You are on page 1of 20

COLD START-UP CHECKLIST OF

210 MW BOILERS
Unit: Date:
1 Men & material removed from furnace PP
S NO. &Description
Second pass & manholes/peepholes RESP. STATU Remarks
closed. S
216 All
Forducts cleared
all APHs fireand manholes
detection closed
system C&I PP
3 is kept in service.
All works on pressure parts completed and boxed up.
17 All protections & interlocks of boiler C&I
4 I
All safety valve gags and hydro-plugs PP
(FSSS) are checked & kept in service.
removed.
18 All alarms set as per the design, tested C&I
5 and
All kept in service.
available oil guns are flushed PP
checked for any leakage, cleaned
19 and
APHclamped.
soot blowers are cleared for C&I
Operation.
620 Bottom
All ash hopper
wall blowers and and seal are
LRSBS trough filled. . Opn PP
retracted fully.
21 Boiler is filled upto the normal level. Opn.
7 All air pre-heater soot blowers PP
22 Burner &
checked front & airfor
cleared pre-heaters
operation. . Opn
Fire water ensured.
23 Burner front, air pre-heaters and . Opn
Other boiler areas are accessible
8 Men and material cleared from ducts, RM
24 All boiler
dampers, protections
fans are checked
and airpreheaters. Opn.
and kept in service.

925 All air pre-heater


Availability fire water
of APH is
fire detection . Opn RM
charged up to the last valve .
System, oil carry over probes, air
10 All air pre-heater
Pre-heater oil carry
dampers & air over probes
pre-heater RM
are fixed in position
Soot blowers ensured. and cleared
26 for operation.
Service air availability ensured for . Opn
11 Clearance givenand
Air pre-heater fromigniters.
mills, feeders RM
27 & fuel piping side. Opn
12 Men
Main and material
turbine removed
is on barringfrom
gear.bottom AHM
28 ash hopper,
Clearance obtainedeconomizer hopper, air
from Pressure Opn.
pre-heater hopper and boxed
Parts Rotary Machines, ash handling up.
Maint. & C&I maint. for light-up and
13 All majortwo
Minimum PTWs are incancelled.
passes ESP boxed up and cleared for AHM
29 Major
operationdeviations from standard Opn.
14 Check listgiven
Clearance notedfrom
and critical
submitted for HP/LP bypass
piping, TM
Approval by competent
& main turbine side. authority.
15 All instruments related to APHs and C&I
boiler combustion are working.
CLEARANCES

S.NO. DEPARTMENT SIGNATURE REMARK

01. Pressure Parts (PP)

02. Rotating Machines (RM)

03. Turbine Maintenance (TM)

04. C&I Maintenance (C&I)

05. Ash Handling Maint. (AHM)

06. Operation / Recommissioning

DEVIATIONS:

Shift Charge Engineer/ Sr. Supdt. (Opn.) DGM (Opn.)


Supdt. (Opn.)

AGM (O&M) :
.

START-UP CHECKLIST OF
210 MW TURBO-GENERATORS

UNIT: DATE:

