Professional Documents
Culture Documents
DATA ANALYSIS
BRIDGE PROPER
SUBHEAD : 2.0
Site Clearence
Dismantling of existing structures like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood work, steel work, including T&P and
2.4.2.A scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable
material and stacking the serviceable material with all lifts and lead of 1000 metres
Cement Concrete Grade M-15 & M-20 - By Mechanical Means
unit=cum
202 Taking output = 1.25 cum
a) Labour
Mazdoor
Public Works Department
L-13 for loading and unloading Day 0.25 368.00 92.00
L-14
PRICE
Mazdoor/Dresser (Semi Skilled)
with Pneumatic breaker
Day 0.25 368.00 92.00
b) Machinery
Air Compressor
250 cfm with 2 leads of pneumatic
P&M-001 hour 0.67 322.00 215.74 MR200
breaker @ 1.5 cum per hour
TOTAL 506.43
1. The excavation of earth, dismantling of stone masonry work in head walls and protection works is
Note not included which is to be measured and paid separately. 2. Credit for retrieved stone from masonry
work may be taken as per actual availability.
Say 599.79
SUBHEAD : 2.0
Site Clearence
Dismantling of existing structures like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood work, steel work, including T&P and
2.4.2.B scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable
material and stacking the serviceable material with all lifts and lead of 1000 metres
Prestressed / reinforced cement concrete grade M-20 & above - By Mechanical Means
L-12
202
Mate
PRICE
unit=cum
Taking output = 1.25 cum
a) Labour
Mazdoor
for loading and unloading
L-13 b) Machinery Day 0.25 368.00 92.00
Air Compressor
250 cfm with 2 leads of pneumatic
P&M-001 hour 1.0 322.00 322.00 MR200
breaker @ 1.00 cum per hour
TOTAL 897.53
1. The excavation of earth, dismantling of stone masonry work in head walls and protection works is
Note not included which is to be measured and paid separately. 2. Credit for retrieved stone from masonry
work may be taken as per actual availability.
Say 1109.17
SUBHEAD : 2.0
Site Clearence
Public Works Department
Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery of
2.2
Morth
SOR
Ref. to
MoRTH
the area
Unit = Hectate
201 Taking output = 1 Heatare
a) Labour
TOTAL 19214.00
Say 33488.62
SUBHEAD : 12.0
Foundations
Earth work in excavation of foundation of structures as per drawing and technical
specification, including setting out, construction of shoring and bracing, removal of stumps
12.1.B.1 and other deleterious matter, dressing of sides and bottom and backfilling with approved
material.
Ordinary Soil - Depth upto 3m - Mechanical Means
Unit = cum
304 Taking output =240 cum
a) Labour
PRICE
Mazdoor
L-13 Day 8.0 368.00 2944.00
b) Machinery
TOTAL 10946.24
Labour provided for excavation by mechanical means includes that required for trimming of bottom
Note
and side slopes.
Say 65.62
SUBHEAD : 12.0
Foundations
Earth work in excavation of foundation of structures as per drawing and technical
specification, including setting out, removal of stumps and other deleterious matter, only for
12.1.B.2
dressing of sides and bottom and backfilling with approved material.
Ordinary Soil - Depth 3 M to 6 M- Mechanical Means
Unit = cum
304 Taking output = 210 cum
a)Labour
Mazdoor
L-13 Day 8.0 368.00 2944.00
b) Machinery
Say 74.99
SUBHEAD : 12.0
Foundations
Unit= cum
Taking output= 10 cum
304
Mechanical Means
a) Labour
Mazdoor
L-13 Day 5.0 368.00 1840.00
b) Machinery
Air Compressor
250 cfm with 2 leads of pneumatic
P&M-001 hour 6.0 322.00 1932.00 MR200
breaker
TOTAL 3853.40
Public Works Department
Cost of 10.0 cum 3853.40
Note
PRICE Cost of 1 cum 385.34
In case of rock, foundation beyound 3 m is not dug and hence not included.
Say 589.91
od18544/2019_2020 :Providing dowel bars using 25mm dia rods, 3.00m long at about 1.0m c/c, keeping 1.50m
length within concrete and 1.50m into the rock, after drilling holes in granite rock including cost and coneyance of
all materials cutting ros in position with grout 1:2 etc complete with all incidental charges etc.
