Re-excavation, Renovation and Development of khals for Mitigation water Logging problem in Chittagong City

IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY Contract Amount (BDT): 4520000000.00
Consultant: Center for Environmental and Geographic Information Services (CEGIS) Date of Work Order: 28 September 2018
Contractor: Taher Brothers Ltd. Date of issue: 29/06/2022
Name of Works: Construction of Retaining Wall at Mohesh Khal

Summary of Bills Sheet


Interim Payment Certificate -115

SL. No Particulars Amount Remarks


BOQ Up to Date Total Previous Bill Previous Bill This Interim
A B C D=E+G E F G H
1 Permanent Work Completed 4,520,000,000.00 2,722,466,351.00 2,695,202,228.00 14,858,985.00 27,264,123.00
2 Advance Payment 452,000,000.00 452,000,000.00 452,000,000.00
3 Deduction of Advance
a. 1st Instalment : Up to 20 Crore @ 20% 90,400,000.00 90,400,000.00
a. 2nd Instalment : Up to 20-40 Crore @ 20% 91,431,695.00 91,431,695.00
a. 3rd Instalment : Up to 40-60 Crore @ 25% 113,802,050.50 113,802,050.50
a. 4th Instalment : Up to 60-80 Crore @ 25% 156,366,285.00 156,366,285.00
a. 5th Instalment : Up to 80-90 Crore @ 10% - -
4 Total Advance Deduction ( a+b+c+d+e) 452,000,000.00 452,000,000.00 - -
5 Sub-total (1+2-4) without C column 4,520,000,000.00 2,722,466,351.00 2,695,202,228.00 14,858,985.00 27,264,123.00
6 Deuction of VAT (7.5% of 5) 316,400,000.00 191,626,864.00 189,724,715.00 1,036,674.00 1,902,149.00
7 Deduction of Incom tax (7% of 5) 316,400,000.00 156,610,042.00 154,701,553.00 1,040,129.00 1,908,489.00
8 Sub- Total (Tax +Vat )= (6+7) 632,800,000.00 348,236,906.00 344,426,268.00 2,076,803.00 3,810,638.00
9 Amount after deduction of VAT & IT 12.5%(1+2-4-8) 3,887,200,000.00 2,374,229,445.00 2,350,775,960.00 12,782,182.00 23,453,485.00
10 Deduction of Retention Money (5% of 1) 226,000,000.00 126,171,380.00 124,808,173.00 742,950.00 1,363,207.00
12 Net Payable Amount (9-10) 3,661,200,000.00 2,248,058,065.00 2,225,967,787.00 12,039,232.00 22,090,278.00
Amount payable in this IPC -115: Two Crore Twenty Lac Ninety Thousand Two Hundred Seventy Eight Taka Only.
Certified that the works has been carried out as per terms and condtion of the contract and materials used satisfy the requirment of the specification

Taher Brothers Ltd. Center of Environmental and Geographic Information


Head Quarters 34 Engineering Construction of Brigade
(TBL) Services (CEGIS)

BA-4251
Project Engineer Resident Engineer Major Md Jayedi Ahsan Habib
Project Officer

Major Sarder Ziaur Rahman (Retd) BA-6013


Project Manager Lt Col Md Shah Ali
Deputy Team Leader Project Director
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY

Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of work: Construction of Retaining Wall at Mohesh Khal
BILL OF QUANTITIES (BOQ), IPC -115

Amount
Sl. No. NAME OF WORK Remarks
BOQ Bill to Date Total Previous Bill Previous Bill This Interim

1 Re-excavation of …………………………………………………………………. Khal.


213,958,100.05 46,965,331.00 46,965,331.00
2 Construction of RCC Retaining Wall (Length =……... km, Height =…...m) for Canal Bank
Protection.

4,023,989,804.31 1,698,415,365.00 1,671,151,242.00 27,264,123.00


3 Construction of Flexible Road…..
4,907,856.00 4,907,856.00
3 Construction of RCC Road With Side Drain.
133,970,195.00
4 Construction of RCC Culvert (3 Vents: 3.50mx4.00m) in the ------- Khal at Ch. --------.
15,000,000.80 7,423,387.00 7,423,387.00
5 Construction of RCC Bridge of 1 Bay: Span 20.0m and 10.10m wide over the ------- Khal at
Ch. --------.
133,081,899.85 65,417,736.00 65,417,736.00
6 Construction of Mohesh Khal RCC Drainage Regulator (12 Vents: 1.65mx1.950m) cum
Navigation Lock (6.0m X 33.40m) cum Pump House (3 nos. Submersible Pump of 5.5
m3/s Capacity each) near the Outfall of Mohes Khal
899,336,668.00 899,336,668.00

Total Amount Tk.= 4,520,000,000.01 2,722,466,343.00 2,695,202,220.00 27,264,123.00


IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Interim Payment Certificate -115
Summary as per price BOQ
Name of Works: Construction of Retaining Wall at Mohesh Khal

Price in BDT
Sl. No. Descriiption of Item Up-to Remarks
Previous period This Period
This Period
1 Re-excavation of
…………………………………………………………………. Khal.

2 Construction of RCC Retaining Wall (Length =……... km, Height =…...m)


for Canal Bank Protection. 1,703,323,221.00 1,676,059,098.00 27,264,123.00

3 Construction of RCC Road With Side Drain.

4 Construction of Flexible Road…..

5 Construction of RCC Culvert (3 Vents: 3.50mx4.00m) in the ------- Khal at


Ch. --------.

6 Construction of RCC Bridge of 1 Bay: Span ……...m and ………...m wide


over the ------- Khal at Ch. --------.

7 Construction of Mohesh Khal RCC Drainage Regulator (12 Vents:


1.5mx1.8m) cum Navigation Lock (6.0m X 33.40m) cum Pump House (3
nos. Submersible Pump of 5.5 m3/s Capacity each) near the Outfall of
Mohesh Khal.

8 Construction of Mohesh Khal RCC Drainage Regulator (12 Vents:


1.5mx1.8m) cum Navigation Lock (6.0m X 33.40m) cum Pump House (3
nos. Submersible Pump of 5.5 m3/s Capacity each) near the Outfall of
Mohes Khal. (Electric and Automation Work)
- -
Total Amount Tk.= 1,703,323,221.00 1,676,059,098.00 27,264,123.00
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY

BOQ of Retaining Wall at Mohesh Khal


Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chattogram City
Name of Works: Construction of Retaining wall, Financial Year: 2021-2022

As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
2 Providing Layout and carry over Bench Mark (BM) at site from nearby BM sqm 12.00 2,002.72 24,032.59 18,021.431 216,257.174 198.00 2,376.000 18,219.431 218,633.174
pillar, demarcating property lines, existing ground level (EGL), formation
ground level (FGL), highest flood level (HFL), plinth level (PL). Setting and
marking all pillars, markers, pegs etc. showing and maintaining reduced levels
(RLs) including locating, establishing, protecting all public utilities within the
premise of work and finally all to be presented in black and white etc. all
complete as per direction of the E-I-C.

3 Earth Work in excavation in foundation trenches for hydraulic structures in all cum 400.00 1.00 400.00 18,791.982 7,516,792.800 - 18,791.982 7,516,792.800
sorts of soil except rocky, gravelly, slushy or organic type, up to a depth of 2m
to the lines, grades and elevation as shown on the drawings, removing
boulders, logs and other objectionable materials, clearing all loose materials,
disposing of all excavated materials to a safe distance designated by the
Engineer-in-Charge for an initial lead of 20m, and cut to a firm surface etc. all
complete as per requirement and direction of the Engineer-in-Charge.

4 Earth Work in excavation in foundation trenches for hydraulic structures in all - - - - - -


sorts of soil except of rocky, gravelly, slushy or organic type, for each
additional depth beyond 2m to the lines, grades and elevation as shown on
the drawings, removing boulders, logs and other objectionable materials,
clearing all loose materials, disposing of all excavated materials to a safe
distance designated by the Engineer-in-Charge for an initial lead of 20m, and
cut to a firm surface, etc. all complete as per requirement and instruction of
the Engineer-in-Charge.

1st 1m and part thereof cum 526.630 1.00 526.63 10,679.933 5,624,373.116 - 10,679.933 5,624,373.116
2nd 1m and part thereof cum 549.69 1.00 549.69 10,486.100 5,764,104.309 - 10,486.100 5,764,104.309
3rd 1m and part thereof cum 572.00 1.00 572.00 19,407.399 11,101,032.371 - 19,407.399 11,101,032.371
5 Earth work in excavation of foundation of structures by mechanical (Hydraulic cum 370.00 180,593.08 66,819,439.60 - - - - -
excavator - Long Boom)/ manual means in all sorts of soil up to specified
depth in accordance with requirements of lines, grades, cross sections and
elevation as shown in the drawing including setting out, removal of stumps,
logs, boulders and other deleterious materials, providing necessary tools and
plants, construction of shoring and bracing, cleaning the excavated materials
to a safe distance out of the site premises, cut to a firm surface including
pumping/ bailing out water, removal of spoils to a safe distance, dressing of
sides and bottom and backfilling of trenches up to original level with approved
material etc. all complete as per approval of E-I-C. Contractor shall get
acquainted with site conditions, nature of soil and adopt suitable adequate
dewatering system as deemed fit for the nature of soil and prevailing water
table to get the surface reasonably dry for laying PCC at the time of execution
so that execution will not be hampered or delayed. Back-filled materials shall
be compacted to a density comparable with the adjacent undisturbed
material.
Earth work in Ordinary Soil by Mechanical Means (Hydaulic Excavator) for an
initial lead of 30m
For depth up to 3m

Page 4 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
NT Item 17 Removal of all type of rocky, gravell, Slushy or organic Soil by excavating earth cum 410.00 180,593.08 74,043,162.80 22,694.692 9,304,823.720 - 22,694.692 9,304,823.720
of canal/Khals/drain to the lines, grades and elevation as shown in the
drawing including of all leads and lift and carrying, disposing of all excavated
material at a sate distance designated by the E-I-C including arranging for and
supplying all necessary tools and equipment at work site, etc complete as per
direction of the E-I-C

6 Earth work in excavation of foundation of structures by mechanical (Hydraulic cum 440.00 130,210.49 57,292,615.60 - - - - -
excavator - Long Boom)/ manual means in all sorts of soil up to specified
depth in accordance with requirements of lines, grades, cross sections and
elevation as shown in the drawing including setting out, removal of stumps,
logs, boulders and other deleterious materials, providing necessary tools and
plants, construction of shoring and bracing, cleaning the excavated materials
to a safe distance out of the site premises, cut to a firm surface including
pumping/ bailing out water, removal of spoils to a safe distance, dressing of
sides and bottom and backfilling of trenches up to original level with approved
material etc. all complete as per approval of E-I-C. Contractor shall get
acquainted with site conditions, nature of soil and adopt suitable adequate
dewatering system as deemed fit for the nature of soil and prevailing water
table to get the surface reasonably dry for laying PCC at the time of execution
so that execution will not be hampered or delayed. Back-filled materials shall
be compacted to a density comparable with the adjacent undisturbed
material.
Earth work in Ordinary Soil by Mechanical Means (Hydaulic Excavator) for an
initial lead of 30m
For depth 3m to 6m

7 Shore protection work during excavation in foundation trenches up to 1.5 m sqm 740.81 1.00 740.81 - - - - -
depth, to protect loose soil due to damage of property by supplying Bitumen
drum sheet walling tied with 20 gauge G. I wire, fixing the same with already
driven bamboo posts with half split Borrak bamboo runners @450mm c/c
horizontally with iron nail, G.I wire etc. all complete as plan and direction of E-
I-C. (the rate is including cost of vertical posts).

8 Shore protection work during excavation in foundation trenches to protect sqm 1,420.00 83,662.50 118,800,756.97 1,350.450 1,917,639.000 - 1,350.450 1,917,639.000
loose soil due to damage of property with bitumen drum sheet fitted with
gazari post 150mm minimum dia, 0.90m c/c to be driven half of the total
length of the post Drum sheet to be fitted with Garzan wooden batten
50mmx50mm size at 0.60 meter c/c supplying and fixing with 150mm dia
gazari post crosses 1.80 meter c/c fixed with necessary nuts and bolts at the
slope side of palisading and tied up the palisading work by GI wire No. 10 with
gazari past 150mm dia and 1.8 meter c/c driven at the opposite direction up
to 1.20 meter depth including supplying all necessary nails and spikes etc.
complete as per direction of E-I-C. (Payment will be made for the work above
ground levels.).(the rate is including cost of vertical posts)

Page 5 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
9 Hiring charge of U-Type Hot rolled Steel Sheet piles as per approval and kg 25.00 1,455,000.00 36,375,000.00 11,717,438.400 292,935,960.000 172,800.000 4,320,000.000 11,890,238.400 297,255,960.000
specifications (sections, thickness, lengths & Mechanical properties) for
shoring during earth excavation for foundation trenches to support the soil
due avoiding damages of property, road, houses etc. Before using the sheet
pile supplied by the contractor a written approval from Project Director must
be taken.

