Name of Works : “Improvement / Widening to Two Laning with Paved Shoulder of Agartala-Udaipur Section from Km 6.

800
to Km 55.000 of NH-44 in the State of Tripura under SARDP-NE Phase ‘A’ ”.
Authority : National Highways & Infrastructure Development Corporation Limited (NHIDCL)
Authority's
EPC Engineer : M/s. Rodic Consultants Pvt. Ltd.
Contractor
: M/s. KMC Constructions Ltd.
Billing Period : Period from 01-12-2019 to 23.03.2020 GSTIN NO: 16AABCK6483B1ZP

Change of Scope (RA Bill No-03)


(D) PAYMENT ABSTRACT
Annexure_1
Total Value upto this
Previous Value of 100% of COS Bill -
Sl No. Description of Items COS Bill (Rs.)
COS Bill (Rs.) 03 (Rs.)

1 2 3 4 6
The estimated amount for the works
a executed in accordance with Clause 19.3.1 68212244 44933442 23278802.11
subsquent to the Last Claim
Amount reflecting adjustment in price for the
b 0 0 0
aforesaid claim

The total value of executed after adjusting


c 68212244 44933442 23278802
the price escalation (a+b)

Payment recommended for release @100%


d 68212244 44933442 23278802
of ( a+b) i.e C

Release of the 10 % withheld from the up to


e 0 0 0
current bill

f Mobilization Advance Payment 0 0 0

g Repayment of Mobilisation advance 0 0 0

h Total Gross Amount Payable 68212244 44933442 23278802


Retention @ 6% of (d+e) upto 5% of final
i 4092735 2696007 1396728
contract price as per clause 7.5.1
j Income tax (TDS) @ 2% of (h) 1364245 898669 465576
k TDS (GST) @ 2% of (d+e) 1364245 898669 465576
Cess under the building and other
l construction workers welfare Act 1996 @ 1 682122 449334 232788
% of (h)
m Work Contract tax @ 8% of 75% on (d+e) 0 0 0
n Total statutory deductions (i+j+k+l+m) 7503347 4942679 2560668
o Payable Amount (h-n) 60708897 39990763 20718134
Other recoveries/ Releases 0 0
Recovery of intrest on Mobilisation Advance
p 0 0 0
on delayed payment
Release of retention money in terms of
q 0 0 0
clause 7.5.3 of CA

Amount withheld on account of non-


r 0 0 0
achievement of Milestone -IV

s total recoveries/ Releases (p+q+r) 0 0 0

t Net Payable Amount (o-s) 60708897 39990763 20718134

In word: Two Crore Seven Lakh Eighteen Thousand One Hundred Thirty Four Only.

Project Manager Quantity Surveyor Resident Engineer Team Leader General Manager
KMCCL RCPL RCPL RCPL NHIDCL
Contractor Authority Engineer Authority Engineer Authority Engineer Authority
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the
state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
COS RA BILL-03
Abstract of Change of Scope
Type of Work done Amount in Previous COS Approved Percentage of Work
Sl No. Chainage Remarks
Structure Amount (Rs.) RA Bill (Rs.) Amount (Rs.) Completed (%)

1 Box Culvert 21+488 421295.88 0.00 3610168.00 11.67%

2 Box Culvert 54+771 425464.16 744770.40 3452135.43 33.90%

3 VUP 19+420 14394360.28 2326062.87 36896283.00 45.32%

4 VUP 19+750 4826654.65 20018197.54 36086980.00 68.85%

54+640 (LHS)
5 Bus Lay Bye 3211027.15 0.00 12891700.00 24.91%
54+632 (RHS)

Total = 23278802.11
Net Amount for COS RA Bill - 03 = 23278802.11

Project Manager Quantity Surveyor Resident Engineer Team Leader


KMCCL RCPL RCPL RCPL
EPC Contractor Authority Engineer Authority Engineer Authority Engineer
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Box Culvert Chainage: 21+488 (3X2)

Length in Width in Thickness in Amount PWD SOR 2017


Sr No Ref. to MoRTH Spec. Descriptions Unit Nos Quantity Rate
(m) (m) (m) (Rs.) Page No.

12.1 304 Earth work in excavation of foundation of structures as per


drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps
and other deleterious matter, dressing of sides and bottom
and backfilling with approved material.

By meachanical Means
IB Upto 3 Metre depth (Ordinary Soil)
For Box Culvert Cum 0.5 10.700 4.800 2.500 64.200 50% Completed
Shear Key for Step -B =2*1/2=1 Cum 0.5 0.800 4.800 0.800 1.536 50% Completed
Shear Key for Step -A Cum 1.0 0.400 4.800 0.800 1.536 50% Completed
Return Wall Cum 4 4.050 5.200 4.200 0.000
For Curtain Wal
Type-I Cum 1 10.500 1.850 2.500 0.000
Type-II Cum 1 10.500 1.500 2.000 0.000
67.272 49.20 3309.78 Page no 69 of 240

12.4 2100 Plain cement concrete 1:3:6 nominal mix in foundation


with crushed stone aggregate 40 mm nominal size
mechanically mixed, placed in foundation and compacted
by vibration including curing for 14 days.

PCC 1:3:6 in Foundation


for Apron Cum 1 10.50 6.00 0.75 0.000
for Apron 1 10.50 3.00 0.75 0.000
for Apron 2 10.50 4.60 0.30 0.000
Deduction for side slab Cum 9.522 0
0.000 6545.90 0.00 Page no 71 of 240
12.6 1500 ,1700,2100 Plain/Reinforcement cement concrete in Open foudation
as per drwaing and Morth Technical specification clause
1500,1700,2100 (including centring shuttering staging
extera but excluding reinforcement.)

A. PCC Grade M-15

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Box Culvert Chainage: 21+488 (3X2)

Length in Width in Thickness in Amount PWD SOR 2017


Sr No Ref. to MoRTH Spec. Descriptions Unit Nos Quantity Rate
(m) (m) (m) (Rs.) Page No.

PCC below Raft of BoX Culvert Cum 0.5 10.700 3.800 0.150 3.050 50% Completed
Shear Key for Step -I Cum 1 1.150 3.800 0.150 0.656 50% Completed
Shear Key for Step -II Cum 1 0.400 3.800 0.150 0.228 50% Completed
Return Wall Cum 4 3.550 4.000 0.150 0.000
Curtain Wall Type I Cum 1 10.500 1.850 0.150 0.000
Curtain Wall Type II Cum 1 10.500 1.500 0.150 0.000
Curtain Wall Type I Step-I Cum 1 10.500 1.650 0.550 0.000
Curtain Wall Type I Step-II Cum 1 10.500 0.750 0.750 0.000
Curtain Wall Type I Step-III Cum 1 10.500 0.450 0.750 0.000
Curtain Wall Type I Step-IV Cum 1 10.500 0.200 0.450 0.000
Curtain Wall Type II
Curtain Wall Type II Step-I Cum 1 10.500 1.300 0.800 0.000
Curtain Wall Type II Step-II Cum 1 10.500 0.450 0.750 0.000
Curtain Wall Type II Step-III Cum 1 10.500 0.200 0.450 0.000
Toe Wall for Curve Cum 4 5.840 0.600 0.200 0.000
Toe Wall for Curve Cum 4 5.840 0.300 0.800 0.000
Toe Wall for road edge Cum 4 1.800 0.600 0.200 0.000
Toe Wall for road edge Cum 4 1.800 0.300 0.800 0.000
For Guard Stone fixing
Cum 20 0.500 0.500 0.150 0.000
20 0.250 0.226 0.600 0.000
For Appron
UP Stream & Down Stream Cum 2 10.500 4.600 0.150 0.000
Deduction for side slab Cum 4.761 0.000
3.933 6971.10 27417.34 Page no 72 of 240

14.10 2700 PCC M-15 grade leveling Couarse below approch Slab
Complete including all Form works required as per
drawing and Morth Technical Specification Clause 2700

PCC below appoach Slab Cum 2 12.000 2.600 0.100 0.00


0 6703.40 0.00 Page no 95 of 240

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Box Culvert Chainage: 21+488 (3X2)

Length in Width in Thickness in Amount PWD SOR 2017


Sr No Ref. to MoRTH Spec. Descriptions Unit Nos Quantity Rate
(m) (m) (m) (Rs.) Page No.