TOTAL 617.25
say 617.25
SAY 814.77
Say 1075.82
Public Works Department
8. Specification Code : od18545/2019_2020
PRICE
od18545/2019_2020 :Pumping or Bailing out water and removing slush etc by using pump set including cost of
labour, oil hire charges of pumpset, etc complete
TOTAL 125.39
say 125.39
SAY 165.51
Say 218.07
SUBHEAD : 12.0
Foundations
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and
12.8.1.C Technical Specifications
RCC Grade M20 - Using Concrete Mixer - (Without formwork)
Unit = cum
1500,170
Taking output = 15 cum
0 & 2100
a) Material
PRICE
M-053 Aggregates 20mm nominal size cum 8.1 1403.77 11370.54
Mazdoor
L-13 Day 20.0 368.00 7360.00
c) Machinery
TOTAL 70017.44
Say 8032.84
SUBHEAD : 12.0
FOUNDATIONS
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and
12.8.H.2.1 Technical Specifications.
RCC Grade M35 - Using Batching Plant, Transit Mixer and Concrete Pump
1500,170
0 & 2100
PRICE
T RCC Grade M35
Formwork @ 3 per cent on cost of
concrete of 12.8.H.2
B*3/100 140.488(T)
Say 8268.23
SUBHEAD : 12.0
Foundations
Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as
12.40
per Drawing and Technical Specifications
Unit = 1 MT
1600 Taking output = 1 MT
a) Material
Binding wire
b) Labour for cutting, bending,
M-072 kg 6.0 48.09 288.54
shifting to site, tying and placing
in position
Cost of 1 MT 42895.19
Say 74763.23
SUBHEAD : 13.0
SUB-STRUCTURE
1500,170
0 & 2200
The basic components of this analysis are the same as those of items 12.8 (A to H). The only
changes are as under:
a) Ramps/Stairs: Extra expenditure on structures which are more than 5 m high @ 2 per cent of cost
for height upto 10 m and 4 per cent for heights above 10 m will be involved for approaching the work
Note Public Works Department
spot by providing higher ramp/stair case for use by the working parties.
b) The above mentioned percentages have been suitably modified for different categories as cost for
PRICE
various categories varies, whereas effort for access for same height will be similar. As the cost of
richer concrete is comparatively more, the percentage to be added has been reduced to maintain the
same cost for extra efforts.
Say 9665.29
SUBHEAD : 13.0
Sub-Structure
Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per
13.6
drawing and Technical Specifications
Output: MT
1600 &
Taking output = 1 MT
2200
a) Material
Binding wire
b) Labour for cutting, bending,
shifting to site, tying and placing
M-072 kg 6.0 48.09 288.54
in position
Cost of 1 MT 43054.77
Say 75041.36
SUBHEAD : 14.0
SUPER-STRUCTURE
"Furnishing and Placing PSC Grade M40 Using Concrete Mixer as per drawing and Technical
14.1E.1.2.A Specification.
For T-beam & slab - Height upto 5m"
1500,160
0 & 1700
1.Where ever concrete is carried out using batching plant, transit mixer, concrete pump, admixers
conforming IS: 9103 @ 0.4 per cent of weight of cement may be added for achieving desired slump of
concrete.2. Cement provided for various components of the super structure is for estimating purpose
Note only. Actual quantity of cement will be as per approved mix design. Similarly, the provision for coarse
Public Works Department
and fine aggregates is for estimating purpose and the exact quantity shall be as per the mix design.3.
The items like needle and surface vibrators are part of minor T & P which is already covered under
PRICE
the overhead charges. As such these items have not been added separately in the rate analysis.
Say 11374.82
SUBHEAD : 14.0
SUPER-STRUCTURE
"Furnishing and Placing PSC Grade M45 Using Batching Plant, Transit Mixer and Concrete
14.1F.1.A Pump as per drawing and Technical Specification.