10 Driving U-type steel sheet pile of various sections and weights in any type of sqm 1,220.00 53,653.00 65,456,660.00 98,460.660 120,122,005.200 1,440.000 1,756,800.000 99,900.660 121,878,805.200
soil by monkey hammer including handling and placing in position, staging and
supplying of all equipment like monkey hammer, pulley, rope, bamboo, bullah
etc. including correcting leaning beyond tolerance & other defects etc.
complete as per drawing and direction of the Engineer in charge
(Measurement will be taken on projected "width x driven depth" from lowest
ground level) up to 4.5m depth.

11 Taking out u-type steel sheet piles of various sections and weights from any sqm 3,150.00 53,653.00 169,006,950.00 95,970.508 302,307,100.200 1,440.000 4,536,000.000 97,410.508 306,843,100.200
type of soil by mechanical device including handling and placing in stacks etc.
complete (measurement will be taken on projected "width x embeded depth"
including arranging all equipment etc. all complete as per direction of the
Engineer in charge.

12 Carrying steel sheet piles of specified sections & length from stack yard as tonne-km - - - - - -
specified by appropriate means to the construction site and stacking at proper
place including loading, unloading, local handling as per design, drawing and
specifications etc. all complete as per direction of the E-I-C.
13 Sub - Soil investigation by exploratory borings and/ or by CPT, DCP etc. - - - - - -
collecting and necessary testing of samples in numbers as required for
Stratification of Layers, physical parameters of soils like Atterberg
limits,Specific Gravity, Gain size distribution(by wet seive, Hydrometer if
required) ,shrinkage & swelling, Settlement ; C -ф values and other Strength
parameters to ascertain Bearing Capacity , Skin friction, End bearings etc at
layers of interest as per respective National/International standards and
entering all theese data & information in necessary Tables & Graphs ,
furnishing them in the form of Standard Sub-Soil Investigation Report duly
signed by competent Engineer & Exploratory Office including mobilization &
demobilization.

a. on dry land up to depth 0 to 20m boring each 20,667.00 10.00 206,670.00 - - - - -


b. in water up to 1.50m depth of water for boring depth 0 to 20m each 24,890.00 1.00 24,890.00 - - - - -

Page 6 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
14 Construction of temporary cross dam in all type of soil, including cutting, Rm 18,500.00 1,100.00 20,350,000.00 - - - - -
carrying throwing & filling with all leads and lifts etc. and removing the cross
dam after complete the re-excavation of khal, etc. all complete as per
direction of the Engineer-in-Charge.
15 P&B: Pumping and bailing out water from the interior of any foundation 430.00 28,392.06 12,208,584.08 682.382 293,424.260 - 682.382 293,424.260
enclosure of work site with all leads and lifts including supply, operation and
maintenance of requisite number of water pumps, arrangements for
protection of ringh bund and side slopes of foundation pit against erosion or Per
washout etc. It should be carried out in such a manner as to preclude the Hr/
possibility of the movement of water through or alongside any concrete being Pump
placed, etc. all complete as per direction of E-I-C. No pumping or bailing will
be permitted during the placing of concrete.

16 Disposing surplus excavated soils of all types outside the site premises up to a cum 320.00 155,466.00 49,749,120.00 23,640.027 7,564,808.640 - 23,640.027 7,564,808.640
lead of specified distance including cost of labour, cost of equipment and
machinery, loading and unloading at both ends, transportation, all other
incidental charges at all leads and lifts etc. complete as per approval of the E-I-
C. The surplus excavated material must be dumped in an unobjectionable
place outside the site premises with minimum traffic disruption and the
procuring entity will not be responsible for any irregularities by the party
regarding disposing of the earth.
Lead 4km to 5km

17 Disposing surplus excavated soils of all types outside the site premises up to a cum 399.00 155,466.00 62,030,934.00 - - - - -
lead of specified distance including cost of labour, cost of equipment and
machinery, loading and unloading at both ends, transportation, all other
incidental charges at all leads and lifts etc. complete as per approval of the E-I-
C. The surplus excavated material must be dumped in an unobjectionable
place outside the site premises with minimum traffic disruption and the
procuring entity will not be responsible for any irregularities by the party
regarding disposing of the earth.
Lead above 5km

18 Sand filling on the prepared foundation bed with sand of minimum FM 0.80 in cum 795.00 340,985.00 271,083,075.00 1,125.338 894,643.356 - 1,125.338 894,643.356
difficult areas with 150mm in thickness each layer including supplying, placing
in conformity with the profile and level as per design including watering,
compaction etc. all complete as per instruction of the Engineer-in-Charge.

Page 7 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
19 RCC-25SCCM: Reinforced cement concrete work for pre-cast pile with cement cum 15,500.00 1.00 15,500.00 2,619.382 40,600,420.225 - 2,619.382 40,600,420.225
content relates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4
having minimum required average compressive strength, f'cr = 33.5 MPa and
satisfying a compressive strength f'c = 25 MPa at 28 days on standard
cylinders as per standard practice of code AASHTO/ ASTM and cement
conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, water reducing
admixture of complying type A under ASTM C 494 (Doses of admixture to be
fixed by the mix design), sand of minimum FM 2.5 and 20mm down well
graded crushed stone chips broken from boulders (Preferably stone chips
from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM
C 33, including breaking stone boulders into chips, screening through proper
sieves, cleaning and washing, centering and shuttering with MS sheet, MS
angle, nuts and bolts, chamfering edges, preparation of casting beds, laying
polythene, placing reinforcement cages in position, mixing in standard mixture
machine with hoper, maintaining allowable slump of 50mm to 100mm,
casting, compacting by mechanical vibrators and tapered rods as where
necessary, curing for 28 days etc. The cost of reinforcement and it's
fabrication, binding, welding and placing is not included but the cost of
admixture is included in this unit rate. Additional quantity of cement to be
added if required to attain the specified strength to be provided by the
contractor at his own cost.
Note: Using Concrete Mixer

20 RCC-25SCBP: Reinforced cement concrete work for pre-cast pile with cement cum 16,000.00 1.00 16,000.00 835.395 13,366,320.000 101.723 1,627,560.000 937.118 14,993,880.000
content relates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4
having minimum required average compressive strength, f'cr = 33.5 MPa and
satisfying a compressive strength f'c = 25 MPa at 28 days on standard
cylinders as per standard practice of code AASHTO/ ASTM and cement
conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, water reducing
admixture of complying type A under ASTM C 494 (Doses of admixture to be
fixed by the mix design), sand of minimum FM 2.5 and 20mm down well
graded crushed stone chips broken from boulders (Preferably stone chips
from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM
C 33, including breaking stone boulders into chips, screening through proper
sieves, cleaning and washing, centering and shuttering with MS sheet, MS
angle, nuts and bolts, chamfering edges, preparation of casting beds, laying
polythene, placing reinforcement cages in position, mixing in mechanized
batch mix plant & pumping using line pump or boom placer, maintaining
allowable slump of 50mm to 100mm, casting, compacting by mechanical
vibrators and tapered rods as where necessary, curing for 28 days etc. The
cost of reinforcement and it's fabrication, binding, welding and placing is not
included but the cost of admixture is included in this unit rate. Additional
quantity of cement to be added if required to attain the specified strength to
be provided by the contractor at his own cost.
Note: Using Batching Plant, Transit Mixer & Concrete Pump

Page 8 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
21 RCC-30SCBP: Reinforced cement concrete work for pre-cast pile with cum 18,600.00 11,520.00 214,272,000.00 - - - - -
minimum cement content and maximum water cement ratio as specified by
the laboratory having minimum required average compressive strength, f'cr =
38.5 MPa and satisfying a specified compressive strength, f'c = 30 MPa at 28
days on standard cylinders as per standard practice of code AASHTO/ ASTM
and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150
Type-1, water reducing admixture of complying type A under ASTM C 494
(Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5
and 20mm down well graded crushed stone chips broken from boulders
(Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding
30) conforming to ASTM C 33, including breaking stone boulders into chips,
screening through proper sieves, cleaning and washing, centering and
shuttering with MS sheet, MS angle, nuts and bolts, chamfering edges,
preparation of casting beds, laying polythene, placing reinforcement cages in
position, mixing in mechanized batch mix plant & pumping using line pump or
boom placer, maintaining allowable slump of 50mm to 100mm, casting,
compacting by mechanical vibrators and tapered rods as where necessary,
curing for 28 days etc. The cost of reinforcement and it's fabrication, binding,
welding and placing is not included but the cost of admixture is included in
this unit rate. Additional quantity of cement to be added if required to attain
the specified strength to be provided by the contractor at his own cost. The
Mix Design shall have to be approved by the concerned District Quality
Control Laboratory or any other reputed laboratory approved by the
competent authority before execution of the work.
Note: Using Batching Plant, Transit Mixer & Concrete Pump

22 - - - - -
23 Driving pre-cast RCC piles with drop hammer type rig in any type of soil to the m 850.00 1.00 850.00 - - - - -
required depth including fitting and fixing steel cap, handling and keeping in
position and maintaining driving log in prescribed format as per design,
drawing & direction of the E-I-C. Before commencing driving operation,
contractor shall submit the methodology for carrying the driving operation
including sequence of driving to the E-I-C. The maximum permitted deviation
of the finished pile from the horizontal & vertical shall be 50mm & 25mm
respectively. Cutting of a pile not being installed to the planned depth is
exclusively subject to the approval of Design Unit, LGED.
X-section of pre-cast pile: 350mm X 350mm
For height: Up to 6m

Page 9 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
24 Driving pre-cast RCC piles with drop hammer type rig in any type of soil to the m 1,048.00 1.00 1,048.00 - - - - -
required depth including fitting and fixing steel cap, handling and keeping in
position and maintaining driving log in prescribed format as per design,
drawing & direction of the E-I-C. Before commencing driving operation,
contractor shall submit the methodology for carrying the driving operation
including sequence of driving to the E-I-C. The maximum permitted deviation
of the finished pile from the horizontal & vertical shall be 50mm & 25mm
respectively. Cutting of a pile not being installed to the planned depth is
exclusively subject to the approval of Design Unit, LGED.
X-section of pre-cast pile: 350mm X 350mm
For height: 6m and above

25 - - - - -
26 Driving pre-cast RCC piles with automatic diesel hammer mounted rig in any m 1,100.00 1.00 1,100.00 - - - - -
type of soil to the required depth including fitting and fixing steel cap,
handling and keeping in position and maintaining driving log in prescribed
format as per design, drawing & direction of the E-I-C. Before commencing
driving operation, contractor shall submit the methodology for carrying the
driving operation including sequence of driving to the E-I-C. The maximum
permitted deviation of the finished pile from the horizontal & vertical shall be
50mm & 25mm respectively. Cutting of a pile not being installed to the
planned depth is exclusively subject to the approval of Design Unit, LGED.
X-section of pre-cast pile: 350 mm X 350 mm

27 Driving pre-cast RCC piles with automatic diesel hammer mounted rig in any m 1,310.00 72,000.00 94,320,000.00 - - - - -
type of soil to the required depth including fitting and fixing steel cap,
handling and keeping in position and maintaining driving log in prescribed
format as per design, drawing & direction of the E-I-C. Before commencing
driving operation, contractor shall submit the methodology for carrying the
driving operation including sequence of driving to the E-I-C. The maximum
permitted deviation of the finished pile from the horizontal & vertical shall be
50mm & 25mm respectively. Cutting of a pile not being installed to the
planned depth is exclusively subject to the approval of Design Unit, LGED.
X-section of pre-cast pile: 400 mm X 400 mm

Page 10 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
28 Manufacturing, supplying and fitting fixing MS shoe at RCC pre-cast pile tip each 2,070.00 6,160.00 12,751,200.00 6,583.000 13,626,810.000 198.000 409,860.000 6,781.000 14,036,670.000
with tip area 12mm x 12 mm, butt area 150mm x 150mm and height 250mm,
fabricated with 6mm thick 4 nos MS plate (12mm x 150mm x 250mm) at sides
and one plate (12mm x 12mm) at tip, having 6mm thick continuous fillet weld
at all joints and 20mm dia. 800mm long anchor MS re-bar along with 4 nos.
20mm x 20mm x 3mm MS angle welded to the tip plate including cost of all
materials, labour etc. all complete as per design, drawing & direction of the E-
I-C.

29 Single layer brick flat soling with 1st class or picked bricks, true to level, sqm 405.00 4,609.24 1,866,742.20 8,185.433 3,315,100.345 - 8,185.433 3,315,100.345
cambering/super elevation and grade including carrying bricks, filling the
interstices tightly with sand of minimum FM 0.80, etc. all complete as per
direction of the Engineer-in-Charge.
30 Cement Concrete work (1:4:8) in blinding/ centering layer below RCC works, cum 9,990.00 6,439.00 64,325,610.00 - - - - -
RCC pipes, pipe collar joint, pump house and bottom of sump well in
connection with Rubber Dam construction with Portland cement, sand
(minimum FM1.8) and 20mm down graded gravel (LAA value not exceeding
35) including mixing by concrete mixer machine, laying, casting, compacting
by concrete vibrator, curing for the requisite period etc. all complete as per
direction of the Engineer in charge. Cylinder crushing strength of concrete
should be as specified in the design.

