FUNNEL DECK PORT SIDE STEEL RENEWALFOR FPSO KIKEH - ADDITIONAL SCOPE

CONTRACT REFERENCE: SO 10590-20 (FUNNEL DECK PORT SIDE STEEL RENEWAL FOR FPSO KIKEH) LOCATION : FPSO KIKEH

PROGRESS DETAIL
DAYS
NO TASK DESCRIPTION PLANNING DATE ACTUAL DATE PROGRESS REMARKS
PLAN
Weightage Actual
A FUNNEL DECK PORT SIDE STEEL RENEWAL FOR FPSO KIKEH 1.000 35.51%
ADDITIONAL SCOPE
1 BULKHEAD HOR GIRDER FAN #3 - LOOKING PORT & AFT 0.131 0.00%
Scaffolding Erection for Working Platform 3 days 0.012
Preparation for Hot Work Task (Cover area with canvas) 1 days 0.004
Set-up for rigging activities 2 days 0.008
Cutting and Removal Bulkhead Plate 3 days 0.012
Transfer Scrap Material From Working area 2 days 0.008
Preparation area for fit-up new plate 2 days 0.008
Transfer Fabrication Material to No.2 Hor Girder Area 2 days 0.008
Preparation Fabrication Material For Installation 2 days 0.008
Fit-up New Angle Bar & Plate 3 days 0.012
ABS Fit-up Inspection 1 days 0.004
Welding New Angle Bar & Plate 7 days 0.029
Welding Inspection & NDT 1 days 0.004
Touch up Painting 3 days 0.012
2 BULKHEAD AT HOR GIRDER FAN #3 - LOOKING STBD 0.110 88.89%
Scaffolding Erection for Working Platform 2 days TBA TBA TBA TBA 0.008 100.00%
Preparation for Hot Work Task (Cover area with canvas) 1 days TBA TBA TBA TBA 0.004 100.00%
Set-up for rigging activities 2 days TBA TBA TBA TBA 0.008 100.00%
Cutting and Removal Bulkhead Plate 3 days TBA TBA TBA TBA 0.012 100.00%
Transfer Scrap Material From Working area 2 days TBA TBA TBA TBA 0.008 100.00%
Preparation area for fit-up new plate 2 days TBA TBA TBA TBA 0.008 100.00%
Transfer Fabrication Material to No.2 Hor Girder Area 2 days TBA TBA TBA TBA 0.008 100.00%
Preparation Fabrication Material For Installation 2 days TBA TBA TBA TBA 0.008 100.00%
Fit-up New Angle Bar & Plate 3 days TBA TBA TBA TBA 0.012 100.00%
ABS Fit-up Inspection 1 days TBA TBA TBA TBA 0.004 100.00%
Welding New Angle Bar & Plate 3 days TBA TBA TBA TBA 0.012 100.00%
Welding Inspection & NDT 1 days TBA TBA TBA TBA 0.004 100.00%
Touch up Painting 3 days 0.012
3 BULKHEAD HOR GIRDER FAN #1 - LOOKING FWD 0.114 0.00%
Scaffolding Erection for Working Platform 2 days 0.008
Preparation for Hot Work Task (Cover area with canvas) 1 days 0.004
Set-up for rigging activities 2 days 0.008
Cutting and Removal Bulkhead Plate 3 days 0.012
Transfer Scrap Material From Working area 2 days 0.008
Preparation area for fit-up new plate 2 days 0.008
Transfer Fabrication Material to No.2 Hor Girder Area 2 days 0.008
Preparation Fabrication Material For Installation 2 days 0.008
Fit-up New Angle Bar & Plate 4 days 0.016
ABS Fit-up Inspection 1 days 0.004
Welding New Angle Bar & Plate 3 days 0.012
Welding Inspection & NDT 1 days 0.004
Touch up Painting 3 days 0.012
4 BULKHEAD AT HOR GIRDER FAN #1 - LOOKING STBD 0.110 0.00%
Scaffolding Erection for Working Platform 2 days 0.008
Preparation for Hot Work Task (Cover area with canvas) 1 days 0.004