For solid slab/voided slab super-structure - Height upto 5m"
1500,160
0 & 1700
1.Where ever concrete is carried out using batching plant, transit mixer, concrete pump, admixers
conforming IS: 9103 @ 0.4 per cent of weight of cement may be added for achieving desired slump of
concrete.2. Cement provided for various components of the super structure is for estimating purpose
Note only. Actual quantity of cement will be as per approved mix design. Similarly, the provision for coarse
and fine aggregates is for estimating purpose and the exact quantity shall be as per the mix design.3.
The items like needle and surface vibrators are part of minor T & P which is already covered under
the overhead charges. As such these items have not been added separately in the rate analysis.
Cost index
697.55
32.04% 2302.31
Say 9975.45
SUBHEAD : 14.0
Super-Structure
Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per
14.2
drawing and technical specifications
Unit = 1 MT
1600 Taking output = 1 MT
a) Material
Binding wire
M-072 b) Labour for cutting, bending, kg 8.0 48.09 384.72
typing and placing in position
TOTAL 44230.65
Say 77090.84
SUBHEAD : 14.0
SUPER-STRUCTURE
High tensile steel wires/strands including all accessories for stressing, stressing operations
14.3
and grouting complete as per drawing and Technical Specifications
Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand
40 m long cable (weight = 0.377
MT)
a) Material
1800
HTS Strand
@ 9.42 kg/m including 2 per cent 22620.00(
tonne 0.39 58000.00 MR134
M-119 for wastage and extra length for B)
jacking
Sheathing duct
M-165 ID 66 mm along with 5 per cent metre 42.0 180.00 7560.00(C) MR163
extra length 40 x 1.05 = 42 m.
Cement
b) Labour
M-081 i) For making and fixing cables, tonne 0.125 5792.24 724.03(E)
anchorages
Public Works Department
PRICE
Add 0.50 per cent cost of material
for Spacers, Insulation tape and
miscellaneous items
(B+C+D+E
)*0.5/100
183.52(T)
Mate
L-12 Day 0.16 407.00 65.12
Blacksmith
L-02 Day 1.0 487.00 487.00
Mazdoor
L-13 ii) For prestressing Day 3.0 368.00 1104.00
Mate
L-12 Day 0.05 407.00 20.35
Fitter
L-08 Day 0.25 487.00 121.75
Mazdoor
L-13 iii) For grouting Day 1.0 368.00 368.00
Mate
L-12 Day 0.05 407.00 20.35
Mazdoor
L-13 Day 1.0 368.00 368.00
c) Machinery
Generator 33 KVA
P&M-079 hour 3.5 374.00 1309.00 MR278
Cost of 1 MT 111172.07
Note Cost of HT steel has been taken for delivery at site. Hence carriage has not been considered.
Say 150565.79
SUBHEAD : 14.0
SUPER-STRUCTURE
Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post not to exceed 1 in 500, center to center spacing
14.7
between vertical post not to exceed 2000 mm, leaving adequate space between vertical post
for expansion, complete as per approved drawings and technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span =
48 m.
a) Material
2703
Cost of 1 RM
59356.80
1236.60
1. Quantities of material have been adopted from standard plans of MoRTH vide drawing no.
Note
SD/202.2. 48 m length is the total linear length adding both sides of 24 m span.
Say 2142.45
SUBHEAD : 14.0
Super-Structure
Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
14.4
complete as per drawing and Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
2702
a) Material
Mazdoor
L-13 Public Works Department
for cleaning deck slab concrete
Day 0.15 368.00 55.20
surface.
Say 14554.51
SUBHEAD : 14.0
Super-Structure
PCC M15 Grade leveling course below approach slab complete as per drawing and Technical
14.10
specification.
Unit = 1 cum
Taking output = 1 cum
2700
Material
TOTAL 4228.66
SUBHEAD : 14.0
SUPER-STRUCTURE
Reinforced cement concrete approach slab including reinforcement and formwork complete
14.11
as per drawing and Technical specification.
Unit = 1 cum
Taking output = 1 cum
a) Material
1500,160
0,1700,27
04
The grade of reinforced cement concrete may be adopted as M30 for severe conditions and M25 for
Note
moderate conditions.
Say 11884.59
SUBHEAD : 14.0
SUPER-STRUCTURE
14.9 Drainage Spouts complete as per drawing and Technical specification
Unit = 1 No.