31 RCC-25SCCM: Reinforced cement concrete work with minimum cement cum 15,200.00 31,534.14 479,318,928.00 3,202.479 48,677,673.200 - 3,202.479 48,677,673.200
content ralated to nominal mix ratio 1:1.5:3 and maximum water cement ratio
0.4 achieving minimum required average strength, f'cr = 33.5 Mpa and
satisfying a compressive strength, f'c = 25 Mpa at 28 days on standard
cylinders as per standard practice of Code AASHTO/ ASTM and using cement
conforming to BDS EN 197-1 : 2003 CEM-II 42.5N / ASTM C150 Type-1, with
high range water reducing admixture complying type A or F under ASTM C 494
(Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5
and 20mm down well graded crushed stone chips broken from boulders
(Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding
30) conforming to ASTM C33 including breaking chips, screening through
proper sieves, cleaning, placing shutters in position, making shutters water-
tight properly, placing reinforcement in position, mixing in standard mixture
machine with hoper, maintaining allowable slump of 50mm to 100mm, casting
in forms, compacting by mechanical vibrator machine, curing for 28 days,
removing centering-shuttering after approved specified time period, other
incidental charges, etc. all complete as per drawing, specification & direction
of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling,
placing, binding etc. is not included but the cost of admixture is included in
this unit rate. Additional quantity of cement to be added if required to attain
the strength at the contractor's own cost.
Note: Using Concrete Mixer
For bottom and approach slab of box culvert, regulator/ pipe sluice/ Rubber
Dam/ WRS of any height

Page 11 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
32 RCC-25SCCM: Reinforced cement concrete work with minimum cement cum 19,100.00 32,665.58 623,912,578.00 7,219.594 137,894,253.871 - 7,219.594 137,894,253.871
content ralated to nominal mix ratio 1:1.5:3 and maximum water cement ratio
0.4 achieving minimum required average strength, f'cr = 33.5 Mpa and
satisfying a compressive strength, f'c = 25 Mpa at 28 days on standard
cylinders as per standard practice of Code AASHTO/ ASTM and using cement
conforming to BDS EN 197-1 : 2003 CEM-II 42.5N / ASTM C150 Type-1, with
high range water reducing admixture complying type A or F under ASTM C 494
(Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5
and 20mm down well graded crushed stone chips broken from boulders
(Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding
30) conforming to ASTM C33 including breaking chips, screening through
proper sieves, cleaning, placing shutters in position, making shutters water-
tight properly, placing reinforcement in position, mixing in standard mixture
machine with hoper, maintaining allowable slump of 50mm to 100mm, casting
in forms, compacting by mechanical vibrator machine, curing for 28 days,
removing centering-shuttering after approved specified time period, other
incidental charges, etc. all complete as per drawing, specification & direction
of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling,
placing, binding etc. is not included but the cost of admixture is included in
this unit rate. Additional quantity of cement to be added if required to attain
the strength at the contractor's own cost.
Note: Using Concrete Mixer
For diaphragm walls, wing walls, pier columns, abutments and other vertical
members of hydraulic structure
Height up to 5 m

NT Item RCC-25SCCM: Reinforced cement concrete work with minimum cement cum 19,600.00 1.00 19,600.00 3,565.347 69,880,801.935 165.300 3,239,880.000 3,730.647 73,120,681.935
content ralated to nominal mix ratio 1:1.5:3 and maximum water cement ratio
0.4 achieving minimum required average strength, f'cr = 33.5 Mpa and
satisfying a compressive strength, f'c = 25 Mpa at 28 days on standard
cylinders as per standard practice of Code AASHTO/ ASTM and using cement
conforming to BDS EN 197-1 : 2003 CEM-II 42.5N / ASTM C150 Type-1, with
high range water reducing admixture complying type A or F under ASTM C 494
(Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5
and 20mm down well graded crushed stone chips broken from boulders
(Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding
30) conforming to ASTM C33 including breaking chips, screening through
proper sieves, cleaning, placing shutters in position, making shutters water-
tight properly, placing reinforcement in position, mixing in standard mixture
machine with hoper, maintaining allowable slump of 50mm to 100mm, casting
in forms, compacting by mechanical vibrator machine, curing for 28 days,
removing centering-shuttering after approved specified time period, other
incidental charges, etc. all complete as per drawing, specification & direction
of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling,
placing, binding etc. is not included but the cost of admixture is included in
this unit rate. Additional quantity of cement to be added if required to attain
the strength at the contractor's own cost.
For diaphragm walls, wing walls, pier columns, abutments and other vertical
members of hydraulic structure
Height up to 5 m
Note: Using Transit Mixer and Concrete Pump

Page 12 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
33 RCC-25SCCM: Reinforced cement concrete work with minimum cement cum 19,200.00 1.00 19,200.00 - - - - -
content ralated to nominal mix ratio 1:1.5:3 and maximum water cement ratio
0.4 achieving minimum required average strength, f'cr = 33.5 Mpa and
satisfying a compressive strength, f'c = 25 Mpa at 28 days on standard
cylinders as per standard practice of Code AASHTO/ ASTM and using cement
conforming to BDS EN 197-1 : 2003 CEM-II 42.5N / ASTM C150 Type-1, with
high range water reducing admixture complying type A or F under ASTM C 494
(Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5
and 20mm down well graded crushed stone chips broken from boulders
(Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding
30) conforming to ASTM C33 including breaking chips, screening through
proper sieves, cleaning, placing shutters in position, making shutters water-
tight properly, placing reinforcement in position, mixing in standard mixture
machine with hoper, maintaining allowable slump of 50mm to 100mm, casting
in forms, compacting by mechanical vibrator machine, curing for 28 days,
removing centering-shuttering after approved specified time period, other
incidental charges, etc. all complete as per drawing, specification & direction
of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling,
placing, binding etc. is not included but the cost of admixture is included in
this unit rate. Additional quantity of cement to be added if required to attain
the strength at the contractor's own cost.
Note: Using Concrete Mixer
For diaphragm walls, wing walls, pier columns, abutments and other vertical
members of hydraulic structure
For each additional height 300mm beyond 5m

NT RCC-25SCCM: Reinforced cement concrete work with minimum cement cum 19,700.00 1.00 19,700.00 262.944 5,180,000.676 27.508 541,905.039 290.452 5,721,905.715
content ralated to nominal mix ratio 1:1.5:3 and maximum water cement ratio
0.4 achieving minimum required average strength, f'cr = 33.5 Mpa and
satisfying a compressive strength, f'c = 25 Mpa at 28 days on standard
cylinders as per standard practice of Code AASHTO/ ASTM and using cement
conforming to BDS EN 197-1 : 2003 CEM-II 42.5N / ASTM C150 Type-1, with
high range water reducing admixture complying type A or F under ASTM C 494
(Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5
and 20mm down well graded crushed stone chips broken from boulders
(Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding
30) conforming to ASTM C33 including breaking chips, screening through
proper sieves, cleaning, placing shutters in position, making shutters water-
tight properly, placing reinforcement in position, mixing in standard mixture
machine with hoper, maintaining allowable slump of 50mm to 100mm, casting
in forms, compacting by mechanical vibrator machine, curing for 28 days,
removing centering-shuttering after approved specified time period, other
incidental charges, etc. all complete as per drawing, specification & direction
of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling,
placing, binding etc. is not included but the cost of admixture is included in
this unit rate. Additional quantity of cement to be added if required to attain
the strength at the contractor's own cost.
Note: Using Concrete Mixer
For diaphragm walls, wing walls, pier columns, abutments and other vertical
members of hydraulic structure
For each additional height 300mm beyond 5m

Page 13 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
34 RCC-25SCCM: Reinforced cement concrete work with minimum cement cum 18,100.00 7,269.39 131,575,868.50 - - - - -
content ralated to nominal mix ratio 1:1.5:3 and maximum water cement ratio
0.4 achieving minimum required average strength, f'cr = 33.5 Mpa and
satisfying a compressive strength, f'c = 25 Mpa at 28 days on standard
cylinders as per standard practice of Code AASHTO/ ASTM and using cement
conforming to BDS EN 197-1 : 2003 CEM-II 42.5N / ASTM C150 Type-1, with
high range water reducing admixture complying type A or F under ASTM C 494
(Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5
and 20mm down well graded crushed stone chips broken from boulders
(Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding
30) conforming to ASTM C33 including breaking chips, screening through
proper sieves, cleaning, placing shutters in position, making shutters water-
tight properly, placing reinforcement in position, mixing in standard mixture
machine with hoper, maintaining allowable slump of 50mm to 100mm, casting
in forms, compacting by mechanical vibrator machine, curing for 28 days,
removing centering-shuttering after approved specified time period, other
incidental charges, etc. all complete as per drawing, specification & direction
of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling,
placing, binding etc. is not included but the cost of admixture is included in
this unit rate. Additional quantity of cement to be added if required to attain
the strength at the contractor's own cost.
Note: Using Concrete Mixer
For cast-in-situ/ pre-cast railing and rail post of Hydraulic Structure

Page 14 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
35 Supplying and fabrication of Ribbed or deformed bar reinforcement kg 99.00 13,277,505.88 1,314,473,082.12 1,285,877.628 127,301,885.193 - 1,285,877.628 127,301,885.193
conforming to BDS ISO 6935-2:2006 (or standard subsequently released from
BSTI) for all types of RCC work including straightening, removing ruts,
cleaning, cutting, hooking, bending, lapping and/or welding wherever required
as directed, placing in position, tieing with 22 BWG black annealed binding
wire double fold, cost of binding wire and anchoring to the adjoining members
wherever necessary, supplying and placing with proper cover blocks (1:1),
supports, chairs, spacers, splices or laps etc. including cost of all materials,
cost of labour, cost of equipment & machinery, loading and unloading,
transportation, all other incidental charges and work at all leads and lifts etc.
to complete the work as per design, drawing, specifications and direction of
the E-I-C. Reinforcement shall be measured only in lengths of bars as
actually placed in position on standard weight i.e. 7850 kg/m3 (BNBC Table
6.2.1) basis. No separate payment shall be allowed for Chairs of any shape &
profile, spacer bar of any shape & profile, lap/ splice, wastages, binding wire,
concrete cover blocks etc. as the cost of these is included in the unit rate.
RB 400 / 400W: Ribbed or Deformed bar produced and marked as per BDS ISO
6935-2:2006 with minimum yield stress, fy (ReH) = 400 MPa, but the actual
yield strength based on mill tests does not exceed fy by more than the 125
MPa, the ratio of actual ultimate strength, fu (Re) to actual tensile yield
strength (fy) shall be at least 1.25 and minimum elongation after fracture
(A5.65) & minimum total elongation at maximum force (Agt) is 14% and 2.5%
respectively.

Page 15 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
35 Supplying and fabrication of Ribbed or deformed bar reinforcement kg 104.00 1,866,930.016 194,160,721.683 69,753.632 7,254,377.730 1,936,683.648 201,415,099.412
Revised conforming to BDS ISO 6935-2:2006 (or standard subsequently released from
BSTI) for all types of RCC work including straightening, removing ruts,
cleaning, cutting, hooking, bending, lapping and/or welding wherever required
as directed, placing in position, tieing with 22 BWG black annealed binding
wire double fold, cost of binding wire and anchoring to the adjoining members
wherever necessary, supplying and placing with proper cover blocks (1:1),
supports, chairs, spacers, splices or laps etc. including cost of all materials,
cost of labour, cost of equipment & machinery, loading and unloading,
transportation, all other incidental charges and work at all leads and lifts etc.
to complete the work as per design, drawing, specifications and direction of
the E-I-C. Reinforcement shall be measured only in lengths of bars as
actually placed in position on standard weight i.e. 7850 kg/m3 (BNBC Table
6.2.1) basis. No separate payment shall be allowed for Chairs of any shape &
profile, spacer bar of any shape & profile, lap/ splice, wastages, binding wire,
concrete cover blocks etc. as the cost of these is included in the unit rate.
RB 400 / 400W: Ribbed or Deformed bar produced and marked as per BDS ISO
6935-2:2006 with minimum yield stress, fy (ReH) = 400 MPa, but the actual
yield strength based on mill tests does not exceed fy by more than the 125
MPa, the ratio of actual ultimate strength, fu (Re) to actual tensile yield
strength (fy) shall be at least 1.25 and minimum elongation after fracture
(A5.65) & minimum total elongation at maximum force (Agt) is 14% and 2.5%
respectively.