13.4 1500, 1700 & 2200 Plain/Reinforced cement concrete in sub-structure


complete as per drawing and Technical Specifications
including centring shuttering staging extra but excluding
reinforcement.
VII a). RCC M-30 Grade, (upto5 m height)
Case: II Using With Baching Plant, Transit Mixture and
Concrete Pump
Return wall
(Raft) Step 1 Cum 4 3.450 0.900 0.475 0.000
Step 2 Cum 4 3.450 0.600 0.650 0.000
Step 3 Cum 4 3.450 2.300 0.475 0.000
Wall Cum 4 3.450 0.450 3.450 0.000
0.000 9301.50 0.00 Page no 84 of 240
13.4 1500, 1700 & 2200 Plain/Reinforced cement concrete in sub-structure
complete as per drawing and Technical Specifications
including centring shuttering staging extra but excluding
reinforcement.
VI RCC Grade M-25 (upto5 m height)
Case: II Using With Baching Plant, Transit Mixture and
Concrete Pump

Invert Slab Cum 0.5 12.900 3.600 0.300 6.966 50% Completed
Wall Cum 1.0 12.900 0.300 2.000 7.740 50% Completed
Haunch Cum 1.0 12.900 0.150 0.150 0.290 50% Completed
Shear Key 1 Cum 0.5 3.600 0.800 0.800 1.152 50% Completed
Shear Key 2 Cum 1.0 3.600 0.300 0.800 0.864 50% Completed
Bracket 1 Cum 1.0 12.900 0.300 0.300 1.161 50% Completed
Bracket 2 Cum 0.5 12.900 0.300 0.300 0.581 50% Completed
18.754 9273.70 173916.65 Page no 83 of 240
Furnishing and Placing Reinforced/ Prestressed cement
14.1 1500 , 1700 & 2100 concrete in super-structure as per drawing and Technical
Specification
B RCC Grade M- 25
Case II Using Batching Plant, Transit Mixer and Concrete Pump

I) a for Solid slab super-structure

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Box Culvert Chainage: 21+488 (3X2)

Length in Width in Thickness in Amount PWD SOR 2017


Sr No Ref. to MoRTH Spec. Descriptions Unit Nos Quantity Rate
(m) (m) (m) (Rs.) Page No.

Height upto 5m
Deck Slab Cum 0.5 12.900 3.600 0.300 6.966 10087.20 70267.44 Page no 90 of 240

14.4 2702 Providing and laying Cement concrete wearing coat M-30
grade including reinforcement complete as per drawing
and Technical Specifications
On Top of Crrageway Cum 1 12.000 3.600 0.065 0
0 12071.20 0.00 Page no 94 of 240
14.11 2704, 1500 , 1600, 1700Reinforcement cement concrete approch Slab including
Reinforcement and form works as per drawing and Morth
Technical Specifications Clause 2704,1500,1600,1700.

A. RCC M-30 Grade


RCC below appoach Slab Cum 2 12.000 2.500 0.300 0.000 10794.50 0.00 Page no 95 of 240

13.9 710.1.4 of IRC: 78 & Providing and laying of Filter Media with Granular
2200 materials/Stone crushed aggregates satisfing the
requirement laid down in clause 2504.2.2 of MoRT &H
specifications to a thickness of not less than 600mm with
smaller size towards the soil and bigger size towards the
wall and provided over the entier surface beind abutment
wing wall and return wall to the full height compected to a
firm condition complete as per drawing & Cl. 710.4 of IRC:
78 & MoRTH & H Technical specification 2200

For Box Culvert Cum 2 11.900 0.600 1.90 0.000


For Retaining Wall Cum 4 2.85 0.600 1.900 0.000
0.000 4127.10 0.00 Page no 85 of 240
13.7 2706 ,2200 Providing Weep holes in Brick masonry, Stone masonry,
Plain/RCC abutment ,wing wall,return wall with 100 mm
dia AC pipe or PVC pipe (110 mm OD of 6.0 kg/Cm2
pressure ) extended through the width of structures with
slope of 1 (V): 20(H) towards drawing and MoRTH & H
Technical Specification clause 2706, 2200.

Weep Holes PVC Pipe


12*2 M 24 0.30 24.30

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Box Culvert Chainage: 21+488 (3X2)

Length in Width in Thickness in Amount PWD SOR 2017


Sr No Ref. to MoRTH Spec. Descriptions Unit Nos Quantity Rate
(m) (m) (m) (Rs.) Page No.

Utility duct PVC Pipe in Crash Barrier M 2 10.50 0.00


24.30 257.60 6259.68 Page no 85 of 240
14.17 2605 Filler Joint
II ) Providing and fixing 20 mm thick Compressible fibre
board in expension joint complete as per drawings and
MoRT &H Technical Specification clause 2605

M 1 11.90 11.90 205.70 2447.83 Page no 96 of 240

14.1 1500,1700 & 2100 Plain Reinforced cement concrete in superstructure


including all form works required as per drawing amd
MoRT&H technical specifications caluse 1500,1700 ,2100
(including centering and shuttering , staging etc.but
excluding reinforcement.

E RCC / PSC Grade M-40


Using Batching Plant, Transit Mixer and Concrete Pump
Case II
Height upto 5m
RCC Crash Barrier M-40
Step-I Cum 2 10.500 0.150 0.300 0.000
Step-II Cum 2 10.500 0.250 0.725 0.000
Step-III=2*1/2=1 Cum 1 10.500 0.250 0.175 0.000
Guard stone=4*4=16 Cum 16 0.049 0.900 0.175 0.000
0.000 10275.20 0.00 Page no 92 of 240

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Box Culvert Chainage: 21+488 (3X2)

Length in Width in Thickness in Amount PWD SOR 2017


Sr No Ref. to MoRTH Spec. Descriptions Unit Nos Quantity Rate
(m) (m) (m) (Rs.) Page No.

Providing and laying Pitching on slopes laid over prepared


filter media including boulder apron laid dry in front of toe
15.4 2504 of embankment complete as per drawing and Technical
specifications
Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast in
B cement concrete of Grade M15
for paraller section Cum 4 1.800 5.200 0.300 0.000
for slope section Cum 4 5.850 5.200 0.300 0.000
0.000 7180.20 0.00 Page no 101 of 240
Providing and laying Filter material underneath pitching in
15.5 2504 slopes complete as per drawing and Technical
specification
for paraller section Cum 4 1.800 5.200 0.150 0.000
for slope section Cum 4 5.850 5.200 0.150 0.000
0.000 4284.40 0.00 Page no 101 of 240

Supplying, Fitting and Placing un-coated HYSD bar


13.5 1600 & 2200 Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
100 kg/cum MT 18.754 1.875375 53218.60 99804.83 Page no 85 of 240
Supplying, Fitting and Placing un-coated HYSD bar
14.2 1600 Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
100 kg/cum MT 6.966 0.697 54367.40 37872.33 Page no 93 of 240
Total Amount (Rs.) 421295.88 A

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Box Culvert Chainage: 54+771, (2X2)

Length in Width in Thickness in Amount PWD SOR 2017


Sr No Ref. to MoRTH Spec. Descriptions Unit Nos Quantity Rate
(m) (m) (m) (Rs.) Page No.