Taking output = 1 No.
a) Material
2705
Mate
L-12 Day 0.02 407.00 8.14(F)
Blacksmith
L-02 Day 0.02 487.00 9.74(G)
Mazdoor
L-13 Day 0.02 368.00 7.36(H)
For fixing in position
Mate
L-12 Day 0.01 407.00 4.07(I)
PRICE
Mazdoor
L-13 Day 0.2 368.00 73.60(K)
1. In case of viaducts in urban areas, the drainage spouts should be connected with suitably located
pipelines to discharge the surface run-off to drains provided at ground level.2. In case of bridges,
Note
sufficient length of G.I Pipe shall be provided to ensure that there is no splashing of water from the
drainage spout on the structure.
Say 4517.42
SUBHEAD : 14.0
Super-Structure
Providing and applying 2 coats of water based cement paint to unplastered concrete surface
14.16 after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1
litre for 2 sqm.
Unit: sqm
800 Taking output = 10 sqm
a) Labour
L-12 Mate
Public Works Department
Day 0.01 407.00 4.07
L-18
L-15
PRICE
Painter 1 class
Mazdoor/Dresser/Sinker (skilled)
b) Material
Day
Day
0.25
0.25
448.00
407.00
112.00
101.75
TOTAL 1217.82
Say 212.25
Approach road
printed on 11-10-2019 22:25:09 page 23
PRICE EST NO:BR/2019/7248
SUBHEAD : 12.0
Foundations
Earth work in excavation of foundation of structures as per drawing and technical
specification, including setting out, construction of shoring and bracing, removal of stumps
12.1.2.B and other deleterious matter, dressing of sides and bottom and backfilling with approved
material.
Ordinary Rock (not requiring blasting ) - Depth up to 3 m - Mechanical Means
Mechanical Means
Unit = cum
304
Taking output= 180 cum
a) Laour
Mazdoor
L-13 Day 6.0 368.00 2208.00
b) Machinery
Public Works Department
Hydraulic Excavator of 1 cum
PRICE
P&M-026 hour 6.0 1312.00 7872.00 MR225
bucket
TOTAL 10177.68
Note In case of rock, foundation beyond 3 m is not dug and hence not included
Say 73.38
SUBHEAD : 12.0
Foundations
Unit = cum
1500,170
Taking output = 15 cum
0 & 2100
a) Material
P&M-009
PRICE
c) Machinery
hour
20.0
6.0
368.00
234.00
7360.00
1404.00 MR208
TOTAL 63429.88
Needle Vibrator is an item of minor T & P which is already included in overhead charges. Hence not
Note
added in rate analysis of cement concrete works.
Say 6661.78
SUBHEAD : 15.0
Unit = cum
Taking output = 1 cum
a) Material
2506
L-12
L-11
Mate
PRICE
Mason (1st class)
Day
Day
0.1
0.5
407.00
487.00
40.70(A)
243.50(B)
Mazdoor
L-13 Day 1.5 368.00 552.00(C)
Say 3189.07
SUBHEAD : 12.0
FOUNDATIONS
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and
12.8.G.1.1 Technical Specifications.
RCC Grade M30 - Using Concrete Mixer
1500,170
0 & 2100
PRICE
of concrete of 12.8.G.1
Say 8189.44
SUBHEAD : 12.0
Foundations
Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as
12.40
per Drawing and Technical Specifications
Unit = 1 MT
1600 Taking output = 1 MT
a) Material
Binding wire
b) Labour for cutting, bending,
M-072 kg 6.0 48.09 288.54
shifting to site, tying and placing
in position
Cost of 1 MT 42895.19
Say 68532.96
SUBHEAD : 12.0
FOUNDATIONS
1500,170
0 & 2100
Cost index
530.10
32.04% 1770.23
Say 7601.37
SUBHEAD : 13.0
SUB-STRUCTURE
Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical
13.5.G.P.1 Specifications
RCC Grade M30 - Using concrete Mixer - Height upto 5m
1500,170
0 & 2200
The basic components of this analysis are the same as those of items 13.8 (A to H). The only
changes are as under
:a) Ramps/Stairs: Extra expenditure on structures which are more than 5 m high @ 2 per cent of cost
for height upto 10 m and 4 per cent for heights above 10 m will be involved for approaching the work
Note spot by providing higher ramp/stair case for use by the working parties.
b) The above mentioned percentages have been suitably modified for different categories as cost for
various categories varies, whereas effort for access for same height will be similar. As the cost of
richer concrete is comparatively more, the percentage to be added has been reduced to maintain the
same cost for extra efforts.