36 Providing weep holes in Reinforced concrete retaining wall, abutment, wing/ each 820.00 13,071.70 10,718,794.00 180.000 147,600.000 - 180.000 147,600.000
return wall, with 50 mm dia PVC pipe extending through the full width of
structure with slope 1V : 7H towards draining face including hand packing of
filter materials shown in the drawings (60mm - 40mm, 40mm - 20mm and
20mm - 5mm sized shingles wrapped in coarse sand (FM>1.5)filter in the back
of each weep hole etc. all compete as per direction of the E-I-C.
[Cost of PVC pipe is included in this item and shall not be paid separately.]

37 Suppying and fitting and fixing 23cm wide, 3 bulb type PVC water stops having m 900.00 7,804.00 7,023,600.00 1,513.627 1,362,264.300 19.978 17,980.200 1,533.605 1,380,244.500
minimum strength of 13.80 N/mm2 at 225% elongation and of approved
quality in expansion joints with necessary arrangments for modification in
shuttering and keeping the water stop in position etc. complete as per design,
specification and direction of Engineer in charge.

Page 16 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
38 Labour Charge for fitting and fixing 23cm wide P.V.C water stops, in the m 49.89 7,804.63 389,372.99 1,513.627 75,514.851 19.978 996.702 1,533.605 76,511.553
expansion joints of hydraulic structures with necessary modification of
formworks as per design, specification and direction of Engineer in charge.
39 Supplying and fitting, fixing dowel bar in expansion joints of each 510.00 19,510.00 9,950,100.00 2,472.000 1,260,720.000 44.000 22,440.000 2,516.000 1,283,160.000
hydraulic structures with 20 mm dia M.S. Plain bar 1000mm long embeded
in concrete in one end and painted other end for a length of 500 mm inserted
into a 25mm 600mm long PVC pipe that closed other end by plastic cap as
shown in the design drawings including placing in position, binding with G.I.
wire etc. complete as per direction of Engineer in charge.

40 Supplying and laying shingles and peagravels as filter in three layers behind - - - - -
expansion joint as per specific size ranges shown in the design drawings and
gradation including grading, preparation of surface, compacting each layer
etc. complete with supply of all materials and as per direction of Engineer in
Charge.

a. Well graded between 65mm to 40mm size cum 5,200.00 629.20 3,271,840.00 - - - - -
b. Well graded between 40mm to 20mm size cum 5,100.00 13,878.72 70,781,472.00 - - - - -
c. Well graded between 20mm to 5mm size cum 4,900.00 2,162.50 10,596,250.00 - - - - -
41 Supplying and laying coarse sand as filter layers behind expansion joint as per - - - - - -
specific size ranges shown in the design drawings and gradation including
grading, preparation of surface, compacting each layer etc. complete with
supply of all materials and as per direction of Engineer in Charge.
a. F.M. 2.0 to 2.5 cum 2,700.00 2,926.70 7,902,090.00 - - - - -
b. F.M. 1.5 to 2.0 cum 1,500.00 2,192.73 3,289,095.00 - - - - -
42 Providing cork sheet/ polysterene sheet in the expansion joints of concrete - - - - - -
works including supply of all materials etc. complete as design drawings and
direction of Engineer in charge.
a. 20mm thick sheet sqm 461.70 9,310.90 4,298,842.53 603.162 278,480.092 10.960 5,060.001 614.122 283,540.093
43 Minimum 6mm thick cement plaster (1:4) to rail bar and rail post with neat sqm 216.00 135,594.00 29,288,304.00 - - - - -
cement finishing including washing of sand, finishing the edges and corners
and curing for requisite period etc. all complete as per direction of the
Engineer-in-Charge. (Sand FM 1.2 be used)
44 Supplying Sign Board at site of 1.5mx1.0m size in plain CI sheet; painting, No. 3,570.00 40.00 142,800.00 1.000 3,570.000 - 1.000 3,570.000
writing, erecting & fixing with bamboo including all complete as per direction
of Engineer-in-Charge.

Page 17 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
45 Dismantling damaged structural works in bridge/culvert and removing the cum 890.00 5.00 4,450.00 - - - - -
debris to a safe distance, stacking properly for measurement, etc. all complete
as per direction of the E-I-C.
CC Work
Nt Itme Dismantling damaged structural works in bridge/culvert and removing the cum 1,058.00 5.00 5,290.00 98.055 103,742.190 - 98.055 103,742.190
debris to a safe distance, stacking properly for measurement, etc. all complete
as per direction of the E-I-C.
CC Work
46 Dismantling damaged structural works in bridge/culvert and removing the cum 2,537.00 10.00 25,370.00 - - - - -
debris to a safe distance, stacking properly for measurement, etc. all complete
as per direction of the E-I-C.
RCC Work - - - - - -

NT Item Dismantling damaged structural works in bridge/culvert and removing the cum 4,200.00 10.00 42,000.00 18.448 77,481.600 - 18.448 77,481.600
debris to a safe distance, stacking properly for measurement, etc. all complete
as per direction of the E-I-C.
RCC Work - - - - - -

47 Dismantling damaged structural works in bridge/culvert and removing the cum 620.00 10.00 6,200.00 55.662 34,510.177 - 55.662 34,510.177
debris to a safe distance, stacking properly for measurement, etc. all complete
as per direction of the E-I-C.
Brick Work

NT Item Dismantling damaged structural works in bridge/culvert and removing the cum 900.00 10.00 827.688 744,919.175 - 827.688 744,919.175
debris to a safe distance, stacking properly for measurement, etc. all complete
as per direction of the E-I-C.
Brick Work

Sand filling on the prepared to undation bed with sand of minimum FM> 1.5 2510.00 1,266.0846 3,177,872.346 - 1,266.085 3,177,872.346
relative density > 50% with 150 mm in thickness each layer including
NT supplying, placing in Confirmity with the profile and level as per design cum
item 1
including watering, Compaction etc all complete as per instruction of the
Engineer in charge.
Cement Concrete work (1:3:6) in blinding/ centering layer below RCC works, 11530.40 1,041.2850 12,006,433.011 - 1,041.285 12,006,433.011

pump house and bottom of sump well in connection with Rubber Dam

construction with Portland cement, sand (minimum FM1.8) and 20mm down
NT
graded stone chips (LAA value not exceeding 35) including mixing by concrete cum
item 2
mixer machine, laying, casting, compacting by concrete vibrator, curing for the

requisite period etc. all complete as per direction of the Engineer in charge.

Cylinder crushing strength of concrete should be as specified in the design.

Page 18 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
Driving pre-cast RCC piles with drop hammer type rig in any type of soil to the 800.00 225.0000 180,000.000 - 225.000 180,000.000

required depth including fitting and fixing steel cap, handling and keeping in

position and maintaining driving log in prescribed format as per design,

drawing & direction of the E-I-C. Before commencing driving operation,

contractor shall submit the methodology for carrying the driving operation
NT including sequence of driving to the E-I-C. The maximum permitted deviation m
item 3
of the finished pile from the horizontal & vertical shall be 50mm & 25mm

respectively. Cutting of a pile not being installed to the planned depth is

exclusively subject to the approval of Design Unit, LGED.


X-section of pre-cast pile: 300mm X 300mm
For height: Up to 6m

Driving pre-cast RCC piles with drop hammer type rig in any type of soil to the 4,008.0000 4,008,000.000 - 4,008.000 4,008,000.000
required depth including fitting and fixing steel cap, handling and keeping in
position and maintaining driving log in prescribed format as per design,
drawing & direction of the E-I-C. Before commencing driving operation,
contractor shall submit the methodology for carrying the driving operation
NT
item 04 including sequence of driving to the E-I-C. The maximum permitted deviation m 1000.00
of the finished pile from the horizontal & vertical shall be 50mm & 25mm
respectively. Cutting of a pile not being installed to the planned depth is
exclusively subject to the approval of Design Unit, LGED.
X-section of pre-cast pile: 300mm X 300mm
For height: 6m and above

Driving pre-cast RCC piles with automatic diesel hammer mounted rig in any 1050.00 33,161.3390 34,819,405.950 1,089.000 1,143,450.000 34,250.339 35,962,855.950
type of soil to the required depth including fitting and fixing steel cap,
handling and keeping in position and maintaining driving log in prescribed
format as per design, drawing & direction of the E-I-C. Before commencing
driving operation, contractor shall submit the methodology for carrying the
NT item 05 driving operation including sequence of driving to the E-I-C. The maximum m
permitted deviation of the finished pile from the horizontal & vertical shall be
50mm & 25mm respectively. Cutting of a pile not being installed to the
planned depth is exclusively subject to the approval of Design Unit, LGED.
X-section of pre-cast pile: 300mm X 300mm

Back filling in hydraulic structure with sand of FM >= 0.8 in layer not more 795.00 2,912.5462 2,315,474.229 27.027 21,486.465 2,939.573 2,336,960.694
than 150 mm thick including necessary Carriage, Levelling, watering and
NT item 06 ramming to achieve minimum dry density (MDD) of 95% STD Compaction with cum
optimum moisture content (OMC) by ramming each layer upto finished level
as per direction of E-I-C

Page 19 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
Providing compacted sand, Cement & aggregate sub base course with Using 6714.00 - - - - -
cement confirming to BDS EN 197-1 : 2003 CEM-ll 42.5N / ASTM C150 Type-1
NT (BDS EN ), 50mm down well graded 1st class bricks chips and sand FM 0.80
cum
item 07 mixed in proportion 1:4:8 including mixing properly, watering, compacting
mechanically to give to compaction 100%. All complete as per drawing,
specification & direction of the E-I-C
Providing compacted sand, Cement & aggregate sub base course with Using 2,239.6656 11,460,368.875 - 2,239.666 11,460,368.875

cement confirming to BDS EN 197-1 : 2003 CEM-ll 42.5N / ASTM C150 Type-1

(BDS EN ), 50mm down well graded 1st class bricks chips and sand FM 0.80
NT
cum 5117.00
item 08
mixed in proportion 1:15:15 including mixing properly, watering, compacting

mechanically to give to compaction 100%. All complete as per drawing,

specification & direction of the E-I-C


Supplying of non bio-degradable geo-textile bags (empty) of sizes (600 mm x 135.00 925.0000 124,875.000 12.000 1,620.000 937.000 126,495.000

600 mm) at project/work site including fabrication and supply of geo-

textile fabric (mass>= 400gm/m²) and sewing in accordance with the


NT
nos
item 09
detailed drawing and Technical Specifications including cost of all

materials, labours, taxes, incidental charges etc. complete as per direction

of Engineer in charge.
Geo-bag; size:600mmx600mm, geo-fabric th.=>3.0mm, - - - - -
Filling, sewing & placing of non bio-degradable geo-textile bags of sizes (600 812.00 925.0000 751,100.000 12.000 9,744.000 937.000 760,844.000
mm x 600 mm) with 50 mm down graded singles, sewing along one
transverse (top) side after filling singles including cost of all materials,
NT labours, taxes, incidental charges but excluding cost of geo-bags as per nos
item 10
design, technical specification and detailed drawing etc. complete as per
direction of Engineer in Charge.
Geo-bag (600mmx600mm): geo-fabric thickness =>3.0 mm

Page 20 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
SLT: Conducting static load test as per ASTM D 1143 or equivalent standard for - - - -
the cast in situ/ pre-cast pile providing required scaffolding, bracing, jacks,
pressure test gauge, loading unloading, arranging other necessary plants and
equipment including staying, mobilization, demobilization, hire charge of
gunny bag/ concrete block/ steel sheet, sand and filling sacs/ gunny bags for
loading, record readings and preparation of results in standard forms and
other incidental charges as per standard practice and procedures including
submission of load test report, furnishing all graph and chart etc. complete in
all respects approved and accepted by the Engineer (Minimum two cyclic
loading; one at service load and another cycle at double the load of service
load then to continue loading till failure of the pile). Before commencing load
test, Contractor shall submit methodology along with combined calibration
NT report for conducting load test to the E-I-C for approval. The Testing firm will
item 11
be selected taking prior approval of procuring entity.
The methodology of static load test and driving logs/ boring & pouring logs
shall be the part of test report. Load Test and Report shall be conducted under
the supervision of a professional Geotechnical Engineer registered in the
Bangladesh Professional Engineers Registration Board (BPERB), Institute of
Engineers Bangladesh (IEB).
[Cost of Combined Calibration Test (Hydraulic Jack, pressure gauge &
electric/hydraulic pump) has been included in all sub-items.]

a. Above 75 ton and up to 125 ton nos 248421.00 - - - -


b. Above 125 ton and up to 175 ton nos 307164.00 - - - -
c. Above 175 ton and up to 225 ton nos 354246.00 - - - -
Manufacturing and supplying CC blocks with ordinary Portland Cement , sand 660.00 - - - -
(FM ≥ 1.5) and st (40mm down graded) to attain a minimum 28 days cylinder
strength of 15 MPa including grading, washings shingles, mixing, laying in
NT
item forms, consolidating, curing for at least 21 days, including preparation of nos
12
platform, shuttering and stacking in measurable stacks etc. all complete as per
direction of the Engineer in charge (Steel shutter to be used)
Size: 400mm x 400mm x 300mm

Labour charge for protective works in laying C.C blocks of different sizes 1511.00 - - - -