Set-up for rigging activities 2 days 0.008
Cutting and Removal Bulkhead Plate 3 days 0.012
Transfer Scrap Material From Working area 2 days 0.008
Preparation area for fit-up new plate 2 days 0.008
Transfer Fabrication Material to No.2 Hor Girder Area 2 days 0.008
Preparation Fabrication Material For Installation 2 days 0.008
Fit-up New Angle Bar & Plate 4 days 0.016
ABS Fit-up Inspection 1 days 0.004
Welding New Angle Bar & Plate 3 days 0.012
Welding Inspection & NDT 1 days 0.004
Touch up Painting 2 days 0.008
5 FABRICATION & INSTALLATION FAN #1 FLAPPER ON FAN UNIT TBA TBA TBA TBA 0.045 100.00%
Site Preparation / Hot Work task preparation 1 days TBA TBA TBA TBA 0.004 100.00%
Fabrication Fan #1 flapper 3 days TBA TBA TBA TBA 0.012 100.00%
Welding Inspection & NDT 1 days TBA TBA TBA TBA 0.004 100.00%
Touch up Painting at No.2 Hor Girder Area 2 days TBA TBA TBA TBA 0.008 100.00%
Set-up for rigging activities 2 days TBA TBA TBA TBA 0.008 100.00%
Installation Fan #1 flapper with bearing at fan unit #1 2 days TBA TBA TBA TBA 0.008 100.00%
6 FABRICATION & INSTALLATION FAN #3 FLAPPER ON FAN UNIT TBA TBA TBA TBA 0.045 100.00%
Site Preparation / Hot Work task preparation 1 days TBA TBA TBA TBA 0.004 100.00%
Fabrication Fan #3 flapper 3 days TBA TBA TBA TBA 0.012 100.00%
Welding Inspection & NDT 1 days TBA TBA TBA TBA 0.004 100.00%
Touch up Painting at No.2 Hor Girder Area 2 days TBA TBA TBA TBA 0.008 100.00%
Set-up for rigging activities 2 days TBA TBA TBA TBA 0.008 100.00%
Installation Fan #3 flapper with bearing at fan unit #3 2 days TBA TBA TBA TBA 0.008 100.00%
7 INSTALLATION CONE INTAKE DAMPER FOR FAN #1 AT HOR GIRDER 0.057 0.00%
Preparation for Hot Work Task (Cover area with canvas) 1 days 0.004
Set-up for rigging activities 2 days 0.008
Transfer new Air Intake Cone Fan #1 to Hor Girder area 2 days 0.008
Welding Air Intake Cone Fan#1 at No.2 Hor Girder 4 days 0.016
Welding Inspection & NDT 1 days 0.004
Touch up Painting at No.2 Hor Girder Area 2 days 0.008
Dismantling Scaffolding at Horizontal Girder 2 days 0.008
8 INSTALLATION CONE INTAKE DAMPER FOR FAN #3 AT HOR GIRDER 0.057 0.00%
Preparation for Hot Work Task (Cover area with canvas) 1 days 0.004
Set-up for rigging activities 2 days 0.008
Transfer new Air Intake Cone Fan #3 to Hor Girder area 2 days 0.008
Welding Air Intake Cone Fan#3 at No.2 Hor Girder 4 days 0.016
Welding Inspection & NDT 2 days 0.004
Touch up Painting at No.2 Hor Girder Area 3 days 0.008
Dismantling Scaffolding at Horizontal Girder 2 days 0.008
9 ADDITIONAL AREA TO CROP & REPLACE AT TRUNKING BOX FAN #3 TBA TBA TBA TBA 0.094 100.00%
Scaffolding Erection for Working Platform 2 days TBA TBA TBA TBA 0.008 100.00%
Preparation for Hot Work Task (Cover area with canvas) 1 days TBA TBA TBA TBA 0.004 100.00%
Set-up for rigging activities 2 days TBA TBA TBA TBA 0.008 100.00%
Cutting and Removal plate/strcutural at corroded area 3 days TBA TBA TBA TBA 0.012 100.00%
