You are on page 1of 10

CALENDARIO DE AVANCE DE OBRA VALORIZADO ACTUALIZADO A LA FECHA DE INICIO DE OBRA

OBRA : INSTALACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DE LOS PP.JJ. VILLA PROGRESO, MIRAFLORES, LAS VEGAS, SAMAN, SAN FRANCISCO DE ASIS, LA UNION, SAN JUAN DE DIOS Y RAMIRO PRIALE II - CHICLAYO
ENTIDAD : ENTIDAD PRESTADORA DE SERVICIOS DE SANEAMIENTO DE LAMBAYEQUE S.A. - EPSEL S.A.
CONTRATISTA : CONSORCIO PROGRESO
SUPERVISION : CONSORCIO SUPERVISOR ASIS
UBICACIÓN : CHICLAYO - CHICLAYO - LAMBAYEQUE
Duración (Meses)
Item Descripción Parcial (S/.)
Mar-2019 Abr-2019 May-2019 Jun-2019 Jul-2019 Ago-2019 Sep-2019 Oct-2019 Nov-2019 Dic-2019 Ene-2020 Feb-2020 Mar-2020 Abr-2020 May-2020 Jun-2020 Jul-2020 Ago-2020 Sep-2020 Oct-2020
01 CAPTACION BORO I 597,472.38 4,508.28 0.00 0.00 77,484.57 36,989.25 0.00 0.00 0.00 105,869.43 152,620.85 65,000.00 155,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01 EMPALME A ESTRUCTURA EXISTENTE 84,825.19 4,508.28 0.00 0.00 72,110.71 8,206.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.01 CARTEL IDENTIFICACION OBRA 3.60 * 2.40 m 4,508.28 4,508.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.02 INSTALACION Y DESINSTALACION DE EMPEDRADO DE PROTECCIÓN DIQUE 68,385.00 0.00 0.00 0.00 60,178.80 8,206.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.03 DRENAJE DE ZANJAS 2,495.70 0.00 0.00 0.00 2,495.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.04 INSTALACION Y DESINSTALACION DE ANDAMIO DE RIELES MATALICOS TIPO CASTILLO 5,178.75 0.00 0.00 0.00 5,178.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.05 SUMINISTRO E INSTALACION DE COMPUERTA METALICA TIPO ARMCO 1.00 x 1.00 m 3,475.00 0.00 0.00 0.00 3,475.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.06 PERFORACION DE LA PARED DE LA ESTRUCTURA EXISTENTE 533.46 0.00 0.00 0.00 533.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01.07 ENTIBADO ZANJA HASTA 3.00 m 249.00 0.00 0.00 0.00 249.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02 ESTRUCTURA PROYECTADA DE SALIDA BORO I 34,156.91 0.00 0.00 0.00 5,373.86 28,783.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.01 TRABAJOS PRELIMINARES 30.38 0.00 0.00 0.00 30.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.01.01 TRAZO y REPLANTEO 30.38 0.00 0.00 0.00 30.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.02 MOVIMIENTO DE TIERRAS 6,184.58 0.00 0.00 0.00 5,343.48 841.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.02.01 EXCAVACION PARA ESTRUCTURAS 352.08 0.00 0.00 0.00 352.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.02.02 DRENAJE DE ZANJAS 4,991.40 0.00 0.00 0.00 4,991.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.02.03 REFINE, NIVELACION y COMPACTACION ZONA EXCAVADA TNS 94.84 0.00 0.00 0.00 0.00 94.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.02.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 746.26 0.00 0.00 0.00 0.00 746.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.03 OBRAS DE CONCRETO SIMPLE 272.36 0.00 0.00 0.00 0.00 272.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.03.01 SOLADO CONCRETO f'c =100 Kg/cm² , e=0.10m 272.36 0.00 0.00 0.00 0.00 272.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.04 OBRAS DE CONCRETO ARMADO 18,951.78 0.00 0.00 0.00 0.00 18,951.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.04.01 CONCRETO f'c = 280 Kg/cm² p/ESTRUCTURA PROYECTADA SALIDA BORO I 6,678.97 0.00 0.00 0.00 0.00 6,678.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.04.02 ENCOFRADO y DESENCOFRADO p/ESTRUCTURA PROYECTADA SALIDA BORO I 3,834.51 0.00 0.00 0.00 0.00 3,834.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 8,438.30 0.00 0.00 0.00 0.00 8,438.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.05 REVOQUES y ENLUCIDOS 1,767.81 0.00 0.00 0.00 0.00 1,767.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.05.01 REVESTIMIENTO c/IMPERMEABILIZANTE p/LOSA FONDO 221.21 0.00 0.00 0.00 0.00 221.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.05.02 REVESTIMIENTO c/IMPERMEABILIZANTE p/MURO de ESTRUCTURAS 1,546.60 0.00 0.00 0.00 0.00 1,546.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.06 CARPINTERIA METALICA 6,950.00 0.00 0.00 0.00 0.00 6,950.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.06.01 SUMINISTRO E INSTALACION DE COMPUERTA METALICA TIPO ARMCO 1.00 x 1.00 m 6,950.00 0.00 0.00 0.00 0.00 6,950.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.03 CONEXIONES DE TELEMETRIA EN LA CAPTACION DE BORO I, BORO II Y ESTACION DE PURGA 478,490.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 105,869.43 152,620.85 65,000.00 155,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.03.01 INSTRUMENTACION MULTIPARAMETRO , BATIMETRIA, TURBIDEZ, DETECCION DE ALGAS Y NIVEL DE AGUA 81,129.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 40,564.96 40,564.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.03.02 CONEXION Y ADAPTACION DE ACTUADORES AUMA, EN COMPUERTA DE LA LAGUNA BORO I Y BORO II 149,267.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 65,304.47 83,962.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.03.03 EQUIPAMIENTO DE SISTEMAS DE TRANSMISION DE INF. 2.4 GH DE TELEMETRIA EN CAPTACION BORO I y BORO II 248,092.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28,092.99 65,000.00 155,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02 CAPTACION BORO II 430,621.47 0.00 0.00 0.00 0.00 90,206.16 32,999.34 46,187.46 133,166.15 128,062.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01 EMPALME A ESTRUCTURA EXISTENTE 80,323.21 0.00 0.00 0.00 0.00 80,323.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.01 INSTALACION Y DESINSTALACION DE EMPEDRADO DE PROTECCIÓN DIQUE 68,385.00 0.00 0.00 0.00 0.00 68,385.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.02 DRENAJE DE ZANJAS 2,495.70 0.00 0.00 0.00 0.00 2,495.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.03 INSTALACION Y DESINSTALACION DE ANDAMIO RIELES MATALICOS TIPO CASTILLO 5,178.75 0.00 0.00 0.00 0.00 5,178.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.04 SUMINISTRO E INSTAL. COMPUERTA METALICA TIPO ARMCO DE 1.00 x 1.00 3,475.00 0.00 0.00 0.00 0.00 3,475.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.05 PERFORACION PARED ESTRUCTURA EXISTENTE 533.46 0.00 0.00 0.00 0.00 533.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.06 ENTIBADO ZANJA HASTA 3.50 m 255.30 0.00 0.00 0.00 0.00 255.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02 ESTRUCTURA PROYECTADA DE SALIDA BORO II 350,298.26 0.00 0.00 0.00 0.00 9,882.95 32,999.34 46,187.46 133,166.15 128,062.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.01 TRABAJOS PRELIMINARES 26.41 0.00 0.00 0.00 0.00 26.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.01.01 TRAZO y REPLANTEO 26.41 0.00 0.00 0.00 0.00 26.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.02 MOVIMIENTO DE TIERRAS 6,095.40 0.00 0.00 0.00 0.00 6,095.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.02.01 EXCAVACION PARA ESTRUCTURAS 327.39 0.00 0.00 0.00 0.00 327.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.02.02 DRENAJE DE ZANJAS 4,991.40 0.00 0.00 0.00 0.00 4,991.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.02.03 REFINE, NIVELACION y COMPACTACION ZONA EXCAVADA TNS 82.45 0.00 0.00 0.00 0.00 82.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.02.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 694.16 0.00 0.00 0.00 0.00 694.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.03 OBRAS DE CONCRETO SIMPLE 236.77 0.00 0.00 0.00 0.00 236.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.03.01 SOLADO CONCRETO f'c =100 Kg/cm² , e=0.10m 236.77 0.00 0.00 0.00 0.00 236.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.04 OBRAS DE CONCRETO ARMADO 19,084.31 0.00 0.00 0.00 0.00 3,524.37 15,559.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.04.01 CONCRETO f'c = 280 Kg/cm² p/ESTRUCTURA PROYECTADA DE SALIDA BORO II 6,767.14 0.00 0.00 0.00 0.00 0.00 6,767.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.04.02 ENCOFRADO y DESENCOFRADO p/ESTRUCTURA PROYECTADA SALIDA BORO II 4,387.34 0.00 0.00 0.00 0.00 0.00 4,387.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 7,929.83 0.00 0.00 0.00 0.00 3,524.37 4,405.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.05 REVOQUES y ENLUCIDOS 1,706.54 0.00 0.00 0.00 0.00 0.00 1,706.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.05.01 REVESTIMIENTO c/IMPERMEABILIZANTE p/LOSA FONDO 187.58 0.00 0.00 0.00 0.00 0.00 187.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.05.02 REVESTIMIENTO c/IMPERMEABILIZANTE p/MURO 1,518.96 0.00 0.00 0.00 0.00 0.00 1,518.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.06 CARPINTERIA METALICA 6,950.00 0.00 0.00 0.00 0.00 0.00 6,950.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.06.01 SUMINISTRO E INSTALACION COMPUERTA METALICA TIPO ARMCO 1.00 x 1.00 m 6,950.00 0.00 0.00 0.00 0.00 0.00 6,950.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.07 SUMINISTRO Y MONTAJE ELECTRICO MT LAGUNAS BORO 1 Y BORO 2 316,198.83 0.00 0.00 0.00 0.00 0.00 8,782.86 46,187.46 133,166.15 128,062.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.07.01 OBRAS PRELIMINARES Y EXPEDIENTE FINAL 18,703.20 0.00 0.00 0.00 0.00 0.00 2,078.13 6,234.41 6,442.21 3,948.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.07.02 POSTES Y ACCESORIOS DE CONCRETO ARMADO 30,171.30 0.00 0.00 0.00 0.00 0.00 6,704.73 20,114.20 3,352.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.07.03 AISLADORES POLIMERICOS Y ACCESORIOS 10,062.18 0.00 0.00 0.00 0.00 0.00 0.00 6,037.31 4,024.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.07.04 CONDUCTORES DE ENERGIA ELECTRICA 23,002.57 0.00 0.00 0.00 0.00 0.00 0.00 13,801.54 9,201.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.07.05 PUESTAS A TIERRA EN MEDIA Y BAJA TENSION 43,209.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 43,209.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.07.06 RETENIDAS Y ANCLAJES EN MEDIA TENSION 8,691.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,691.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.07.07 ARMADOS CON EQUIPOS DE POTENCIA Y ACCESORIOS 22.9 KV 54,845.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30,164.77 24,680.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.07.08 POSTES Y FERRETERIA ELECTRICA PARA SISTEMA 1O, 13.2 Kv 62,399.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28,079.61 34,319.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.07.09 ARMADOS CON EQUIPOS DE POTENCIA Y ACCESORIOS 1O, 13.2Kv 65,114.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 65,114.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03 LINEA DE CONDUCCION 1,045,775.50 0.00 0.00 0.00 0.00 0.00 0.00 121,760.45 145,474.45 458,529.42 320,011.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01 TRABAJOS PRELIMINARES 5,138.00 0.00 0.00 0.00 0.00 0.00 0.00 2,885.27 1,163.91 1,088.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 1,834.00 0.00 0.00 0.00 0.00 0.00 0.00 1,834.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.02 TRAZOS, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 3,304.00 0.00 0.00 0.00 0.00 0.00 0.00 1,051.27 1,163.91 1,088.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02 MOVIMIENTO DE TIERRAS 138,352.85 0.00 0.00 0.00 0.00 0.00 0.00 61,965.91 47,732.09 28,654.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.01 EXCAVACION DE ZANJAS 11,452.20 0.00 0.00 0.00 0.00 0.00 0.00 11,452.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.01.01 EXCAVACION ZANJA c/EQUIPO P/TUB Ø 400 mm; HASTA 1.80 m; af = 1.00 m 8,601.00 0.00 0.00 0.00 0.00 0.00 0.00 8,601.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.01.02 EXCAVACION ZANJA c/EQUIPO P/TUB Ø 400 mm; HASTA 3.00 m; af = 1.00 m 2,851.20 0.00 0.00 0.00 0.00 0.00 0.00 2,851.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.02 REFINE y NIVELACION DE ZANJAS 1,960.00 0.00 0.00 0.00 0.00 0.00 0.00 1,960.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.02.01 REFINE y NIVELACION FONDO ZANJA P/TUB. Ø 400 mm 1,960.00 0.00 0.00 0.00 0.00 0.00 0.00 1,960.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.03 CAMA DE APOYO P/TUBERIAS 16,394.00 0.00 0.00 0.00 0.00 0.00 0.00 16,394.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.03.01 CAMA APOYO (equipo) P/TUB Ø 400 mm; C/ARENA FINA e=0.20m 16,394.00 0.00 0.00 0.00 0.00 0.00 0.00 16,394.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.04 RELLENO, APISONADO y COMPACTACION LATERAL CON MATERIAL DE PRESTAMO 13,020.00 0.00 0.00 0.00 0.00 0.00 0.00 1,183.64 11,836.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.04.01 RELLENO, APISONADO Y COMPACTACION LATERAL p/TUBERIA Ø 400 mm C/ARENA FINA 13,020.00 0.00 0.00 0.00 0.00 0.00 0.00 1,183.64 11,836.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.05 RELLENO y COMPACTACION S/CLAVE TUBERIA C/MATERIAL DE PRESTAMO 21,966.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21,966.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.05.01 RELLENO y COMPACTACION HASTA h = 0.30 m; S/CLAVE TUB Ø 400 mm; C/ARENA FINA 21,966.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21,966.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.06 RELLENO y COMPACTACION DE ZANJAS CON MATERIAL PROPIO SELECCIONADO 17,457.20 0.00 0.00 0.00 0.00 0.00 0.00 434.87 13,929.73 3,092.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.06.01 RELLENO y APISONADO ZANJA p/TUBERIA Ø = 400 mm c/MATERIAL PROPIO SELECCIONADO h = 1.80 m 13,481.00 0.00 0.00 0.00 0.00 0.00 0.00 434.87 13,046.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.06.02 RELLENO y APISONADO ZANJA p/TUBERIA Ø = 400 mm c/MATERIAL PROPIO SELECCIONADO h = 3.00 m 3,976.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 883.60 3,092.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.07 ACARREO y ELIMINACION MATERIAL EXCEDENTE 25,562.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,562.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.07.01 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 25,562.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,562.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.08 ENTIBADO DE ZANJAS 30,541.20 0.00 0.00 0.00 0.00 0.00 0.00 30,541.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.08.01 ENTIBADO ZANJA HASTA 1.80 m 26,059.20 0.00 0.00 0.00 0.00 0.00 0.00 26,059.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.08.02 ENTIBADO ZANJA HASTA 3.00 m 4,482.00 0.00 0.00 0.00 0.00 0.00 0.00 4,482.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.03 SUMINISTRO e INSTALACION DE TUBERIAS PVC-UF PN 7.5 = 7.5 bar 284,971.60 0.00 0.00 0.00 0.00 0.00 0.00 26,023.95 62,015.65 196,932.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.03.01 SUMINISTRO E INSTALACION DE TUBERIA Ø = 400 mm PVC UF PN 7.5 h = 1.80 m 248,062.60 0.00 0.00 0.00 0.00 0.00 0.00 26,023.95 62,015.65 160,023.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.03.02 SUMINISTRO E INSTALACION DE TUBERIA Ø = 400 mm PVC UF PN 7.5 h = 3.00 m 36,909.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36,909.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04 ACCESORIOS 535,862.14 0.00 0.00 0.00 0.00 0.00 0.00 30,885.32 15,286.92 189,452.90 300,237.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.01 SUMINISTRO e INSTALACION CODO PVC ISO 400 mm x 90° PN 7.5 9,854.64 0.00 0.00 0.00 0.00 0.00 0.00 9,854.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.02 SUMINISTRO e INSTALACION CODO PVC ISO 400 mm x 45° PN 7.5 9,276.80 0.00 0.00 0.00 0.00 0.00 0.00 9,276.