Professional Documents
Culture Documents
D Boile drains/vents
1.Boiler ring header drains closed
2.Boiler Superheater drains opened
3.Drum vents/Superheater vents /Startup ventopened
4.MS line drains /CRH/HRH line drains on Boiler side opened
E Gas path
G Aux PRDS
1.Header pressure and temperature:
(Aux PRDS charged from station header)
2.Scaph line ,Atomising line,oil gun Tracing lines,APH sootblowing line are charged
H Oil guns
1.Guns cleaned and clamped & lined up
2.Tracing steam availablev & Steam traps lined up.
3.Oil trip valve close & short recirculation opened
4.Atomising steam charged & controller in auto
5.Atomising steam pressure & temperature :
5.Boiler spring loaded safety valves gags removed & ERV's lined up & in auto
6.All wallblowers & LRSB's in retracted condition
7.Burner front fire water is charged/Deluge valve lined up
8.Drum pr/temp: ksc/ ⁰ C.
9.Feedwater temp at Economiser inlet: ⁰ C.
L Milling system
1.All mills PTW cancelled & lined up
2.Mill reject system lined up
3.Mill lube oil systems& grease systems are in service & standby pumps are
available
4.Seal air fans lined up& supply on
5.RC feeders supplies on & lined up
6.Bunker gates& feeders gates open
7.Bunker levels:
M APH
1.APH A/B inservice & all dampers in open condition
2.APH A/B Lube oil system in service
3.APH A/B air motors lined up & air pressure:
4.Soot blowres supply on& steam lined up
5.Fire water charged up to last valve
6.All manhole doors closed
7.Guide& support bearing area clean
8.Oil carry over probes put in place & cooling water charged
9.APH fire detection system inservice & values normal
N Dearator
1.Dearator level:
2.Dearator pr: ksc.
3.Dearator temp: ⁰ C.
4.Dearator pr controller in auto
5.Dearator pegging control valve position: %.
6.Dearator level controllers both lined up (stage II/III)
O Condesate system
1.Condenser charged from CW side
2.Hotwell level normal & make up lined up
3.CEP in service & on recirculation
4.Standby CEP on auto (SLC ON )
5.LPH's lined up on condensate side & drip/vent side
6.CST lined up
P Feedwater system
1.BFP's lined up & one BFP in service
2.HPH's linedup on feed water side/drip side
Q TURBINE
1.MOT level: & level normal (+/- 20 mm on barring)
2.MOT vapour fan in service
3.MOT Centrifuge in service
15.Extraction NRV's (A2, A3, A4, A5) and CRH line NRV's L/R are closed.
16.Turbine Stop valves Test Valve in open condition
17.All mal drains open& isolating valves open as checked physically
& SLC ON
18.All MS /CRH/HRH strainer draines /line drains open & their isolating valves
open condition
19.Strainer drains line upto UFT
20.All extraction drains open (including isolating valves)
P Generator
1.GRP all relays reset
2.GT line&bus isolator closed
3.Generator and field breakers are in RESET condition and Generator /Field
breakers tripped" & "Generator trip relay operated" alarms are reset.
3.GT marshalling box supply on& cooler suuply on (both sources)
4.Generator coolers & excitor coolers charged from water side
5.Generator H2 pressure: (stageI: 3.3 ksc & stage II&III:1.80 KSC)
6.Generator H2 purity: (should be 98%)
7.Generator stator water flow&conductivity: m³/hr & mho
8.Stator water standby pump supply on & in auto
9.LLD position: (no alarm in UCB & LLD clear at local)
10.H2 Drier on&lined up:
11.All Switch gear charged from normal I/C
T HP/LP Bypass
1.HP Bypass oil supply unit in service
2.HP Bypass spray manual valve closed &to be opened at HP Bypass down stream
temp of 250 ⁰ C.