NT item
including preparation, watering and ramming of base etc. all complete as per cum
13

drawing & direction of the Engineer in charge

Page 21 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
Disposing surplus excavated soils of all types outside the site premises up to a - - - -
lead of specified distance including cost of labour, cost of equipment and
machinery, loading and unloading at both ends, transportation, all other
incidental charges at all leads and lifts etc. complete as per approval of the E-I-
NT item
14 C. The surplus excavated material must be dumped in an unobjectionable cum
place outside the site premises with minimum traffic disruption and the
procuring entity will not be responsible for any irregularities by the party
regarding disposing of the earth.

a. Lead 0 km to 1 km 125.00 - - - -
b. Lead 1 km to 2 km 155.00 - - - -
c. Lead 2 km to 3 km 210.00 - - - -
d. Lead 3 km to 4 km 265.00 - - - -
e. Lead 4 km to 5 km 320.00 - - - -
BCIS: Boring for cast-in-situ piles up to the required depth and specified - - - -
diameter with driving temporary steel casing (shall be 8mm thick with
necessary stiffener bands and sharp edge at bottom and provided up to non-
collapsible strata from the existing ground level but not less then 4.0 m) in all
types of soils including min. 2-chamber slurry tank, drilling with bentonite
circulation (Dry Bentonite powder of liquid limit of minimum 350 shall be
mixed with water @ minimum 4% by weight to make the fresh drilling fluid of
viscosity between 32-50 seconds and density less than 1.1gm/cc), maintaining
fluid level inside casing at all time at least 2 m higher than outside the casings,
washing bore hole by air lift cleanup method with fresh bentonite slurry until
the slurry from bore hole bottom have density less than 1.15gm/cc and sand
content is less than 4%, make the bore hole ready for concreting including
disposal/removal of all bored material, hire charge of mechanical winch
machine/ skid mounted mechanical table drive rotary/ hydraulic rotary boring
equipment, derrick, trimie pipe, cost of fuel, lubricant, mobilization,
demobilization, spares, insurance coverage, water, electricity and other
charges all complete as per design, drawing, specification and direction of E-I-
C. Contractor shall submit the methodology of cast-in-situ pile work including
information on boring equipment, sequence of boring & casting, quality
control, disposal of spoils, test result of materials to the E-I-C for approval
before commencing any boring operation. Boring and excavation for a pile
NT item shall not commence until 24 hours after completion of any pile within radius m 2418.55
15 of 6 meters c/c. Cost of collecting, conveying, loading, transportation of
spoils/mud accumulated during boring of cast-in-situ pile with all lifts and lead
is included in this unit rate. The spoils must be dumped in an unobjectionable
place outside the site premises with minimum traffic disruption and the
procuring entity will not be responsible for any irregularities by the party
regarding dumping of the spoils.
Note: Boring method shall be selected as per instruction given in the drawing.
BCIS_PM: Boring by PERCUSSION METHOD using Direct Mud Circulation
(DMC) or Bailer and Chisel technique by tripod and mechanical winch
machine. Tubewell boring machine shall not be used.
800mm diameter

- -
- - - -
- - - -

Page 22 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
BCIS_HRM: Boring by HYDRAULIC ROTARY METHOD using Crawler mounted, - - - -
telescopic boom hydraulic piling rig. Tube well boring machine/ Bailer and
NT item chisel technique by tripod and mechanical winch machine/ Skid Mounted
16 m 2827.92
Mechanical Table Drive Rotary Boring/ Spindle Type Rotary Drilling Machine
shall not be used.

RCC-25SCCM: Reinforced cement concrete work with minimum cement cum 15,700.00 - 7,332.961 115,127,491.704 136.818 2,148,042.600 7,469.779 117,275,534.304
content ralated to nominal mix ratio 1:1.5:3 and maximum water cement ratio
0.4 achieving minimum required average strength, f'cr = 33.5 Mpa and
satisfying a compressive strength, f'c = 25 Mpa at 28 days on standard
cylinders as per standard practice of Code AASHTO/ ASTM and using cement
conforming to BDS EN 197-1 : 2003 CEM-II 42.5N / ASTM C150 Type-1, with
high range water reducing admixture complying type A or F under ASTM C 494
(Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5
and 20mm down well graded crushed stone chips broken from boulders
(Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding
30) conforming to ASTM C33 including breaking chips, screening through
proper sieves, cleaning, placing shutters in position, making shutters water-
tight properly, placing reinforcement in position, mixing in standard mixture
NT item machine with hoper, maintaining allowable slump of 50mm to 100mm, casting
18 in forms, compacting by mechanical vibrator machine, curing for 28 days,
removing centering-shuttering after approved specified time period, other
incidental charges, etc. all complete as per drawing, specification & direction
of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling,
placing, binding etc. is not included but the cost of admixture is included in
this unit rate. Additional quantity of cement to be added if required to attain
the strength at the contractor's own cost.
Note: Using Transit Mixer and Concrete Pump
For bottom and approach slab of box culvert, regulator/ pipe sluice/ Rubber
Dam/ WRS of any height

Making of temporary approach and removal after work, for movement of 132.0000 1,980,000.000 - 132.000 1,980,000.000
plant and equipment inside the khal where no approach is available at the
bank, minimum top width of 5m and height 2m, with required side slope to
NT item sustain against slide, including filling by soil, compaction, topping with brick RM 15000.00
bats/debris as necessary all complete. Prior approval of PD must be taken
through proper drawing.

Making of temporary approach and removal after work, for movement of 414.5000 7,668,250.000 - 414.500 7,668,250.000
plant and equipment inside the khal where no approach is available at the
bank, minimum top width of 5m and height 2m, with required side slope to
NT item sustain against slide, including filling by soil, compaction, topping with brick RM 18500.00
bats/debris as necessary all complete. Prior approval of PD must be taken
through proper drawing.

BOQ Item Earth filling work with specified soil in any type of dykes/ embankment cum 696.00 1,500.00 1,044,000.00 1,834.50 1,276,812.766 - 1,834.50 1,276,812.77
(From including cutting, carrying, filling by throwing earth in layers not more than
Bidge): 05 150mm in each layer in proper alignment, grade, cambering and side slope in
all types of soil except rocky, gravelly and slushy including benching not more
than 30cm in vertical and 60cm in horizontal steps along the sides while
widening any embankment, etc. all complete as per the direction of E-I-C.
Payment will be made on compacted volume.
Initial lift upto 1.50 m from the toe of embankment

Page 23 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
Labour for breaking head of hardened cast-in-situ bored pile/ pre-cast piles to 261.1115 1,292,501.925 7.574 37,488.825 268.685 1,329,990.750
the correct lines and levels from the top of the piles to the cut-off level as
indicated in the approved drawing and exposing pile reinforcement for
embedment in pile cap by any means and disposal of the debris to an
unobjectionable place outside the site premises including scrapping and
removing concrete from steel/ MS rods, straightening and bending of pile
bars, preparation and making of platform where necessary, carrying, all sorts
BoQ ITEM of handling, stacking the same properly after clearing, leveling and dressing
(From the site and clearing the river bed, etc. all complete as per direction of the E-I- cum 4950.00
Bridge): 14 C. Measurement will be given for the actual pile head volume to be
broken.The debris from pile chipping shall be disposed outside the site
premises at an environmentally safe place with minimum traffic disruption
and procuring entity will not be responsilbe for any irregularities by the party
regarding dumping of the debris.

PS: Providing and laying polythene sheet (0.18mm thick) on prepared road 3,731.4406 89,554.573 - 3,731.441 89,554.573
surface underneath the cement concrete, etc. all complete as per S.P.D of the
BoQ ITEM E-I-C
(From sqm 24.00
Road): 12

Painting of steel sheet piles, 2 coat of epoxy paint, including preparation of 9,621.6000 3,078,912.000 - 9,621.600 3,078,912.000
BOQ surface with sand paper, brush etc. including the cost of all materials and
ITEM labour etc. complete as per direction of the E-I-C.
sqm 320.00
(From
Regulator)

Supply and carrying of U-Type Hot rolled steel sheet piles as per approval and 371,298.8100 44,555,857.200 - 371,298.810 44,555,857.200
BOQ specifications ( Sections, thickness, lengths & Mechanical properties) for
ITEM permanent bank prodection to support the soil due avoiding damanes of
property, road , houses etc and belo structure, Before using the sheet pile kg 120.00
(From
Regulator) supplied by the contractor a witten approval from Project Director must be
taken.
Mortar work(1:9) in foundation with cement conforming to BDS EN 197- 50.8318 292,542.222 - 50.832 292,542.222
1 :2003 CEM-II/A/L/M/V/W 42.5N , sand of minimum FM 1.8, shuttering ,
casting, laying, compacting, and curing for the requisite period etc. all
NT Item complete as per direction of the E-I-C. cum 5755.10

Mortar work(1:6) in foundation with cement conforming to BDS EN 197- 6.0469 41,112.703 - 6.047 41,112.703
1 :2003 CEM-II/A/L/M/V/W 42.5N , sand of minimum FM 1.8, shuttering ,
casting, laying, compacting, and curing for the requisite period etc. all
NT Item complete as per direction of the E-I-C. cum 6799.00

Page 24 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
CC-10: Cement concrete work in foundation with minimum compressive 242.8794 2,222,473.036 13.514 123,655.552 256.393 2,346,128.588
strength of 10 Mpa at 28 days (suggested mic proportion 1:3:6) on standard
cylinder as per standard practice of Code AASHTO/ASTM and cement
conforming to BDS EN 197-1 : 2003 CEM-II/A/L/M/V/W 42.5N , sand of
minimum FM 1.8, and 20mm down well graded 1st class/picked brick chips
NT Item (LAA value to excedding 40) conforming to ASTM C33 including breaking bricks cum 9150.52
into chips, shuttering, mixing by concrete mixer machine, casting, laying
compacting and curing for the requisite period etc. all complete as per
direction of the E-I-C. Additional quantity of cement to be added if required to
attain the strength at the contractor's own cost.

RCC Road BC&SGC(450mm): Earth work in box cutting on road crest up to 450mm cum 430.00 - -
BOQ depth, maintaining proper grade, camber and alignment, super elevation on
Item 3 curves, removing soils to a safe distance or if necessary, spreading the
excavated earth on road flanks and slopes uniformly including leveling,
dressing, watering to bring moisture content + 2% of OMC & compacting the
sub-grade by appropriate mechanical means to attain design CBR at minimum
compaction 98% of MDD (Standard) etc. all complete as per direction of the E-
l-C.

RCC Road Sand (FM 0.80) filling on the road bed in the improved sub-grade with sand cum 795.00 - -
BOQ free from dust, earth, other vegetable growth and foreign materials including
Item 4 supplying all materials, spreading, watering, compacting by appropriate
mechanical means to obtain a minimum Design Soaked CBR but not less than
8% at minimum compaction 98% of MDD (Modified), etc. all complete as per
direction of the E-I-C.

RCC Road EE(125mm): Brick on end edging (125mm across) with 1st class/picked bricks m 215.00 - -
BOQ including cutting trenches true to level & grade, removing earth, re-filling &
Item 6 ramming the sides properly, including supplying and filling the gaps with local
sand, etc. all complete as per direction of the E-l-C.

NT Item Sand (FM 1.5) on the road bed in the improved sub-grage with sand free from cum 2,510.00 79.20336 198,800.434 - 79.203 198,800.434
dust, earth, other vegetable growth and foreign materials including supplying
all materials, spreading, watering, compacting by appropriate mechanical
means to obtain a minimum design soaked CBR bur not less than 6% at
minimum compaction 98% MDD (Modified) etc, all complete as per the
direction of E-I-C

NT Item Providing compacted aggregate sans-sub base course with 38mm down brick cum 6,510.00 114.20336 743,463.874 - 114.203 743,463.874
chips made of 1st class/pricked brick (LAA value not excedding 40) mixed
thoroghly with sand of requisite FM (FM not less than 1.5)

Page 25 of 47
As per Contract/BOQ Previous IPC This IPC Total Upto This IPC
Sl. No. Description of Works Unit Rate Quantity (TBL) Amount (Tk) Qty Amount Qty Amount Qty Amount
A B C D E F=(DxE) G H=DxG) I J=(DxI) K=(G+I) L=(DxK)
1 - - -
NT Item Base Course (70:30) Providing compacted aggregate base course with 38mm cum 9,513.00 188.475 1,792,962.675 - 188.475 1,792,962.675
down graded stone chips mixed throughly with sand of requisite FM (FM=0.8)

NT Item Bitumionus Prime coat (Plant method) sqm 130.00 0 - - - -

NT Item Dense bitumionus surfacing base course (plant method) Bitumin Grade -60/70 cum 25,429.00 62.115 1,579,522.335 - 62.115 1,579,522.335

NT Item Bitumionus Tack coat (Plant method) sqm 57.50 0 - - - -

NT Item Dense bitumionus wearing course (plant method) Bitumin Grade -60/70 cum 26,789.00 15.078 403,924.542 - 15.078 403,924.542

RCC Road EE(125mm): Brick on end edging (125mm across) with 1st class/picked bricks m 215.00 524.1 112,681.500 - 524.100 112,681.500
BOQ Item 6 including cutting trenches true to level & grade, removing earth, re-filling &
ramming the sides properly, including supplying and filling the gaps with local
sand, etc. all complete as per direction of the E-I-C.

