Professional Documents
Culture Documents
BOILER SIDE
Activity To Be Monitored Remarks
,0. APH dampers for Flue gas and Secondary air are open No
1 APH dampers for Primary air are closed No
12 All four ESP passes I/L and OlL Gates open, ACP in service Fields Yes No
ready to be taken Into service
Firing System Preparation
13 All the manholes and peep holes of the Boiler are closed No
Bumer Tilt Horizontal Yes No
15 Boiler expansion indicating rods are in position No
16 Instrument& Service air pressures are adequate Yes No
17 One LDO/HFO pump is in service and developing sufficient
(18 ksc)
pressure Yes No
2 APH sOO1 blowing is lined up from Service air and trial of both APH soot
No
Dlower taken
A vailaple mlls teeders are
kept normaized electrically and mechanically No
All Mills Burner knife gates are open
No
24 AIl Mills LP pumps/heaters are in running condition
Boiler Firng floor deluge is in charged condition
No
AHP preparation.
26. Fly ash evacuation system ready. Clearance from AHP available
27 Bottom Ash Hopper is filled and Seal YesNo
Main Boiler Preparation
trough is charged Yes No
A) If drum
pressure is less than 2 kg/cm2 before
28 Ensure SH header drain valves and master light up
drain valve are open. No
SH/RH/Drum manual vent valves are
SH Stat Up vents open YesNo
(S30/3 1) are open
1. Boiler shutoff valves
MS-1,2,3,4,5,6 are closed. Yes No
32. MS lines motonized and
their manual drain valves Yes No
(to UFT) upstream
HPBP at 8.5 mtr are
open ( BP-6/BP-8)
of YesNo
33. HPBP warm up line valve are
B) If drum pressure is >2 closed(BP-3/BP-4)
kg/cm2
4. SH startup vents open Condenser vacuum available for
or
HP/LP bypass system
Immediately after light up vents
charging Yes No
35. Boiler filled up to nommal drum
36. Economizer Recirculation valve
level
37 SHRH spray manual valves closed (E17)
open Yes No
esNo
38 MS. BD. SS, FW and
HRH sampling lines are
normalized. YesNo
39 CBD manual valves at
Firing floor and 3.5 mtr are kept Yes No
40. BD manual valve at 3.5 open
mtr is No
41. CBD/IBD and EBD motorized open No
valves are normalized and
(B62,63.66,77,78) available Yes No
42. Manual valves of Boiler side
drains of MS
(101/104) are
43 Manual Valves of MS/HRH
open.
Yes No
strainer drains to UFT are
HRH 101/102) open. (MS 105/106
44. Ensure HP YesNo
Bypass spray manual valve is
45. All
available ERVs manual kept closed.
46. APH-oil isolating valves are in open Yes No
caryover probe is condition
end air side kept after cleaning/Lights are glowing in cold Y9sNo
YesNo
TGSIDE
76. One AC SOP in service and 2nd ACSOP/ DC SOP in auto. DC SOP trial Kes No
taken. SOT Vacuum pump are available in Auto.
77. Seal oil Parameters are ok yes No
80. Gen casing H2, pressure 3.3 kg/cm and purity 99% Ys No
81. H2 Driers are in service. No
82. Sufficient H2 and CO2 cylinders are available in stock No
83. Generator LLD are clear. Yes No
Rolling preparation
84 Turbine governing HPSU system taken into service and running nomal. Ye[ No
84.
85 On EHTC Mimic Yes No
Yes No
Speed controller is active
TSE influence and Load
gradient are in service.
Load controller ON
86. All MAL drain and
MS/CRH/HRH line drains to HP Flash tank manual Yes No
valves are open
87. No "MCC disturbance" in MAL
valves, MS/HRH strainer drain valves, Yes No
CRH NRV drain valve, HP/LP
bypass warm-up drain valves
Electrical Side Preparation
89 Both 6.6 kv buses charged from Station bus.
90. UAT breakers racked in and available and Yes No
in remoteput Yes No
91. Supply to all the
HTLT SWGR available. All Switchgears Charged
Independently Yes No
92. Excitation supplies are on
93.