PRICE
Add Contractors Profit @ 10.0% 606.39
Say 8703.76
SUBHEAD : 13.0
Sub-Structure
Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per
13.6
drawing and Technical Specifications
Output: MT
1600 &
Taking output = 1 MT
2200
a) Material
Binding wire
b) Labour for cutting, bending,
shifting to site, tying and placing
M-072 kg 6.0 48.09 288.54
in position
TOTAL 43054.77
Cost of 1 MT 43054.77
Cost index
4736.02
32.04% 16691.64
Say 68787.92
SUBHEAD : 13.0
SUB-STRUCTURE
Plain/Reinforced Cement Concrete in sub-structure complete as per drawing and Technical
13.5.B Specifications
PCC Grade M20 - Height upto 5m
1500,170
0 & 2200
The basic components of this analysis are the same as those of items 12.8 (A to H). The only
changes are as under:
a) Ramps/Stairs: Extra expenditure on structures which are more than 5 m high @ 2 per cent of cost
for height upto 10 m and 4 per cent for heights above 10 m will be involved for approaching the work
Note spot by providing higher ramp/stair case for use by the working parties.
b) The above mentioned percentages have been suitably modified for different categories as cost for
various categories varies, whereas effort for access for same height will be similar. As the cost of
Public Works Department
richer concrete is comparatively more, the percentage to be added has been reduced to maintain the
PRICE
same cost for extra efforts.
Say 8039.92
SUBHEAD : 13.0
Sub-Structure
Providing and laying of Filter media with granular materials/stone crushed aggregates
satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a
thickness of not less than 600 mm with smaller size towards the soil and bigger size towards
13.10
the wall and provided over the entire surface behind abutment, wing wall and return wall to
the full height compacted to a firm condition complete as per drawing and Technical
Specification.
Unit = cum
2200 Taking output = 10 cum.
a) Labour
Mazdoor
L-13 for filling, watering, ramming etc. Day 7.0 368.00 2576.00
Mazdoor/Dresser/Sinker (skilled)
L-15 Day 1.0 407.00 407.00
b) Material
M-012
PRICE
conforming to clause 2504.2.2. of
MoRTH specifications.
c) Machinery
cum 12.0 1241.54 14898.48
Water Tanker
P&M-060 6 KL Capacity hour 0.06 250.00 15.00 MR259
TOTAL 18026.72
Say 2879.52
TOTAL 9902.83
PRICE
Add Overhead @ 10.0% 33.00
SAY 399.40
Say 406.62
SUBHEAD : 3.0
Unit = cum
Taking output = 100 cum
a) Labour
305
Mazdoor
L-13 Day 1.0 368.00 368.00
b) Machinery
Tipper 10 tonne
P&M-102 tonne km 160.0 3.00 480.00(A) MR384
capacity
Dozer D - 80 - A 12
P&M-014
Public Works Department
for spreading @ 200 cum per
hour 0.5 3748.00 1874.00 MR213
P&M-140
hour
PRICE
Motor Grader for grading
@ 100 cum per hour
Water Tanker
hour 1.0 2413.00 2413.00 MR471
Water
M-189 Kilo litre 24.0 13.00 312.00 MR177
Compensation for earth will vary from place to place and will have to be assessed realistically as per
Note particular ground situation. In case earth is available from Govt. land, compensation for earth will not
be required. The position is required to be clearly stated in the cost estimate.