Drain BOQ Brick works of any thickness with first class bricks and cement sand (F.M. 1.2) cum 8,850.00 3.23 28,585.500 - 3.230 28,585.500
34 mortar (1:4) in foundation, plinth, and superstructure including raking out
joints, filling the interstices with mortar, cleaning and soaking the bricks at
least for 24 hours before use and washing of sand, necessary scaffolding,
curing at least for 7 days etc, all completed and accepted by the E-I-C.
Drain BOQ Minimum 12mm thick cement sand (F.M. 1.2) Plaster (1:4) with fresh cement cum 243.00 9.18 2,230.740 - 9.180 2,230.740
35 to both inner-and outer surface of wall, finishing the corner and edges
including washing of sand, cleaning the surface, curing at least for 7 days, cost
of water, electricity, scaffolding and other charges etc all complete in all
respect as per drawing and accepted by the E-I-C.
Cost for relocation/Replacement of existing Utilities Like as electricity, 1.0000 1,002,096.280 1.000 43,400.000 1.000 1,045,496.280
telephone, Gas etc and Dismantling etc along the alignment. Repair and
reconstruction of affected structure, Environmental Management
environmental Monitoring, dust suppression measures, providing adequate
potable water supply and sanitation facilities at work site, disposal of
Extras construction wastes, maintain first aid box at site etc.). Payment will be each
reimbursed as per work done and actual cost Certified by concerned
authorities.

Total Amount= 4,099,163,557.11 1,676,059,098.00 27,264,123.11 - 1,703,323,221.00

1,676,059,098.00 27,264,123.00 1,703,323,221.00

Page 26 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : 02
Item Name: Providing Layout and carry over Bench Mark (BM) at site from nearby BM pillar….
Chainage Reference
Length Width Height Quantity
SL No Description of Item Unit Side Remarks
From To (m) (m) (m) (Sqm) MB No. MB Page No.

Providing Layout and carry over Bench Mark (BM) at site from nearby BM pillar,
demarcating property lines, existing ground level (EGL), formation ground level (FGL),
highest flood level (HFL), plinth level (PL). Setting and marking all pillars, markers,
1 pegs etc. showing and maintaining reduced levels (RLs) including locating, Sqm
establishing, protecting all public utilities within the premise of work and finally all to
be presented in black and white etc. all complete as per direction of the E-I-C.

Nimtola West Sqm R/S 4+710 4+740 30.00 3.30 99.000 58 11

ESACK Brothers Sqm R/S 5+215 5+245 30.00 3.30 99.000 59 6

198.00
SL. No. : 09
Item Name: Hiring charge of U-Type Hot rolled Stee …..
Chainage Reference
Nos Height Weight Quantity
SL No Description of Item Unit Side Remarks
From To (m) (KG/M) (Kg) MB No. MB Page No.

Hiring charge of U-Type Hot rolled Steel Sheet piles as per approval and specifications
(sections, thickness, lengths & Mechanical properties) for shoring during earth
1 excavation for foundation trenches to support the soil due avoiding damages of
property, road, houses etc. Before using the sheet pile supplied by the contractor a
written approval from Project Director must be taken.

4+710 4+740 75.00 12.00 48.00 43,200.000 58 11 Earth Face


Nimtola West kg R/S
4+710 4+740 75.00 12.00 48.00 43,200.000 58 11 Canal Face
5+215 5+245 75.00 12.00 48.00 43,200.000 59 6 Earth Face
ESACK Brothers kg R/S
5+215 5+245 75.00 12.00 48.00 43,200.000 59 6 Canal Face
Total= 172,800.000

Page 27 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : 10
Item Name: Driving U-type steel sheet pile …..
Chainage Reference
Length Width Quantity
SL No Description of Item Unit Side Nos Remarks
From To (m) (m) (Sqm) MB No. MB Page No.

Driving U-type steel sheet pile of various sections and weights in any type of soil by
monkey hammer including handling and placing in position, staging and supplying of
all equipment like monkey hammer, pulley, rope, bamboo, bullah etc. including
1 correcting leaning beyond tolerance & other defects etc. complete as per drawing and Sqm
direction of the Engineer in charge (Measurement will be taken on projected "width x
driven depth" from lowest ground level) up to 4.5m depth.

4+710 4+740 75.00 12.00 0.40 360.000 58 11 Earth Face


Nimtola West Sqm R/S
4+710 4+740 75.00 12.00 0.40 360.000 58 11 Canal Face
5+215 5+245 75.00 12.00 0.40 360.000 59 6 Earth Face
ESACK Brothers Sqm R/S
5+215 5+245 75.00 12.00 0.40 360.000 59 6 Canal Face
Total= 1,440.000

SL. No. : 11
Item Name: Taking out u-type steel sheet piles of various sections…….
Chainage Reference
Height Width Quantity
SL No Description of Item Unit Side Nos Remarks
From To (m) (m) (Sqm) MB No. MB Page No.

Taking out u-type steel sheet piles of various sections and weights from any type of
soil by mechanical device including handling and placing in stacks etc. complete
1 (measurement will be taken on projected "width x embeded depth" including Sqm
arranging all equipment etc. all complete as per direction of the Engineer in charge.

4+710 4+740 75.00 12.00 0.40 360.000 58 14 Earth Face


Nimtola West Sqm R/S
4+710 4+740 75.00 12.00 0.40 360.000 58 14 Canal Face
5+215 5+245 75.00 12.00 0.40 360.000 59 9 Earth Face
ESACK Brothers Sqm R/S
5+215 5+245 75.00 12.00 0.40 360.000 59 9 Canal Face
Total= 1440.000

Page 28 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : 20
Item Name: RCC-25SCCM: Reinforced cement concrete work for pre-cast pile with cement content relates to mix ratio 1:1.5:3…
Chainage Reference Remarks
Length Height Total Quantity
SL No Description of Item Unit Nos
From~To (m) (m) (Cum) MB No. Page No.

RCC-25SCCM: Reinforced cement concrete work for pre-cast pile with cement content relates to
mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average
compressive strength, f'cr = 33.5 MPa and satisfying a compressive strength f'c = 25 MPa at 28
days on standard cylinders as per standard practice of code AASHTO/ ASTM and cement
conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, water reducing admixture of
complying type A under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand
of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulders
(Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to
ASTM C 33, including breaking stone boulders into chips, screening through proper sieves,
cleaning and washing, centering and shuttering with MS sheet, MS angle, nuts and bolts,
chamfering edges, preparation of casting beds, laying polythene, placing reinforcement cages in
1 position, mixing in standard mixture machine with hoper, maintaining allowable slump of 50mm
to 100mm, casting, compacting by mechanical vibrators and tapered rods as where necessary,
curing for 28 days etc. The cost of reinforcement and it's fabrication, binding, welding and
placing is not included but the cost of admixture is included in this unit rate. Additional quantity
of cement to be added if required to attain the specified strength to be provided by the contractor
at his own cost.
Note: Using Batching Plant, Transit Mixer & Concrete Pump

6m Length Pile
6m Length Pile (Straight Portion) Cum 5.4*0.3 0.3 12.000 5.832 58 10 at page 10 (12 of 16)
Shoe Area:
((0.3x0.3) [((0.3*0.3)+(0.05x0.05))/2] =
6m Length Pile (Sloped Portion) Cum 0.6 (0.05x0.05))/2 12.000 0.333 58 10 0.04625 Sqm
at page 10 (12 of 16)

6m Length Pile (Straight Portion) Cum 5.4*0.3 0.3 44.000 21.384 58 15


Shoe Area:
((0.3x0.3) [((0.3*0.3)+(0.05x0.05))/2] =
6m Length Pile (Sloped Portion) Cum 0.6 (0.05x0.05))/2 44.000 1.221 58 15 0.04625 Sqm

6m Length Pile (Straight Portion) Cum 5.4*0.3 0.3 54.000 26.244 59 10


Shoe Area:
((0.3x0.3)
6m Length Pile (Sloped Portion) Cum 0.6 (0.05x0.05))/2 54.000 1.499 59 10 [((0.3*0.3)+(0.05x0.05))/2] =
0.04625 Sqm

6m Length Pile (Straight Portion) Cum 5.4*0.3 0.3 62.000 30.132 59 11


Shoe Area:
((0.3x0.3)
6m Length Pile (Sloped Portion) Cum 0.6 (0.05x0.05))/2 62.000 1.721 59 11 [((0.3*0.3)+(0.05x0.05))/2] =
0.04625 Sqm
6m Length Pile (Straight Portion) Cum 5.4*0.3 0.3 26.000 12.636 59 12 at page 12 (26 pile of 50)
Shoe Area:
((0.3x0.3) [((0.3*0.3)+(0.05x0.05))/2] =
6m Length Pile (Sloped Portion) Cum 0.6 (0.05x0.05))/2 26.000 0.722 59 12 0.04625 Sqm
at page 12 (26 pile of 50)

Total= 101.723

Page 29 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : 28
Item Name: Manufacturing, supplying and fitting fixing MS shoe at RCC pre-cast pile tip……….
Chainage Reference
Total Quantity
SL No Description of Item Unit Nos Remarks
From To (Nos) MB No. Page No.

Manufacturing, supplying and fitting fixing MS shoe at RCC pre-cast pile tip with tip
area 12mm x 12 mm, butt area 150mm x 150mm and height 250mm, fabricated with
6mm thick 4 nos MS plate (12mm x 150mm x 250mm) at sides and one plate (12mm x
12mm) at tip, having 6mm thick continuous fillet weld at all joints and 20mm dia.
800mm long anchor MS re-bar along with 4 nos. 20mm x 20mm x 3mm MS angle
1
welded to the tip plate including cost of all materials, labour etc. all complete as per
design, drawing & direction of the E-I-C.

12 12.000 58 10 at page 10 (12 of 16)

44 44.000 58 15

6m Length Pile Each 54 54.000 59 10

62 62.000 59 11

26 26.000 59 12 at page 12 (26 of 50)

Total= 198.000

Page 30 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : NT Item 18
Item Name: RCC-25SCCM: Reinforced cement concrete work with minimum cement…….
Chainage Reference
Length Width Height Quantity
SL No Description of Item Unit Side (m) (m) (m) (Cum)
Remarks
From To MB No. MB Page No.

RCC-25SCCM: Reinforced cement concrete work with minimum cement content


ralated to nominal mix ratio 1:1.5:3 and maximum water cement ratio 0.4 achieving
minimum required average strength, f'cr = 33.5 Mpa and satisfying a compressive
strength, f'c = 25 Mpa at 28 days on standard cylinders as per standard practice of Code
AASHTO/ ASTM and using cement conforming to BDS EN 197-1 : 2003 CEM-II
42.5N / ASTM C150 Type-1, with high range water reducing admixture complying
type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design),
sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken
from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not
exceeding 30) conforming to ASTM C33 including breaking chips, screening through
proper sieves, cleaning, placing shutters in position, making shutters water-tight
properly, placing reinforcement in position, mixing in standard mixture machine with
hoper, maintaining allowable slump of 50mm to 100mm, casting in forms, compacting
by mechanical vibrator machine, curing for 28 days, removing centering-shuttering after
1 approved specified time period, other incidental charges, etc. all complete as per
drawing, specification & direction of the E-I-C. The cost of reinforcement and it's
fabrication, welding, coupling, placing, binding etc. is not included but the cost of
admixture is included in this unit rate. Additional quantity of cement to be added if
required to attain the strength at the contractor's own cost.
Note: Using Transit Mixer and Concrete Pump
For bottom and approach slab of box culvert, regulator/ pipe sluice/ Rubber Dam/ WRS
of any height

