Professional Documents
Culture Documents
HISTORY OF MACHINE
Turbine Maintenance 1
UNIT # I AOH OF TURBINE, GENERATOR AND TG AUXILLIARIES
(10.06.18 TO 14.07.18)
MAJOR WORK CARRIED OUT DURING AOH OF UNIT NO 1
MAJOR EVENTS
Turbine Maintenance 2
ACTIVITIES CARRIED OUT DURING OVERHAUL
I. TURBINE-GENERATOR
A LP TURBINE
Observations –
All the three casing of LP 1 &2 Turbine (outer, inner- outer, inner-inner) were opened.
Silica deposition found on the LPT1&2 blades.
LPT atmospheric relief diaphragm checked and found ok.
Last stage blades and rotor grooves of both LP rotors MPI & NFT done and two nos blades
found cracked at root of blade( one blade each of left and right side of LPT 1).
All palm packers, axial and radial keys of HP and IP Turbine checked and found OK.
LP turbine bottom casing drain modification.
LP steam path radial clearance found less in few stages at both turbine and generator end.
NFT values not coming as per requriment between new blades and rotor groove of LPT 1
(Left side).
Action Taken :-
LP rotor was lifted from position. Sand blasting of Rotor and LP inner inner & inner outer
top half casing carried out.
MPI (Magnetic Particle Inspection) test of freestanding LPT1& 2 Rotor blades (8th stage on
either side)was carried and crack / abnormalities were reported in LPT 1 stage 3L blade no
34 & stage3R blade no 30.
NFT of LPT 1 stage 3R 14 nos blades blue matching done with rotor groove to achieve the
requried NFT values.
LP Inner inner casing ovality checked and found O.K.
LP Gland box segments checked and found in good condition. All Extraction, CAP (Cross
Around Pipe) and LP Rotor Bellows were checked and found O.K.
BVMS installed for LP last stage blades.
LPT flow path checked and stage blade shrouds were ground off to improve the radial
clearances and LP Roll check carried out.
LPT atmospheric relief diaphragm replaced.
IP Turbine centering done, Roll, Bump check and Horn drop test carried out.
HP Turbine centering done, Roll, Bump check and Horn drop test carried out
Turbine Maintenance 3
LP Blades Crack at root.
Turbine Maintenance 4
Honing of all coupling holes of HP-IP (16 nos) & IP-LP (3 nos) , LP-LP (2 nos) done for
maintaining the clearances.
Emergency Governor Striker Bolt opened and servicing done
Yoke Keys blue matching done and clearances maintained as per requirement.
MOP Wear rings & Bearing clearances checked and found within limit. DPT of Impeller
carried out and found satisfactory. Bevel gear coupling checked and found O.K.
OBSERVATION:
Foreign material found inside genearator.
Hydrogen seal ring (turbine side) clearance with rotor found more then design value.
OWVMS installation work completed.
Compressor centering reading was recorded however punch values not available in
corresponding segments.
Minor pitting observed on coupling face of generator and excitor.
Oil catcher clearance of bearing no 6 and 7 & 8 found on higher side
Generator rotor CC bolts leak test done.
Turbine Maintenance 5
ACTION TAKEN :
Generator Rotor Threading out done. Rotor compressor blades checked for looseness and
found intact.
DPT of blades and retaining ring carried out and found satisfactory.
DPT and Ultrasonic test of seal ring(TE &EE) , retaining ring and bearings carried out and
found ok.
DPT of compressor fixed blades carried out and found ok.
Hydrogen seal ring (TE side) clearance with rotor was found on higher side and replaced
with new seal ring (machining done as per requirement)
Blue matching of bearings and saddle carried out.
Hydrogen coolers cleaning done and hydro test carried out and found satisfactory.
Primary water system hydro test carried out and found satisfactory.
Exciter coolers cleaning done and hydro test carried out and found satisfactory.
Generator Rotor CC bolts leak test carried out with nitrogen pressure 6kg/cm2 and no
leakageobserved.
Scrapping and Polishing of Bearing No-6,7,8 done. Blue matching of the Bearing with
Pedestal carried out.
Air leak test of Generator carried out after boxing up and found satisfactory.
Primary water inlet strainer Generator rotor thread out Compressor three stage
moving blades.
D TURBINE SPRING DECK
OBSERVATION:
Turbine Maintenance 6
E SYSTEM RESTORATION
OBSERVATION:
For oil flushing all throttle replaced with the line filter with dummy flanges.
Jop Header pressure and individual bearing pressure setting.
Lube oil header pressure obsereved on higher side.
Foreign material found in bearing no 07 throttle & line filter.
Bearing no 03 indiviual oil pressure found on higher side.
Bearing no 06 & 07 having more oil flow and Bearing No. 04 having less oil flow.
Oil leakge obsereved through Bearing no 03 front oil catcher.
ACTION TAKEN:
For oil flushing cloth bag also put in both basket strainers.
Individual lift of rotor(as per design) at each bearing acheieved with adjustment of flow and
header pressure.
Lube Oil Header Pressure reduced for flushing and after flushing adjusted according to
requirement of system.
Bearing No 03 oil pressure adjustement carried out as per requirement.
Machine Put on Barring after acieving the required oil specification.