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.03 SUMINISTRO e INSTALACION CODO PVC ISO 400 mm x 22.5° PN 7.5 10,075.52 0.00 0.00 0.00 0.00 0.00 0.00 10,075.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.04 SUMINISTRO e INSTALACION CODO PVC ISO 400 mm x 11.25° PN 7.5 1,678.36 0.00 0.00 0.00 0.00 0.00 0.00 1,678.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.05 SUMINISTRO e INSTALACION TEE PVC ISO 400 mm PN 7.5 3,541.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,541.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.06 SUMINISTRO e INSTALACION VALVULA ELECTROACTUADA DN 400 mm 171,745.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,745.56 65,023.00 94,977.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.07 SUMINISTRO e INSTALACION VALVULA CHECK ISO f°f° DN 400 mm 42,435.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 42,435.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.08 SUMINISTRO e INSTALACION VALVULA COMPUERTA HFD DN 400 mm (Aire) 143,627.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33,627.40 110,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04.09 SUMINISTRO e INSTALACION VALVULA COMPUERTA HFD DN 400 mm (Purga) 143,627.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48,367.40 95,260.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.05 PRUEBA HIDRAULICA y DESINFECCION 15,218.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,609.00 7,609.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.05.01 DOBLE PRUEBA HIDRAULICA y DESINFECCION p/TUBERIA Ø 400 mm PVC 15,218.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,609.00 7,609.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.06 OBRAS DE CONCRETO ARMADO 12,451.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,666.88 784.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.06.01 CAJA Y TECHO PARA VALVULAS f'c=245 Kg/cm2 11,666.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,666.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.06.02 CAJA Y TECHO PARA MEDIDOR ELECTROMAGNETICO f'c=245 Kg/cm2 784.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 784.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07 VARIOS 39,548.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,774.19 19,774.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.01 MEDIDOR ELECTROMAGNETICO 39,548.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,774.19 19,774.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02 SIFON PARA CRUCE DE DREN 14,232.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,232.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.01 MOVIMIENTO DE TIERRAS 6,391.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,391.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.01.01 EXCAVACION PARA ESTRUCTURAS CON MAQUINARIA 578.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 578.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.01.02 PERFILADO Y COMPACTACION EN LA SUPERFICIE DE LA ZANJA 502.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 502.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.01.03 SUMINISTRO COLOCACION Y COMPACTACION DE MATERIAL DE FILTRO 397.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 397.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.01.04 RELLENO COMPACTADO C/MATERIAL PRESTAMO 4,189.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,189.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.01.05 ACARREO Y ELIMINACION DE MATERIAL EXCEDENTE Dist. min = 5.0Km 723.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 723.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.02 CONCRETO ARMADO 568.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 568.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.02.01 CONCRETO FC=210 kg/cm2 PARA DADOS DE CONCRETO 568.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 568.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.03 ENCOFRADO 525.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 525.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.03.01 ENCOFRADO Y DESENCOFRADO 525.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 525.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.04 VARIOS 6,747.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,747.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.04.01 SUMINISTRO E INSTALACION DE TUBERIA P.V.C.-O UF Ø = 400 mm 5,142.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,142.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.07.02.04.02 BOMBEO DE AGUA 1,604.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,604.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04 PLANTA DE TRATAMIENTO DE AGUA POTABLE 6,137,974.12 0.00 43,100.75 64,949.29 136,072.64 124,528.09 233,248.95 299,657.10 331,723.77 269,952.43 594,014.60 584,552.01 727,953.28 341,641.83 584,062.95 240,866.33 428,348.87 232,191.92 347,688.48 553,420.83 0.00
04.01 PLANTA DE TRATAMIENTO DE AGUA POTABLE 519,202.26 0.00 43,100.75 64,949.29 136,072.64 124,528.09 69,588.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 68,528.27 12,434.64 0.00 0.00 0.00
04.01.01 OBRAS PROVISIONALES 33,563.07 0.00 33,563.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.01.01 CARTEL IDENTIFICACION OBRA 3.60 * 2.40 m 1,127.07 0.00 1,127.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.01.02 CASETA p/GUARDIANIA y/o DEPOSITO 32,436.00 0.00 32,436.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.02 TRABAJOS PRELIMINARES 127,646.43 0.00 9,537.68 48,608.33 57,118.75 12,381.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.02.01 LIMPIEZA y DEFORESTACION 2,056.43 0.00 2,056.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.02.02 TRAZO, NIVELACION y REPLANTEO 51,300.00 0.00 7,481.25 33,131.25 10,687.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.02.03 TRAZO, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 74,290.00 0.00 0.00 15,477.08 46,431.25 12,381.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.03 MOVIMIENTO DE TIERRAS 277,029.85 0.00 0.00 16,340.96 78,953.89 112,146.42 69,588.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.03.01 EXCAVACION MASIVA TERRENO SATURADO 88,967.47 0.00 0.00 16,340.96 54,469.88 18,156.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.03.02 DRENAJE DE ZONA DE EXCAVACION 30,974.88 0.00 0.00 0.00 19,254.66 11,720.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.03.03 REFINE, NIVELACION y COMPACTACION ZONA EXCAVADA TNS 15,439.04 0.00 0.00 0.00 5,229.35 7,719.52 2,490.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.03.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 141,648.46 0.00 0.00 0.00 0.00 74,550.05 67,098.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.04 OBRAS DE CONCRETO SIMPLE 38,685.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38,685.12 0.00 0.00 0.00 0.00
04.01.04.01 VEREDAS DE CONCRETO F'c=175 Kg/cm2 (e=0.15m) 10,603.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,603.21 0.00 0.00 0.00 0.00
04.01.04.02 PISO DE CONCRETO F'C=175 KG/CM2 E=10CM 28,081.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28,081.91 0.00 0.00 0.00 0.00
04.01.05 CARPINTERIA METALICA Y HERRERIA 42,277.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 29,843.15 12,434.64 0.00 0.00 0.00
04.01.05.01 BARANDAS METALICAS F°G° Ø 1 1/2" 42,277.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 29,843.15 12,434.64 0.00 0.00 0.00
04.02 MEZCLADOR HIDRAULICO TIPO RAMPA 37,264.98 0.00 0.00 0.00 0.00 0.00 0.00 14,839.47 22,425.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.01 OBRAS DE CONCRETO ARMADO 23,890.84 0.00 0.00 0.00 0.00 0.00 0.00 14,448.04 9,442.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.01.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 8,389.41 0.00 0.00 0.00 0.00 0.00 0.00 8,389.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.01.02 ENCOFRADO y DESENCOFRADO NORMAL p/MEZCLADOR HIDRAULICO 6,609.42 0.00 0.00 0.00 0.00 0.00 0.00 6,058.63 550.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.01.03 CONCRETO f'c = 280 Kg/cm² p/MEZCLADOR HIDRAULICO 8,892.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,892.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.02 REVOQUES y REVESTIMIENTOS 2,557.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,557.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.02.01 TARRAJEO c/IMPERMEABILIZANTE p/LOSA FONDO 685.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 685.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.02.02 TARRAJEO c/IMPERMEABILIZANTE p/MURO 1,872.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,872.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.03 PINTURA 644.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 644.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.03.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 644.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 644.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.04 VARIOS 10,171.53 0.00 0.00 0.00 0.00 0.00 0.00 391.43 9,780.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.04.01 SUMINISTRO e INSTALACION SENSOR TURBIEDAD 9,441.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,441.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.04.02 SUMINISTRO e INSTALACION DIFUSOR 338.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 338.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.04.03 JUNTA CONSTRUCCION c/WATER STOP 10" 391.43 0.00 0.00 0.00 0.00 0.00 0.00 391.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03 FLOCULADOR 149,181.38 0.00 0.00 0.00 0.00 0.00 26,176.68 67,780.05 41,043.60 14,181.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.01 OBRAS DE CONCRETO SIMPLE 2,088.94 0.00 0.00 0.00 0.00 0.00 2,088.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.01.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/SOLADO y/o SUB BASE 2,088.94 0.00 0.00 0.00 0.00 0.00 2,088.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.02 OBRAS DE CONCRETO ARMADO 76,671.68 0.00 0.00 0.00 0.00 0.00 24,087.74 52,583.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 30,654.13 0.00 0.00 0.00 0.00 0.00 19,158.83 11,495.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.02.02 ENCOFRADO y DESENCOFRADO NORMAL p/FLOCULADOR 18,620.32 0.00 0.00 0.00 0.00 0.00 4,928.91 13,691.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.02.03 CONCRETO f'c = 280 Kg/cm² p/FLOCULADOR 27,397.23 0.00 0.00 0.00 0.00 0.00 0.00 27,397.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.03 REVOQUES y REVESTIMIENTOS 8,046.04 0.00 0.00 0.00 0.00 0.00 0.00 1,270.83 6,775.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.03.01 TARRAJEO c/IMPERMEABILIZANTE p/LOSA FONDO 2,223.95 0.00 0.00 0.00 0.00 0.00 0.00 1,270.83 953.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.03.02 TARRAJEO c/IMPERMEABILIZANTE p/MURO 5,822.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,822.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.04 VARIOS 62,374.72 0.00 0.00 0.00 0.00 0.00 0.00 13,925.28 34,268.39 14,181.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.04.01 SUMINISTRO E INSTALACION VALVULA Ø 160 mm F°F° ISO (equipada) 11,983.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,983.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.04.02 SUMINISTRO e INSTALACION PANTALLA MADERA TRATADA 36,465.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,284.50 14,181.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.04.03 JUNTA CONSTRUCCION c/WATER STOP 10" 13,925.28 0.00 0.00 0.00 0.00 0.00 0.00 13,925.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04 CANAL DE DISTRIBUCION P/AGUA FLOCULADA 27,438.85 0.00 0.00 0.00 0.00 0.00 0.00 4,402.75 23,036.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.01 OBRAS DE CONCRETO SIMPLE 634.72 0.00 0.00 0.00 0.00 0.00 0.00 634.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.01.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/SOLADO y/o SUB BASE 634.72 0.00 0.00 0.00 0.00 0.00 0.00 634.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02 OBRAS DE CONCRETO ARMADO 23,088.61 0.00 0.00 0.00 0.00 0.00 0.00 3,768.03 19,320.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 10,362.08 0.00 0.00 0.00 0.00 0.00 0.00 3,768.03 6,594.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02.02 ENCOFRADO y DESENCOFRADO NORMAL p/CANAL DISTRIBUCION 4,918.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,918.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02.03 CONCRETO f'c = 280 Kg/cm² p/CANAL DISTRIBUCION 7,807.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,807.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.03 REVOQUES y REVESTIMIENTOS 3,043.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,043.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.03.01 TARRAJEO c/IMPERMEABILIZANTE p/LOSA FONDO 436.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 436.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.03.02 TARRAJEO c/IMPERMEABILIZANTE p/MURO 2,607.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,607.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.04 PINTURA 261.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 261.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.04.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 261.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 261.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.05 VARIOS 410.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 410.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.05.01 JUNTA CONSTRUCCION c/WATER STOP 10" 410.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 410.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05 DECANTADOR 384,604.31 0.00 0.00 0.00 0.00 0.00 0.00 11,439.15 78,573.22 68,113.58 101,039.88 28,303.08 50,074.46 47,060.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.01 OBRAS DE CONCRETO SIMPLE 4,915.23 0.00 0.00 0.00 0.00 0.00 0.00 4,915.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.01.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/SOLADO 4,915.23 0.00 0.00 0.00 0.00 0.00 0.00 4,915.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.02 OBRAS DE CONCRETO ARMADO 228,745.50 0.00 0.00 0.00 0.00 0.00 0.00 5,159.05 70,384.03 68,113.58 85,088.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 103,989.39 0.00 0.00 0.00 0.00 0.00 0.00 4,332.89 44,773.21 43,328.91 11,554.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.02.02 ENCOFRADO y DESENCOFRADO NORMAL p/DECANTADOR 57,830.89 0.00 0.00 0.00 0.00 0.00 0.00 826.16 25,610.82 24,784.67 6,609.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.02.03 CONCRETO f'c = 280 Kg/cm² p/DECANTADOR 66,925.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 66,925.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.03 REVOQUES y REVESTIMIENTOS 49,624.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,951.04 28,303.08 5,370.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.03.01 TARRAJEO c/IMPERMEABILIZANTE p/LOSA FONDO 30,077.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,816.03 16,649.85 1,611.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.03.02 TARRAJEO c/IMPERMEABILIZANTE p/MURO 19,547.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,135.01 11,653.23 3,759.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.04 PINTURA 454.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 454.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.04.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 454.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 454.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.05 VARIOS 100,864.37 0.00 0.00 0.00 0.00 0.00 0.00 1,364.87 8,189.19 0.00 0.00 0.00 44,704.08 46,606.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.05.01 SUMINISTRO e INSTALACION VINILONA Al p/DECANTADOR 75,184.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 44,704.08 30,480.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.05.02 SUMINISTRO E INSTALACION DE TUBERIA PVC PN 10 Ø 200 mm CON ORIFICIOS 1/2" 3,651.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,651.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.05.03 SUMINISTRO e INSTALACION TACOS MADERA 7,563.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,563.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.05.04 JUNTA CONSTRUCCION c/WATER STOP 10" 9,554.06 0.00 0.00 0.00 0.00 0.00 0.00 1,364.87 8,189.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.05.05 SUMINISTRO e INSTALACION DE COMPUERTA ATAGUIA DE ALUMINIO (0.60x0.80m) INC. VASTAGO, VOLANTE Y SOPORTE 4,911.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,911.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.06 COLECTOR MULTIPLE 16,889.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,889.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.06.01 SUMINISTRO E INSTALACION DE TUBERIAS 11,092.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,092.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.06.01.01 SUMINISTRO E INSTALACION DE TUBERIA DE PVC PN 10 Ø 500mm 11,092.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,092.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.06.02 SUMINISTRO E INSTALACION DE ACCESORIOS 5,797.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,797.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.06.02.01 SUMINISTRO E INSTALACION DE TAPON (Inyectado) DE PVC PN 10 Ø 500mm 2,284.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,284.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.06.02.02 SUMINISTRO E INSTALCION DE SILLA TEE (Inyectada) DE PVC PN 10 500X200mm 3,513.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,513.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.07 FILTRO 274,511.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 34,535.49 74,186.60 123,364.95 25,453.51 16,971.19 0.00 0.00 0.00 0.00 0.00 0.00