3.HP Bypass warm lines open
4.LP Bypass governing system charged
5.LP Bypass injection v/v's manual isolating valve open
6.LPT exhaaust spray line isolating v/v open
U Vacuum pulling
a.Puto seal steam header drain/before seal steam controller drain in auto.
b.Open seal steam supply line manual drain .
c.Keep GSC blower in service.
d.Ensure close position of AS 51 &AS 51A & open their isolating valves
e.Open seal steam supply line isolating valve from PRDS (also open AS17 in ST#1 ,
AS 09 in ST#2 & st#3) f.seal sream temp before seal staem pr control v/v is ~
250 ⁰ C.
f.Start vac p/p OR take starting ejector into service.
g.At a vacuum of -0.7 ksc ,charge seal steam into seal steam header by opening
AS51 Valve
h.Maintain seal steam header pr ~ 100 mmof wc./temp of ~ 250 ⁰ C. & obseve
for improvement in vacuum)
i. vacuum:
After BLU Status
(write data
or tick) Remarks
1.Oil flme condition at local
(Preferably CD guns for Hot startup & AB for cold& warm startup)
2.Oil flame intensity :1/2/3/4:
28.raise speed reference to 600 rpm and observe speed raising to 600 rpm
a.keep watch on
TG brg vibns:1/2/3/4/5/6/7
TG Shaft vibrns:1/2/3/4:
Overall exp:HP/IP:
Diff expn:HPT/IPT/LPT:
brg temp:1/2/3/4/5/6/7:
TSE margin:
HPC/IPC DT
29.Soak turbine at 600 rpm until margins improve
30.steam parameters for rolling to 3000 rpm. (from X6 curve)
MS pr/temp: 33 ksc/300 ⁰ C (st#1) & 45ksc /350 ⁰C (st#2/3)
b.MS temp depending on HP Casing (50%) temp
Say for a HP Caing(50%) metal temp of 300 ⁰ C ,required max MS temp before
HPSV is 400 ⁰ C .
c.lube oil temp :43 to 45 ⁰ C & temp controller in auto
d.lube oil pr > 3.0ksc
e.H2 pr:3.3 (st#1) ,1.8 (st#2/3)
31.raise speed reference to 3000 rpm and observe speed raising to 3000 rpm
a.keep watch on
TG brg vibns:1/2/3/4/5/6/7
TG Shaft vibrns:1/2/3/4:
Overall exp:HP/IP:
Diff expn:HPT/IPT/LPT:
brg temp:1/2/3/4/5/6/7:
TSE margin:
HPC/IPC DT
32.Line and bus isolators closed
33.Soak until until margins improve & steam parameters as specified by turbine
startup curve X 7
a.keep watch on
TG brg vibns:1/2/3/4/5/6/7
TG Shaft vibrns:1/2/3/4:
Overall exp:HP/IP:
Diff expn:HPT/IPT/LPT:
brg temp:1/2/3/4/5/6/7:
TSE margin:
HPC/IPC DT
34.MOP discharge pr. is adequate after transfer of load from AOP to MOP
35.AOP cut out at speed >2800 rpm.
36.Lub oil, seal oil, temperatures are within limit
(45 0C, 40 0C).
37.S.W., Cold gas, Exciter air temp. are within limit (~ 40, 36, 55) 0C
38.Ensure before closing the field breaker ,Generator excitation control is on
remote
39.Close field breaker
Field voltage
40.G.T. fans and oil pumps are running.
41.Oil in generator LLD and alarm healthiness to be confirmed.
42.H2 driers are in service.
43.Turbine lub oil, filters DP High / Not High
44.Steps bypassed during rolling.
45.Put synchroniser in check mode & make on auto synchroniser
46.After syncronisation load raise by speed reference upto 4o MW.
(EHC in speed control mode.)
47.close HP bypass
close LPbypass
48.Close MS/HRH/CRH line/strainer drains
put MAL drains in auto
After Synchronisation Status
(write data
or tick) Remarks
1.raise load as per DC/Check MVAR,Gen volts
2.take EHC on load control
3.charge LPH1,2,3 on staem side after ensuring Extraction drains in open
condition
4.Charge dea extraction
(pegging v/v in auto)
6.attemperation lined up
a.attemperation need not be given until BLI is 120 TPH
b. later to be controlled as per start up curve temp
c.or as per steam temperatures allowed as per TSE upper margin)
7.start 2nd mill
8.start 2nd PA Fan
take 2nd PA Fan & load (balancing to be done st#2/3)
9.CBD position:
silca