Professional Documents
Culture Documents
Document No.
CHECK LIST For Cold Startup che
S No.
1
S No.
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
42
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
Boiler Light up
activity
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
Turbine
Rolling
Activities
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
Prepared By
NANDHALAL B
SEPC POWER PRIVATE LIMITED
Description
Ensure Station bus supply is available and unit board power supply is in charge condition
Ensure power supply is available to the aux system required for boiler light up.
Ensure all peep hole and manholes of boiler are closed & manholes (55 m floor & 11 m floor)
cooling line opened.
Ensure HP LP heater vent line is isolated and Normal and emergency drip line MIV opened and
lined up condition.
Ensure CBD and EBD lines all manual valves are in open conditions.
Both APH-A & APH-B are in service & Air motor trial taken.
All ESP hopper heaters, CERM and EERM are running in auto mode.
Ensure Bottom ash hoppers & fly ash system is ready and lined up.
Ensure Seal trough, bottom ash hoppers are filled up and refractory cooling water line is also
lined up.
All ID Fans, FD Fans & PA Fans & its LOPs are lined up and ready to start.
Ensure VFD room AC system, reactor air washer units are in service.
SCAPH is through for FD and PA, and drains are lined up to IBD tank.
Ensure blade pitch operation for fans are ok and connecting links are ok.
Ensure all SH and RH and APRDS spray lines are lined-up condition.
Ensure APH oil carry probe is working and is in inserted condition and cooling water is charged.
Ensure all sample lines MIVs are opened and sample cooler is charged from SGECW.
Ensure all boiler expansion indicator are available, format of expansion measurement is
available.
Ensure two SACW pumps are in service with two cells of aux CT fan in service.
Ensure CT make up line is charged either through gravity or at least one CT make up pump is
running.
Ensure either fire hydrant water pump running or fire booster pump trial taken and movable fire
tender is available at site.
Ensure both DM storage tanks are filled up with 10mtr of DM water and at least 2 streams are
available.
Ensure CHP, AHP, DM plant and Fire & safety department is duly informed about boiler light up.
Ensure LDO &HFO tank level is ok and at least one LDO/HFO pump is running for maintain 20-
25 kg/cm2 header pressure and short re circulation CV is in Auto.
Ensure two instrument air compressor with respective drier and one service air compressor
should be running and line should be charged in TG side & Boiler side with pressure more than
6.5 kg/cm2
Confirm from AHP for ESP evacuation system has been lined up for evacuation.
Ensure CHP has been informed for making conveyors stream ready for bunker feeding.
Ensure at least 2 TG ECW is running and at least 2 PHE is charged with ACW system.
Ensure at least 1 SG ECW is running and at least 1 PHE is charged with ACW system.
Ensure all MOT, TDBFPA&B , Seal Oil Vacuum tank, HPCF, HPBP, LPBP oil tank levels should
be normal.
Ensure Turbine is on barring gear and DC EOP and DC JOP trial taken and its temp CV is in
auto. (Set pt. 50˚C)
Ensure one CEP is running and ensure line up for PRDS, LP exhaust hood spray, LPBP &
Turbine flash tank.(Ensure CV are in auto, check set points)
Ensure Seal oil pump is running and DC seal oil pump trial is already taken.
Ensure hydrogen is filled, its purity (99%) and pressure (>4.5kg/cm2) is OK and its temp CV is
in Auto. (Set point 40˚C)
Both TDBFPs lube oil pumps are running and their respective EOPs trails taken.
Ensure MAL drains are in auto and their manual isolating valve is in open condition. (MAL-
11,26,22,32,31,47,12,27,23,51,52,57,54,55,58,81,65)
Ensure all temp control valves are healthy and are in Auto.
Ensure all spray lines are lined-up condition. (MAC01AA001, MAC02AA001, Manual isolation
valve of HPBP spray line, BD1 and BD-2, BPE-1, BPE-2)
Ensure chemical dosing system is ready.( Ensure chemicals are available, mixing tanks are
filled, power supply for local panel and pumps, agitator motors are available, dozing line valves
for D/A, condensate and drum are open.)
Ensure Excitation system is ready and all GRP relays are reset.
Ensure deaerator level is normal (+400mm) and its drain to flash tank is in close condition.
Ensure One ID and FD fan is running with airflow 750T/h and furnace draft -10 mmwc.
After HFO temperature rises >120 deg C, charge HFO to boiler gradually and put in long
recirculation.
Check temp in FG is raising, BCWP cavity temp & Drum metal temp starting increasing
Check drum metal temperature difference for TOP & Bottom should not exceed more than 50˚C
Ensure temp rise in metal temp of SH/RH is not more than 1 to 2˚C per min.
At drum pressure reaches 2 kg/cm2 than close all drum vents after ensuring sufficient steam
flow from local.
At drum pressure 5 kg/cm2, close all the SH vents and drains except start-up vent.
Charge the MS line by opening MSV-3, MSV-4, and MSV-5 & MSV-6 at MS Pressure of 5-10 kg
/cm2
Charge MS line by opening MSV-1 & MSV-2 by ensuring both sides pressures equal.
Take HFO guns in CD elevation (Flue gas temperature before platen above 100 ˚C).
Open LP and HP bypass around 10%. Ensure their respective warm-up lines are already open.
Ensure the CRH and HRH drains open from local
Ensure chemical parameters for MS before rolling (Silica < 40ppb) and drum are ok.
Ensure Temp curves X1 & X2 are satisfied for opening ESV during HP/LP Bypass running.
Bring starting device to zero position this will cause generation of trip oil, check trip oil pressure
and Start up Oil pressure around 8 kg/cm2.
Raise the Starting device position to approx 27-30% & ensure start up oil pressure zero and
check HP/IP turbine Stop valve is full opened. Same ensure from local.
Raise starting device position to 55% and ensure CRH NRV open & not open status in EHG
console.
Ensure lube oil temp and control oil temp controls are in AUTO and set point is 50˚C.
Put “360” rpm in rpm ref in EHTC page and check that turbine speed is rising. DN/DT is ok.
Check that TG barring gear is stopped at 240 rpm otherwise stop it manually.
Check all bearing vibration & other turbovisory parameters are within permissible range. If not
trip the turbine and search the cause.
Check drains are operating as per SLC logic. Temp. is in increasing trend.
After APH Secondary air temperature is >180˚C, Start one PA Fan and check Seal air fan start
in auto, Maintain PA header pressure around 800 mmWC and seal air pressure 1200 mmWC.
Line up for one mill (Lowest Elev possible).
Check all mill conditions and keep other mills ready for start.
Start rolling the turbine by giving speed reference to ‘3000 rpm’ and check turbine speed is
rising.
Check all bearing vibration & other turbovisory parameters are within permissible range. If not
trip the turbine and search the cause.
Check turbine oil system, seal oil system, Hydrogen and primary water system for any
abnormality.
If everything ok, Start the running mill feeder and keep running mill on min loading.
Close all the isolator for GEN main breaker and TIE breaker.
Close the field breaker from “Gen & 400KV“ graphics page
Switch ‘ON’ the Excitation system and check voltage building across the generator terminal up
to 21KV.
After Unit synchronisation close slowly HP and LP Bypass and close all line drain valves.
Take out all gun after ensuring intensity and frequency of flame at 350 to 400 MW.
Prepared By
NANDHALAL B
IN; TAMILNADU
Issue No R0
kList Date
ecklist
Name Signature