04.07.01 OBRAS DE CONCRETO SIMPLE 4,062.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,062.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.07.01.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/SOLADO y/o SUB BASE 4,062.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,062.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.07.02 OBRAS DE CONCRETO ARMADO 221,664.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30,473.01 69,836.86 121,354.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.07.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 100,125.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30,473.01 44,983.97 24,668.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.07.02.02 ENCOFRADO y DESENCOFRADO NORMAL p/FILTRO 43,078.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24,852.89 18,225.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.07.02.03 CONCRETO f'c = 280 Kg/cm² p/FILTRO 78,460.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 78,460.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.07.03 REVOQUES y REVESTIMIENTOS 33,513.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,010.67 25,453.51 6,049.77 0.00 0.00 0.00 0.00 0.00 0.00
04.07.03.01 TARRAJEO c/IMPERMEABILIZANTE p/LOSA FONDO 4,021.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,010.67 2,010.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.07.03.02 TARRAJEO c/IMPERMEABILIZANTE p/MURO 29,492.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23,442.85 6,049.77 0.00 0.00 0.00 0.00 0.00 0.00
04.07.04 PINTURA 4,615.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,615.85 0.00 0.00 0.00 0.00 0.00 0.00
04.07.04.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 4,615.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,615.85 0.00 0.00 0.00 0.00 0.00 0.00
04.07.05 VARIOS 10,655.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,349.74 0.00 0.00 6,305.57 0.00 0.00 0.00 0.00 0.00 0.00
04.07.05.01 RELLENO PARA FILTRO C/MEDIO FILTRANTE ARENA 4,455.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,455.35 0.00 0.00 0.00 0.00 0.00 0.00
04.07.05.02 RELLENO PARA FILTRO C/MEDIO SOPORTE GRAVA 1,850.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,850.22 0.00 0.00 0.00 0.00 0.00 0.00
04.07.05.03 JUNTA CONSTRUCCION c/WATER STOP 10" 4,349.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,349.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08 CAMARA P/CONTACTO DE CLORO 228,282.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 27,550.83 73,006.88 103,334.69 16,283.44 8,106.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.01 OBRAS DE CONCRETO SIMPLE 3,761.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,761.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.01.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/SOLADO y/o SUB BASE 3,761.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,761.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.02 OBRAS DE CONCRETO ARMADO 188,589.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23,789.27 70,011.21 94,789.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 72,953.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,165.58 44,344.41 11,443.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.02.02 ENCOFRADO y DESENCOFRADO NORMAL p/CAMARA 43,881.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,623.69 25,666.80 11,591.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.02.03 CONCRETO f'c = 280 Kg/cm² p/CAMARA 71,754.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 71,754.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.03 REVOQUES y REVESTIMIENTOS 32,128.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,545.30 16,283.44 7,299.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.03.01 TARRAJEO c/IMPERMEABILIZANTE p/LOSA FONDO 2,930.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,930.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.03.02 TARRAJEO c/IMPERMEABILIZANTE p/MURO 29,197.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,614.98 16,283.44 7,299.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.04 PINTURA 807.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 807.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.04.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 807.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 807.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.05 VARIOS 2,995.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,995.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.05.01 JUNTA CONSTRUCCION c/WATER STOP 10" 2,995.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,995.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09 CISTERNA 425,460.49 0.00 0.00 0.00 0.00 0.00 50,737.29 67,353.31 73,975.71 80,303.00 112,788.14 21,340.83 13,118.01 5,844.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.01 OBRAS DE CONCRETO SIMPLE 16,325.17 0.00 0.00 0.00 0.00 0.00 16,325.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.01.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/SOLADO y/o SUB BASE 16,325.17 0.00 0.00 0.00 0.00 0.00 16,325.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.02 OBRAS DE CONCRETO ARMADO 332,282.38 0.00 0.00 0.00 0.00 0.00 34,412.12 67,353.31 69,598.42 70,901.21 90,017.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 157,676.41 0.00 0.00 0.00 0.00 0.00 32,213.46 50,863.36 52,558.80 22,040.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.02.02 ENCOFRADO y DESENCOFRADO NORMAL p/CISTERNA 44,522.87 0.00 0.00 0.00 0.00 0.00 2,198.66 16,489.95 17,039.62 4,397.32 4,397.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.02.03 CONCRETO f'c = 280 Kg/cm² p/CISTERNA 130,083.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 44,463.10 85,620.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.03 REVOQUES y REVESTIMIENTOS 55,922.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,024.51 22,770.82 21,340.83 6,786.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.03.01 TARRAJEO c/IMPERMEABILIZANTE p/LOSA FONDO 25,382.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,647.47 11,082.44 9,652.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.03.02 TARRAJEO c/IMPERMEABILIZANTE p/MURO 30,540.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 377.04 11,688.38 11,688.38 6,786.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.04 PINTURA 12,175.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,331.21 5,844.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.04.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 12,175.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,331.21 5,844.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.05 VARIOS 8,754.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,377.29 4,377.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.05.01 JUNTA CONSTRUCCION c/WATER STOP 10" 8,754.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,377.29 4,377.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10 ESTACION DE BOMBEO 348,103.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,377.95 35,743.10 106,566.67 196,415.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.01 OBRAS DE CONCRETO ARMADO 18,377.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,377.95 8,999.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.01.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 2,929.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,929.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.01.02 ENCOFRADO y DESENCOFRADO NORMAL p/ESTACION BOMBEO 7,522.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,448.28 1,074.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.01.03 CONCRETO f'c = 280 Kg/cm² p/ESTACION BOMBEO 7,924.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,924.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.02 REVOQUES y REVESTIMIENTOS 7,405.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,354.51 1,050.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.02.01 TARRAJEO c/IMPERMEABILIZANTE p/MURO 5,303.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,303.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.02.02 CIELO RASO c/MORTERO C:A 1:5 2,101.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,050.87 1,050.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.03 PINTURA 2,015.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,015.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.03.01 PINTURA LATEX EN MUROS INC. IMPRIMANTE 1,389.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,389.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.03.02 PINTURA LATEX CIELO RASO INC/ IMPRIMANTE 625.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 625.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.04 INSTALACIONES ELECTROMECANICAS 320,305.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20,389.47 105,515.79 194,400.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.04.01 SUMINISTRO e INSTALACION ELECTROBOMBA p/ESTACION BOMBEO 226,105.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20,389.47 105,515.79 100,200.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.04.02 SUMINISTRO e INSTALACION ACCESORIOS ELECTROBOMBA p/ESTACION BOMBEO 90,645.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 90,645.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.04.03 SUMINISTRO e INSTALACION VALVULA DISIPADORA ONDA p/GOLPE DE ARIETE 3,554.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,554.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11 CERCO PERIMETRICO 339,677.61 0.00 0.00 0.00 0.00 0.00 86,746.40 118,491.06 61,250.05 36,640.11 36,549.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.01 TRABAJOS PRELIMINARES 15,885.94 0.00 0.00 0.00 0.00 0.00 9,713.04 3,779.32 2,393.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.01.01 LIMPIEZA TERRENO MANUAL 8,566.48 0.00 0.00 0.00 0.00 0.00 2,393.58 3,779.32 2,393.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.01.02 TRAZO y REPLANTEO 7,319.46 0.00 0.00 0.00 0.00 0.00 7,319.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.02 MOVIMIENTO DE TIERRAS 16,714.88 0.00 0.00 0.00 0.00 0.00 4,241.09 7,484.27 4,989.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.02.01 EXCAVACION MANUAL ZANJA HASTA 1.00 m; a = 0.60 m 16,714.88 0.00 0.00 0.00 0.00 0.00 4,241.09 7,484.27 4,989.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.03 OBRAS DE CONCRETO SIMPLE 9,900.21 0.00 0.00 0.00 0.00 0.00 9,900.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.03.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/SOLADO y/o SUB BASE 9,900.21 0.00 0.00 0.00 0.00 0.00 9,900.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.04 OBRAS DE CONCRETO ARMADO 297,176.58 0.00 0.00 0.00 0.00 0.00 62,892.06 107,227.47 53,866.95 36,640.11 36,549.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.04.01 CIMENTACION 75,998.67 0.00 0.00 0.00 0.00 0.00 57,564.35 18,434.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.04.01.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 8,406.18 0.00 0.00 0.00 0.00 0.00 8,406.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.04.01.02 CONCRETO f'c = 210 Kg/cm² p/CIMENTACION 67,592.49 0.00 0.00 0.00 0.00 0.00 49,158.17 18,434.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.04.02 SOBRECIMIENTO 80,395.62 0.00 0.00 0.00 0.00 0.00 5,327.71 56,812.79 17,148.75 1,106.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.04.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 10,087.42 0.00 0.00 0.00 0.00 0.00 3,668.15 6,419.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.04.02.02 ENCOFRADO y DESENCOFRADO NORMAL HASTA 0.30 m p/SOBRECIMIENTO 36,510.24 0.00 0.00 0.00 0.00 0.00 1,659.56 16,595.56 17,148.75 1,106.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.04.02.03 CONCRETO f'c = 210 Kg/cm² p/SOBRECIMIENTO 33,797.96 0.00 0.00 0.00 0.00 0.00 0.00 33,797.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.04.03 CERCO TIPO UNI 140,782.29 0.00 0.00 0.00 0.00 0.00 0.00 31,980.36 36,718.20 35,533.74 36,549.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.04.03.01 SUMINISTRO E INSTALACION DE CERCO TIPO "UNI" CONCRETO f'c = 210 Kg/cm² p/PLANTA TRATAMIENTO 130,290.37 0.00 0.00 0.00 0.00 0.00 0.00 31,980.36 36,718.20 35,533.74 26,058.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.11.04.03.02 PUERTA METALICA (inc. pintura) 10,491.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,491.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12 CASA DE CLORACION 417,988.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,013.20 38,054.17 40,882.57 17,352.43 33,643.37 280,956.02 5,086.67 0.00 0.00 0.00 0.00 0.00
04.12.01 TRABAJOS PRELIMINARES 494.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 494.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1 de 10
CALENDARIO DE AVANCE DE OBRA VALORIZADO ACTUALIZADO A LA FECHA DE INICIO DE OBRA
OBRA : INSTALACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DE LOS PP.JJ. VILLA PROGRESO, MIRAFLORES, LAS VEGAS, SAMAN, SAN FRANCISCO DE ASIS, LA UNION, SAN JUAN DE DIOS Y RAMIRO PRIALE II - CHICLAYO
ENTIDAD : ENTIDAD PRESTADORA DE SERVICIOS DE SANEAMIENTO DE LAMBAYEQUE S.A. - EPSEL S.A.