12.1 304 Earth work in excavation of foundation of structures


as per drawing and technical specification, including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with
approved material.

By meachanical Means
IB Upto 3 Metre depth (Ordinary Soil)
For Box Culvert Cum 0.5 10.700 3.800 2.000 40.660 50% already billed
Shear Key for Step -B =2*1/2=1 Cum 0.5 0.800 3.800 0.800 1.216 50% already billed
Shear Key for Step -A Cum 1.0 0.400 3.800 0.800 1.216 50% already billed
Return Wall Cum 0.0 4.050 4.000 3.500 0.000
For Curtain Wal
Type-I Cum 1 10.500 1.850 2.500
Type-II Cum 1 10.500 1.500 2.000
43.092 49.20 2120.13 Page 69 of 240
12.4 2100 Plain cement concrete 1:3:6 nominal mix in
foundation with crushed stone aggregate 40 mm
nominal size mechanically mixed, placed in
foundation and compacted by vibration including
curing for 14 days.

PCC 1:3:6 in Foundation


For Apron Cum 1 10.50 6.00 0.75 0.000
For Apron 1 10.50 3.00 0.75 0.000
For Apron 2 10.50 4.60 0.30 0.000
Deduction for side slab Cum 9.522 -9.522
0.000 6545.90 0.00 Page no 71 of 240

12.6 1500 ,1700,2100 Plain/Reinforcement cement concrete in Open


foudation as per drwaing and Morth Technical
specification clause 1500,1700,2100 (including
centring shuttering staging extera but excluding
reinforcement.)

Project Manager QS BE Cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Box Culvert Chainage: 54+771, (2X2)

Length in Width in Thickness in Amount PWD SOR 2017


Sr No Ref. to MoRTH Spec. Descriptions Unit Nos Quantity Rate
(m) (m) (m) (Rs.) Page No.

A. PCC Grade M-15


PCC below Raft of BoX Culvert Cum 0.5 10.700 2.800 0.150 2.247 50% already billed
Shear Key for Step -I Cum 0.5 1.150 3.680 0.150 0.317 50% already billed
Shear Key for Step -II Cum 1 0.300 3.680 0.150 0.166 50% already billed
Return Wall Cum 4 3.550 4.000 0.150 0.000
Curtain Wall Type I Cum 1 10.500 1.850 0.150 0.000
Curtain Wall Type II Cum 1 10.500 1.500 0.150 0.000
Curtain Wall Type I
Step -I Cum 1 10.500 1.650 0.550 0.000
Step -II Cum 1 10.500 0.750 0.750 0.000
Step -III Cum 1 10.500 0.450 0.750 0.000
Step -IV Cum 1 10.500 0.200 0.450 0.000
Curtain Wall Type II
Step -I Cum 1 10.500 1.300 0.800 0.000
Step -II Cum 1 10.500 0.450 0.750 0.000
Step -III Cum 1 10.500 0.200 0.450 0.000
Toe Wall Step-I Cum 4 5.840 0.600 0.200 0.000
Toe Wall Step-II Cum 4 5.840 0.300 0.800 0.000
Toe Wall Step-I for curve Cum 4 1.800 0.600 0.200 0.000
Toe Wall Step-II for road edge Cum 4 1.800 0.300 0.800 0.000
For Guard Stone fixing
Section-I Pcc Cum 20 0.700 0.700 0.150 0.000
Section-II Foundation Cum 20 0.600 0.201 0.000
For Appron
UP Stream & Down Stream Cum 2 10.500 4.600 0.150 0.000
Deduction for side slope Cum 4.761 0.000
2.730 6971.10 19031.10 Page no 72 of 240

14.10 2700 PCC M-15 grade leveling Couarse below approch


Slab Complete including all Form works required as
per drawing and Morth Technical Specification
Clause 2700

PCC below appoach Slab Cum 2 12.000 2.600 0.100 0.00


0 6703.40 0.00 Page no 95 of 240

Project Manager QS BE Cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Box Culvert Chainage: 54+771, (2X2)

Length in Width in Thickness in Amount PWD SOR 2017


Sr No Ref. to MoRTH Spec. Descriptions Unit Nos Quantity Rate
(m) (m) (m) (Rs.) Page No.

13.4 1500, 1700 & 2200 Plain/Reinforced cement concrete in sub-structure


complete as per drawing and Technical
Specifications including centring shuttering staging
extra but excluding reinforcement.

VII a). RCC M-30 Grade, (upto5 m height)


Case: II Using With Baching Plant, Transit Mixture
and Concrete Pump
Return wall Section for 3 Mts Height
(Raft) Step 1 Cum 4 3.450 0.900 0.475 0.000
Step 2 Cum 4 3.450 0.600 0.650 0.000
Step 3 Cum 4 3.450 2.300 0.475 0.000
Wall Cum 4 3.450 0.450 3.450 0.000

0.000 9301.50 0.00 Page no 84 of 240


13.4 1500, 1700 & 2200 Plain/Reinforced cement concrete in sub-structure
complete as per drawing and Technical
Specifications including centring shuttering staging
extra but excluding reinforcement.

VI RCC Grade M-25 (upto 5 m height)


Case: II Using With Baching Plant, Transit Mixture
and Concrete Pump

Invert Slab Cum 0.5 12.900 2.600 0.300 5.031 50% already billed
Wall Cum 1 12.900 0.300 2.000 7.740 50% already billed
Haunch Cum 1 12.900 0.150 0.150 0.290 50% already billed
Shear Key 1 Cum 0.5 2.600 0.800 0.800 0.832 50% already billed
Shear Key 2 Cum 1 2.600 0.300 0.800 0.624 50% already billed
Bracket 1 Cum 1 12.900 0.300 0.300 1.161 50% already billed
Bracket 2 Cum 0.5 12.900 0.300 0.300 0.581 50% already billed
16.259 9273.70 150778.77 Page no 83 of 240
Furnishing and Placing Reinforced/ Prestressed
14.1 1500 , 1700 & 2100 cement concrete in super-structure as per drawing
and Technical Specification

Project Manager QS BE Cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Box Culvert Chainage: 54+771, (2X2)

Length in Width in Thickness in Amount PWD SOR 2017


Sr No Ref. to MoRTH Spec. Descriptions Unit Nos Quantity Rate
(m) (m) (m) (Rs.) Page No.

