During the CNC 2022 TAR, twenty-nine (29) exchangers were opened, cleaned,
inspected and in instances where repairs were deemed necessary, the affected
exchangers were serviced accordingly. Each exchanger was also subjected to tests
such as Eddy Current Testing (ECT) and Hydro or Leak Testing etc. to ensure that all
exchangers were in suitable condition before reassembly and handback to
Operations. Additionally, the 105-C and 172-C were replaced/upgraded, in which
both the bundle and shell were replaced entirely. The 172-C was upgraded to a
welded channel to tube sheet arrangement similar to N2000 and the 105-C was
replaced in kind with the addition of two nozzles for level transmitters to be mounted
for monitoring purposes.
Page 50 of 107
Proman TAR Executive Report – CNC 2022 TAR
subsequently plugged. All turbulators were reinstalled, however only partial
lengths were able to be re-inserted into the tubes due to restrictions during
installation. The exchanger was reassembled and placed back into service
without issue.
5. CO2 Reboiler, 105C – The 105C exchanger was replaced in kind during the
turnaround. All piping flanged joints were reassembled and torqued, and the
exchanger was reinsulated. This exchanger is fit for service and should be
inspected at the next recommended inspection interval or TAR for acquisition
of base line in-service data.
Page 53 of 107
Proman TAR Executive Report – CNC 2022 TAR