CONTRATISTA : CONSORCIO PROGRESO
SUPERVISION : CONSORCIO SUPERVISOR ASIS
UBICACIÓN : CHICLAYO - CHICLAYO - LAMBAYEQUE
Duración (Meses)
Item Descripción Parcial (S/.)
Mar-2019 Abr-2019 May-2019 Jun-2019 Jul-2019 Ago-2019 Sep-2019 Oct-2019 Nov-2019 Dic-2019 Ene-2020 Feb-2020 Mar-2020 Abr-2020 May-2020 Jun-2020 Jul-2020 Ago-2020 Sep-2020 Oct-2020
04.12.01.01 LIMPIEZA TERRENO MANUAL 266.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 266.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.01.02 TRAZO y REPLANTEO 228.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 228.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.02 MOVIMIENTO DE TIERRAS 3,625.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,518.32 2,107.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.02.01 EXCAVACION PARA CIMIENTOS HASTA 1.50M TERRENO NORMAL 2,070.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,518.32 552.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.02.02 NIVELACION INTERIOR APISONADO MANUAL 239.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 239.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.02.03 RELLENO CON MATERIAL PROPIO 702.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 702.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.02.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 613.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 613.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.03 OBRAS DE CONCRETO SIMPLE 5,786.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,351.76 2,434.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.03.01 ENCOFRADO y DESENCOFRADO SOBRECIMIENTO HASTA 0.30M 1,630.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,630.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.03.02 CONCRETO C:H 1:8 + 25 % PM; f'c = 100 Kg/cm² p/SOBRECIMIENTO 577.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 577.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.03.03 CONCRETO EN FALSOPISO DE 4" DE 1:8 CEM-HOR 2,434.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,434.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.03.04 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDDO 1,143.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,143.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04 OBRAS DE CONCRETO ARMADO 64,375.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32,595.28 31,780.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.01 ZAPATA 5,908.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,908.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.01.01 CONCRETO f'c = 210 Kg/cm² p/ZAPATA 4,624.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,624.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.01.02 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,284.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,284.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.02 VIGAS DE CIMENTACION 11,869.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,869.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.02.01 CONCRETO f'c = 210 Kg/cm² p/VIGA CIMENTACION 4,521.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,521.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.02.02 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 3,945.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,945.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.02.03 ENCOFRADO Y DESENCOFRADO VIGA DE CIMENTACION 3,402.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,402.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.03 COLUMNAS 21,641.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,816.51 6,824.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.03.01 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 3,932.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,932.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 5,991.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,901.75 1,089.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.03.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 11,717.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,914.76 1,802.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.04 VIGAS 10,182.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,182.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.04.01 CONCRETO f'c = 210 Kg/cm² p/VIGA 3,000.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,000.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.04.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 3,813.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,813.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 3,368.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,368.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.05 LOSAS ALIGERADAS 8,106.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,106.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.05.01 CONCRETO f'c = 210 Kg/cm² p/LOSA ALIGERADA 2,066.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,066.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.05.02 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA ALIGERADA 3,207.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,207.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.05.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,070.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,070.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.05.04 LADRILLO HUECO ARCILLA 15 x 30 x 30 cm p/LOSA ALIGERADA 1,762.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,762.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.06 CISTERNA 6,010.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,010.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.06.01 CONCRETO f'c = 245 Kg/cm² p/CISTERNA 2,327.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,327.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL p/CISTERNA 1,196.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,196.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.06.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 2,486.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,486.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.07 BASE DE MOTOR 655.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 655.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.07.01 CONCRETO f'c = 210 Kg/cm² p/BASE MOTOR 141.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 141.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.07.02 ENCOFRADO y DESENCOFRADO NORMAL p/BASE MOTOR 272.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 272.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.04.07.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 241.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 241.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.05 ALBAÑILERIA 16,076.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,667.56 9,409.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.05.01 MURO CABEZA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 6,667.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,667.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.05.02 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 9,409.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,409.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.06 REVOQUES y REVESTIMIENTOS 20,960.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,593.10 14,367.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.06.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO c/MORTERO C:A 1:5 425.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 425.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.06.02 TARRAJEO INTERIOR c/MORTERO C:A 1:5 x 1.5 cm ( in. colum empot) 11,774.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,167.60 5,606.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.06.03 TARRAJEO EXTERIOR c/MORTERO C:A 1:5 x 1.5 cm ( in. colum empot) 7,719.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,719.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.06.04 VESTIDURA DERRAME 1,040.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,040.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.07 CIELO RASO y FALSO CIELO RASO 5,062.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,349.93 3,712.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.07.01 CIELO RASO c/MORTERO C:A 1:5 5,062.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,349.93 3,712.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.08 PISOS y PAVIMENTOS 4,349.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,349.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.08.01 CONTRAPISO (e = 48 mm) 2,006.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,006.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.08.02 VEREDA c/CONCRETO f' = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base de afirmado 2,343.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,343.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.09 CONTRAZOCALOS 2,210.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,210.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.09.01 CONTRAZOCALO CEDRO 3/4" x 4" RODON 3/4" 2,210.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,210.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.10 ZOCALOS 1,140.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,140.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.10.01 ZOCALO CERAMICO COLOR (20 x 20 cm) 1,140.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,140.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.11 CARPINTERIA METALICA 8,774.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,514.62 1,259.87 0.00 0.00 0.00 0.00 0.00 0.00
04.12.11.01 PORTON METALICO 3.40 x 3.00 m (inc. pintura) 5,680.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,680.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.11.02 PUERTA DE CUARTO DE CLORO 0.90x2.70(inc. pintura) 1,203.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,203.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.11.03 VENTANA FIERRO (inc. pintura) 1,889.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 629.93 1,259.87 0.00 0.00 0.00 0.00 0.00 0.00
04.12.12 CERRAJERIA 347.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 347.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.12.01 BISAGRA CAPUCHINA ACERO ALUMINIZADO 3 1/2" x 3 1/2" 127.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 127.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.12.02 CERRADURA PRINCIPAL p/PUERTA EXTERIOR 86.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 86.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.12.03 CERRADURA p/EMBUTIR c/DOBLE TAMBOR y PERILLA p/INTERIOR 133.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 133.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.13 VIDRIOS, CRISTALES y SIMILARES 504.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 504.79 0.00 0.00 0.00 0.00 0.00 0.00
04.12.13.01 VIDRIO SEMIDOBLE. PROVISION Y COLOCACION EN VENTANAS FIERRO 504.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 504.79 0.00 0.00 0.00 0.00 0.00 0.00
04.12.14 PINTURA 5,463.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 376.82 5,086.67 0.00 0.00 0.00 0.00 0.00
04.12.14.01 PINTURA DE MURO INTERIOR/EXTERIOR C/LATEX VINILICO 02 MANOS inc./IMPRIMANTE 3,956.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,956.21 0.00 0.00 0.00 0.00 0.00
04.12.14.02 PINTURA DE CIELO RASO C/LATEX VINILICO 1,507.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 376.82 1,130.46 0.00 0.00 0.00 0.00 0.00
04.12.15 SISTEMA DE DOSIFICACION DE CLORO 108,415.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 108,415.14 0.00 0.00 0.00 0.00 0.00 0.00
04.12.15.01 SUMINISTRO e INSTALACION BOMBA p/DOSIFICADOR Cl 36,919.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36,919.44 0.00 0.00 0.00 0.00 0.00 0.00
04.12.15.02 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 2" 322.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 322.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.15.03 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 3" 17.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17.25 0.00 0.00 0.00 0.00 0.00 0.00
04.12.15.04 SUMINISTRO e INSTALACION TUBERIA f°g° DN 2" 196.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 196.32 0.00 0.00 0.00 0.00 0.00 0.00
04.12.15.05 SUMINISTRO e INSTALACION CLORADORES 20,382.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20,382.26 0.00 0.00 0.00 0.00 0.00 0.00
04.12.15.06 SUMINISTRO e INSTALACION BOTELLA Cl (Neto 907 Kg) 21,018.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21,018.99 0.00 0.00 0.00 0.00 0.00 0.00
04.12.15.07 SUMINISTRO e INSTALACION BALANZA PLATAFORMA 4,667.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,667.94 0.00 0.00 0.00 0.00 0.00 0.00
04.12.15.08 SUMINISTRO e INSTALACION MASCARA ANTIGAS 1,264.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,264.24 0.00 0.00 0.00 0.00 0.00 0.00
04.12.15.09 SUMINISTRO e INSTALACION BOTELLA Cl (Neto 68 Kg) 1,430.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,430.04 0.00 0.00 0.00 0.00 0.00 0.00
04.12.15.10 SUMINISTRO E INSTALACION DE SISTEMA DE RIELES 22,196.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,196.66 0.00 0.00 0.00 0.00 0.00 0.00
04.12.16 SISTEMA DE AGUA FRIA 170,399.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 170,399.40 0.00 0.00 0.00 0.00 0.00 0.00
04.12.16.01 RED DISTRIBUCION TUBERIA PVC SAP 1 1/2" 471.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 471.75 0.00 0.00 0.00 0.00 0.00 0.00
04.12.16.02 RED DISTRIBUCION TUBERIA PVC SAP 2" 603.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 603.57 0.00 0.00 0.00 0.00 0.00 0.00
04.12.16.03 VALVULAS COMPUERTA BRONCE 1/2" 1,838.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,838.60 0.00 0.00 0.00 0.00 0.00 0.00
04.12.16.04 VALVULAS COMPUERTA BRONCE 2" 2,403.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,403.40 0.00 0.00 0.00 0.00 0.00 0.00
04.12.16.05 TANQUE APOYADO (C = 5.00 m3) 2,074.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,074.88 0.00 0.00 0.00 0.00 0.00 0.00
04.12.16.06 TANQUE APOYADO (C = 2.50 m3) 1,174.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,174.88 0.00 0.00 0.00 0.00 0.00 0.00
04.12.16.07 TANQUE ELEVADO DE ETERNIT ACCESORIOS 30,684.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30,684.00 0.00 0.00 0.00 0.00 0.00 0.00
04.12.16.08 SUMINISTRO e INSTALACION BOMBA p/SISTEMA LAVADO 38,063.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38,063.44 0.00 0.00 0.00 0.00 0.00 0.00
04.12.16.09 SUMINISTRO e INSTALACION BOMBA p/ABASTECIMIENTO SISTEMA DOSIFICACION QUIMICA 37,313.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37,313.44 0.00 0.00 0.00 0.00 0.00 0.00
04.12.16.10 SUMINISTRO e INSTALACION BOMBA p/SISTEMA ABASTECIMIENTO OFICINA, LABORATORIO y CASETAS 37,259.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37,259.44 0.00 0.00 0.00 0.00 0.00 0.00
04.12.16.11 SUMINISTRO e INSTALACION MANGUERA LONA REFORZADA FLEXIBLE DN 2" 18,512.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,512.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13 CASA DE DOSIFICACION 240,026.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,447.90 24,800.81 38,992.76 24,300.33 21,810.66 125,852.68 2,821.12 0.00 0.00 0.00
04.13.01 TRABAJOS PRELIMINARES 494.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 494.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.01.01 LIMPIEZA TERRENO MANUAL 266.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 266.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.01.02 TRAZO y REPLANTEO 228.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 228.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.02 MOVIMIENTO DE TIERRAS 3,582.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 953.02 2,629.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.02.01 EXCAVACION PARA CIMIENTOS HASTA 1.50M TERRENO NORMAL 2,042.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 953.02 1,089.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.02.02 NIVELACION INTERIOR APISONADO MANUAL 239.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 239.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.02.03 RELLENO CON MATERIAL PROPIO 702.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 702.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.02.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 598.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 598.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.03 OBRAS DE CONCRETO SIMPLE 5,058.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,623.96 0.00 2,434.69 0.00 0.00 0.00 0.00 0.00 0.00
04.13.03.01 ENCOFRADO y DESENCOFRADO SOBRECIMIENTO HASTA 0.30M 1,277.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,277.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.03.02 CONCRETO C:H 1:8 + 25 % PM; f'c = 100 Kg/cm² p/SOBRECIMIENTO 453.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 453.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.03.03 CONCRETO EN FALSO PISO DE 4" C:H 2,434.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,434.69 0.00 0.00 0.00 0.00 0.00 0.00