B RCC Grade M- 25
Case II Using Batching Plant, Transit Mixer and Concrete
Pump
I) a for Solid slab super-structure
Height upto 5m
Deck Slab Cum 0.5 12.900 2.600 0.300 5.031 10087.20 50748.70 Page no 90 of 240

14.4 2702 Providing and laying Cement concrete wearing coat


M-30 grade including reinforcement complete as per
drawing and Technical Specifications

On Top of Crrageway Cum 1 12.000 2.600 0.065 0


0 12071.20 0.00 Page no 94 of 240
14.11 2704, 1500 , 1600, 1700Reinforcement cement concrete approch Slab
including Reinforcement and form works as per
drawing and Morth Technical Specifications Clause
2704,1500,1600,1700.
A. RCC M-30 Grade
RCC below appoach Slab Cum 2 12.000 2.500 0.300 0.000 10794.50 0.00 Page no 95 of 240

13.9 710.1.4 of IRC: 78 Providing and laying of Filter Media with Granular
materials/Stone crushed aggregates satisfing the
requirement laid down in clause 2504.2.2 of MoRT
&H specifications to a thickness of not less than
600mm with smaller size towards the soil and bigger
size towards the wall and provided over the entier
surface beind abutment wing wall and return wall to
the full height compected to a firm condition complete
as per drawing & Cl. 710.4 of IRC: 78 & MoRTH & H
Technical specification 2200

For Box Culvert Cum 2 11.900 0.600 1.90 16.400


For Retaining Wall Cum 4 2.85 0.600 1.900 0.000
16.400 4127.10 67684.44 Page no 85 of 240

Project Manager QS BE Cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Box Culvert Chainage: 54+771, (2X2)

Length in Width in Thickness in Amount PWD SOR 2017


Sr No Ref. to MoRTH Spec. Descriptions Unit Nos Quantity Rate
(m) (m) (m) (Rs.) Page No.

13.7 2706 ,2200 Providing Weep holes in Brick masonry, Stone


masonry, Plain/RCC abutment ,wing wall,return wall
with 100 mm dia AC pipe or PVC pipe (110 mm OD
of 6.0 kg/Cm2 pressure ) extended through the width
of structures with slope of 1 (V): 20(H) towards
drawing and MoRTH & H Technical Specification
clause 2706, 2200.

Weep Holes PVC Pipe


12*2 M 24 0.30 24.30
Utility duct PVC Pipe in Crash Barrier M 2 9.50 0.00
for Return wall M 12 0.60 0.00
24.30 257.60 6259.68 Page no 85 of 240
14.17 2605 Filler Joint
II ) Providing and fixing 20 mm thick Compressible
fibre board in expension joint complete as per
drawings and MoRT &H Technical Specification
clause 2605
M 1 12.900 12.90 205.70 2653.53 Page no 96 of 240

14.1 1500,1700 & 2100 Plain Reinforced cement concrete in superstructure


including all form works required as per drawing amd
MoRT&H technical specifications caluse
1500,1700 ,2100 (including centering and shuttering ,
staging etc.but excluding reinforcement.

E RCC / PSC Grade M-40


Using Batching Plant, Transit Mixer and Concrete
Case II Pump
Height upto 5m
RCC Crash Barrier M-40
Step-I Cum 2 9.500 0.150 0.300 0.000
Step-II Cum 2 9.500 0.250 0.725 0.000
Step-III=2*1/2=1 Cum 1 9.500 0.250 0.175 0.000
Guard stone=4*4=16 Cum 20 0.049 0.900 0.175 0.000
0.000 10275.20 0.00 Page no 92 of 240

Project Manager QS BE Cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Box Culvert Chainage: 54+771, (2X2)

Length in Width in Thickness in Amount PWD SOR 2017


Sr No Ref. to MoRTH Spec. Descriptions Unit Nos Quantity Rate
(m) (m) (m) (Rs.) Page No.

Providing and laying Pitching on slopes laid over


prepared filter media including boulder apron laid dry
15.4 2504 in front of toe of embankment complete as per
drawing and Technical specifications

Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast


B in cement concrete of Grade M15
for paraller section Cum 4 1.800 5.200 0.300 0.000
for slope section Cum 4 5.850 5.200 0.300 0.000
0.000 7180.20 0.00 Page no 101 of 240
Providing and laying Filter material underneath
15.5 2504 pitching in slopes complete as per drawing and
Technical specification
for paraller section Cum 4 1.800 5.200 0.150 0.000
for slope section Cum 4 5.850 5.200 0.150 0.000
0.000 4284.40 0.00 Page no 101 of 240

Supplying, Fitting and Placing un-coated HYSD bar


13.5 1600 & 2200 Reinforcement in Foundation complete as per
Drawing and Technical Specifications.
100 kg/cum MT 16.259 1.626 53218.60 86526.79 Page no 85 of 240
Supplying, Fitting and Placing un-coated HYSD bar
14.2 1600 Reinforcement in Foundation complete as per
Drawing and Technical Specifications.
100 kg/cum MT 14.59 0.730 54367.40 39661.02 Page no 93 of 240
Total Amount (Rs.) 425464.16 A

Project Manager QS BE Cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+420

Ref. to MoRTH Length in Width in Thickness in Amount PWD SOR 2017 Page
Sr No Descriptions Unit Nos Quantity Rate
Spec. (m) (m) (m) (Rs.) No.

12.1 304 Earth work in excavation of foundation of structures


as per drawing and technical specification, including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with
approved material.

By meachanical Means
IB Upto 3 Metre depth (Ordinary Soil)
For VUP Cum 1 14.700 14.100 1.700 0.00 Already Paid
Retaining wall ,(A1 & A2 side on BHS ) for 6 m Cum 1 12.500 8.700 2.500 271.88 A1 Side RHS
Retaining wall ,(A1 & A2 side on BHS ) for 5 m Cum 1 70.000 8.700 2.000 1218.00
1489.88 49.20 73301.85 Page no 69 of 240

12.6 1500 ,1700,2100 Plain/Reinforcement cement concrete in Open


foudation as per drwaing and Morth Technical
specification clause 1500,1700,2100 (including
centring shuttering staging extera but excluding
reinforcement.)

A. PCC Grade M-15


PCC below Raft Cum 1 14.700 13.100 0.150 0.00 Already Paid
Pcc for Foot Path Cum 2 12.900 1.100 0.100 0.00
Retaining wall ,(A1 & A2 side on BHS ) for 6 m Cum 1 12.500 6.800 0.150 12.75 A1 Side RHS
Retaining wall ,(A1 & A2 side on BHS ) for 5 m Cum 1 70.000 5.700 0.150 59.85
72.600 6971.10 506101.86 Page no 72 of 240

14.10 2700 PCC M-15 grade leveling Couarse below approch


Slab Complete including all Form works required as
per drawing and Morth Technical Specification
Clause 2700

PCC below appoach Slab Cum 2 12.900 3.600 0.150 0


PCC below Friction Slab Cum 2 12.900 3.700 0.100 0
0 6703.40 0.00 Page no 95 of 240

Project Manager QS BE Sr.QS Team Leader


KMCCL RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+420

Ref. to MoRTH Length in Width in Thickness in Amount PWD SOR 2017 Page
Sr No Descriptions Unit Nos Quantity Rate
Spec. (m) (m) (m) (Rs.) No.

14.11 2704, 1500 , 1600, Reinforcement cement concrete approch Slab


1700 including Reinforcement and form works as per
drawing and Morth Technical Specifications Clause
2704,1500,1600,1700.

A. RCC M-30 Grade


Approach Slab Cum 2 12.900 3.500 0.300 0 10794.50 0.00 Page no 95 of 240

12.6 1500, 1700, 2100 Plain/Reinforcement cement concrete in Open


foudation as per drwaing and Morth Technical
specification clause 1500,1700,2100 (including
centring shuttering staging extera but excluding
reinforcement.)

