From : GM(OS-R&M)
AGM (OS) To: 1. AGM(R&M-Engg)/GM(Fin-Budget)
2. GM(CP-GPA)
EXCEPTION REPORT :
Utilization w.r.t BE (Rs. Cr.) BE for FY RE Prop Actual(YTM) RE Shortfall
a. Ramagundam 240.40 171.83 102.24 69.59
b. Rihand 178.46 135.13 84.69 50.44
c. Singrauli 130.52 64.09 31.72 32.37
d. Unchahar 72.61 41.90 18.04 23.86
e. Korba 204.98 90.37 70.09 20.28
Page 1 of 4
Financial Progress Report of R&M works of NTPC Stations as on 28-02-2022
All cost figures in ₹ Crores
A : R&M Schemes under Compensation Allowance
Station Investment Approval Total value FY:2021-22 Cumulative Remarks
Date Amount of Orders BE YTM expenditure
(excl IDC) placed* BE Actual
(Apr'14
onwards)
DADRI-Coal(Stage-I) 30-04-11 105.19 57.01 0.60 0.60 0.00 55.28
FGUTPP(Stage-I) 28-04-12 46.77 16.12 0.00 0.00 0.00 15.29 Expenditure & BE for Stage-I Schemes are
included in TOTALS under Mega R&M as CA
FGUTPP(Stage-II) 2.51 0.00 0.00 0.00 2.52 was not available from Apr'14 and excluded from
FSTPS(Stage-I) 16-08-11 75.77 8.16 2.64 1.90 0.11 5.20 TOTAL under this table.
Page 2 of 4
Financial Progress Report of R&M works of NTPC Stations as on 28-02-2022
All cost figures in ₹. Crores
Station Investment Approval FY:2021-22 Cumulative TOTAL Remarks/Life as on 01.04.2014 as
Date Amount Special BE YTM Apr-2019 to Feb-2022 Grand Cuml per Tariff Order
Allowance (incl ESP) BE Actual Spl Allowance Expenditure Expenditure
(incl ESP) (incl ESP) Incl ESP Incl ESP
B : MEGA R&M UNDER SPECIAL ALLOWANCE
FGUTPP(Stage-I) 29-09-16 233.30 39.90 72.61 54.21 17.94 113.05 73.38 176.75 dated 22.03.2017 : 4.93 Years
FSTPS(Stage-I+II) 29-09-16 277.78 104.50 80.65 11.70 9.62 201.08 113.96 275.02
KSTPS (Stage-I) 23-08-12 318.10 57.00 17.59 17.45 3.48 161.50 45.58 156.51
KSTPS (Stage-II) 03-02-17 142.50 41.43 41.26 30.22 403.75 174.17 342.10
KSTPS (CA,MBOA,CSP) 03-02-17 145.95 110.13 36.39 90.41 239.25
NCTPS(Stage-I) 08-11-16 24.02 79.80 4.27 4.02 1.76 166.25 50.49 54.40
RHSTPS(Stage-I) 23-01-17 319.68 95.00 178.46 104.26 84.69 269.17 223.34 443.83
RSTPS (Stage-I) 10-05-12 713.28 57.00 124.66 90.67 31.18 161.50 248.33 606.37
RSTPS (Stage-II) 01-11-16 142.50 111.38 51.28 67.75 403.75 185.89 263.82
RSTPS (CA,MBOA,CSP) 01-11-16 4.36 4.36 3.31 13.04 34.18
SSTPS (Stage-I) 25/04/13 658.99 95.00 58.26 43.49 12.00 269.17 133.75 480.79
SSTPS (Stage-II) 17-01-17 95.00 72.26 65.01 18.04 269.17 98.61 299.18
SSTPS CW Duct 26-07-10 137.53 0.00
SSTPS (CA,MBOA,CSP) 17-01-17 0.00 0.00 1.67 49.19 23.64
VSTPS(Stage-I) 07-10-16 743.89 119.70 36.29 35.42 32.85 339.15 229.19 464.68
TOTAL(incl ESP) 3426.57 1087.75 948.18 633.26 350.92 2807.41 1712.49 3894.78
TOTAL(excl ESP) 2030.09 1087.75 817.12 557.73 271.50 2807.41 1541.42 3024.46
C : LIFE EXTENSION(APPROVED/EXECUTED AFTER MARCH, 2009) - For detailed Report, Refer Detailed Financial Progress Report for
March, 2019 available on COS-R&M Webpage
AURAIYA 25/04/13 893.98 0.00 0.00 0.00 728.01
FARIDABAD 16.00 16.00 9.26 12.21
NCTPS-Gas 24-02-11 537.52 1.05 0.96 2.01 211.76
KAWAS 26-11-07 541.85 0.00 0.00 0.00 610.37
GANDHAR 23-03-11 540.33 0.00 0.00 0.00 689.68
BTPS 29-12-09 504.16 0.00 0.00 0.00 71.25
BTPS CW SYSTEM 25-07-11 205.50
BTPS CIVIL WORKS* 29-09-15 27.86
Page 3 of 4
Financial Progress Report of R&M works of NTPC Stations as on 28-02-2022
All cost figures in ₹ Crores
Page 4 of 4