S. DESCRIPTION RESPONSI- STATUS REMARKS


No BILITY
.
01. All major works on TG completed, PTWs TM/Opn.
cancelled. Check list for putting TG on turning
gear is filled.
02. TG put on turning gear. Opn.
03. MS, HRS strainer drains, header drains, CRH Opn.
drains including manual valves are kept open.
04. All drains manual valves are open. Valves are Opn.
open or working in auto.
05. Gland steam drain valves are working in auto. Opn.
06. Both CW passes are charged and CW flow is Opn.
Normal
07. Condenser vacuum pulled & vacuum switches Opn. / C&I
are reset:
Vacuum:
08. Boiler is in service with sufficient steam flow: Opn.
BLI, tph:
09. HP/LP bypass are completely available & TM / C&I/
charged. Opn.
10. All TSI, indicators & recorders are available & C&I
switched ‘On’
11. DAS is switched ‘ON’; X-T curves & temp. C&I
margin values are available.
12. Turbine protections and interlocks checked and C&I/Opn
kept in service.
13. SLC AOPs (DC/AC), JOPs (DC/AC) pumps Opn.
are switched ‘ON’
14. Turbine oil temp. control is in auto. Opn.
15. ATRS and EHC availability ensured. C&I / Opn.
16. ATT programme is available. C&I
17. Main and middle breaker are open and isolators Opn.
are closed.
18. All trip relays are reset. Opn.
19. GTs, UATs and bus ducts cleared: all allied EM/Opn.
supplies made ‘ON’ and mulsifiers kept in auto.
20. GTs, OLTC checked and cleared. EM
21. Exciter panel and allied supplies readiness EM/ Opn.
checked and kept ‘ON’
22. Generator casing H2 filling completed and Opn.
pressure is >1.8 ksc, H2 purity-%:
23. H2 coolers charged and temp. control put in Opn.
auto.
24. Stator water system is in service: Flow adjusted EM/Opn.
and temp. control put in auto. pressure in
normal.
25. Exciter coolers charged. Opn.
26. Availability of AVR ensured. EM
27. Seal oil system is completely available. Oil Opn.
pumps interlocks checked.
28. Seal oil system is in service; standby pumps Opn.
supply is made ‘ON’
29. Seal oil coolers are charged and oil temp. is Opn.
normal.
30. Turbine governing characteristics taken and TM
cleared.
31. DG set is available and diesel tank level is Opn.
normal.
32. Turbine parameters on TG are noted and no Opn.
abnormally is observed.
33. Turbine startup parameters (as given in Opn.
integrated start-up procedure) achieved.
34. Major deviations (if any) from the above Opn.
checklist noted and brought to the notice of
competent authority.
35. Clearance for Turbine rolling : Signature
Turbine Maintenance :
Electrical Maintenance :
C&I Maintenance :
Operation :
36. Ensure that turbine is not accelerating on Opn.
opening of stop valve.
37. Turbine rolled to 600 rpm. Parameters noted Opn
and found OK. Ensure Turning gear valve
closed.
38. Turbine rolled to 3000 rpm after soaking Opn.
(whenever required). Parameters noted & found
OK. Ensure stopping of JOP, AOP etc.
39. Speed cross checked at 3000 rpm with off line Condition
instrument and found satisfactory. Monitoring/
Opn.

40. ATT carried out for protective devices and Opn.


found OK.

41. All Electrical tests completed, and by passing EM


done, if any, normalized.

42. Sufficient margins are available as per TSE. Opn.


43. Information given to grid / switchyard Engineer Opn
and clearance taken for synchronizing.

44. Clearance for Generator synchronizing : Signature


Electrical Maintenance :
Operation :

45. Unit synchronized and block load taken. TG Signature


cleared for operation.
Operation :
Counter Signature :
MODEL OPERATING INSTRUCTIONS OF
210 MW BOILER & AUXILIARIES (COLD –START)

1.0 INITIAL CONDITION :


1.1 Boiler is depressurized condition.
1.2 Boiler is filled upto the normal level.
1.3 All boiler auxiliaries are cleared for operation.

2.0 LINE –UP:

The following systems / equipments should be lined up and made ready for operation:

2.1 Aux. Steam system.


2.2 Fuel oil-handling system.
2.3 Instrument air system.
2.4 Plant air system.
2.5 Equipment cooling water system.
2.6 Both air heaters with associated dampers.
2.7 Both ID fans should be ready and lined up.
2.8 Both FD fans should be ready and lined up.
2.9 AC and DC scanner air fans.
2.10 SCAPH for primary and secondary air heaters
2.11 Both PA fans should be ready and lined up.
2.12 Mills: Those required for full load operation should be made ready and which are
not available should be isolated.
2.13 Coal feeders.
2.14 Both seal air fans.
2.15 Electrostatic precipitator.
2.16 Soot blowing system- for air heaters.
2.17 Furnace temp. probes.
2.18 Water / steam sampling system.

The equipments readiness can be ensured by complying with the Recommissioning checklists.
3.0 CHARGING OF SYSTEMS :

3.1 Charge aux. steam to the boiler (from running unit or aux. boiler). Ensure proper

draining of the lines before charging. Aux. steam for oil heating, oil
lines tracing, atomizing steam, air heater soot blowers and steam coil air
heaters, mill inerting should be made available.