Main/Stand-by DG breaker in
Emergency
Yes No
switchgear are available Yes No
94 GT/ST/UAT A/B deluge are charged
95. Written clearance from Yes No
No
BMDITMDIAHM/C&1/EM in communication register
96. A.C System for C/R, AVR &
thyristor room & ESP controller rooms. O.K Yes No
97. HPBP oil pump and Oil Pressure are Ok.
LYesNo
BOILER LIGHTED UP
Activity To Be Monitored
L. Drum Vents and SH manual Vents closed at 2 ksc Remarks
and 3 ksc Ves No
Check Operation of HP/LP
bypass before charging MS line
3. APH Soot blowing is in |Yes No
MS line charged
progress
at 5 ksc No
No
PRDS is charged.
. Seal steam manual valve at PRDS is Yes No
opened and seal steam inlet temp
is raised to > 210
deg
7. Seal Steam is charged and vacuum
pulling is done
Yes No
8. HP/LP Bypass is charged.
9. Start Up Vent ($30/31) and SH Header Drains
closed
10. Check Turbine 1st stage
pressure and if it is in
Yes No
Activity To Be Monitored
Remarks
Air and Flue gas outlet
temperature of APH s are normal No
Drum metal temperature Top/ Bottom are OK. No
3 Seal steam pressure controller in auto and
supply temperature >210°C No
4 Vacuum Pulling is completed and monitor condenser vacuum.
. No change in turbine speed after charging HP/LP bypass No
6. Check - Load reference should be at 25 MW
Yes No
7. PR-Max (load limiter) at 50MW No
S. CBD is kept open No
Yes
9. Check Hotwell, Deaerator, Drum level, DM O/H tank HFO/LDOtank
levels
Yes No
closed
START UP PARAMETERS
added.
The list is indicative and additional parameters if required may be
ACTIVITY TIME
SL.NO
Boiler Light up
0 1 5hrv
Boiler Coal Firing
HP-LP ByPass Charging c3 uohr
Soaking at N1 Speed 2uShT
4.
Barring Speed-rpm
Turbine Axial shift
5. LP Turbine Diff. Expansion 1. 6 3 2
HP Turbine Casing Temp.
IP Turbine Casing Temp. S'C
8. HP Turbine Shaft Temp. 390
9. IP Turbine Shaft Temp. 245° 255 270°C
10. MOT/EHA HPSU/LPBP HPSU
level
PARAMETERS AFTER BOILER LIGHT UP
HP/LP BY PASS CHARGING
PARAMETERS BEFORE BOILER LIGHT UP
SL.NO
PARAMETER ' Doh TIME
1. Boiler Drum Metal
temp.-°C
(t1,t2,t3,t4 etc-after half an hour interval) |2 2e 256L
2. SH Metal temp.- °C
(t1,t2,t3,t4 etc-after half an hour interval)
3. RH Metal temp.-°C
(t1,t2,t3,t4 etc-after half an hour interval) u SC
4. Boiler Steam Prl.
etc-after half an Kg/cm2,(p1.p2,pt3,p4
hour interval)
Boiler Silica (ppm)
6. Main Steam Pressure 35
7. Main Steam Temp. 52-uC
8. HRH Steam Pr. S 2
HRH Steam Temp.
10. 3 DC
Condenser Vacuum(abs.)
11. Steam silica
S.N.
PARAMETERS AFTER TURBINE
After Turbine After Turbine
ROLLING
Rollinglspeed N1) Rollinglspeed N2)
Soaking duration (Min)
Turbine Axial shift 35Ln
LP Turbine Diff. Expansion
HP Turbine Casing (6 6 hk
Temp
IP Turbine Casing
Temp.
2us
HP Turbine Shaft Temp. 2100 2e C
IP Turbine STC
Shaft Temp. 2 e 26 0
S. Max TG bearing Temp.
Max TG bearing Vibration
10. Max HOT gas/Cold Gas temp/Seal oil
temp
to'
11 Generator casing H2 Pressure
12 MOT/EHA HPSUILPBP HPSU Ilevel t 1132m 131//uo