Say 380.74
SUBHEAD : 3.0
301
PRICE
Unit= cum
Description
a) Labour
Mazdoor
L-13 Day 2.0 368.00 736.00
b)Machinery
Dozer D - 80 - A 12
P&M-014 @ 30 cum per hour hour 6.0 3748.00 22488.00 MR213
TOTAL 23256.56
Say 157.99
SUBHEAD : 3.0
Unit=cum
301 Taking output=108cum
a) Labour Public Works Department
L-12
L-13
Mate
Mazdoor
PRICE
b) Machinery
Dozer D - 80 - A 12
Day
Day
0.12
3.0
407.00
368.00
48.84
1104.00
TOTAL 23640.84
Say 269.01
SUBHEAD : 4.0
Unit = cum
Taking output = 225 cum (450
tonne)
a) Labour
401
PRICE
L-15 Day 2.0 407.00 814.00
Mazdoor
L-13 Day 8.0 368.00 2944.00
b) Machinery
Water Tanker
P&M-060 6 KL capacity 5 km lead with one hour 4.5 250.00 1125.00 MR259
trip per hour
Tipper 10 tonne
P&M-102 tonne km 450.0 3.00 1350.00(A) MR384
c) Material
Granular sub-base Material as per
P&M-059 table 400-1 hour 6.0 1553.00 9318.00 MR258
For Grading-II Material
26.5 mm to 9.5 mm
M-015 cum 100.8 1383.77 139484.02
@ 35 per cent
9.5 mm to 2.36 mm
M-017 cum 72.0 1343.77 96751.44
@ 25 per cent
2.36 mm below
M-020 cum 115.2 1303.77 150194.30
@ 40 per cent
Water
Public Works Department
M-189 Kilo litre 27.0 13.00 351.00 MR177
Say 3003.69
SUBHEAD : 4.0
Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam
specification including premixing the Material with water at OMC in mechanical mix plant
4.12 carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base /
base course on well prepared surface and compacting with vibratory roller to achieve the
desired density.
Unit=cum
Taking output=225 cum (495
tonnes)
Labour
406
Mazdoor/Dresser/Sinker (skilled)
L-15 Day 2.0 407.00 814.00
Mazdoor
P&M-094 PRICE
Wet Mix plant 75 TPH
capacity
hour 6.6 1213.00 8005.80 MR293
Water Tanker
P&M-060 hour 3.0 250.00 750.00 MR259
6 KL capacity
Water
M-189 Kilo litre 18.0 13.00 234.00 MR177
1. Though vibratory roller is required only for 3 hours as per norms, the same is required to be
available at site for 6 hours to match with other machines. The usage rates of vibratory roller may be
Note multiplied with a factor of 0.652. As three wheeled smooth steel rollers are commonly in use, the
same has been provided as an alternative which can be used if the thickness of individual layer does
not exceed 100 mm..
Cost index
183.42
201.76
32.04% 656.53
Say 2875.93
SUBHEAD : 5.0
Unit = sqm
Taking output = 3500 sqm
502
a) Labour
Mazdoor
L-13 Day 2.0 368.00 736.00
b) Machinery
Water Tanker
P&M-060 6 KL capacity @ 1 trip per hour hour 1.0 250.00 250.00 MR259
c) Material
M-189 Water
PRICE Kilo litre 6.0 13.00 78.00
TOTAL 131976.90
MR177
Bitumen primer has been provided @ 0.70 kg per sqm as per clause 502.8. Payment shall be made
Note with adjustment, plus or minus, for the variation between this quantity and the actual quantity
approved by the Engineer after the preliminary trials referred to in clause No. 502.4.3.
Say 45.74
SUBHEAD : 5.0
Unit = sqm
Taking output = 3500 sqm
503
a) Labour
Mazdoor
L-13 Day 2.0 368.00 736.00
b) Manchinery
P&M-001
250cfm
PRICE
Air Compressor
TOTAL 25427.20
1. Bitumen emulsion has been provided @ 0.20 kg per sqm as per clause 503.8. Payment shall be
made with adjustment, plus or minus, for the variation between this quantity and actual quantity
Note approved by the Engineer after preliminary trials referred to in clause No. 503.4.3
2. An output of 3500 sqm has been considered in case of prime coat and tack coat which can be
covered by bituminous courses on the same day.