G. RCC Grade M-30


Case: II Using With Baching Plant, Transit Mixture
and Concrete Pump
Invert Slab ( Raft) Cum 1 13.300 12.900 0.700 0.000 Already Paid
RCC Wall Cum 2 12.900 0.650 5.712 0.000 Already Paid
Haunch =4X1/2=2 Cum 2 12.900 0.300 0.300 0.000 Already Paid
Shear Key for Step -I Cum 2 12.900 0.300 0.500 0.000 Already Paid
Shear Key for Step -II=2X1/2=1 Cum 2 12.900 0.600 0.500 0.000 Already Paid
Bracket for Step -I Cum 1 12.900 0.300 0.300 0.000 Already Paid
Bracket for Step -II=2X1/2=1 Cum 2 12.900 0.300 0.300 0.000 Already Paid
Foot Path for Drain
Raft Cum 2 12.900 1.100 0.050 0.000
Wall Cum 4 12.900 0.125 1.000 0.000
Drain Slab Top Cum 2 12.900 1.100 0.050 0.000
0.000 8750.90 0.00 Page no 72 of 240

13.4 1500, 1700 & 2200 Plain/Reinforced cement concrete in sub-structure


complete as per drawing and Technical
Specifications including centring shuttering staging
extra but excluding reinforcement.

VII a). RCC M-30 Grade, (upto5 m height)


Case: II Using With Baching Plant, Transit Mixture
and Concrete Pump
Retaining wall Section for 6 Mts Height

Project Manager QS BE Sr.QS Team Leader


KMCCL RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+420

Ref. to MoRTH Length in Width in Thickness in Amount PWD SOR 2017 Page
Sr No Descriptions Unit Nos Quantity Rate
Spec. (m) (m) (m) (Rs.) No.

(Raft) Step 1 Cum 1 12.500 1.600 0.950 19.000


Step 2 Cum 1 12.500 1.400 1.400 24.500
Step 3 Cum 1 12.500 3.600 0.950 42.750
Wall Cum 1 12.500 0.950 7.100 84.313
Retaining wall Section for 5 Mts Height
(Raft) Step 1 Cum 1 70.000 1.400 0.750 73.500
Step 2 Cum 1 70.000 1.100 1.000 77.000
Step 3 Cum 1 70.000 3.000 0.750 157.500
Wall Cum 1 70.000 0.800 6.000 336.000
814.563 9301.50 7576653.09 Page no 84 of 240

Furnishing and Placing Reinforced/ Prestressed


14.1 1500 , 1700 & 2100 cement concrete in super-structure as per drawing
and Technical Specification
C RCC Grade M- 30
Case II Using Batching Plant, Transit Mixer and Concrete
Pump
I) a for Solid slab super-structure
Height upto 5m
Deck Slab Cum 1 13.300 12.900 0.700 120.099 10151.40 1219172.99 Page no 90 of 240

14.4 2702 Providing and laying Cement concrete wearing coat


M-30 grade including reinforcement complete as per
drawing and Technical Specifications

In side of Underpass Cum 2 12.900 12.000 0.065 0


On Top of Crrageway Cum 2 12.000 12.000 0.065 0
0 12071.20 0.00 Page no 94 of 240

Project Manager QS BE Sr.QS Team Leader


KMCCL RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+420

Ref. to MoRTH Length in Width in Thickness in Amount PWD SOR 2017 Page
Sr No Descriptions Unit Nos Quantity Rate
Spec. (m) (m) (m) (Rs.) No.

13.9 710.1.4 of IRC: 78 & Providing and laying of Filter Media with Granular
2200 materials/Stone crushed aggregates satisfing the
requirement laid down in clause 2504.2.2 of MoRT
&H specifications to a thickness of not less than
600mm with smaller size towards the soil and bigger
size towards the wall and provided over the entier
surface beind abutment wing wall and return wall to
the full height compected to a firm condition complete
as per drawing & Cl. 710.4 of IRC: 78 & MoRTH & H
Technical specification 2200

For VUP Cum 2 11.900 0.600 6.584 0.000


Retaining wall (inner side)= (12.5+31.25)*4=175 m Cum 1 175.000 0.600 5.00 0.000
0.000 4127.10 0.00 Page no 85 of 240

13.7 2706 ,2200 Providing Weep holes in Brick masonry, Stone


masonry, Plain/RCC abutment ,wing wall,return wall
with 100 mm dia AC pipe or PVC pipe (110 mm OD
of 6.0 kg/Cm2 pressure ) extended through the width
of structures with slope of 1 (V): 20(H) towards
drawing and MoRTH & H Technical Specification
clause 2706, 2200.

Weep Holes PVC Pipe


2*11*3.5=77 M 77 0.65 0.00 Already Billed
Utility duct PVC Pipe in Crash Barrier M 2 20.20 0.00 Already Billed
Retaining wall Section for 6 Mts Height M 44 0.75 33.00 50% Completed
Retaining wall Section for 5 Mts Height M 90 0.75 67.50 50% Completed
100.5 257.60 25888.8 Page no 85 of 240

14.17 2605 Filler Joint


II ) Providing and fixing 20 mm thick Compressible
fibre board in expension joint complete as per
drawings and MoRT &H Technical Specification
clause 2605
M 2 12.90 25.80 205.70 5307.06 Page no 96 of 240

Project Manager QS BE Sr.QS Team Leader


KMCCL RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+420

Ref. to MoRTH Length in Width in Thickness in Amount PWD SOR 2017 Page
Sr No Descriptions Unit Nos Quantity Rate
Spec. (m) (m) (m) (Rs.) No.

14.1 1500,1700 & 2100 Plain Reinforced cement concrete in superstructure


including all form works required as per drawing amd
MoRT&H technical specifications caluse
1500,1700 ,2100 (including centering and shuttering ,
staging etc.but excluding reinforcement.

E RCC / PSC Grade M-40


Using Batching Plant, Transit Mixer and Concrete
Case II Pump
Height upto 5m
RCC Crash Barrier M-40
Step-I Cum 2 20.200 0.300 0.450 0.000
Step-II Cum 2 20.200 0.250 0.725 0.000
Step-III=2*1/2=1 Cum 1 20.200 0.250 0.175 0.000
For Friction Slab
Cum 2 20.200 2.000 0.25 0.000
Cum 2 20.200 0.225 0.375 0.000
0.000 10275.20 0.00 Page no 92 of 240

4.12 406 Wet Mix Macadam


Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification
including premixing the Material with water at OMC in
mechanical mix plant carriage of mixed Material by
tipper to site, laying in uniform layers with paver in
sub- base / base course on well prepared surface
and compacting with vibratory roller to achieve the
desired
In Underdensity.
pass Cum 1 12.900 12.000 0.200 0.000 5119.70 0.00 Page no 25 of 240

5.1 502 Prime Coat


Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base
including clearing of road surface and spraying
primer at the rate of 0.60 kg/sqm using mechanical
means.

In Under pass for WMM Layer Sqm 1 12.900 12.000 0.00 29.10 0.00 Page no 30 of 240

Project Manager QS BE Sr.QS Team Leader


KMCCL RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+420

Ref. to MoRTH Length in Width in Thickness in Amount PWD SOR 2017 Page
Sr No Descriptions Unit Nos Quantity Rate
Spec. (m) (m) (m) (Rs.) No.

5.2 503 Tack Coat


Providing and applying tack coat with bitumen
emulsion using emulsion pressure distributor at the
rate of 0.20 kg per sqm on the prepared
bituminous/granular surface cleaned with mechanical
broom.

for WMM & DBM Layer

In Under pass Sqm 2 12.900 12.000 0.00 9.50 0.00 Page no 30 of 240

5.6 507 Dense Graded Bituminous Macadam


Providing and laying dense graded bituminous
macadam with 100-120 TPH batch type HMP
producing an average output of 75 tonnes per hour
using crushed aggregates of specified grading,
premixed with bituminous binder @ 4.0 to 4.5 per
cent by weight of total mix and filler, transporting the
hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade,
level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No.
507 complete in all respects.