Transfer Scrap Material From Working area 1 days TBA TBA TBA TBA 0.004 100.00%
Preparation area for fit-up new plate 1 days TBA TBA TBA TBA 0.004 100.00%
Transfer Fabrication Material to trunking box area 2 days TBA TBA TBA TBA 0.008 100.00%
Preparation Fabrication Material For Installation 2 days TBA TBA TBA TBA 0.008 100.00%
Fit-up New Angle Bar & Plate 2 days TBA TBA TBA TBA 0.008 100.00%
ABS Fit-up Inspection 1 days TBA TBA TBA TBA 0.004 100.00%
Welding New Angle Bar & Plate 3 days TBA TBA TBA TBA 0.012 100.00%
Welding Inspection & NDT 1 days TBA TBA TBA TBA 0.004 100.00%
Touch up Painting 2 days TBA TBA TBA TBA 0.008 100.00%
10 INSTALLATION FAN UNIT FOR FAN #1 TBA TBA TBA TBA 0.037 100.00%
Site Preparation / Set-up for rigging activities 2 days TBA TBA TBA TBA 0.008 100.00%
Transfer fan unit to Daerator-Hor Girder area 1 days TBA TBA TBA TBA 0.004 100.00%
Installation fan unit on seating & damper fan #1 1 days TBA TBA TBA TBA 0.008 100.00%
Tightening fan unit on seating & damper fan #1 2 days TBA TBA TBA TBA 0.008 100.00%
Touch up Painting 2 days TBA TBA TBA TBA 0.008 100.00%
11 INSTALLATION FAN UNIT FOR FAN #3 TBA TBA TBA TBA 0.037 100.00%
Site Preparation / Set-up for rigging activities 2 days TBA TBA TBA TBA 0.008 100.00%
Transfer fan unit to Daerator-Hor Girder area 1 days TBA TBA TBA TBA 0.004 100.00%
Installation fan unit on seating & damper fan #3 2 days TBA TBA TBA TBA 0.008 100.00%
Tightening fan unit on seating & damper fan #1 2 days TBA TBA TBA TBA 0.008 100.00%
Touch up Painting 2 days TBA TBA TBA TBA 0.008 100.00%
12 DAVIT CRANE INSTALLATION 0.045 0.00%
Preparation for Hot Work Task (Cover area with canvas) 1 days 0.004
Fabricate & welding seating for Davit Crane on lower casing top deck 3 days 0.012
Welding Inspection & NDT 1 days 0.004
Set-up for rigging activities 2 days 0.008
Installation davit crane on seating using bolts & nuts 2 days 0.008
Touch up Painting 2 days 0.008
13 HANDRAIL INSTALLATION 0.033 0.00%
Preparation for Hot Work Task (Cover area with canvas) 1 days 0.004
Transfer Material/Handrails to Lower Casing Top 1 days 0.004
Welding handrails at lower casing top deck 3 days 0.012
Welding Inspection & NDT 1 days 0.004
Touch up Painting 2 days 0.008
14 INSTALLATION CABLE TRAY / E&I SUPPORT 0.041 0.00%
Scaffolding Erection for Working Platform 2 days 0.008
Preparation for Hot Work Task (Cover area with canvas) 1 days 0.004
Welding cable tray support at bulkhead and frame at funnel deck 2 days 0.008
Welding E&I support for smoke detector 2 days 0.008
Welding Inspection & NDT 1 days 0.004
Touch up Painting 2 days 0.008
15 INSTALLATION WIRE MESH AT AIR INTAKE DUCTING 0.016 0.00%
Site Preparation / Clear Working Area 1 days 0.004
Scaffolding Erection for Working Platform 1 days 0.004
Installation wire mesh at air intake ducting Port Side 3 days 0.008
11 HOUSEKEEPING & FINAL TOUCH UP 0.029 0.00%
Final Touch Up & Reinstatement Activities 5 days 0.020
Housekeeping MTEC 2 days 0.008