Say 8.88
SUBHEAD : 5.0
PRICE
Unit = cum
Taking output = 205 cum (450
tonnes)
a) Labour
504
Mazdoor
working with HMP, mechanical
broom, paver, roller, asphalt
L-13 Day 14.0 368.00 5152.00
cutter and assistance for setting
out lines, levels and layout of
construction
Mazdoor/Dresser/Sinker (skilled)
for checking line & levels
L-15 Day 5.0 407.00 2035.00
b) Machinery
Air Compressor
P&M-001 hour 2.2 322.00 708.40 MR200
250 cfm
Tipper 10 tonne
P&M-102 tonne km 450.0 3.00 1350.00(B) MR384
PRICE
for intermediate rolling.
c) Material
i) Bitumen
P&M-045 hour 3.9 1152.00 4492.80 MR244
weight of mix = 205 x 2.2 = 450
tonne
Total weight of mix = 450 tonnes
Weight of bitumen = 450 x3.4
/100 = 15.30 tonnes
Bitumen VG-30
M-401 tonne 15.3 30820.00 471546.00 MR101
@ 3.4 per cent of mix
ii) Aggregate
Weight of aggregate = 450 -15.30
M-197 = 434.70 tonnes tonne 15.3 103.77 1587.68
Taking density of aggregate = 1.5
ton/cum
Volume of aggregate = ( 434.70
/1.50) = 289.80 cum
Aggregates 10 mm to 5 mm
M-040 cum 115.92 1403.77 162725.02
40 per cent
5 mm and below
M-208 cum 57.96 1353.77 78464.51
20 per cent
1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be
available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving
the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
Public Works Department
2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job
Note
mix formula.
PRICE
3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries
have been included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of Mechanical broom and 2 mazdoors for
the same shall be deleted as the same has been included in the cost of tack coat.
Say 6995.43
SUBHEAD : 5.0
Providing and laying bituminous concrete with 100-120 TPH hot mix plant producing an
average output of 75 tonnes per hour using crushed aggregates of specified grading,
premixed with bituminous binder (NRMB) @ 5.4 per cent of mix and filler, transporting the hot
mix to work site, laying with a hydrostatic paver finisher with sensor control to the required
5.6.2.b
grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MORTH specification clause No. 507 complete in all
respects
For Grading -II (13.2 mm Nominal size).
Unit = cum
Taking output = 191 cum (450
tonnes)
a) Labour
507
Mazdoor
Public Works Department
working with HMP, mechanical
L-13
PRICE
broom, paver, roller, asphalt
cutter and assistance for setting
out lines, levels and layout of
construction
Day 14.0 368.00 5152.00
Mazdoor/Dresser/Sinker (skilled)
for checking line & levels
L-15 Day 5.0 407.00 2035.00
b) Machinery
Tipper 10 tonne
P&M-102 tonne km 450.0 3.00 1350.00(B) MR384
c) Material
P&M-045 hour 3.9 1152.00 4492.80 MR244
i) Bitumen
Bitumen (NRMB)
M-402 tonne 24.3 35370.00 859491.00 MR102
Public Works Department
@ 5.4 per cent of weight of mix
PRICE
carriage code of Bitumen
ii) Aggregate
Aggregates 10 mm to 5 mm
M-040D cum 70.95 1403.77 99597.48
25 per cent
5 mm and below
M-208 cum 122.034 1353.77 165205.97
43 per cent
1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be
available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving
the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65
2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job
mix formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries
have been included in administrative overheads of the contractor.
Note
4. In case BC is laid over freshly laid tack coat, provision of mechanical broom and 2 mazdoors shall
be deleted as the same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be used for construction i.e. 37.5-25 mm, 25-
10 mm etc. should be found in the laboratory and accordingly the quantities should be ammended for
use in field. The average density of 1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be calculated from the total weight of dry
aggregates i.e.. excluding the weight of bitumen. The weight of filler will also be 2 per cent by weight
of dry aggregates.
Public WorksAddDepartment
Contractors Profit @ 10.0% 829.27
PRICE
Cost index 32.04% 811.63
Say 9933.68
SUBHEAD : 8.0
Unit = Each
Taking output = one traffic sign
801
Mate
Public Works Department
L-12 Day 0.01 407.00 4.07
L-13
Mazdoor
PRICE
b) Material Day 0.25 368.00 92.00
GI pipe 50 mm dia
M-210 metre 3.1 220.00 682.00(A)
3.1 m long
Structural Steel
M-179 Mild steel angle 25 x 25 x 3 - tonne 0.00264 37842.24 99.90(B)
2.4m @ 1.10Kg/m
c) Machinery
Tractor
P&M-053 hour 0.01 365.00 3.65 MR252
1.Rate for excavation, cement concrete M-15 may be taken from respective chapters 2. The depth of
foundation and quantity of cement concrete in the foundation are indicative. These may be increased
Note
for areas having higher wind velocities like in coastal areas. This is applicable to all road signs and
directions boards. 3. Price of Aluminium sheeting is inclusive of cost for lettering.