Grading - II19 mm (Nominal Size) , VG-30

In Under pass Cum 1 12.900 12.000 0.095 0.000 11921.20 0.00 Page no 3 1& 32 of 240

Project Manager QS BE Sr.QS Team Leader


KMCCL RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+420

Ref. to MoRTH Length in Width in Thickness in Amount PWD SOR 2017 Page
Sr No Descriptions Unit Nos Quantity Rate
Spec. (m) (m) (m) (Rs.) No.

5.8 509 Bituminous Concrete


Providing and laying bituminous concrete with 100-
120 TPH batch type hot mix plant producing an
average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with
bituminous binder @ 5.4 to 5.6 per cent of mix and
filler, transporting the hot mix to work site, laying with
a hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MORTH
specification clause No. 509 complete in all respects

Grading - II-13 mm (Nominal Size) ,VG-30


In Underpass Cum 1 12.900 12.00 0.040 0 13520.90 0.00 Page no 33 of 240

13.5 1600 & 2200 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per
Drawing and Technical Specifications.
100 kg/cum MT 814.563 81.456 53218.60 4334987.59 Page no 85 of 240
14.2 1600 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per
Drawing and Technical Specifications.
100 kg/cum MT 120.10 12.010 54367.40 652947.04 Page no 93 of 240
Total Amount (Rs.) 14394360.28 A

Project Manager QS BE Sr.QS Team Leader


KMCCL RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+750

Ref. to MoRTH Length in Thickness in Amount PWD SOR 2017


Sr No Descriptions Unit Nos Width in (m) Quantity Rate
Spec. (m) (m) (Rs.) Page No.

12.1 304 Earth work in excavation of foundation of structures as per drawing


and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with approved material.

By meachanical Means
IB Upto 3 Metre depth (Ordinary Soil)
For VUP Cum 1 14.600 14.100 1.050 0
Retaining wall ,(A1 & A2 side on BHS ) for 6 m Cum 1 12.500 8.700 2.500 0
Retaining wall ,(A1 & A2 side on BHS ) for 5 m Cum 1 34.000 8.700 2.000 591.6
591.6 49.20 29106.72 Page no 69 of 240

12.6 1500 ,1700,2100 Plain/Reinforcement cement concrete in Open foudation as per


drwaing and Morth Technical specification clause 1500,1700,2100
(including centring shuttering staging extera but excluding
reinforcement.)
A. PCC Grade M-15
PCC below Raft Cum 1 13.100 14.600 0.150 0
Pcc for Foot Path Cum 2 13.100 1.500 0.100 0
Retaining wall ,(A1 & A2 side on BHS ) for 6 m Cum 1 12.500 6.800 0.150 0.00
Retaining wall ,(A1 & A2 side on BHS ) for 5 m Cum 1 34.000 5.700 0.150 29.07
29.07 6971.10 202649.88 Page no 72 of 240
14.10 2700 PCC M-15 grade leveling Couarse below approch Slab Complete
including all Form works required as per drawing and Morth Technical
Specification Clause 2700
PCC below appoach Slab Cum 2 12.900 3.600 0.150 0
PCC below Friction Slab Cum 2 12.900 2.000 0.100 0
0 6703.40 0.00 Page no 95 of 240

14.11 2704, 1500 , 1600, Reinforcement cement concrete approch Slab including
1700 Reinforcement and form works as per drawing and Morth Technical
Specifications Clause 2704,1500,1600,1700.
A. RCC M-30 Grade
Approach Slab Cum 2 12.900 3.500 0.300 0 10794.50 0.00 Page no 95 of 240

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+750

Ref. to MoRTH Length in Thickness in Amount PWD SOR 2017


Sr No Descriptions Unit Nos Width in (m) Quantity Rate
Spec. (m) (m) (Rs.) Page No.

12.6 1500, 1700, 2100 Plain/Reinforcement cement concrete in Open foudation as per
drwaing and Morth Technical specification clause 1500,1700,2100
(including centring shuttering staging extera but excluding
reinforcement.)
G. RCC Grade M-30
Case: II Using With Baching Plant, Transit Mixture and Concrete
Pump
Invert Slab ( Raft) Cum 1 12.900 13.200 0.600 0.000
RCC Wall Cum 2 12.900 0.600 5.65 0.000
Haunch =4X1/2=2 Cum 2 12.900 0.300 0.300 0.000
Bracket for Step -I Cum 2 12.900 0.300 0.300 0.000
Bracket for Step -II=2X1/2=1 Cum 1 12.900 0.300 0.300 0.000
Shear Key for Step -I Cum 2 12.900 0.500 0.300 0.000
Shear Key for Step -II=2X1/2=1 Cum 1 12.900 0.600 0.500 0.000
Foot Path for Drain
Raft Cum 2 12.900 1.350 0.050 0.000
Wall Cum 4 12.900 0.125 1.000 0.000
Drain Slab Top Cum 2 12.900 1.350 0.050 0.000
0.000 8750.9 0 Page no 72 of 240

13.4 1500, 1700 & 2200 Plain/Reinforced cement concrete in sub-structure complete as per
drawing and Technical Specifications including centring shuttering
staging extra but excluding reinforcement.
VII a). RCC M-30 Grade, (upto5 m height)
Case: II Using With Baching Plant, Transit Mixture and Concrete
Pump
Retaining wall Section for 6 Mts Height
(Raft) Step 1 Cum 4 12.500 1.600 0.950 0.000
Step 2 Cum 4 12.500 1.400 1.400 0.000
Step 3 Cum 4 12.500 3.600 0.950 0.000
Wall Cum 4 12.500 0.950 7.100 0.000

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+750

Ref. to MoRTH Length in Thickness in Amount PWD SOR 2017


Sr No Descriptions Unit Nos Width in (m) Quantity Rate
Spec. (m) (m) (Rs.) Page No.

Retaining wall Section for 5 Mts Height


(Raft) Step 1 Cum 1 34.000 1.400 0.750 35.700
Step 2 Cum 1 34.000 1.100 1.000 37.400
Step 3 Cum 1 34.000 3.000 0.750 76.500
Wall Cum 1 34.000 0.800 6.000 163.200
312.800 9301.50 2909509.20 Page no 84 of 240

1500 , 1700 & Furnishing and Placing Reinforced/ Prestressed cement concrete in
14.1
2100 super-structure as per drawing and Technical Specification

C RCC Grade M- 30
Case II Using Batching Plant, Transit Mixer and Concrete Pump
I) a for Solid slab super-structure
Height upto 5m
Deck Slab Cum 1 12.900 13.200 0.600 0 10151.40 0 Page no 90 of 240

14.4 2702 Providing and laying Cement concrete wearing coat M-30 grade
including reinforcement complete as per drawing and Technical
Specifications
In side of Underpass Cum 2 12.900 12.000 0.065 0
On Top of Crrageway Cum 2 12.000 13.200 0.065 0
0 12071.20 0.00 Page no 94 of 240

13.9 710.1.4 of IRC: 78 Providing and laying of Filter Media with Granular materials/Stone
& 2200 crushed aggregates satisfing the requirement laid down in clause
2504.2.2 of MoRT &H specifications to a thickness of not less than
600mm with smaller size towards the soil and bigger size towards the
wall and provided over the entier surface beind abutment wing wall
and return wall to the full height compected to a firm condition
complete as per drawing & Cl. 710.4 of IRC: 78 & MoRTH & H
Technical specification 2200

For VUP Cum 2 12.000 0.600 5.9 0.000


Retaining wall (inner side)= (12.5+31.25)*4=175 m Cum 1 175.000 0.600 4.53 0.000
0.000 4127.10 0.00 Page no 85of 240

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+750

Ref. to MoRTH Length in Thickness in Amount PWD SOR 2017


Sr No Descriptions Unit Nos Width in (m) Quantity Rate
Spec. (m) (m) (Rs.) Page No.