3.2 Start instrument air compressors and charge instrument air to boiler, turbine,
auxiliaries and off-sites.
3.3 Start plant air compressors and charge plant air igniter cooling, air heater, air
motors and other cooling/ cleaning requirement.
3.4 Start equipment cooling water pumps and charge the coolers for all equipments.
3.5 Charge HFO up to the burner front and keep it on long recirculation.

4.0 PRESTART CHECKS :

Fill the boiler cold startup checklist and get the deviation approved by the competent authority

5.0 START-UP :

The sequences of starting of the equipments are given below. For details refer to the standard
operating procedure of the individual equipment.

5.1 Line up Bottom ash hoppers including seal trough filling.

5.2 Line up ESP from flue gas side, line up ESP hoppers, Eco hoppers and APH hoppers.

5.3 Start the air heaters one by one and Keep the associated dampers open.

5.4 Start the first ID fan .Ensure that its suction & discharge dampers open to full.
Also check for the closure of the suction /discharge damper /inlet vane of the
Other fan.

5.5 Gradually raise the scoop and then vane of the running fan and maintain a furunace draft
of about -10 mm of wc.

5.6 Start the corresponding FD fan (if it is not available the other FD fan can be started).
Ensure that the discharge damper of the running fan opens full and the blade pitch and
discharge damper of the non-running fan closes full.

5.7 Gradually raise the load on the FD fan. Parallely control the scoop and vane of the
running ID fan to maintain the furnace draft. (Ensure that the secondary air dampers
are open and modulating ). Raise the total air flow to more then 30% and less than 40%,
which is the purge requirement.

5.8 Put the wind box pressure control (aux.air dampers) in auto and maintain the desired
wind box to furnace differential pressure.

5.9 Start the second ID fan. Ensure full opening of its suction and discharge damper.

5.10 Slowly raise the scoop and vane of the second ID fan and reduce those of the first ID
Fan to equalize the loading on both fans, always maintaining the furnace draft within
limits.

5.11 Start the second FD fan, ensure that its discharge damper opens fully.

5.12 Gradually raise the blade pitch of the second FD fan and reduce that of the first FD fan
to equalize the loading on both fans maintaining the minimum air flow and normal
furnace draft.

NOTE: If so desired, the second set of ID/FD fan can be started at a later stage (after
synchronization and auxiliary supply changeover) to reduce the auxiliary power consumption
and loading on station transformer. But keeping both the fans in service is preferable from the
operation flexibility point of view. It avoids tripping of the boiler on protection in the event of
outage of one fan and reduces the furnace disturbance at a later stage while starting the second
set of fans.

5.13 Put the furnace draft control in auto. However, the performance of the auto loop should
be kept under observation during low load operation.

5.14 Start the AC scanner fan and keep it in service. Keep the other fan as auto standby.
Ensure that the scanner air pressure is normal.

5.15 Charge the SCAPH of both FD fans. Regulate the steam flow to maintain the air heater
cold end temp.

5.16 Close the HFO trip valve and recirculation valve (which were opened earlier for
charging and warming up the oil lines- Refer Sec. 3.5). Open the short Recirculation
Valve. Line up Oil burners.

5.17 After completing the above activities, ensure that the following purge permissives are
satisfied and the ‘PURGE READY’ Light is ‘ON’ :
a) All HFO nozzle valves are closed.
b) All mills are OFF.
c) No boiler trip.
d) All feeders are OFF.
e) All scanners sense ‘No Flame’.
f) All auxiliary air dampers are modulating.
g) Both PA fans are OFF.
h) All hot air gates are closed.
i) Air flow> 30% and < 40%
j) HFO trip valve is closed.
k) Wind box to furnace difference pressure is normal.

5.18 Ensure that the cold startup checklist is completed in all respects and the deviations are
noted.

BOILER LIGHT UP:

5.19 Start the furnace purge cycle by depressing the ‘PUSH To PURGE’ button. ‘PURGING’
light comes ‘ON’ and purging continues for 5 minutes (if the purge time is disturbed, it
should be corrected).

