Row Labels Budget EV

Div_02 134,000.00 134,000.00


Backfilling Under Foundation 54,000.00 54,000.00
Excavation Works 80,000.00 80,000.00
Div_03 2,313,771.00 80,500.00
Concrete Slab Works 459,897.00 0.00
Grade Beams Works 234,127.00 0.00
PC under slab on grade 970,290.00 0.00
Plain Concrete Works 80,500.00 80,500.00
RC Column Necks & Walls 109,020.00 0.00
RC Columns Works 459,897.00 0.00
RC under slab on grade 40.00 0.00
Div_GEN 0.00 0.00
Approval Package - Phase 01 0.00 0.00
Approval Package - Phase 02 0.00 0.00
Approval Package - Phase 03 0.00 0.00
Approval Package - Phase 04 0.00 0.00
Project Finish Date 0.00 0.00
Project Start Date 0.00 0.00
Skeleton Finish Date 0.00 0.00
Skeleton Start Date 0.00 0.00
Submittal Package - Phase 01 0.00 0.00
Submittal Package - Phase 02 0.00 0.00
Submittal Package - Phase 03 0.00 0.00
Submittal Package - Phase 04 0.00 0.00
Grand Total 2,447,771.00 214,500.00
Remaining
0.00
0.00
0.00
2,233,271.00
459,897.00
234,127.00
970,290.00
0.00
109,020.00
459,897.00
40.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2,233,271.00