Work Module:
BOILER MAIN:-
5 Other Areas Tubes/ Bends Repair/ Replacement Based on Physical Inspection and
De-metering.
7 Water Wall/ Steam Cooled Wall eroded Tubes/ Bends (Manhole) Replacement
13
RAPH:-
3 Basket inspection
VALVES:-
2 Boiler Safety Valves and Other Valves in Steam and Water Circuit Overhauling/
Servicing.
DUCTS:-
1 Primary Air, Secondary Air and Flue Gas Ducts Cleaning, Inspection and Repair.
ESP:-
FANS:-
COAL MILLS:-
2 Coal Mill Gearbox Chamber & Oil Cooler Cleaning/ hydro test.
INSULATION
B TURBINE MAINT
1 TURBINE MAIN:
4 BFP 1A: Bearing checking, Lube oil tank cleaning, Mech seal cooler cleaning,
Suction Strainer checking and cleaning, Cooling water lines cleaning/ replacement as
per requirement. (Pump DE brg checking)
BFP 1B: Bearing checking, Lube oil tank cleaning, Mech seal cooler cleaning,
Suction Strainer checking and cleaning, Cooling water lines cleaning/ replacement as
per requirement. (pump Both brg to be checked.)
5 CEP 1 A: Bearing checking, Cooling coil hydro test, Suction strainer cleaning, NRV
checking. Suction v/v servicing
CEP 1 B: Bearing checking, Cooling coil hydro test, Suction strainer cleaning, NRV
checking. Suction v/v servicing
8 COOLING TOWER: Hot basin cleaning, Sump Cleaning, Gear box checking, Oil
replacement, Blade angle checking, Deck valve servicing/ repair etc.
10 S/D related jobs. - BFP warm up line pipe replacement( near condenser),
ACW pipe replacement near main oil cooler , Duplex oil filter vent line repair
C ELECTRICAL MAINT
SNO
. JOB DESCRIPTION
GT, UAT :-
132KV SWITCHYARD :-
1 GT#1, MSDS-3 Feeder-1 & 2, MSDS-5 Feeder-1 & 2, Bus Coupler & Bus Transfer
bay CTs testing by M/s ERDA, Vadodara
2 132KV GT#1, MSDS-3 Feeder-1 & 2, Bus Coupler Bay & Bus-1 equipments
maintenance, hot spots attending & clamps tightness.
HT/LT MOTOR :-
2 BFP # 1A & 1B motor coolers cleaning & MTB, Star Point checking
3 Overhauling of LT Motors (AC Seal Oil Pump, Bearing Chamber Exhaust Blower-1
& 2, Thyristor Cooling Fans, CM LOPs, PA FAN LOPs, Scanner Fan-1 & 2, Front &
Rear Clinker Grinder, Oil Vapour Extractor Fans, BFP-1A & 1B LOP-1 & 2, SAB-1C,
RAPH-1A & 1B Normal & Emergency Motors, GSEF-1 & 2)
4 HT/LT Motors PM- (PAFANs, Coal Mills, CEPs, FD FAN-1A, ID FAN-1A, ACWs, DC
SOP, JOP, EOP-AC & DC, Rapper Motors)
RELAYS TESTING :-
HT/LT SWITCHGEARS :-
5 Cleaning & Maintenance of FBT, CDB Panels, Local Panels of Scanner Fan-1 & 2,
Coal Feeders, Seal oil panel, LAVT, Excitation Transformer, Generator Reactor,
Neutral Grounding Transformer of Generator & UAT
ACTUATORS :-
1 Overhauling of actuators
OTHER JOBS:-
D C&I MAINT
SN. JOB DESCRIPTION
Boiler Area:-
1 OH of Burner instruments.
2 OH of Coal Feeder Instruments.
3 Cleaning of piezo rings of Primary & secondary air flow, transmitter impulse lines of
air , flue gas, Furnace draft & DP signals.
4 Cleaning & calibration of Flue gas Oxygen analyser.
5 Checking & cleaning of CM zero speed switches.
6 Checking & cleaning of RAPH zero speed.
7 Checking & calibration of pent house thermocouples.
8 Checking the interlocks & protections of boiler & boiler auxiliaries
9 30T PRDS R&M JOB(Cable laying, impulse pipe laying, JB mounting, Cable
termination, logic modification, signal integration with DCS etc.)
Turbine area:-
1 Overhauling of EHTC.
2 OH of BFP, CEP C&I instruments.
3 Checking of Turbine speed signal ( both control & protection ckt)
4 OH of Turbo supervisory instruments.
5 Calibration checking of Governing control valve.
6. Calibration & checking of HOTWELL LEVEL & LPH/HPH LEVEL TRANSMITTERS.
7 Checking the interlocks & protections of Turbine & turbine auxiliaries
Common area:-
1 Calibration of Pressure transmitters & local gauges.
2 Cleaning & tightness checking of LIE/LIRs and local JBs.
3 OH of 24V DC charger & battery bank.
4 Cleaning & tightness checking of DCS panels in CER & UCR.
5 Cleaning & functional checking of pneumatic actuators of Blr & Turbine area.
6 OH of UPS.
7 Cleaning & functional checking of motorised actuators of Blr & Turbine area.
8 OH of LVS System.
9 OH of OWS & EWS .
10 Checking & calibration of Temperature signals of Boiler & Turbine
Jobs for other department