5.20 If the purging is interrupted due to any reason (loss of one or more of the purge
permissive), purging should be restarted.

5.21 On completion of purge, ‘PURGE COMPLETE’ light becomes ‘ON’ and MFT gets reset.
Then, wait for Fuel air dampers to close and other auxiliary air dampers to modulate as
per SADC command. Check for sufficient wind box pressure.

5.22 Open the HFO recirculation valve and HFO trip valve: close the short recirculation valve.

5.23 Bring the HFO header pressure and temperature to normal value. Ensure that atomizing
steam pressure is normal.

5.24 Ensure that burner is horizontal.

5.25 Scavenge all Oil guns.


5.26 Select the oil burners to be fired. During cold startup normally lower (AB) elevation oil
burners are selected.

5.27 Give start command to the selected burner. it is preferable to start one burner at a time by
monitoring it performance at local ( individual burner selection can be done by keeping
its selector switch in remote at local).

5.28 Eve if Oil gun is proved, check and ensure that the burner is firing properly at local. In
case of poor flame or a leak, take out the burner immediately. Identify the cause and
attend it.

5.29 After proving the first burner successfully select the burner (preferably on the opposite
side in the same elevation) and give start command. Ensure proper flame at local.
Similarly all the four burners in the elevation (maximum) can be kept in service. Regulate
the oil pressure.

5.30 Keep the furnace draft at normal values while cutting in oil burners.

5.31 Ensure that the auxiliary air dampers of the burners in service are open.

5.32 Check the chimney exit. If excessive black smoke is observed, adjust air flow.

5.33 Start air pre heater soot blowers.

1. Check for any oil carry over with the help of oil carry over probe.

2. Inspect the air heater through inspection doors provided on the air side.

3. Check for opening of soot blower poppet valves.

4. Check steam pressure of soot blower after poppet valve at local.

5. Keep monitoring Flue gas temperature at air pre hearter outlet.

5.34 Maintain drum level within normal limits). Keep economizer recirculation valve open
when there is no feeding to the drum.

5.35 Monitor the boiler pressure increase and ensure that it is within allowable limits (it should
not exceed a corresponding increase in saturation temp. of 100 0C / hr).

Also do condenser vacuum pulling after making the associated system ready.
5.36 At a drum pressure of 2 kg/cm2 close all Drum vents and close SH vents at 3.5 ksc. Leave
the startup vents open. Close SH drains at 7 ksc drum pressure.

5.37 Insert furnace temp. probe occasionally and ensure that the gas temp. is less then 540 C

5.38 Monitor the rate of increase of SH outlet temp. and ensure that it is within limits. (less
than 5 C/min).

5.39 Monitor the drum, SH and RH metal temp. and ensure that they are within limit. (Drum
metal temp. raise should be within 20 C/min.)

5.40 Start the dosing pumps and do chemical dosing as per Chemist’s advice. Open CBD as
per the Chemist’s advice.

Main steam line charging:

5.41 Ensure that MS, CRH, HRH line drains and MAL drains open (turbine side) and system
is ready for operation: turbine is on turning gear and stop /control valves are closed.

5.42 Ensure the readiness of HP/ LP bypass system.

5.43 When drum pressure reaches about 4 kg/cm2 start charging main steam line by gradually
opening the bypass (warm up) valves of Boiler stop valves on both sides. Ensure that the
main valves are not in Auto. In auto the valves gets open command when the bypass
valves are full open).

5.44 Open the boiler stop valve and monitor the pressure rise of MS line after opening bypass
valves to full. Open HP bypass warm-up valves to warm up the CRH lines. Observe for
any abnormally (like hammering etc.) in the system.

5.45 Open HP bypass valves partially and ensure that the pr. Control valves, spray valves and
the protection system are working properly.

5.46 Monitor the pressure rise in the boiler. When the pressure exceeds 5 kg/cm2, and after
opening boiler stop valves, regulate HP bypass valves to control the pressure and close
start-up vents. Close HP bypass worm up valves.

