machine.

printed on 11-10-2019 22:25:09 page 55


PRICE EST NO:BR/2019/7248

Add Overhead @ 10.0% 31.73

Add Contractors Profit @ 10.0% 34.90

Cost index 32.04% 122.30

Total with Cost index 506.28

Say 506.28

25. Specification Code : 8.35

SUBHEAD : 8.0

TRAFFIC SIGNS,MARKINGS & OTHER ROAD APPURTENANCES


Providing and fixing reflective road studs (Raised Pavement Marker) of ' category A' made out
of ASA/HIPS/ABS moulded body with shanks and conforming to ASTM D 4280, strong
enough to support a load of more than 13.635 T when tested in accordance with ASTM D
8.35 4280, reflective panel confirming to ASTM D 788, and reflectivity conforming to clause 804.4.
including installation, drilling, fixing with adhesive etc. with 2 years warranty for the road stud
as well as for in field performance as per clause 804.7.3
Road Markers/Road Stud with Lense Reflector :-

Morth Ref. to Public Works Department Remarks

PRICE
SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.

Unit = Nos
Taking output = 50Nos
a) Labour

804

Mate Day 0.04 407.00 16.28


L-12

Mazdoor
L-13 Day 1.0 368.00 368.00
b) Material

Roads studs 100 x 100 mm fitted


M-214 with lense reflectors each 50.0 105.00 5250.00(A)

Add 10 per cent of cost of


material for fixing and installation. A*10/100 525.0(T)

Cost of 50.0 no 6159.50

printed on 11-10-2019 22:25:09 page 56


PRICE EST NO:BR/2019/7248

Cost of each 123.19

Add Overhead @ 10.0% 12.31

Add Contractors Profit @ 10.0% 13.55

Cost index 32.04% 47.75

Total with Cost index 196.82

Say 196.82

26. Specification Code : 13.3

SUBHEAD : 13.0

Sub-Structure
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical
13.3
Specifications

Morth Ref. to Remarks


SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.
Public Works Department
Unit: 10 sqm
1300 &
2200
PRICE
Taking output = 10 sqm
a) Material

Rate as per item Number of SH:


Foundations
12.6.A Cement mortat 1:3 ( Rate as in cum 0.144 4670.48 672.55
item 12.6)
b) Labour

L-12 Mate Day 0.04 407.00 16.28

L-11 Mason (1st class) Day 0.5 487.00 243.50

L-13 Mazdoor Day 0.5 368.00 184.00

TOTAL 1116.33

Cost of 10.0 sqm 1116.33

Cost of 1 sqm 111.63

1.Scaffolding is already included in item no. 13.1


Note 2.The number of masons and Mazdoors already catered in the cement mortar have been taken into
account while providing these categories in brick masonry, pointing and plastering.

printed on 11-10-2019 22:25:09 page 57


PRICE EST NO:BR/2019/7248

Add Overhead @ 10.0% 11.16

Add Contractors Profit @ 10.0% 12.27

Cost index 32.04% 43.27

Total with Cost index 178.35

Say 178.35

Public Works Department

PRICE

printed on 11-10-2019 22:25:09 page 58

You might also like