04.13.03.04 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDO 893.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 893.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04 CONCRETO ARMADO 66,993.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,547.13 38,992.76 8,453.95 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.01 ZAPATAS 5,908.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,908.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.01.01 CONCRETO f'c = 210 Kg/cm² p/ZAPATA 4,624.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,624.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.01.02 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,284.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,284.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.02 VIGAS DE CIMENTACION 11,869.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,869.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.02.01 CONCRETO f'c = 210 Kg/cm² p/VIGA CIMENTACION 4,521.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,521.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.02.02 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 3,945.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,945.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.02.03 ENCOFRADO Y DESENCOFRADO VIGA DE CIMENTACION 3,402.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,402.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.03 COLUMNAS 15,945.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,768.36 14,177.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.03.01 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 3,213.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,213.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 3,890.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,890.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.03.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 8,841.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,768.36 7,073.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.04 VIGAS 8,063.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,063.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.04.01 CONCRETO f'c = 210 Kg/cm² p/VIGA 2,456.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,456.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.04.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 2,976.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,976.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 2,630.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,630.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.05 LOSAS ALIGERADAS 9,546.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,546.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.05.01 CONCRETO f'c = 210 Kg/cm² p/LOSA ALIGERADA 3,484.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,484.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.05.02 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA ALIGERADA 3,207.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,207.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.05.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,092.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,092.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.05.04 LADRILLO HUECO ARCILLA 15 x 30 x 30 cm p/LOSA ALIGERADA 1,762.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,762.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.06 TANQUES DE SOLUCION DE QUIMICOS 15,003.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,691.53 8,312.03 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.06.01 CONCRETO f'c = 210 Kg/cm² p/TANQUE SOLUCION QUIMICOS 2,877.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,877.15 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL p/TANQUE SOLUCION QUIMICOS 7,246.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,811.62 5,434.88 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.06.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 4,879.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,879.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.07 BASE PARA MOTOR 655.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 513.89 141.92 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.07.01 CONCRETO f'c = 210 Kg/cm² p/BASE MOTOR 141.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 141.92 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.07.02 ENCOFRADO y DESENCOFRADO NORMAL p/BASE MOTOR 272.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 272.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.04.07.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 241.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 241.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.13.05 ALBAÑILERIA 13,973.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,411.69 562.01 0.00 0.00 0.00 0.00 0.00
04.13.05.01 MURO CABEZA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 6,667.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,667.56 0.00 0.00 0.00 0.00 0.00 0.00
04.13.05.02 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 7,306.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,744.13 562.01 0.00 0.00 0.00 0.00 0.00
04.13.06 REVOQUES y REVESTIMIENTOS 18,726.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,177.43 2,549.52 0.00 0.00 0.00 0.00
04.13.06.01 TARRAJEO INTERIOR c/MORTERO C:A 1:5 x 1.5 cm ( in. colum empot) 11,410.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,410.65 0.00 0.00 0.00 0.00 0.00
04.13.06.02 TARRAJEO EXTERIOR c/MORTERO C:A 1:5 x 1.5 cm ( in. colum empot) 6,355.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,766.78 1,588.93 0.00 0.00 0.00 0.00
04.13.06.03 VESTIDURA DERRAME 960.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 960.59 0.00 0.00 0.00 0.00
04.13.07 CIELORRASOS 5,071.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,071.22 0.00 0.00 0.00 0.00 0.00
04.13.07.01 CIELORRASO c/MEZCLA DE CEMENTO-ARENA 5,071.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,071.22 0.00 0.00 0.00 0.00 0.00
04.13.08 PISOS y PAVIMENTOS 4,355.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,355.57 0.00 0.00 0.00 0.00
04.13.08.01 CONTRAPISO (e = 48 mm) 2,009.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,009.91 0.00 0.00 0.00 0.00
04.13.08.02 VEREDA RIGIDA DE CONCRETO f' = 140 Kg/cm² E=0.10m pasta 1:2 2,345.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,345.66 0.00 0.00 0.00 0.00
04.13.09 CONTRAZOCALOS 1,881.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,881.45 0.00 0.00 0.00 0.00
04.13.09.01 CONTRAZOCALO CEDRO 3/4" x 4" RODON 3/4" 1,881.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,881.45 0.00 0.00 0.00 0.00
04.13.10 CARPINTERIA METALICA y HERRERIA 12,873.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,873.30 0.00 0.00 0.00 0.00
04.13.10.01 PORTON METALICO 3.40 x 3.00 m (inc. pintura) 11,361.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,361.46 0.00 0.00 0.00 0.00
04.13.10.02 VENTANA FIERRO (inc. pintura) 1,511.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,511.84 0.00 0.00 0.00 0.00
04.13.11 CARPINTERIA DE MADERA 635.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 635.60 0.00 0.00 0.00 0.00
04.13.11.01 TARIMA p/ALMACEN INSUMOS 635.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 635.60 0.00 0.00 0.00 0.00
04.13.12 CERRAJERIA 434.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 434.62 0.00 0.00 0.00 0.00
04.13.12.01 BISAGRA CAPUCHINA ACERO ALUMINIZADO 3 1/2" x 3 1/2" 127.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 127.56 0.00 0.00 0.00 0.00
04.13.12.02 CERRADURA PRINCIPAL p/PUERTA EXTERIOR 173.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 173.78 0.00 0.00 0.00 0.00
04.13.12.03 CERRADURA p/EMBUTIR c/DOBLE TAMBOR y PERILLA p/INTERIOR 133.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 133.28 0.00 0.00 0.00 0.00
04.13.13 VIDRIOS, CRISTALES y SIMILARES 371.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 371.04 0.00 0.00 0.00 0.00
04.13.13.01 VIDRIO SEMIDOBLE. PROVISION Y COLOCACION EN VENTANAS FIERRO 371.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 371.04 0.00 0.00 0.00 0.00
04.13.14 PINTURA 5,115.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,294.51 2,821.12 0.00 0.00 0.00
04.13.14.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 3,605.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,294.51 1,311.15 0.00 0.00 0.00
04.13.14.02 PINTURA LATEX CIELO RASO 02 MANOS inc./IMPRIMANTE 1,509.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,509.97 0.00 0.00 0.00
04.13.15 SISTEMA DE DOSIFICACION 98,837.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 98,837.14 0.00 0.00 0.00 0.00
04.13.15.01 SUMINISTRO e INSTALACION BOMBA p/DOSIFICADOR QUIMICOS 37,156.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37,156.44 0.00 0.00 0.00 0.00
04.13.15.02 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 1 1/2" 346.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 346.52 0.00 0.00 0.00 0.00
04.13.15.03 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 3" 57.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57.50 0.00 0.00 0.00 0.00
04.13.15.04 SUMINISTRO e INSTALACION AGITADOR ELECTRICO 61,276.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 61,276.68 0.00 0.00 0.00 0.00
04.13.16 SISTEMA DE AGUA FRIA 1,619.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,619.93 0.00 0.00 0.00 0.00
04.13.16.01 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 1 1/4" 46.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 46.74 0.00 0.00 0.00 0.00
04.13.16.02 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 1" 29.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 29.26 0.00 0.00 0.00 0.00
04.13.16.03 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 3/4" 61.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 61.95 0.00 0.00 0.00 0.00
04.13.16.04 VALVULAS COMPUERTA BRONCE 2" 240.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 240.34 0.00 0.00 0.00 0.00
04.13.16.05 VALVULAS COMPUERTA BRONCE 1/2" 1,103.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,103.16 0.00 0.00 0.00 0.00
04.13.16.06 SUMINISTRO e INSTALACION DUCHA EMERGENCIA 138.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 138.48 0.00 0.00 0.00 0.00
04.14 LABORATORIO, OFICINA y OFICINA DE CONTROL DE AUTOMATIZACION 179,205.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,186.69 27,873.01 34,035.08 25,899.57 18,378.56 71,832.49 0.00 0.00 0.00 0.00
04.14.01 TRABAJOS PRELIMINARES 514.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 514.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.01.01 LIMPIEZA TERRENO MANUAL 277.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 277.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.01.02 TRAZO y REPLANTEO 236.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 236.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.02 MOVIMIENTO DE TIERRAS 3,098.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 672.47 2,426.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.02.01 EXCAVACION PARA CIMIENTOS HASTA 1.50M TERRENO NORMAL 1,748.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 672.47 1,075.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.02.02 NIVELACION INTERIOR APISONADO MANUAL 249.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 249.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.02.03 RELLENO CON MATERIAL PROPIO 568.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 568.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.02.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 533.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 533.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.03 OBRAS DE CONCRETO SIMPLE 8,315.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,785.75 2,529.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.03.01 ENCOFRADO y DESENCOFRADO SOBRECIMIENTO HASTA 0.30M 2,793.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,793.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.03.02 CONCRETO C:H 1:8 + 25 % PM; f'c = 100 Kg/cm² p/SOBRECIMIENTO 991.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 991.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.03.03 CONCRETO EN FALSO PISO DE 4" C:H 2,529.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,529.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.03.04 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDO 2,000.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,000.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04 OBRAS DE CONCRETO ARMADO 38,611.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,660.93 18,950.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.01 ZAPATAS 6,046.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,046.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.01.01 CONCRETO f'c = 210 Kg/cm² p/ZAPATA 5,056.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,056.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.01.02 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 990.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 990.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.02 VIGAS DE CIMENTACION 7,345.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,345.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.02.01 CONCRETO f'c = 210 Kg/cm² p/VIGA CIMENTACION 2,706.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,706.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.02.02 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 3,852.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,852.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.02.03 ENCOFRADO Y DESENCOFRADO VIGA DE CIMENTACION 786.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 786.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.03 COLUMNAS 5,743.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,743.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.03.01 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 1,387.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,387.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 2,501.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,501.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.03.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,854.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,854.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.04 VIGAS 8,668.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,668.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.04.01 CONCRETO f'c = 210 Kg/cm² p/VIGA 2,182.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,182.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.04.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 3,798.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,798.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 2,687.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,687.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.05 LOSAS ALIGERADAS 10,808.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 525.92 10,282.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.05.01 CONCRETO f'c = 210 Kg/cm² p/LOSA ALIGERADA 2,772.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,772.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.05.02 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA ALIGERADA 4,207.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 525.92 3,681.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.05.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,517.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,517.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.04.05.04 LADRILLO HUECO ARCILLA 15 x 30 x 30 cm p/LOSA ALIGERADA 2,311.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,311.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.05 ALBAÑILERIA 11,199.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,199.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.05.01 MURO CABEZA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 611.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 611.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.05.02 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 10,588.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,588.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.06 REVOQUES y REVESTIMIENTO 14,103.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,355.36 12,748.03 0.00 0.00 0.00 0.00 0.00 0.00
04.14.06.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO c/MORTERO C:A 1:5 241.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 241.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.14.06.02 TARRAJEO INTERIOR c/MORTERO C:A 1:5 x 1.5 cm ( in. colum empot) 7,794.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,113.55 6,681.31 0.00 0.00 0.00 0.00 0.00 0.00
04.14.06.03 TARRAJEO EXTERIOR c/MORTERO C:A 1:5 x 1.5 cm ( in. colum empot) 5,063.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,063.49 0.00 0.00 0.00 0.00 0.00 0.00
04.14.06.04 VESTIDURA DERRAME 1,003.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,003.23 0.00 0.00 0.00 0.00 0.00 0.00
04.14.07 CIELORRASO 5,269.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,269.39 0.00 0.00 0.00 0.00 0.00 0.00
04.14.07.01 CIELORRASO c/MEZCLA C:A 1:5 5,269.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,269.39 0.00 0.00 0.00 0.00 0.00 0.00
04.14.08 PISOS y PAVIMENTOS 5,049.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,049.31 0.00 0.00 0.00 0.00 0.00 0.00
04.14.08.01 CONTRAPISO (e = 48 mm) 2,088.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,088.45 0.00 0.00 0.00 0.00 0.00 0.00
04.14.08.02 PISO CERAMICA (20 x 20 cm) p/BAÑO 202.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 202.91 0.00 0.00 0.00 0.00 0.00 0.00
04.14.08.03 VEREDA RIGIDA DE CONCRETO f' = 140 Kg/cm² (10.00 cm); PASTA 1:2 2,757.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,757.95 0.00 0.00 0.00 0.00 0.00 0.00
04.14.09 CONTRAZOCALOS 2,832.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,832.84 0.00 0.00 0.00 0.00 0.00 0.00
04.14.09.01 CONTRAZOCALO CEDRO 3/4" x 4" RODON 3/4" 2,832.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,832.84 0.00 0.00 0.00 0.00 0.00 0.00
04.14.10 ZOCALOS 648.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 648.31 0.00 0.00 0.00 0.00 0.00
04.14.10.01 ZOCALO CERAMICO COLOR (20 x 20 cm) 648.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 648.31 0.00 0.00 0.00 0.00 0.00
04.14.11 CARPINTERIA METALICA 7,875.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,875.82 0.00 0.00 0.00 0.00 0.00
04.14.11.01 PUERTA METAL LAC 1/16" y VENTANA PLEGADA c/MARCO 2" x 2" x 1/4" (inc. pintura) 6,175.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,175.00 0.00 0.00 0.00 0.00 0.00
04.14.11.02 VENTANA FIERRO (inc. pintura) 1,700.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,700.82 0.00 0.00 0.00 0.00 0.00
04.14.12 CARPINTERIA DE MADERA 5,058.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,058.36 0.00 0.00 0.00 0.00 0.00
04.14.12.01 PUERTA MADERA CEDRO (2.10 x 0.90 m) 847.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 847.65 0.00 0.00 0.00 0.00 0.00