Base Slab Nimtola West cum R/S 4+710 4+740 30.000 3.30 0.70 69.300 58 13

Deduction for pile head 99.000 0.09 0.10 -0.891 58 13

Base Slab ESACK Brothers cum R/S 5+215 5+245 30.000 3.30 0.70 69.300 59 8

Deduction for pile head 99.000 0.09 0.10 -0.891 59 8

Total= 136.818

Page 31 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : NT Item
Item Name:RCC-25SCCM: Reinforced cement concrete work (Note: Using Concrete Mixer-For diaphragm walls, wing walls, pier columns, abutments and other vertical members of hydraulic structure-For each additional
Height up to 5 m
Chainage Reference
Length Width Height Quantity
SL No Description of Item Unit Side Remarks
From To (m) (m) (m) (Cum) MB No. MB Page No.
RCC-25SCCM: Reinforced cement concrete work with minimum cement content
ralated to nominal mix ratio 1:1.5:3 and maximum water cement ratio 0.4 achieving
minimum required average strength, f'cr = 33.5 Mpa and satisfying a compressive
strength, f'c = 25 Mpa at 28 days on standard cylinders as per standard practice of Code
AASHTO/ ASTM and using cement conforming to BDS EN 197-1 : 2003 CEM-II
42.5N / ASTM C150 Type-1, with high range water reducing admixture complying
type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design),
sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken
from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not
exceeding 30) conforming to ASTM C33 including breaking chips, screening through
proper sieves, cleaning, placing shutters in position, making shutters water-tight
properly, placing reinforcement in position, mixing in standard mixture machine with
hoper, maintaining allowable slump of 50mm to 100mm, casting in forms, compacting
cum
by mechanical vibrator machine, curing for 28 days, removing centering-shuttering after
approved specified time period, other incidental charges, etc. all complete as per
drawing, specification & direction of the E-I-C. The cost of reinforcement and it's
fabrication, welding, coupling, placing, binding etc. is not included but the cost of
admixture is included in this unit rate. Additional quantity of cement to be added if
required to attain the strength at the contractor's own cost.
Note: Using Concrete Mixer
For diaphragm walls, wing walls, pier columns, abutments and other vertical members
of hydraulic structure
Height up to 5 m
Note: Using Transit Mixer and Concrete Pump
Nimtola West
Fillet cum R/S 4+710 4+740 30.00 0.150 0.3 1.350 58 14

4+710 4+740 Total wall height 6.221m


Wall (up to 5m height) cum R/S 30.00 0.539 5.000 80.850 58 14 (0.378+0.7)/2=0.539
ESACK Brothers
Fillet cum L/S 5+215 5+245 30.00 0.150 0.3 1.350 59 9

5+215 5+245 Total wall height 6.458m


Wall (up to 5m height) cum L/S 30.00 0.545 5.000 81.750 59 9 (0.39+0.7)/2=0.545

Total= 165.300

Page 32 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : NT
Item Name:RCC-25SCCM: Reinforced cement concrete work …

Chainage Reference
Length Width Height Quantity
SL No Description of Item Unit Side Remarks
From To (m) (m) (m) (Cum) MB No. MB Page No.
RCC-25SCCM: Reinforced cement concrete work with minimum cement content ralated to
nominal mix ratio 1:1.5:3 and maximum water cement ratio 0.4 achieving minimum required
average strength, f'cr = 33.5 Mpa and satisfying a compressive strength, f'c = 25 Mpa at 28 days
on standard cylinders as per standard practice of Code AASHTO/ ASTM and using cement
conforming to BDS EN 197-1 : 2003 CEM-II 42.5N / ASTM C150 Type-1, with high range
water reducing admixture complying type A or F under ASTM C 494 (Doses of admixture to be
fixed by the mix design), sand of minimum FM 2.5 and 20mm down well graded crushed stone
chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not
exceeding 30) conforming to ASTM C33 including breaking chips, screening through proper
sieves, cleaning, placing shutters in position, making shutters water-tight properly, placing
reinforcement in position, mixing in standard mixture machine with hoper, maintaining allowable
slump of 50mm to 100mm, casting in forms, compacting by mechanical vibrator machine, curing
for 28 days, removing centering-shuttering after approved specified time period, other incidental
charges, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of
reinforcement and it's fabrication, welding, coupling, placing, binding etc. is not included but the
cum
cost of admixture is included in this unit rate. Additional quantity of cement to be added if
required to attain the strength at the contractor's own cost.
Note: Using Transit Mixer and Concrete Pump
For diaphragm walls, wing walls, pier columns, abutments and other vertical members of
hydraulic structure
For each additional height 300mm beyond 5m

Chainage Reference
Length Width Height Quantity
SL No Description of Item Unit Side Remarks
From To (m) (m) (m) (Cum) MB No. MB Page No.
Nimtola West
Total wall height
Wall (Above 5m height) cum R/S 4+710 4+740 30.00 0.339 1.221 12.418 58 14 6.221m
(0.378+0.3)/2=0.339
ESACK Brothers
Total wall height
Wall (Above 5m height) cum L/S 5+215 5+245 30.00 0.345 1.458 15.090 59 9 6.458m
(0.39+0.3)/2=0.345

Total= 27.508

Page 33 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : 35
Item Name: Supplying and fabrication of Ribbed or deformed bar reinforcement……….
Chainage Length Unit Wt Quantity Reference
SL No Description of Item Unit Side Nos Remarks
From To (m) (kg/m) (Kg) MB MB Page No.
Supplying and fabrication of Ribbed or deformed bar reinforcement conforming to BDS
ISO 6935-2:2006 (or standard subsequently released from BSTI) for all types of RCC
work including straightening, removing ruts, cleaning, cutting, hooking, bending,
lapping and/or welding wherever required as directed, placing in position, tieing with
22 BWG black annealed binding wire double fold, cost of binding wire and anchoring
to the adjoining members wherever necessary, supplying and placing with proper cover
blocks (1:1), supports, chairs, spacers, splices or laps etc. including cost of all materials,
cost of labour, cost of equipment & machinery, loading and unloading, transportation,
all other incidental charges and work at all leads and lifts etc. to complete the work as
per design, drawing, specifications and direction of the E-I-C. Reinforcement shall be
measured only in lengths of bars as actually placed in position on standard
weight i.e. 7850 kg/m3 (BNBC Table 6.2.1) basis. No separate payment shall be
allowed for Chairs of any shape & profile, spacer bar of any shape & profile, lap/ splice,
wastages, binding wire, concrete cover blocks etc. as the cost of these is included in the
unit rate.
RB 400 / 400W: Ribbed or Deformed bar produced and marked as per BDS ISO 6935-
2:2006 with minimum yield stress, fy (ReH) = 400 MPa, but the actual yield strength
based on mill tests does not exceed fy by more than the 125 MPa, the ratio of actual
ultimate strength, fu (Re) to actual tensile yield strength (fy) shall be at least 1.25 and
minimum elongation after fracture (A5.65) & minimum total elongation at maximum
force (Agt) is 14% and 2.5% respectively.
Nimtola West

Base slab Bottom Main bar ZA-D-25mm dia @125mm c/c Kg 4+710 4+740 240 3.450 3.853 3,190.284 58 13
Base Slab Bottom Binder ZB-D-16mm dia @200mm c/c Kg 4+710 4+740 17 29.850 1.578 800.756 58 13
Base Slab Top Main bar ZD-D-20mm dia @125mm c/c Kg 4+710 4+740 240 3.450 2.466 2,041.848 58 13

Base Slab Top Binder ZE-D-12mm dia @200mm c/c Kg 4+710 4+740 17 29.850 0.888 450.616 58 13

Fillet Top of Base RK-D-12mm dia @250mm c/c Kg 4+710 4+740 120 2.300 0.888 245.088 58 13
R/S
Stem (E.F) Verticle Main bar ZG1-D-25mm dia @250mm c/c Kg 4+710 4+740 120 7.220 3.853 3,338.239 58 13

Stem (Short) Verticle Main bar ZG-D-25mm dia @250mm c/c Kg 4+710 4+740 119 3.333 3.853 1,528.204 58 13

Stem (W.F) Verticle Main bar ZH-D-20mm dia @125mm c/c Kg 4+710 4+740 240 7.220 2.466 4,273.085 58 13
ZI-12mm @150mm c/c Kg 4+710 4+740 43 29.850 0.888 1,139.792 58 14
ZJ-12mm @150mm c/c Kg 4+710 4+740 43 29.850 0.888 1,139.792 58 14

Page 34 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
ESACK Brothers

Base slab Bottom Main bar ZA-D-25mm dia @100mm c/c Kg 5+215 5+245 240 3.450 3.853 3,190.284 59 8
Base Slab Bottom Binder ZB-D-16mm dia @200mm c/c Kg 5+215 5+245 17 29.850 1.578 800.756 59 8
Base Slab Top Main bar ZD-D-20mm dia @125mm c/c Kg 5+215 5+245 240 3.450 2.466 2,041.848 59 8
Base Slab Top Binder ZE-D-12mm dia @200mm c/c Kg 5+215 5+245 17 29.850 0.888 450.616 59 8

Fillet Top of Base RK-D-12mm dia @250mm c/c Kg 5+215 5+245 120 2.000 0.888 213.120 59 8
R/S
Stem (E.F) Verticle Main bar ZG1-D-25mm dia @200mm c/c Kg 5+215 5+245 120 7.457 3.853 3,447.819 59 8

Stem (Short) Verticle Main bar ZG-D-25mm dia @200mm c/c Kg 5+215 5+245 119 3.412 3.853 1,564.426 59 8

Stem (W.F) Verticle Main bar ZH-D-20mm dia @125mm c/c Kg 5+215 5+245 240 7.457 2.466 4,413.351 59 8
ZI-12mm @150mm c/c Kg 5+215 5+245 44 29.850 0.888 1,166.299 59 9
ZJ-12mm @150mm c/c Kg 5+215 5+245 44 29.850 0.888 1,166.299 59 9

Page 35 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
6m Length Pile (20mm Design)
20mm dia St. Bar kg 12.00 4x5.675 2.466 671.7384 58 10
20mm dia St. Bar kg 12.00 4x5.575 2.466 659.902 58 10
16mm dia St. Bar kg 12.00 6x2.00 1.578 227.232 58 10
8mm dia Spiral kg 12.00 28x0.421 0.395 55.875 58 10
10mm dia Stirup kg 12.00 53x0.950 0.617 372.791 58 10 at page 10 (12 of 16)
10mm dia Stirup kg 12.00 1x0.870 0.617 6.441 58 10
10mm dia Stirup kg 12.00 1x0.790 0.617 5.849 58 10
10mm dia Stirup kg 12.00 1x0.670 0.617 4.961 58 10
10mm dia Stirup kg 12.00 1x0.590 0.617 4.368 58 10
6m Length Pile (20mm Design)
20mm dia St. Bar kg 44.00 4x5.675 2.466 2463.0408 58 15
20mm dia St. Bar kg 44.00 4x5.575 2.466 2,419.639 58 15
16mm dia St. Bar kg 44.00 6x2.00 1.578 833.184 58 15
8mm dia Spiral kg 44.00 28x0.421 0.395 204.875 58 15
10mm dia Stirup kg 44.00 53x0.950 0.617 1,366.902 58 15
10mm dia Stirup kg 44.00 1x0.870 0.617 23.619 58 15
10mm dia Stirup kg 44.00 1x0.790 0.617 21.447 58 15
10mm dia Stirup kg 44.00 1x0.670 0.617 18.189 58 15
10mm dia Stirup kg 44.00 1x0.590 0.617 16.017 58 15
6m Length Pile (20mm Design)
20mm dia St. Bar kg 54.00 4x5.675 2.466 3022.8228 59 10
20mm dia St. Bar kg 54.00 4x5.575 2.466 2,969.557 59 10
16mm dia St. Bar kg 54.00 6x2.00 1.578 1,022.544 59 10
8mm dia Spiral kg 54.00 28x0.421 0.395 251.438 59 10
10mm dia Stirup kg 54.00 53x0.950 0.617 1,677.561 59 10
10mm dia Stirup kg 54.00 1x0.870 0.617 28.987 59 10
10mm dia Stirup kg 54.00 1x0.790 0.617 26.321 59 10
10mm dia Stirup kg 54.00 1x0.670 0.617 22.323 59 10
10mm dia Stirup kg 54.00 1x0.590 0.617 19.658 59 10

Page 36 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
6m Length Pile (20mm Design)
20mm dia St. Bar kg 62.00 4x5.675 2.466 3470.6484 59 11
20mm dia St. Bar kg 62.00 4x5.575 2.466 3,409.492 59 11
16mm dia St. Bar kg 62.00 6x2.00 1.578 1,174.032 59 11
8mm dia Spiral kg 62.00 28x0.421 0.395 288.688 59 11
10mm dia Stirup kg 62.00 53x0.950 0.617 1,926.089 59 11
10mm dia Stirup kg 62.00 1x0.870 0.617 33.281 59 11
10mm dia Stirup kg 62.00 1x0.790 0.617 30.221 59 11
10mm dia Stirup kg 62.00 1x0.670 0.617 25.630 59 11
10mm dia Stirup kg 62.00 1x0.590 0.617 22.570 59 11
6m Length Pile (20mm Design)
20mm dia St. Bar kg 26.00 4x5.675 2.466 1455.4332 59 12
20mm dia St. Bar kg 26.00 4x5.575 2.466 1,429.787 59 12
16mm dia St. Bar kg 26.00 6x2.00 1.578 492.336 59 12
8mm dia Spiral kg 26.00 28x0.421 0.395 121.063 59 12
10mm dia Stirup kg 26.00 53x0.950 0.617 807.715 59 12 at page 12 (26 of 50)
10mm dia Stirup kg 26.00 1x0.870 0.617 13.957 59 12
10mm dia Stirup kg 26.00 1x0.790 0.617 12.673 59 12
10mm dia Stirup kg 26.00 1x0.670 0.617 10.748 59 12
10mm dia Stirup kg 26.00 1x0.590 0.617 9.465 59 12
Total= 69,753.632

Page 37 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : 37
Item Name: Suppying and fitting and fixing 23cm wide, 3 bulb type PVC water stops……. WS
Quantity
SL No Description of Item Unit side Chainage QTY Reference Remarks
(Rm)

From To Nos Base Stem MB No. MB Page No.