5.47 Open LP bypass valves and keep it partially open at lower pressures. When the pressure
improves control the LP bypass valves opening so as to maintain a pr of about 12 kg/cm2
in the HRH.
TURBINE ROLLING & SYNCHRONIZING :

5.48 Raise the boiler parameters (by controlling the firing rate) as per the requirements of
turbine by following the allowable ramp rate.

5.48 Refer X-1, X-2 & X-3 curves and at around a main steam pressure of 15 kg/cm2 and
HRH pressure of 8-12 kg/cm2 reset the turbine and open turbine stop valves. Observe for
any raise in speed.(Use SGC Turbine programme for turbine start up)

5.49 Refer X-4, X-5 curves and roll the turbine to 600rpm and monitor turbine parameters.

5.50 Refer X-6 curve and at around 35 kg/cm2 MS pressure, 12kg/cm2 HRH pressure and

3200 C MS/HRH temp. roll the turbine through ATRS up to 3000 rpm.

5.51 At 3000 rpm carry out all tests as per recommissioning checklist (speed cross checking.
ATT of protective devices, Electrical testing etc.).

5.52 After successfully completion of all tests normalize any bypassing, earthing etc. carried
out for testing.

5.53 After getting the required clearances and ensuring that turbine parameters and margins
are normal (Refer X-7 curve), synchronize the machine, preferably through auto
synchronizer.

5.54 After taking block load ,close HP/LP Bypass and Keep them in auto with proper pressure
set point.

5.55 Close MS, CRH, HRH and drains, Ensure closing of MAL drains in auto.

5.56 Take LPH’s-1, 2 & 3 into service.

5.57 Before the feed water flow to the boiler reaches the capacity of the low load line, one of
the high capacity lines should be placed in service.

5.58 Economizer recirculation valves should be closed after establishing a constant feed water
flow.

COAL FIRING:

5.59 Ensure that both ID /FD fans are in service and equally loaded. Furnace draft control is
put in auto

5.60 Start the first PA fan and ensure opening of its discharge damper.
5.61 Start the second PA fan .Ensure opening of its discharge damper .Load both the fans
gradually and raise the P.A header pressure to normal value. (PA fans should not be run
without air flow for long duration).

5.62 Ensure that one of the seal air fans starts auto. If not Keep it in service Keep the other fan
as standby.

5.63 Start the first mill (preferably bottom elevation) and keep it in service. Increase the
loading gradually.

5.64 Keep the other mills in service as per the load requirement.

5.65 Gradually raise the steam parameters and unit load as per the start-up curves by observing
TSE margins.

Notes: Controlling of firing rte and parameter rising shall be as per the integrated start up curves.
This may be monitored through DAS/DDC MIS.
Complete startup records shall be maintained for each and every startup.

210 MW UNITS

START-UP PROCEDURES

TG AND AUXILIARIES START – UP:

The following steps describe the sequential start –up of turbine auxiliaries and then Rolling and
Synchronizing of turbine and generator.

Initial condition : All equipments are in stopped condition : TG is standstill.

NOTE: Before charging a system or starting equipment ,necessary clearances should be


obtained.

1.0 START _UP OF TURBINE AUXILIARIES;

Condenser & Circuiting Water system:

1.1 Before starting the CW system ensure that the condenser water box is properly vented
and fully charged.
1.2 After informing the running unit, open the CW inlet and outlet valves of one pass and
Start one CW pump. Ensure CW flow .

1.3 The second CW pass can be charged after boiler light up, before charging LP Bypass.

2.0 CLCW SYSTEM;

2.1 After charging the CW system charge CLCW pumps by opening suction valves and
pump vents (Drain before NRV is to be closed)

-SCW system –Stage I.


-CLCW Pump –Stage II
-ACW Pump –Stage III

2.2 Open the vents of duplex strainers and PHE inlet /outlet lines and close header drain
and duplex strainer / PHE drains. Charge the system upto PHEs by opening ClCW
recirculation valve.

2.3 Charge PHE after proper venting. Line up one set of duplex strainers and one PHE fully.

2.4 Start one CLCW pump. Close CLCW recirculation valve.

2.5 After charging the second PHE, start the second CLCW pump. Charge the second set of
duplex strainer

2.6 Put the third in auto after checking its availability.

3.0 ECW SYSTEM;

3.1 After filling the ECW system by gravity, line up the system thro’ one PHE, for which
CLCW is already charged.

3.2 As the ECW header pr. is controlled by the lines charged, open only
Turbine side or boiler side lines before starting the pump.