Say 3527.05
Unit = sqm
Taking output = 1.50 sqm
801
Mate
L-12 Day 0.01 407.00 4.07
Mazdoor
L-13 Day 0.3 368.00 110.40
b) Material
GI pipe 50 mm dia
M-210 metre 7.0 220.00 1540.00(A)
3.5m long,2nos
Structural Steel
M-179
Public Works Department
Mild steel angle iron 40mm x 40
tonne 0.02239 37842.24 847.29(B)
mm x 6 mm,6.4metres long @
M-212
PRICE
3.498 kg/m
Tractor
P&M-053 hour 0.02 365.00 7.30 MR252
i) Rate for excavation, cement concrete M-15 and painting may be taken from respective chapters ii)
Note
For large sign boards size of supporting pole may be increased suitably as the case may be.
Say 8322.69
SUBHEAD : 55.0
OD MORTH
Providing and erecting retro-reflectorised Object Hazard Marker 300mm x 900mm
Providing and erecting retro-reflectorised Object Hazard Marker sign with 07 years warranty,
manufactured as per IRC 67 USING Type IV ASTM D 4956-09 micro prismatic retro reflective
sheeting fixed over aluminium sheetig, 2 mm thick / aluminium composit material sheeting 4
mm thick with suitable back support frame and supported on a mild steel angle iron post
55.10.1
75mmx75mmx6mm, firmly fixed 30cm above ground level by means of properly designed
foundation with M 15 grade cement concrete 30cmx30x45cm, 45cm below ground level
including painting all non-reflective faces with epoxy paint 2 coats over epoxy primer as per
Public Works Department
approved drawing and clause 801.
300 mm x 900 mm
Morth
SOR
Code
Ref. to
MoRTH
Spec.
PRICEDescription Unit Quantity Rate Rs Cost Rs
Remarks
/Input
ref.
Mate
Painting angle iron post and
frame two coats
Mazdoor
L-13 Day 0.25 368.00 92.00
Structural Steel
Structural Steel
Mild steel angle iron 75 x 75 x 6
M-179 tonne 0.00264 37842.24 99.90(C)
mm -1.6m @6.8m/kg
PRICE
Aluminium sheeting fixed with
ASTM Type IV retroreflective
M-212 sqm 0.27 3495.00 943.65 MR419
sheeting
Tractor
of size including lettering and
signs as applicable
P&M-053 hour 0.01 365.00 3.65 MR252
c) Machinery
1.Rate for excavation, cement concrete M-15 and painting may be taken from respective chapters
2. The depth of foundation and quantity of cement concrete in the foundation are indicative. These
Note
may be increased for areas having higher wind velocities like in coastal areas. This is applicable to all
road signs and directions boards.
Say 2503.70
SUBHEAD : 8.0
Unit=sqm
803
Public Works Department
Taking output= 600 sqm
L-12
L-13
Mate
Mazdoor
PRICE
a) Labour
b) Machinery
Day
Day
0.03
0.75
407.00
368.00
12.21
276.00
Tractor
P&M-053 hour 0.5 365.00 182.50 MR252
c) Material
TOTAL 190400.71
1. A sealing primer may be applied in advance on cement concrete pavement to ensure proper
Note bonding. Any laitance and/or curing compound to be removed where paint is required to be applied
on concrete surface.2. Cost of painter is already included in hire cjharges of road marking machine.
Say 506.28
SUBHEAD : 8.0
PRICE
SOR MoRTH Description Unit Quantity Rate Rs Cost Rs /Input
Code Spec. ref.
Unit = Nos
Taking output = 50Nos
a) Labour
804
Mazdoor
L-13 Day 1.0 368.00 368.00
b) Material
Say 196.82
SUBHEAD : 13.0
Sub-Structure
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical
13.3
Specifications
TOTAL 1116.33
Say 178.35
PRICE