Turbine Maintenance 7
B TURBINE MOT tank Inspection & Cleaning
Firstly, Dirty oil tank cleaning done. Oil from main oil tank was transferred to dirty oil tank and
the manholes were opened. Main oil tank was cleaned and final cleaning was done with flour. After
cleaning carefully inspection of all the pumps suction & pipelines flanged found AC lube oil
pump-B discharge flange gasket damaged & pump-A bearing housing loose & removed condition.
After rectification of gasket & bearing housing final inspection with SSCl & Steag Operation team
,box-up done Hence oil was restored back to MOT through oil purifying device and purifier kept in
service .
Turbine Maintenance 8
D Hotwell Inspection
Hotwell A & B manholes were opened for hotwell inspection. After getting confined space work
clearance from safety department, inspection was done.Mud & slight traces of resin found on the
hotwell surface and then the surface was cleaned. Outlet strainers of hotwell (suction strainers of
CEP) were cleaned. Expansion joints were inspected and then the hotwell was boxed up.
E Deaerator Inspection
Deaerator manholes were opened for internal inspection after ensuring proper isolation & draining.
Internal inspection was carried out, slight layers of resin found inside & RC line end dummy plates
wars fund damaged condition so dummy welding done. Rest of all internals were found in good
condition. Inspection of major welding joints & found some gaps in protection plate so welding
done. Cleaning of resin done & flange bolts tightened done after inspection of deaerator by
operation & chemist dept boxed up done with replacing of new gasket.
Turbine Maintenance 9
area of shaft damaged. Damaged shaft, bearings were replaced with new one. Coupling was checked and
found normal. The bearing cooling line & cooling coil were inspected and acid flushing done. After
properly inspecting all the parts, the pump was assembled and coupled.
TDBFP-A
TDBFP-A D.E & N.D.E bearing top covers of turbine were removed. Both side journal bearing,
thrust bearing inspected & DP test was done and found that bearings were in good condition.
Coupling was checked and found normal. After properly inspecting all the parts, bearings were
boxed up. Oil tank of cleaned after tranferring oil to main oil tank and restored after proper
inspection.
TDBFP-B
TDBFP-B was completely isolated, then D.E & N.D.E bearing top covers of turbine were removed.
Both side journal bearing, thrust bearing inspected & DP test was done and found that bearings
were in good condition. Coupling was checked and found ok. After properly inspecting all the
parts, bearings were boxed up. Oil tank is cleaned after tranferring oil to main oil tank and restored
after proper inspection.
Whole catridge of pump is replaced by Gangotri Turbo Tech.(external agency), alignment done and
coupled with turbine.
Final alignment readings of pump to turbine are mentioned below
Turbine Maintenance 10
OCCW Pumps A & B
During overhaul, both occw pumps were dismantled for inspection. The condition of bearings was
found ok , DPT was done on the impeller & no cracks were found. Suction mov of pump-A
replaced. Both pumps discharge nrv seals replaced. Energy efficient ceramic coating was also done
inside the housing of both pumps as shown in figure below.
Self cleaning strainer cleaning & inspection
Strainer tank was drained and top cover was removed for inspection of strainers and tank.The
inside of stainer cleaned with buffing wheel. All the six strainers were in choked condition, they were
dismantled and properly cleaned. Gear box oil & gland packing replacement was done. After cleaning and
proper inspection, strainers were boxed up
OLTC SCREEN CHECKING
Manholes were opened for inspection of OLTC screens on both the cooling water return lines from
condenser. Screens were inspected and maintenance was carried for free movement of the screens.
Glands were replaced for the links holding the screen.OLTC-B screen actuator was replaced by
C&I.
SGDMCW PUMPS
For overhauling, both pumps were dismanled. pump-A & B DE & NDE side bearings were
replaced. Mechanical seals of both the de & nde sides were replaced for both the pumps. DP test
was done on the impellers & no cracks were found. Impeller of both the pumps were in good
condition. Assembly of both pumps done after proper inspection.
Turbine Maintenance 11
Generator H2 Cooler Cleaning
For cleaning of generator H2 cooler, all coolers were isolated from tube side. Top and bottom
covers of all the coolers were removed. All the tubes were cleaned with the help of brush attached
to rod end. All the coolers were boxed up after proper cleaning and inspection completed.
Turbine Maintenance 12
Complete overhauling of LPT-1 & LPT-2.
Main turbine Lube oil tank(MOT)system were completely drained cleaned & inspected..
TDBFP -A & B lube oil system, HP-LP bypass oil system were completely drained cleaned &
inspected.
Condenser chemicals & jet cleaning done & flood test was carried out and 02nos dummies plug
were made on the condenser tubes.
Energy efficient ceramic coating done inside condenser & replacement of resilience seals of
condenser water box-A & B inlet & outlet valve.
Deaerator internals inspection & cleaning done, slight traces of resin and welding joint cracked
observed.
CEP-A, B & C suction strainers cleaning, all CEP bearing lube oil flushing done.
TDBFP-A & B bucket strainers & MDBFP bucket & conical strainer cleaning done & flange
gasket was replaced.
Inspection & rectification of all TGDMC & ACW pumps discharge NRV.
Turbine Maintenance 13
MOT coolers-A,B tubes were cleaned & water flushing was carried out.
TDBFP-A & B cooler-A & B tubes were cleaned & water flushing was carried out.
MDBFP working oil & lube oil cooler tubes were cleaned & water flushing was carried out.
All valves related to above systems lapping done and wherever required replaced.
Replacement of DRV-51 & deaerator drain valve due to damaged of valve set & plug
Turbine Maintenance 14
Turbine Maintenance 15