3.3 Start one ECW pump. Charge the second PHE and keep the valves partially open.

3.4 Start the second ECW pump and gradually charge the second PHE fully. Open all lines to
boiler and turbine auxiliaries .See that the header pressure is ~8.0 Ksc.

3.5 Put the third ECW pump in auto after checking its availability.
4.0 CONDENSATE SYSTEM

4.1 Fill the hot well the normal level, after flushing. Ensure that all hot well drains and CEP
Header drains are closed.

4.2 Charge the CEPs by opening suction valve, recirculation valve and equalising valve – close
suction strainer drain.

4.3 Close the line drains and open the vents near LPH-1, LPH-2, LPH-3 etc. and line –up up to de-
aerator by partially opening the de –aerator level control valve, Keep GSC minimum
recirculation valve partially open

4.4 Start one CEP on recirculation by keeping the discharge valve closed.

4.5 Slowly open the discharge valve and close all vent valves after sufficient venting.

4.6 After fully charging the condensate system, Open the GSC minimum recirculation valve to
full, to maintain a flow of about 250 tph.

4.7 Open the discharge valve of the 2nd CEP and Keep it in auto.

4.8 Maintain hot well level by controlling the make-up control valve (preferably in auto)

4.9 Maintain de-aerator level at normal value by operating the de-aerator level control valves (If
the level is going high ,LPH-3 outlet valve can be closed temporarily).

5.0 FEED WATER SYSTEM;

5.1 Check for line up of lube oil lines and coolers.

5.2 Ensure that the main pump and booster pump cooling water system lined up properly and
check cooling water pressure. Check for leakages, if, any.

5.3 Line up magnetic filters and mechanical seal cooling water system. Check for leakages, if,
any.

5.4 Check BFP oil level and keep AOP in service and check filter DP and lube oil pressure. Check
for leakages, if, any.
5.5 Keep pump drains in close condition and vents in open condition. Charge the BFPs with feed
water by gradually opening suction and recirculation valves

5.6 Close vents after proper venting. Check for leakages, if, any.

5.7 Note Booster pump suction pressure and main pump suction pressure

5.8 Close the discharge header drains and HP heater /water box drains. Open the HP heater water
box and loop vents and the vent at feed regulating station.

5.9 Open one BFP discharge valve and charge the system by gravity up to Feed regulating station
by keeping the HP heaters in lineup. Close all the vents after proper venting. Keep BFP
discharge valves closed. Check for leakages, if, any.

5.10 Start one BFP on recirculation. Keep a minimum discharge pressure of 55 ksc. Monitor Feed
water DT across main pump. Open the discharge valve when required.

5.11 Start the second BFP as per load requirement.


6.0 OIL SYSTEM:

6.1 Ensure that MOT level is >NORMAL (>350 mm)

6.2 Start and keep one Vapour Extraction fan in service after ensuring that all the bearing and tank
Vapour lines are through.

6.3 After ensuring that all the oil line drains (including thrust bearing filter drain) are closed
start DCOP and keep it in service for line filling

6.4 Once the lube oil pressure increases more than I Ksc, start one AOP and stop DCOP.

6.5 Ensure that one oil cooler is charged and oil temp. control valve is kept in auto.

.
7.0 SEAL OIL SYSTEM;