13.7 2706 ,2200 Providing Weep holes in Brick masonry, Stone masonry, Plain/RCC
abutment ,wing wall,return wall with 100 mm dia AC pipe or PVC pipe
(110 mm OD of 6.0 kg/Cm2 pressure ) extended through the width of
structures with slope of 1 (V): 20(H) towards drawing and MoRTH & H
Technical Specification clause 2706, 2200.

Weep Holes PVC Pipe


2*11*3.5=77 M 77 0.60 0.00
Utility duct PVC Pipe in Crash Barrier M 2 20.20 0.00
Retaining wall Section for 6 Mts Height M 35.2 0.75 26.40
Retaining wall Section for 5 Mts Height M 72 0.75 54.00
80.40 257.60 20711.04 Page no 85 of 240
14.17 2605 Filler Joint
II ) Providing and fixing 20 mm thick Compressible fibre board in
expension joint complete as per drawings and MoRT &H Technical
Specification clause 2605
M 2 12.90 0.00 205.70 0 Page no 96 of 240

14.1 1500,1700 & 2100 Plain Reinforced cement concrete in superstructure including all form
works required as per drawing amd MoRT&H technical specifications
caluse 1500,1700 ,2100 (including centering and shuttering , staging
etc.but excluding reinforcement.

E RCC / PSC Grade M-40


Case II Using Batching Plant, Transit Mixer and Concrete Pump
Height upto 5m
RCC Crash Barrier M-40
Step-I Cum 2 20.200 0.300 0.450 0.000
Step-II Cum 2 20.200 0.250 0.725 0.000
Step-III=2*1/2=1 Cum 1 20.200 0.250 0.175 0.000
For Friction Slab
Cum 2 20.200 2.000 0.25 0.000
Cum 2 20.200 0.225 0.375 0.000
0.000 10275.20 0.00 Page no 92 of 240

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+750

Ref. to MoRTH Length in Thickness in Amount PWD SOR 2017


Sr No Descriptions Unit Nos Width in (m) Quantity Rate
Spec. (m) (m) (Rs.) Page No.

4.12 406 Wet Mix Macadam


Providing, laying, spreading and compacting graded stone aggregate
to wet mix macadam specification including premixing the Material
with water at OMC in mechanical mix plant carriage of mixed Material
by tipper to site, laying in uniform layers with paver in sub- base /
base course on well prepared surface and compacting with vibratory
roller to achieve the desired density.

In Under pass Cum 1 12.900 12.000 0.200 0 5119.7 0.00 Page no 25 of 240

5.1 502 Prime Coat


Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including clearing of road surface
and spraying primer at the rate of 0.60 kg/sqm using mechanical
means.
In Under pass for WMM Layer Sqm 1 12.900 12.000 0.00 29.10 0 Page no 30 of 240

5.2 503 Tack Coat


Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the
prepared bituminous/granular surface cleaned with mechanical
broom.
for WMM & DBM Layer
In Under pass Sqm 2 12.900 12.000 0.00 9.50 0.00 Page no 30 of 240

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope Vehicular Under Pass Chainage: 19+750

Ref. to MoRTH Length in Thickness in Amount PWD SOR 2017


Sr No Descriptions Unit Nos Width in (m) Quantity Rate
Spec. (m) (m) (Rs.) Page No.

5.6 507 Dense Graded Bituminous Macadam


Providing and laying dense graded bituminous macadam with 100-
120 TPH batch type HMP producing an average output of 75 tonnes
per hour using crushed aggregates of specified grading, premixed
with bituminous binder @ 4.0 to 4.5 per cent by weight of total mix
and filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the required grade,
level and alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per MoRTH
specification clause No. 507 complete in all respects.

Grading - II19 mm (Nominal Size), VG-30


In Under pass Cum 1 12.900 12.000 0.095 0.000 11921.20 0.00 Page no 31 & 32 of 240

5.8 509 Bituminous Concrete


Providing and laying bituminous concrete with 100-120 TPH batch
type hot mix plant producing an average output of 75 tonnes per hour
using crushed aggregates of specified grading, premixed with
bituminous binder @ 5.4 to 5.6 per cent of mix and filler, transporting
the hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509 complete in
all respects

Grading - II-13 mm (Nominal Size) ,VG--30


In Underpass Cum 1 12.90 12.00 0.040 0 13520.90 0.00 Page no 33 of 240

13.5 1600 & 2200 Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in
Foundation complete as per Drawing and Technical Specifications.
100 kg/cum MT 312.800 31.280 53218.60 1664677.81 Page no 85 of 240
14.2 1600 Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in
Foundation complete as per Drawing and Technical Specifications.
100 kg/cum MT 0.00 0.000 54367.40 0.00 Page no 93 of 240
Total Amount (Rs.) 4826654.65 A

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope BUS LAY-BYES

Ref. to MoRTH Length in Width Thicknes Amount PWD SOR 2017


Sr No Descriptions Unit Nos Quantity Rate
Spec. (m) in (m) s in (m) (Rs.) Page No.

3.18 305 Construction of Subgrade and Earthen Shoulders

Construction of sub-grade and earthen shoulders with


approved material obtained from borrow pits with all lifts
& leads, transporting to site, spreading, grading to
required slope and compacted to meet requirement of
table No. 300-2

Section-I Cum 1 15.000 7.500 0.500 56.250

Section-II Cum 1 110.000 3.750 0.500 206.250

Section-III Cum 1 75.000 3.750 0.500 140.625

403.125 167.00 67321.88 Page 15 of 240

Granular Sub-Base with Close Graded Material (Table:-


4.1 401 400-1)
B Plant Mix Method
Construction of granular sub-base by providing close
graded Material, mixing in a mechanical mix plant at
OMC, carriage of mixed Material to work site, spreading
in uniform layers with motor grader on prepared surface
and compacting with vibratory power roller to achieve the
desired density, complete as per clause 401

(I) For Grading-I Material

Section-I Cum 1 15.000 7.500 0.200 22.500

Section-II Cum 1 110.000 3.750 0.200 82.500

Section-III Cum 1 75.000 3.750 0.200 56.250

161.250 5102.10 822713.63 Page no 22 of 240

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope BUS LAY-BYES

Ref. to MoRTH Length in Width Thicknes Amount PWD SOR 2017


Sr No Descriptions Unit Nos Quantity Rate
Spec. (m) in (m) s in (m) (Rs.) Page No.

4.12 406 Wet Mix Macadam

Providing, laying, spreading and compacting graded


stone aggregate to wet mix macadam specification
including premixing the Material with water at OMC in
mechanical mix plant carriage of mixed Material by tipper
to site, laying in uniform layers with paver in sub- base /
base course on well prepared surface and compacting
with vibratory roller to achieve the desired density.