Suppying and fitting and fixing 23cm wide, 3 bulb type PVC water stops having
minimum strength of 13.80 N/mm2 at 225% elongation and of approved quality in
expansion joints with necessary arrangments for modification in shuttering and
1 keeping the water stop in position etc. complete as per design, specification and Rm
direction of Engineer in charge.

Nimtola West Rm R/S 4+710 4+740 1.000 3.30 6.570 9.870 58 13

ESACK Brothers Rm R/S 5+215 5+245 1.000 3.30 6.808 10.108 59 8

Total= 19.978
SL. No. : 38
Item Name: Labour Charge for fitting and fixing 23cm wide P.V.C water stops…….
Quantity
SL No Description of Item Unit side Chainage Length (m) Reference Remarks
(Rm)

From To Cut of Wall Base Stem MB No. MB Page No.


Labour Charge for fitting and fixing 23cm wide P.V.C water stops, in the
1 expansion joints of hydraulic structures with necessary modification of formworks as Rm
per design, specification and direction of Engineer in charge.

Nimtola West Rm R/S 4+710 4+740 1.000 3.30 6.570 9.870 58 13

ESACK Brothers Rm R/S 5+215 5+245 1.000 3.30 6.808 10.108 59 8

Total= 19.978

Page 38 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : 39
Item Name: Supplying and fitting, fixing dowel bar in expansion joints of hydraulic structures …….
Chainage Nos Reference
Quantity
SL No Description of Item Unit side Remarks
From To Cut of Wall Base Stem (Each) MB No. MB Page No.
Supplying and fitting, fixing dowel bar in expansion joints of hydraulic
structures with 20 mm dia M.S. Plain bar 1000mm long embeded in concrete in one
end and painted other end for a length of 500 mm inserted into a 25mm 600mm long
1 PVC pipe that closed other end by plastic cap as shown in the design drawings
including placing in position, binding with G.I. wire etc. complete as per direction of
Engineer in charge.

Nimtola West Each R/S 4+710 4+740 8 14 22.00 58 13,14

ESACK Brothers Each R/S 5+215 5+245 8 14 22.00 59 8,9

Total= 44.00
SL. No. : 42
Item Name: Providing cork sheet/ polysterene sheet in the expansion joints…….
Chainage Reference
Length Height Quantity
SL No Description of Item Unit side Remarks
From To (m) (m) (Sqm) MB No. MB Page No.
Nimtola west Base Sqm R/S 4+710 4+740 3.30 0.70 2.310 58 13
Nimtola west wall Sqm R/S 4+710 4+740 0.50 6.221 3.111 58 14
ESACK Brothers Base Sqm R/S 5+215 5+245 3.30 0.70 2.310 59 8
ESACK Brothers wall Sqm R/S 5+215 5+245 0.50 6.458 3.229 59 9
10.960

Page 39 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : 18
Item Name: Sand filling on the prepared foundation bed with sand of minimum FM 0.80……………..
Chainage Reference
Length Width Height Quantity
SL No Description of Item Unit Side Remarks
From To (m) (m) (m) (Cum) MB No. MB Page No.
Sand filling on the prepared foundation bed with sand of minimum FM 0.80 in difficult
areas with 150mm in thickness each layer including supplying, placing in conformity
with the profile and level as per design including watering, compaction etc. all
1 complete as per instruction of the Engineer-in-Charge. cum

Nimtola West cum R/S 4+710 4+740 30.000 3.300 0.150 14.850 58 12
Deduction for pile head 99.000 0.090 0.150 (1.337) 58 12
ESACK Brothers cum R/S 5+215 5+245 30.000 3.300 0.150 14.850 59 7
Deduction for pile head 99.000 0.090 0.150 (1.337) 59 7
Total= 27.027
SL. No. : NT
Item Name: Cement Concrete work (1:3:6) in blinding/ centering layer below RCC works……. CC
Chainage Reference
Length Width Height Quantity
SL No Description of Item Unit Side Remarks
From To (m) (m) (m) (Cum) MB No. MB Page No.
CC-10: Cement concrete work in foundation with minimum compressive strength of 10
Mpa at 28 days (suggested mic proportion 1:3:6) on standard cylinder as per standard
practice of Code AASHTO/ASTM and cement conforming to BDS EN 197-1 : 2003
CEM-II/A/L/M/V/W 42.5N , sand of minimum FM 1.8, and 20mm down well graded
1 1st class/picked brick chips (LAA value to excedding 40) conforming to ASTM C33 Cum
including breaking bricks into chips, shuttering, mixing by concrete mixer machine,
casting, laying compacting and curing for the requisite period etc. all complete as per
direction of the E-I-C. Additional quantity of cement to be added if required to attain
the strength at the contractor's own cost.
Nimtola West cum R/S 4+710 4+740 30.000 3.300 0.075 7.425 58 12
Deduction for pile head 99.000 0.090 0.075 (0.668) 58 12
ESACK Brothers cum R/S 5+215 5+245 30.000 3.300 0.075 7.425 59 7
Deduction for pile head 99.000 0.090 0.075 (0.668) 59 7
Total= 13.514

Page 40 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : NT 05
Item Name: Driving pre-cast RCC piles with diesel hammer……. Hammer
Chainage Reference
Length Quantity
SL No Description of Item Unit Side Nos. Remarks
From To (m) (m) MB No. MB Page No.
Driving pre-cast RCC piles with automatic diesel hammer mounted rig in any type of
soil to the required depth including fitting and fixing steel cap, handling and keeping in
position and maintaining driving log in prescribed format as per design, drawing &
direction of the E-I-C. Before commencing driving operation, contractor shall submit
1 the methodology for carrying the driving operation including sequence of driving to Rm
the E-I-C. The maximum permitted deviation of the finished pile from the horizontal &
vertical shall be 50mm & 25mm respectively. Cutting of a pile not being installed to
the planned depth is exclusively subject to the approval of Design Unit, LGED.
X-section of pre-cast pile: 300mm X 300mm

Nimtola West m R/S 4+710 4+740 99 5.50 544.50 58 11

ESACK Brothers m R/S 5+215 5+245 99 5.50 544.50 59 6


1089.00

Page 41 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : NT 09
Item Name: Supplying of non bio-degradable geo-textile bags (empty) of sizes (600 mm x 600 mm) at project/work site ……… geo
Chainage Nos Reference
Quantity
SL No Description of Item Unit Side Remarks
From To Cut of Wall Base Stem (Each) MB No. MB Page No.
Supplying of non bio-degradable geo-textile bags (empty) of sizes (600 mm x 600
mm) at project/work site including fabrication and supply of geo-textile fabric
(mass>= 400gm/m²) and sewing in accordance with the detailed drawing and
Technical Specifications including cost of all materials, labours, taxes, incidental
1 charges etc. complete as per direction of Engineer in charge. Each

Nimtola West Each R/S 4+710 4+740 6 6.00 58 11

ESACK Brothers Each R/S 5+215 5+245 6 6.00 54 6

Total= 12.00

SL. No. : NT 10
Item Name:Filling, sewing & placing of non bio-degradable geo-textile bags of sizes (600 mm x 600 mm) with 50 mm down graded singles………
Chainage Nos Quantity Reference
SL No Description of Item Unit Side Remarks
From To Cut of Wall Base Stem (Each) MB No. MB Page No.
Filling, sewing & placing of non bio-degradable geo-textile bags of sizes (600 mm x
600 mm) with 50 mm down graded singles, sewing along one transverse (top) side
after filling singles including cost of all materials, labours, taxes, incidental
charges but excluding cost of geo-bags as per design, technical specification and
1 detailed drawing etc. complete as per direction of Engineer in Charge. Each

Nimtola West Each R/S 4+710 4+740 6 6.00 58 11

ESACK Brothers Each R/S 5+215 5+245 6 6.00 54 6

Total= 12.00

Page 42 of 47
MINISTRY OF HOUSING AND PUBLIC WORKS
CHITTAGONG DEVELOPMENT AUTHORITY (CDA)
IMPLEMENTING AGENCY: HQ 34 ENGR CONSTR BDE, BANGLADESH ARMY
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chittagong City
Name of Works: Construction of Retaining Wall at Mohesh Khal, Financial Year: 2021-2022
Measurement Sheet IPC - 115
SL. No. : 14 (From Bridge)
Item Name: Labour for breaking head of hardened cast-in-situ bored pile/ pre-cast piles …………….. Hb
Chainage Reference
Pile LxW Height Quantity
SL No Description of Item Unit Side Remarks
From To Nos (sqm) (m) (Cum) MB No. MB Page No.
Labour for breaking head of hardened cast-in-situ bored pile/ pre-cast piles to
the correct lines and levels from the top of the piles to the cut-off level as
indicated in the approved drawing and exposing pile reinforcement for
embedment in pile cap by any means and disposal of the debris to an
unobjectionable place outside the site premises including scrapping and
removing concrete from steel/ MS rods, straightening and bending of pile bars,
preparation and making of platform where necessary, carrying, all sorts of
handling, stacking the same properly after clearing, leveling and dressing the
site and clearing the river bed, etc. all complete as per direction of the E-I-C.
Measurement will be given for the actual pile head volume to be broken.The
1 debris from pile chipping shall be disposed outside the site premises at an cum
environmentally safe place with minimum traffic disruption and procuring
entity will not be responsilbe for any irregularities by the party regarding
dumping of the debris.

Nimtola West cum R/S 4+710 4+740 99.000 0.090 0.425 3.787 58 12

ESACK Brothers cum R/S 5+215 5+245 99.000 0.090 0.425 3.787 54 7

7.574

Page 43 of 47
Contents

IPC-115

location Side Chainage Length Content Pile

Nimtola West R 4+710 4+740 30 Full 6m=99


Nos
ESACK Brothers R 5+215 5+245 30 Full 6m=99
Nos
6M pile making at Mohesh Khal ESACK Brothers Depo.
Casting Date Nos MB no MB page IPC details design
Location
8.2.21 20 6
16.2.21 20 7 ipc-80
18.2.21 32 8
ipc-80 (11
of 20)
46 ipc 90 ( 9
23.2.21 20 9 of 20)
02.03.21 20 10
08.03.21 30 11 ipc90
16.03.21 25 12
ipc90(15
25.03.21 20 13 of 20)
31.3.21 15
42
04.04.21 20
10.4.21 20
43
13.4.21 24
Ipc93
17.4.21 20
44
21.4.21 23
24.4.21 23
46 45
02.6.21 18 Ipc93(30
5.6.21 17 of 35)
46
10.6.21 18 Ipc97(5 of
35)
14.6.21 17
47
19.6.21 17
23.6.21 24 25mm
27.6.21 21 50
ipc 97
29.6.21 17
3.7.21 17 10
ESACK 16.7.21 14
7.11.21 20 11
31.10.21 28 49)
ipc101 (3
19/8/21 21 12 of 49)
22/8/21
26/8/21 74 28 ipc101
31/8/21
54
6/9/2021
### 68 ipc101
14/9/21 29
18/9/21 ipc101(53 of
68)
### 68 ipc102(15 of
### 30 68)
23/12/21
30.12.21
75 31 ipc102
13.1.22 75 31 ipc102
19.2.22 34 41
28.1.22
54
1.2.22 52 40
25.1.22 ipc107
19.2.22
24.2.22 54 59 10 ipc115
2.3.22
20.3.22
23.3.22 62 59 11 ipc115 20mm
25.3.22
07.4.22
ipc115(26
11.4.22 50 59 12
of 50)
13.4.22

6M pile making at Mohesh Khal Bondor Club


Casting Date Nos MB no MB page IPC details
Location
22.12.21 ipc102(14
of 69)
18.12.21 69 41 25 ipc107(55
12.12.21 of 69)

8.12.21 ipc107(15
60 41 26 of 60) 25mm
30.11.21 ipc110(45
28.11.21 of 60)
29.1.22
03.1.22 66 54 47 ipc110
20.2.22
24.2.22 7 54 50 ipc110 25mm
ipc110(4
of 16)
58 10 20mm
ipc115(12
of 16)
24.2.22 16
27.2.22
4.4.22 44 58 15 ipc115 20mm
14.4.22
Name of Project: Re-excavation, Renovation and Development of Khals for Mitigation Water Logging Problems in Chattogram City
Name of Contractor: Taher Brothers Ltd. Date: 08/12/2021

Utility Bill Summary


Including
Chainage/
SL No Description of Item Sub-Total Vat+Tax+Profit Total Amount Remarks
Location
(24%)
Various Electrical
20 establishment removal ESACk 35,000.00 8,400.00 43,400 ipc115
and relocation

Sub-Total 35,000.00

Vat+Tax+Profit 8,400.00
Total Amount 43,400.00