7.1 Ensure that seal oil system is lined-up completely.

7.2 Keep one AOP or JOP in service for providing oil system make –up

7.3 Start DCSOP and Keep it in service for system filling.

7.4 After achieving sufficient pr. and seeing that no leakage is present, start one SOP and stop
DCSOP.

7.5 Start seal oil vacuum pump and maintain vacuum in seal oil tank.

7.6 Keep the other SOP and DCSOP in auto.

7.7 After H2 purging and pressurizing upto 1.8 ksc, ensure that seal oil to H2 DP and other
readings are in order.

7.8 Start one bearing chamber exhaust blower and keep it in service.

7.9 Keep the H2 temp. control under observation.

7.10 Keep H2drier in service.

8.0 JACKING OIL SYSTEM:

8.1 Start DCJOP and check for any leakages. See that the header pr. is developing more than
110 ksc.

8.2 Simultaneously give start command to JOP-1 or JOP-2 and switch ‘OFF’ DCJOP.See that
the header pr. is maintaining.

8.3 Keep the other JOPs in auto, by switching on SLC.

8.4 Observe the jacking oil pressure at all bearings and compare with original readings.

9.0 STATOR WATER STSTEM

9.1 After lining up the system start and keep one pump in service. Stator water system is normally
kept in continuous service irrespective of the unit in service or not.

9.2 Keep the second SW pump in auto.

9.3 Ensure that the SW tank level is normal and maintain normal vacuum in Stator water
expansion tank. Check the SW flow through the winding and adjust if necessary.

9.4 Take SW cooler into service after flushing and attaining normal SW conductivity in the SW
cooler drain.
9.5 Keep SW temp. under observation.

10.0 PUTTING THE TURBINE ON TURNING GEAR:

10.1 Ensure that the following pre-requisites for putting the turbine on turning gear
are ensured and the necessary are signed.

(i) All oil pumps commissioned supply made ’ON’ and one pump is kept in service.
(ii) Oil flow thro’ bearing return lines measured and found satisfactory.
(iii) All JOPs are commissioned supply made ’ON’ and one is kept in service. SLC JOPs
is ‘ON’
(iv) Shaft and jacking oil pressures at all bearing checked and found okay.
(v) Vapour lines at all bearing are through and one VEF kept in service.
(vi) Turbine oil fishing (if applicable) completed successfully. All line filters removed
and throttles fixed
(vii) Thrust bearing filter chocking frequency had reduced (to less than once in 4 hours).
(viii) Turning gear valve electrical operation checked (without pump in service ) and SLC
luring gear is available.
(ix) All TSI cleared.
(x) All indicators and recorders for TG are available and made ’ON’.
(xi) Generator seal oil system is fully available and kept in service.
(xii) All works on generator ,exciter bus ducts GTs and UATs completed.
(xiii) GT earth switches are opened.
(xiv) All TSI reading taken at zero speed.
(xv) Switch ‘ON’SGC oil system and give run command .
(xvi) As a result ,Turning gear valve opens and turbine starts turning .
(xvii) Note down TSI reading at turning gear speed.
(xviii) Check for any abnormality like abnormal sound from bearing , seals etc.
(xix) Clean the thrust bearing filter in case of choking .

12.0 VACUUM PULLING:

12.0 Ensure that condenser water box is charged on both sides and sufficient flow is available.

12.2 Ensure that CLCW systems is in service and vacuum pumps coolers are charged from
CLCW and ECW (CLCW system –Stage-II)
(CLCW system –Stage-III) SCW system –Stag-I)

12.3 Ensure that condensate system is in service and minimum flow of 300 tph is maintained
through GSC.

12.4 Check and close all the drains /vents connected to the vacuum system .

12.7 Charge aux Steam to seals upto the first manual valve after opening the drain to
Atmosphere.

NOTE: Seal steam first isolating valve should be open after starting vacuum pump only as
Steam will be admitted to condenser through warm-up drain on opening this valve.

12.8 Ensure that vacuum pumps are lined up completely and separator tank level is normal.

12.9 After lining up , start one Gland steam blower.


12.10 Start one vacuum pump and open air isolating valve. Close vacuum breaker and Re-heater
vents .(HRH,CRH and MS line atmosphere drains are to be closed)

12.11 Open seal steam station first isolating valve and increase the header temp. to 2200C by
opening warm-up drains (in auto)

12.12 Once a vacuum of 0-7 ksc is developed open seal steam control valve and after developing
pressure put the pr. Control in auto.

12.13 Start second vacuum pump.

12.14 Check for any air ingress through points like HP/LP heater shall drains etc.

12.15 Switch ‘ON’SGC evacuation and give ‘RUN’ command .If sufficient vacuum is developed
second pump will stop in auto.

13.0 TURBINE ROLLING:

Refer to SGC turbine

You might also like