Section-I Cum 1 15.000 5.200 0.250 19.500


Section-II Cum 1 110.000 2.600 0.250 71.500
Section-III Cum 1 75.000 2.600 0.250 48.750

139.750 5119.70 715478.08 Page no 25 of 240

Prime Coat
5.1 502

Providing and applying primer coat with bitumen


emulsion on prepared surface of granular Base including
clearing of road surface and spraying primer at the rate
of 0.60 kg/sqm using mechanical means.

Section-I Sqm 1 15.000 5.200 78.000


Section-II Sqm 1 110.000 2.600 286.000
Section-III Sqm 1 75.000 2.600 195.000
0.000 29.10 0 Page no 30 of 240

5.2 503 Tack Coat


Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.20 kg
per sqm on the prepared bituminous/granular surface
cleaned with mechanical broom.

Section-I Sqm 2 15.000 5.200 156.000

Section-II Sqm 2 110.000 2.600 572.000

Section-III Sqm 2 75.000 2.600 390.000

0.00 9.50 0.00 Page no 30 of 240

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope BUS LAY-BYES

Ref. to MoRTH Length in Width Thicknes Amount PWD SOR 2017


Sr No Descriptions Unit Nos Quantity Rate
Spec. (m) in (m) s in (m) (Rs.) Page No.
5.6 507 Dense Graded Bituminous Macadam
Providing and laying dense graded bituminous macadam
with 100-120 TPH batch type HMP producing an average
output of 75 tonnes per hour using crushed aggregates
of specified grading, premixed with bituminous binder @
4.0 to 4.5 per cent by weight of total mix and filler,
transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the
desired compaction as per MoRTH specification clause
No. 507 complete in all respects.

Grading - II19 mm (Nominal Size) , (VG-30)

Section-I Sqm 2 15.000 5.000 0.060 9.000


Section-II Sqm 2 110.000 2.500 0.060 33.000
Section-III Sqm 2 75.000 2.500 0.060 22.500
0.000 11921.20 0.00 Page no 31 & 32 of 240
5.8 509 Bituminous Concrete
Providing and laying bituminous concrete with 100-120
TPH batch type hot mix plant producing an average
output
Grading of -75 tonnes
II-13 per hour Size)
mm (Nominal using crushed
, (VG-30)aggregates
of specified grading, premixed with bituminous binder @
5.4 to 5.6 per cent of mix and filler, transporting the hot
mix to work site, laying Section-I
with a hydrostatic paver finisher Sqm 2 15.000 5.000 0.040 6.000
with sensor control to the required grade, level and
Section-II
alignment, rolling with smooth wheeled, vibratory and
Sqm 2 110.000 2.500 0.040 22.000
tandem rollers to achieve the desired compaction as per
Section-III Sqm 2 75.000 2.500 0.040 15.000
MORTH specification clause No. 509 complete in all
respects 0.000 13520.90 0.00 Page no 33 of 240

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Name of Works Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'
Authority National Highways & Infrastrucutre Development Corporation Ltd.
EPC Contractor M/s KMC Constructions Ltd.
Authority Engineer M/s Rodic Consultants Pvt. Ltd.
Change of Scope BUS LAY-BYES

Ref. to MoRTH Length in Width Thicknes Amount PWD SOR 2017


Sr No Descriptions Unit Nos Quantity Rate
Spec. (m) in (m) s in (m) (Rs.) Page No.
Cast in Situ Cement Concrete M 20 Kerb with
8.2 408
Channel
Construction of cement concrete kerb with channel with
top and bottom width 115 and 165 mm respectively, 250
mm high in M 20 grade PCC on M10 grade foundation
150 mm thick, kerb channel 300 mm wide, 50 mm thick
in PCCM20 grade, sloped towards the kerb, kerb stone
with channel laid with kerb laying machine, foundation
concrete laid manually, all complete as per clause 408

8.2 B Using Concrete Batching and Mixing Plant


Section-I Length =110.18+15+75.26 RM 1 200.440 200.440
Section-II Length =30.50+15+15.05+60 RM 1 120.550 120.550
0.000 731.40 0.00 Page no 47 of 240
8.8 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces

Top 115 mm+Inner Expose Face 150 mm Sqm 1 320.990 0.265 85.06
0.00 63.90 0.00 Page no 49 of 240
Amount for Single Bus Lay By (Rs.) = 1605513.58 A
Total Amount for 2 Nos. Bus Lay Bys (Rs.) = 3211027.15

Project Manager QS BE cum Sr.QS Team Leader


KMC Constructions Ltd. RCPL RCPL RCPL
Improvement/ widening to two laning with paved shoulder of Agartala - Udaipur section from Km 6.800 to Km 55.000 of NH-44(08) in the state of Tripura under SARDP-NE Phase 'A'

National Highways & Infrastrucutre Development Corporation Ltd.


M/s KMC Constructions Ltd.
M/s Rodic Consultants Pvt. Ltd.
Summery for Change of Scope" Revised"

Amount for one Total Amount


Sr.No. Descriptions Chainage Span Unit Numbers Remarks Page No.
Number Culvert ( Rs.)

1 Box Culvert 18+120 1x2x2 No. 1 4410550.06 4410550.00 Annex -1 01 to 04


2 Box Culvert 18+600 1x2x2 No. 1 3452135.43 3452135.00 Annex -2 05 to 09
3 Box Culvert 19+120 1x2x2 No. 1 3902993.66 3902994.00 Annex -3 10 to 14
4 Box Culvert 19+320 1x2x2 No. 1 4410550.06 4410550.00 Annex -1 01 to 04
5 Box Culvert 19+910 1x3x2 No. 1 3610168.45 3610168.00
6 Box Culvert 20+170 1x3x2 No. 1 3610168.45 3610168.00
15 to 19
7 Box Culvert 20+550 1x3x2 No. 1 3610168.45 3610168.00 Annex -4
8 Box Culvert 20+880 1x3x2 No. 1 3610168.45 3610168.00
9 Box Culvert 21+488 1x3x2 No. 1 3610168.45 3610168.00
10 Box Culvert 54+720 1x2x2 No. 1 3452135.43 3452135.00 Annex -2 05 to 09
VUP 19+420 No. 1 36896282.67 36896283.00 P-20 to P-24
11 Annex-5
VUP 19+750 No. 1 36086979.92 36086980.00 P-25 to P-29
Over Lay of Truck Lay - Bys at Bishalgarh at Ch .21+240 RHS No. 1 3726576.56 3726577.00 P-30 to P-31
12 Over Lay of Truck Lay - Bys at Forest Area at Ch .22+500 RHS No. 1 4145118.17 4145118.00 Annex-6 P-32 to P-33
Over Lay of Truck Lay - Bys at Mata Bari at Ch.54+060 LHS No. 1 4652610.2 4652610.00 P-34 to P-35
13 Foot Over Bridge Ch.09+060 (Central University ) No 1 6187242.60 6187243.00 Annex -7 P-36
14 Bus Lay-Bys No 4 3222925 12891700.00 Annex -8 P-37 to P-40
15 Junction Improvement Ch. 6+800 (Divisional Isaland) No 1 2754861.54 2754862.00 Annex -9 P-41 to P-43
16 RCC NP2 pipe 600 mm dia No 200 5295.18 1059000.00 Annex -10 P-44
Total Amount (Rs.) 146079577 A
Escalation @ 5 % on A 7303979
Total Amount (Rs.) 153383556
Total Amount in Crores under COS 15.338
Project Cost in Crores 369
Variation in Percent 4.16

Project Manager Sr.QS Team Leader General Manager(P)