04.14.12.02 PUERTA MADERA y VIDRIO INTERCONECCION (Oficina de Jefatura c/Oficina de Control) 240.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 240.71 0.00 0.00 0.00 0.00 0.00
04.14.12.03 REPOSTERO SUPERIOR MADERA CEDRO (Laboratorio) 1,488.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,488.15 0.00 0.00 0.00 0.00 0.00
04.14.12.04 REPOSTERO INFERIOR MADERA CEDRO (Laboratorio) 2,481.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,481.85 0.00 0.00 0.00 0.00 0.00
04.14.13 VIDRIOS, CRISTALES y SIMILARES 431.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 431.45 0.00 0.00 0.00 0.00 0.00
04.14.13.01 VIDRIO SEMIDOBLE. PROVISION Y COLOCACION EN VENTANAS FIERRO 431.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 431.45 0.00 0.00 0.00 0.00 0.00
04.14.14 PINTURA 4,178.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,304.79 2,873.76 0.00 0.00 0.00 0.00
04.14.14.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 2,609.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,304.79 1,304.79 0.00 0.00 0.00 0.00
04.14.14.02 PINTURA LATEX CIELO RASO 02 MANOS inc./IMPRIMANTE 1,568.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,568.97 0.00 0.00 0.00 0.00
04.14.15 APARATOS y ACCESORIOS SANITARIOS 1,565.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,565.56 0.00 0.00 0.00 0.00 0.00
04.14.15.01 INODORO TANQUE BAJO BLANCO 205.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 205.39 0.00 0.00 0.00 0.00 0.00
04.14.15.02 LAVADERO DE COCINA- LABORATORIO 896.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 896.56 0.00 0.00 0.00 0.00 0.00
04.14.15.03 LAVATORIO DE BAÑO 396.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 396.59 0.00 0.00 0.00 0.00 0.00
04.14.15.04 DUCHA 67.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 67.02 0.00 0.00 0.00 0.00 0.00
04.14.16 SISTEMA DE AGUA FRIA 1,494.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,494.27 0.00 0.00 0.00 0.00 0.00
04.14.16.01 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 1 1/4" 202.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 202.19 0.00 0.00 0.00 0.00 0.00
04.14.16.02 SUMINISTRO E INSTALACION DE TUBERIA P.V.C. C-10 DN=1" 164.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 164.92 0.00 0.00 0.00 0.00 0.00
04.14.16.03 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 3/4" 24.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24.80 0.00 0.00 0.00 0.00 0.00
04.14.16.04 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 1/2" 4.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.64 0.00 0.00 0.00 0.00 0.00
04.14.16.05 CAJA REGISTRO DESAGUE 12" x 24" 485.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 485.96 0.00 0.00 0.00 0.00 0.00
04.14.16.06 SALIDA DESAGUE PVC 4" 611.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 611.76 0.00 0.00 0.00 0.00 0.00
04.14.17 MOBILIARIO y/o EQUIPAMIENTO 68,958.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 68,958.73 0.00 0.00 0.00 0.00
04.14.17.01 SUMINISTRO e INSTALACION EQUIPOS p/LABORATORIO 60,086.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 60,086.56 0.00 0.00 0.00 0.00
04.14.17.02 SUMINISTRO e INSTALACION MOBILIARIO p/OFICINA 3,054.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,054.86 0.00 0.00 0.00 0.00
04.14.17.03 SUMINISTRO e INSTALACION TELEVISOR SMART TV 60" p/CONTROL y MONITOREO, ENTRADA USB 5,817.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,817.31 0.00 0.00 0.00 0.00
04.15 CASA DEL OPERADOR 50,906.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,039.74 22,601.88 13,181.03 2,083.39 0.00 0.00 0.00 0.00
04.15.01 TRABAJOS PRELIMINARES 181.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 181.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.01.01 LIMPIEZA TERRENO MANUAL 97.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 97.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.01.02 TRAZO y REPLANTEO 83.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 83.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.02 MOVIMIENTO DE TIERRAS 1,058.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,058.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.02.01 EXCAVACION PARA CIMIENTOS HASTA 1.50M TERRENO NORMAL 602.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 602.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.02.02 NIVELACION INTERIOR APISONADO MANUAL 88.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 88.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.02.03 RELLENO CON MATERIAL PROPIO 167.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 167.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.02.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 200.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 200.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.03 CONCRETO SIMPLE 4,194.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,300.90 893.73 0.00 0.00 0.00 0.00 0.00 0.00
04.15.03.01 ENCOFRADO y DESENCOFRADO SOBRECIMIENTO HASTA 0.30M 2,087.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,087.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.03.02 CONCRETO C:H 1:8 + 25 % PM; f'c = 100 Kg/cm² p/SOBRECIMIENTO 448.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 448.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.03.03 CONCRETO EN FALSOPISO DE 4" DE 1:8 CEM-HOR 893.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 893.73 0.00 0.00 0.00 0.00 0.00 0.00
04.15.03.04 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDO 764.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 764.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04 CONCRETO ARMADO 15,321.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,498.37 6,823.55 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.01 ZAPATAS 1,924.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,924.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.01.01 CONCRETO f'c = 210 Kg/cm² p/ZAPATA 1,479.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,479.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.01.02 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 444.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 444.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.02 VIGAS DE CIMENTACION 3,257.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,257.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.02.01 CONCRETO f'c = 210 Kg/cm² p/VIGA CIMENTACION 1,020.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,020.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.02.02 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,686.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,686.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.02.03 ENCOFRADO Y DESENCOFRADO VIGA DE CIMENTACION 550.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 550.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.03 COLUMNAS 2,814.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,814.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.03.01 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 695.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 695.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 1,250.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,250.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.03.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 868.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 868.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.04 VIGAS 3,507.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,507.58 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.04.01 CONCRETO f'c = 210 Kg/cm² p/VIGA 1,000.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,000.30 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.04.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 1,283.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,283.99 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,223.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,223.29 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.05 LOSAS ALIGERADAS 3,818.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 502.36 3,315.97 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.05.01 CONCRETO f'c = 210 Kg/cm² p/LOSA ALIGERADA 993.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 993.14 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.05.02 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA ALIGERADA 1,507.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 502.36 1,004.72 0.00 0.00 0.00 0.00 0.00 0.00
2 de 10
CALENDARIO DE AVANCE DE OBRA VALORIZADO ACTUALIZADO A LA FECHA DE INICIO DE OBRA
OBRA : INSTALACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DE LOS PP.JJ. VILLA PROGRESO, MIRAFLORES, LAS VEGAS, SAMAN, SAN FRANCISCO DE ASIS, LA UNION, SAN JUAN DE DIOS Y RAMIRO PRIALE II - CHICLAYO
ENTIDAD : ENTIDAD PRESTADORA DE SERVICIOS DE SANEAMIENTO DE LAMBAYEQUE S.A. - EPSEL S.A.
CONTRATISTA : CONSORCIO PROGRESO
SUPERVISION : CONSORCIO SUPERVISOR ASIS
UBICACIÓN : CHICLAYO - CHICLAYO - LAMBAYEQUE
Duración (Meses)
Item Descripción Parcial (S/.)
Mar-2019 Abr-2019 May-2019 Jun-2019 Jul-2019 Ago-2019 Sep-2019 Oct-2019 Nov-2019 Dic-2019 Ene-2020 Feb-2020 Mar-2020 Abr-2020 May-2020 Jun-2020 Jul-2020 Ago-2020 Sep-2020 Oct-2020
04.15.04.05.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 490.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 490.32 0.00 0.00 0.00 0.00 0.00 0.00
04.15.04.05.04 LADRILLO HUECO ARCILLA 15 x 30 x 30 cm p/LOSA ALIGERADA 827.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 827.79 0.00 0.00 0.00 0.00 0.00 0.00
04.15.05 ALBAÑILERIA 4,234.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,234.07 0.00 0.00 0.00 0.00 0.00 0.00
04.15.05.01 MURO CABEZA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 596.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 596.80 0.00 0.00 0.00 0.00 0.00 0.00
04.15.05.02 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 3,637.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,637.27 0.00 0.00 0.00 0.00 0.00 0.00
04.15.06 REVOQUES ENLUCIDOS Y MOLDURAS 6,139.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,139.34 0.00 0.00 0.00 0.00 0.00 0.00
04.15.06.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO c/MORTERO C:A 1:5 246.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 246.28 0.00 0.00 0.00 0.00 0.00 0.00
04.15.06.02 TARRAJEO INTERIOR c/MORTERO C:A 1:5 x 1.5 cm ( in. colum empot) 2,621.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,621.08 0.00 0.00 0.00 0.00 0.00 0.00
04.15.06.03 TARRAJEO EXTERIOR c/MORTERO C:A 1:5 x 1.5 cm ( in. colum empot) 2,641.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,641.02 0.00 0.00 0.00 0.00 0.00 0.00
04.15.06.04 VESTIDURA DE DERRAMES EN PUERTAS, VENTANAS Y VANOS. 630.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 630.96 0.00 0.00 0.00 0.00 0.00 0.00
04.15.07 CIELORRASO 1,989.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,989.46 0.00 0.00 0.00 0.00 0.00 0.00
04.15.07.01 CIELO RASO c/MORTERO C:A 1:5 1,989.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,989.46 0.00 0.00 0.00 0.00 0.00 0.00
04.15.08 PISOS y PAVIMENTOS 2,521.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,521.73 0.00 0.00 0.00 0.00 0.00 0.00
04.15.08.01 CONTRAPISO (e = 48 mm) 788.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 788.49 0.00 0.00 0.00 0.00 0.00 0.00
04.15.08.02 PISO CERAMICA (20 x 20 cm) p/BAÑO 211.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 211.03 0.00 0.00 0.00 0.00 0.00 0.00
04.15.08.03 VEREDA c/CONCRETO f' = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base de afirmado 1,522.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,522.21 0.00 0.00 0.00 0.00 0.00 0.00
04.15.09 CONTRAZOCALOS 1,194.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,194.78 0.00 0.00 0.00 0.00 0.00
04.15.09.01 CONTRAZOCALO CEDRO 3/4" x 4" RODON 3/4" 1,194.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,194.78 0.00 0.00 0.00 0.00 0.00
04.15.10 ZOCALOS 660.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 660.30 0.00 0.00 0.00 0.00 0.00
04.15.10.01 ZOCALO CERAMICO COLOR (20 x 20 cm) 660.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 660.30 0.00 0.00 0.00 0.00 0.00
04.15.11 CARPINTERIA METALICA y HERRERIA 7,729.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,729.94 0.00 0.00 0.00 0.00 0.00
04.15.11.01 PUERTA METAL LAC 1/16" y VENTANA PLEGADA c/MARCO 2" x 2" x 1/4" (inc. pintura) 7,163.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,163.00 0.00 0.00 0.00 0.00 0.00
04.15.11.02 VENTANA FIERRO (inc. pintura) 566.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 566.94 0.00 0.00 0.00 0.00 0.00
04.15.12 VIDRIOS, CRISTALES y SIMILARES 195.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 195.71 0.00 0.00 0.00 0.00 0.00
04.15.12.01 VIDRIO SEMIDOBLE. PROVISION Y COLOCACION EN VENTANAS FIERRO 195.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 195.71 0.00 0.00 0.00 0.00 0.00
04.15.13 PINTURA 1,660.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 800.95 859.35 0.00 0.00 0.00 0.00
04.15.13.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 1,067.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 800.95 266.99 0.00 0.00 0.00 0.00
04.15.13.02 PINTURA LATEX CIELO RASO 02 MANOS inc./IMPRIMANTE 592.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 592.36 0.00 0.00 0.00 0.00
04.15.14 APARATOS y ACCESORIOS SANITARIOS 669.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 669.00 0.00 0.00 0.00 0.00 0.00
04.15.14.01 INODORO TANQUE BAJO BLANCO 205.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 205.39 0.00 0.00 0.00 0.00 0.00
04.15.14.02 LAVATORIO FONTANA COLOR BLANCO 396.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 396.59 0.00 0.00 0.00 0.00 0.00
04.15.14.03 DUCHA 67.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 67.02 0.00 0.00 0.00 0.00 0.00
04.15.15 SISTEMA DE AGUA FRIA 1,930.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,930.35 0.00 0.00 0.00 0.00 0.00
04.15.15.01 SUMINISTRO E INSTALACION DE TUBERIA P.V.C. C-10 DN=1 1/2" 1,434.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,434.12 0.00 0.00 0.00 0.00 0.00
04.15.15.02 SUMINISTRO E INSTALACION DE TUBERIA P.V.C. C-10 DN=3/4" 9.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.92 0.00 0.00 0.00 0.00 0.00
04.15.15.03 SUMINISTRO E INSTALACION DE TUBERIA P.V.C. C-10 DN=1/2" 13.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.92 0.00 0.00 0.00 0.00 0.00
04.15.15.04 CAJA REGISTRO 242.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 242.98 0.00 0.00 0.00 0.00 0.00
04.15.15.05 SALIDA DESAGUE EN PVC 229.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 229.41 0.00 0.00 0.00 0.00 0.00
04.15.16 MOBILIARIO y/o EQUIPAMIENTO 1,224.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,224.04 0.00 0.00 0.00 0.00
04.15.16.01 SUMINISTRO e INSTALACION MOBILIARIO p/CASETA 452.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 452.21 0.00 0.00 0.00 0.00
04.15.16.02 SUMINISTRO e INSTALACION ARMARIO p/VESTIDOR 771.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 771.83 0.00 0.00 0.00 0.00
04.16 CASETA DE VIGILANCIA 29,595.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,395.30 15,473.25 1,726.72 0.00 0.00 0.00 0.00
04.16.01 TRABAJOS PRELIMINARES 72.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 72.25 0.00 0.00 0.00 0.00 0.00 0.00
04.16.01.01 LIMPIEZA TERRENO MANUAL 38.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38.96 0.00 0.00 0.00 0.00 0.00 0.00
04.16.01.02 TRAZO, NIVELACION y REPLANTEO 33.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33.29 0.00 0.00 0.00 0.00 0.00 0.00
04.16.02 MOVIMIENTO DE TIERRAS 662.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 662.56 0.00 0.00 0.00 0.00 0.00 0.00
04.16.02.01 EXCAVACION PARA CIMIENTOS HASTA 1.50M TERRENO NORMAL 388.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 388.49 0.00 0.00 0.00 0.00 0.00 0.00
04.16.02.02 NIVELACION INTERIOR APISONADO MANUAL 35.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35.02 0.00 0.00 0.00 0.00 0.00 0.00
04.16.02.03 RELLENO CON MATERIAL PROPIO 110.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 110.83 0.00 0.00 0.00 0.00 0.00 0.00
04.16.02.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 128.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 128.22 0.00 0.00 0.00 0.00 0.00 0.00
04.16.03 OBRAS DE CONCRETO SIMPLE 1,626.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,626.52 0.00 0.00 0.00 0.00 0.00 0.00
04.16.03.01 ENCOFRADO y DESENCOFRADO SOBRECIMIENTO HASTA 0.30M 595.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 595.37 0.00 0.00 0.00 0.00 0.00 0.00
04.16.03.02 CONCRETO C:H 1:8 + 25 % PM; f'c = 100 Kg/cm² p/SOBRECIMIENTO 212.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 212.35 0.00 0.00 0.00 0.00 0.00 0.00
04.16.03.03 CONCRETO EN FALSOPISO DE 4" DE 1:8 CEM-HOR 355.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 355.47 0.00 0.00 0.00 0.00 0.00 0.00
04.16.03.04 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDDO 463.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 463.33 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04 OBRAS DE CONCRETO ARMADO 7,799.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,799.56 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.01 ZAPATAS 1,282.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,282.80 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.01.01 CONCRETO f'c = 210 Kg/cm² p/ZAPATA 986.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 986.60 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.01.02 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 296.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 296.20 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.02 VIGAS DE CIMENTACION 1,716.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,716.49 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.02.01 CONCRETO f'c = 210 Kg/cm² p/VIGA CIMENTACION 510.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 510.43 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.02.02 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 930.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 930.93 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.02.03 ENCOFRADO Y DESENCOFRADO VIGA DE CIMENTACION 275.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 275.13 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.03 COLUMNAS 1,875.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,875.01 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.03.01 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 462.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 462.47 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 833.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 833.76 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.03.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 578.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 578.78 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.04 VIGAS 1,538.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,538.20 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.04.01 CONCRETO f'c = 210 Kg/cm² p/VIGA 414.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 414.51 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.04.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 575.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 575.76 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 547.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 547.93 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.05 LOSAS ALIGERADAS 1,387.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,387.06 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.05.01 CONCRETO f'c = 210 Kg/cm² p/LOSA ALIGERADA 397.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 397.92 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.05.02 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA ALIGERADA 526.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 526.50 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.05.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 181.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 181.51 0.00 0.00 0.00 0.00 0.00 0.00
04.16.04.05.04 LADRILLO HUECO ARCILLA 15 x 30 x 30 cm p/LOSA ALIGERADA 281.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 281.13 0.00 0.00 0.00 0.00 0.00 0.00
04.16.05 ALBAÑILERIA 2,071.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,071.04 0.00 0.00 0.00 0.00 0.00 0.00
04.16.05.01 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 2,071.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,071.04 0.00 0.00 0.00 0.00 0.00 0.00
04.16.06 REVOQUES ENLUCIDOS Y MOLDURAS 3,527.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 163.37 3,363.88 0.00 0.00 0.00 0.00 0.00
04.16.06.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO c/MORTERO C:A 1:5 163.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 163.37 0.00 0.00 0.00 0.00 0.00 0.00
04.16.06.02 TARRAJEO INTERIOR c/MORTERO C:A 1:5 x 1.5 cm ( in. colum empot) 1,452.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,452.18 0.00 0.00 0.00 0.00 0.00
04.16.06.03 TARRAJEO EXTERIOR c/MORTERO C:A 1:5 x 1.5 cm ( in. colum empot) 1,519.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,519.74 0.00 0.00 0.00 0.00 0.00
04.16.06.04 VESTIDURA DERRAME 391.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 391.96 0.00 0.00 0.00 0.00 0.00
04.16.07 CIELORRASOS 675.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 675.56 0.00 0.00 0.00 0.00 0.00
04.16.07.01 CIELORRASO c/MEZCLA C:A 1:5 675.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 675.56 0.00 0.00 0.00 0.00 0.00
04.16.08 PISOS y PAVIMENTOS 1,476.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,476.11 0.00 0.00 0.00 0.00 0.00
04.16.08.01 CONTRAPISO (e = 48 mm) 293.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 293.45 0.00 0.00 0.00 0.00 0.00
04.16.08.02 PISO CERAMICA (20 x 20 cm) p/BAÑO 154.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 154.75 0.00 0.00 0.00 0.00 0.00
04.16.08.03 VEREDA c/CONCRETO f' = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base de afirmado 1,027.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,027.91 0.00 0.00 0.00 0.00 0.00
04.16.09 CONTRAZOCALOS 658.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 658.56 0.00 0.00 0.00 0.00 0.00
04.16.09.01 CONTRAZOCALO CEDRO 3/4" x 4" RODON 3/4" 658.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 658.56 0.00 0.00 0.00 0.00 0.00
04.16.10 ZOCALOS 438.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 438.02 0.00 0.00 0.00 0.00 0.00
04.16.10.01 ZOCALO CERAMICO COLOR (20 x 20 cm) 438.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 438.02 0.00 0.00 0.00 0.00 0.00
04.16.11 CARPINTERIA METALICA 4,518.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,518.94 0.00 0.00 0.00 0.00 0.00
04.16.11.01 PUERTA METAL LAC 1/16" y VENTANA PLEGADA c/MARCO 2" x 2" x 1/4" (inc. pintura) 3,952.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,952.00 0.00 0.00 0.00 0.00 0.00
04.16.11.02 VENTANA FIERRO (inc. pintura) 566.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 566.94 0.00 0.00 0.00 0.00 0.00
04.16.12 VIDRIOS, CRISTALES y SIMILARES 97.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 97.06 0.00 0.00 0.00 0.00 0.00
04.16.12.01 VIDRIO SEMIDOBLE. PROVISION Y COLOCACION EN VENTANAS FIERRO 97.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 97.06 0.00 0.00 0.00 0.00 0.00
04.16.13 PINTURA 804.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 301.53 502.68 0.00 0.00 0.00 0.00
04.16.13.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 603.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 301.53 301.53 0.00 0.00 0.00 0.00
04.16.13.02 PINTURA LATEX CIELO RASO 02 MANOS inc./IMPRIMANTE 201.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201.15 0.00 0.00 0.00 0.00
04.16.14 APARATOS Y ACCESORIOS SANITARIOS 601.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 601.98 0.00 0.00 0.00 0.00 0.00
04.16.14.01 INODORO TANQUE BAJO BLANCO 205.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 205.39 0.00 0.00 0.00 0.00 0.00
04.16.14.02 LAVATORIO FONTANA COLOR BLANCO 396.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 396.59 0.00 0.00 0.00 0.00 0.00
04.16.15 SISTEMA DE AGUA FRIA 3,341.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,341.61 0.00 0.00 0.00 0.00 0.00
04.16.15.01 SUMINISTRO E INSTALACION DE TUBERIA P.V.C. C-10 DN=1 1/2" 2,830.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,830.50 0.00 0.00 0.00 0.00 0.00
04.16.15.02 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 3/4" 24.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24.80 0.00 0.00 0.00 0.00 0.00
04.16.15.03 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 1/2" 13.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.92 0.00 0.00 0.00 0.00 0.00
04.16.15.04 CAJA REGISTRO DESAGUE 12" x 24" 242.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 242.98 0.00 0.00 0.00 0.00 0.00
04.16.15.05 SALIDA DESAGUE EN PVC 229.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 229.41 0.00 0.00 0.00 0.00 0.00
04.16.16 MOBILIARIO y/o EQUIPAMIENTO 1,224.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,224.04 0.00 0.00 0.00 0.00
04.16.16.01 SUMINISTRO e INSTALACION MOBILIARIO p/CASETA 452.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 452.21 0.00 0.00 0.00 0.00
04.16.16.02 SUMINISTRO e INSTALACION ARMARIO p/VESTIDOR 771.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 771.83 0.00 0.00 0.00 0.00
04.17 CASA DE FUERZA 298,345.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,591.60 72,393.77 181,853.64 29,506.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.01 TRABAJOS PRELIMINARES 129.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 129.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.01.01 LIMPIEZA TERRENO MANUAL 69.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 69.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.01.02 TRAZO y REPLANTEO 59.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 59.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.02 MOVIMIENTO DE TIERRAS 776.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 776.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.02.01 EXCAVACION PARA CIMIENTOS HASTA 1.50M TERRENO NORMAL 441.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 441.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.02.02 NIVELACION INTERIOR APISONADO MANUAL 62.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.02.03 RELLENO CON MATERIAL PROPIO 128.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 128.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.02.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 144.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 144.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.03 OBRAS DE CONCRETO SIMPLE 1,811.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,811.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.03.01 ENCOFRADO y DESENCOFRADO SOBRECIMIENTO HASTA 0.30M 344.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 344.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.03.02 CONCRETO C:H 1:8 + 25 % PM; f'c = 100 Kg/cm² p/SOBRECIMIENTO 328.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 328.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.03.03 CONCRETO EN FALSOPISO DE 4" DE 1:8 CEM-HOR 638.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 638.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.03.04 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDO 500.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 500.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04 OBRAS DE CONCRETO ARMADO 9,917.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,917.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.01 ZAPATAS 1,490.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,490.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.01.01 CONCRETO f'c = 210 Kg/cm² p/ZAPATA 1,151.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,151.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.01.02 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 339.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 339.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.02 VIGAS DE CIMENTACION 2,254.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,254.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.02.01 CONCRETO f'c = 210 Kg/cm² p/VIGA CIMENTACION 705.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 705.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.02.02 ACERO DE REFUERZO GRADO 60 1,167.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,167.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.02.03 ENCOFRADO Y DESENCOFRADO VIGA DE CIMENTACION 381.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 381.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.03 COLUMNAS 2,094.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,094.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.03.01 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 462.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 462.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 833.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 833.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.03.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 797.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 797.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.04 VIGAS 1,980.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,980.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.04.01 CONCRETO f'c = 210 Kg/cm² p/VIGA 534.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 534.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.04.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 768.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 768.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 678.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 678.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.05 LOSAS ALIGERADAS 2,097.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,097.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.05.01 CONCRETO f'c = 210 Kg/cm² p/LOSA ALIGERADA 524.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 524.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.05.02 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA ALIGERADA 803.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 803.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.05.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 327.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 327.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.04.05.04 LADRILLO HUECO ARCILLA 15 x 30 x 30 cm p/LOSA ALIGERADA 441.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 441.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05 ARQUITECTURA 13,290.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,956.06 10,237.51 1,097.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.01 MUROS y TABIQUES DE ALBAÑILERIA 2,445.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,956.06 489.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.01.01 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 2,445.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,956.06 489.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.02 REVOQUES y REVESTIMIENTOS 2,293.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,293.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.02.01 TARRAJEO INTERIOR c/MORTERO C:A 1:5 x 1.5 cm ( in. colum empot) 1,779.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,779.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.02.02 TARRAJEO EXTERIOR c/MORTERO C:A 1:5 x 1.5 cm ( in. colum empot) 350.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 350.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.02.03 VESTIDURA DE DERRAMES EN PUERTAS, VENTANAS Y VANOS. 164.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 164.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.03 CIELO RASO y FALSO CIELO RASO 1,061.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,061.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.03.01 CIELO RASO c/MORTERO C:A 1:5 1,061.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,061.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.04 PISOS y PAVIMENTOS 1,594.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,594.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.04.01 CONTRAPISO (e = 48 mm) 420.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 420.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.04.02 VEREDA c/CONCRETO f' = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base de afirmado 1,173.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,173.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.05 CARPINTERIA METALICA y HERRERIA 4,689.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,689.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.05.01 PUERTA METAL LAC 1/16" y VENTANA PLEGADA c/MARCO 2" x 2" x 1/4" (inc. pintura) 3,952.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,952.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.05.02 VENTANA FIERRO (inc. pintura) 737.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 737.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.06 VIDRIOS, CRISTALES y SIMILARES 109.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 109.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.06.01 VIDRIO SEMIDOBLE. PROVISION Y COLOCACION EN VENTANAS FIERRO 109.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 109.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.07 PINTURA 1,097.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,097.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.07.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 781.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 781.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.05.07.02 PINTURA LATEX CIELO RASO 02 MANOS inc./IMPRIMANTE 315.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 315.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.06 VARIOS 272,419.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62,156.26 180,756.63 29,506.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.06.01 SUMINISTRO e INSTALACION GENERADOR ELECTRICO 200 KVA 226,287.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62,156.26 164,131.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.06.02 ESCALERA TELESCOPICA DE ALUMINIO DE 6mts 5,384.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,384.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.17.06.03 SEMBRADO AREAS VERDES p/PLANTA TRATAMIENTO AGUA POTABLE 40,747.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,240.69 29,506.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18 RED PARA SISTEMA DE LODOS 31,863.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31,419.58 443.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.01 TRABAJOS PRELIMINARES 156.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 156.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.01.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 55.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 55.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.01.02 TRAZOS, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 100.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02 MOVIMIENTO DE TIERRAS 10,628.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,628.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.01 TRABAJOS PRELIMINARES 6,742.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,742.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.01.01 EXCAVACION ZANJA c/EQUIPO HASTA 6.50 m; af = 1.00 m 6,742.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,742.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.02 REFINE y NIVELACION DE ZANJAS 59.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 59.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.02.01 REFINE y NIVELACION FONDO ZANJA; a = 1.00 m 59.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 59.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.03 CAMA DE APOYO PARA TUBERIAS 614.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 614.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.03.01 CAMA APOYO (equipo) c/RIPIO CORRIENTE; af = 1.00 m 614.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 614.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.04 RELLENO, APISONADO y COMPACTACION LATERAL CON MATERIAL DE PRESTAMO 659.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 659.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.04.01 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 315 mm; a = 1.00 m 659.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 659.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.05 RELLENO y COMPACTACION S/CLAVE TUBO C/MATERIAL DE PRESTAMO 938.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 938.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.05.01 RELLENO y COMPACTACION c/RIPIO CORRIENTE h = 0.30 m; c/EQUIPO p/TUBERIA Ø 315 mm; a = 1.00 m 938.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 938.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.06 RELLENO y COMPACTACION CON MATERIAL PROPIO 513.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 513.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.06.01 RELLENO y COMPACTACION c/MATERIAL PROPIO SELECCIONADO CAPAS c/0.20 m; a = variable hasta Nivel de Terreno Natural 513.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 513.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.07 ACARREO y ELIMINACION MATERIAL EXCEDENTE 1,100.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,100.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.02.07.01 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 1,100.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,100.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.03 BOMBEO EN ZANJAS 452.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 452.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.03.01 DRENAJE ZANJA HASTA 4.00 m 452.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 452.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.04 ENTIBADO DE ZANJAS 1,087.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,087.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.04.01 ENTIBADO ZANJA HASTA 4.00 m 1,087.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,087.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.05 SUMINISTRO e INSTALACION DE TUBERIAS 4,644.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,644.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.05.01 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 315 mm x 6.00 m hasta h = 4.50 m 4,644.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,644.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.06 PRUEBAS HIDRAULICAS 2,161.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,161.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.06.01 DOBLE PRUEBA HIDRAULICA p/TUBERIA Ø 315 mm PVC 2,161.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,161.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.07 BUZONES 12,732.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,289.07 443.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.07.01 BUZON TIPO "C" Ø interior 4.00 m inc./TARRAJEO INTERIOR prof. = 7.00 m 11,845.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,845.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.18.07.02 EMPALME BUZON y CONSTRUCCION DADO CONCRETO f'c = 175 Kg/cm² (0.55 x 0.55 x 0.55 m) 887.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 443.60 443.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19 CAMARA DE BOMBEO P/SISTEMA DE LODOS 224,224.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,413.23 98,791.24 100,020.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.01 TRABAJOS PRELIMINARES 316.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 316.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.01.01 LIMPIEZA TERRENO MANUAL 170.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 170.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.01.02 TRAZO y REPLANTEO 145.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 145.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02 ESTRUCTURAS 56,061.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,096.38 30,965.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.01 MOVIMIENTO DE TIERRAS 8,221.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,544.53 3,677.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.01.01 EXCAVACION TERRENO NORMAL SECO HASTA 1.30 m 1,060.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,060.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.01.02 EXCAVACION TERRENO NORMAL SATURADO H > 3.00 m 3,483.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,483.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.01.03 RELLENO c/PIEDRA TIPO CASCOTE 405.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 405.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.01.04 RELLENO y APISONADO PARED c/MATERIAL PROPIO SELECCIONADO 1,180.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,180.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.01.05 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 2,090.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,090.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.02 OBRAS DE CONCRETO SIMPLE 589.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 589.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.02.01 CONCRETO f'c = 140 Kg/cm² 589.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 589.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.03 OBRAS DE CONCRETO ARMADO 47,250.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,962.24 27,288.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.03.01 CAMARA DE BOMBEO 46,479.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,962.24 26,516.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.03.01.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 14,979.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,043.22 936.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.03.01.02 ENCOFRADO y DESENCOFRADO NORMAL p/CAMARA BOMBEO 10,761.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,919.02 4,842.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.03.01.03 CONCRETO f'c = 280 Kg/cm² p/CAMARA BOMBEO 20,737.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20,737.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.03.02 LOSA REMOVIBLE 771.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 771.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.03.02.01 LOSA REMOVIBLE CONCRETO 0.75 x 0.55 x 0.07 m; f'c = 280 Kg/cm²; p/CAMARA BOMBEO 164.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 164.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.03.02.02 TAPA DE BUZON D=1.30M CONCRETO 280KG/CM2 P/CAMARA DE BOMBEO INC/COLOCACION 525.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 525.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.02.03.02.03 DADO CONCRETO f'c = 280 Kg/cm² (0.30 x 0.40 x 0.50 m) 80.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 80.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.03 ARQUITECTURA 18,936.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,936.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.03.01 REVOQUES y REVESTIMIENTOS 4,284.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,284.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.03.01.01 TARRAJEO c/IMPERMEABILIZANTE 4,284.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,284.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.03.02 CARPINTERIA METALICA y HERRERIA 14,652.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,652.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.03.02.01 ESCALERA ACCESO f°g° (segun diseño) 12,791.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,791.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.03.02.02 BARANDA c/TUBERIA ACERO 1,794.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,794.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.03.02.03 REJILLA p/SUMIDERO c/PLATINA 1 1/4" x 1/4" @ 1/2" y PERFIL L 1 1/4" 66.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 66.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.04 INSTALACIONES ELECTROMECANICAS 148,909.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48,889.10 100,020.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.04.01 SUMINISTRO e INSTALACION ELECTROBOMBA SUMERGIBLE p/CAMARA BOMBEO 125,986.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,966.12 100,020.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.04.02 SUMINISTRO e INSTALACION ACCESORIOS p/CAMARA BOMBEO 19,789.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,789.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.19.04.03 ANCLAJE p/TUBERIA 3,133.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,133.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20 CASETA P/SISTEMA DE LODOS 66,581.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,741.63 19,606.51 30,233.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.01 TRABAJOS PRELIMINARES 326.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 326.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.01.01 LIMPIEZA TERRENO MANUAL 176.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 176.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.01.02 TRAZO y REPLANTEO 150.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 150.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02 ESTRUCTURAS 23,083.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,415.11 6,668.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.01 MOVIMIENTO DE TIERRAS 1,403.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,403.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.01.01 EXCAVACION TERRENO NORMAL SECO HASTA 3.00 m 912.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 912.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.01.02 RELLENO Y APISONADO PARED c/MATERIAL PRESTAMO (AFIRMADO) 28.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.01.03 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 463.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 463.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.02 OBRAS DE CONCRETO SIMPLE 6,795.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,795.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.02.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDDO 6,795.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,795.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03 OBRAS DE CONCRETO ARMADO 14,884.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,216.54 6,668.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.01 VIGAS DE CONEXION 5,622.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,622.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.01.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,279.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,279.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.01.02 ENCOFRADO Y DESENCOFRADO PVIGA DE CONEXION 606.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 606.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.01.03 CONCRETO f'c = 210 Kg/cm² p/VIGA DE CONEXION 3,737.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,737.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.02 COLUMNAS 2,593.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,593.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 830.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 830.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.02.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 1,204.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,204.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.02.03 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 558.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 558.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.03 VIGAS 3,006.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,006.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.03.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,115.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,115.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 1,157.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,157.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.03.03 CONCRETO f'c = 210 Kg/cm² p/VIGA 733.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 733.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.04 LOSAS ALIGERADAS 3,662.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,662.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.04.01 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA ALIGERADA 1,160.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,160.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.04.02 LADRILLO HUECO ARCILLA 15 x 30 x 30 cm p/LOSA ALIGERADA 637.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 637.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 903.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 903.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.02.03.04.04 CONCRETO f'c = 210 Kg/cm² p/LOSA ALIGERADA 959.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 959.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03 ARQUITECTURA 43,171.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,938.21 30,233.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.01 MUROS y TABIQUES DE ALBAÑILERIA 9,051.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,051.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.01.01 MURO CABEZA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 9,051.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,051.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.02 REVOQUES y REVESTIMIENTOS 7,490.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,703.70 5,787.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.02.01 TARRAJEO INTERIOR/EXTERIOR c/MORTERO C:A 1:5 6,814.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,703.70 5,111.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.02.02 VESTIDURA DERRAME 676.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 676.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.03 CIELO RASO y FALSO CIELO RASO 2,182.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,182.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.03.01 CIELO RASO c/MORTERO C:A 1:5 2,182.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,182.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.04 PISOS y PAVIMENTOS 4,532.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,532.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.04.01 VEREDA c/CONCRETO f' = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base de afirmado 1,817.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,817.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.04.02 PISO c/CONCRETO f' = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base de afirmado 2,715.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,715.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.05 CUBIERTAS 1,362.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,362.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.05.01 CUBIERTA CON PLANCHAS FIBRAFORTE DE 2.44m x 1.10m x 1.9mm 1,362.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,362.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.06 CARPINTERIA DE MADERA 4,874.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,874.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.06.01 ENTRAMADO DE MADERA PARA TECHO 4,874.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,874.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.07 CARPINTERIA METALICA y HERRERIA 11,837.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,837.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.07.01 VENTANA FIERRO (inc. pintura) 2,541.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,541.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.07.02 PUERTA METALICA (inc. pintura) 2,338.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,338.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.07.03 PORTON METALICO INGRESO 3.00 x 2.40 m (inc. pintura) 6,957.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,957.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.08 PINTURA 1,839.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,839.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.08.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 1,383.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,383.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.20.03.08.02 PINTURA LATEX CIELO RASO 02 MANOS inc./IMPRIMANTE 456.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 456.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21 REBOSE DE CAMARA DE BOMBEO P/SISTEMA DE LODOS 3,973.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,973.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.01 TRABAJOS PRELIMINARES 9.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.01.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 3.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.01.02 TRAZOS, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 6.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02 MOVIMIENTO DE TIERRAS 221.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 221.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.01 TRABAJOS PRELIMINARES 30.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 de 10
CALENDARIO DE AVANCE DE OBRA VALORIZADO ACTUALIZADO A LA FECHA DE INICIO DE OBRA
OBRA : INSTALACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DE LOS PP.JJ. VILLA PROGRESO, MIRAFLORES, LAS VEGAS, SAMAN, SAN FRANCISCO DE ASIS, LA UNION, SAN JUAN DE DIOS Y RAMIRO PRIALE II - CHICLAYO
ENTIDAD : ENTIDAD PRESTADORA DE SERVICIOS DE SANEAMIENTO DE LAMBAYEQUE S.A. - EPSEL S.A.
CONTRATISTA : CONSORCIO PROGRESO
SUPERVISION : CONSORCIO SUPERVISOR ASIS
UBICACIÓN : CHICLAYO - CHICLAYO - LAMBAYEQUE
Duración (Meses)
Item Descripción Parcial (S/.)
Mar-2019 Abr-2019 May-2019 Jun-2019 Jul-2019 Ago-2019 Sep-2019 Oct-2019 Nov-2019 Dic-2019 Ene-2020 Feb-2020 Mar-2020 Abr-2020 May-2020 Jun-2020 Jul-2020 Ago-2020 Sep-2020 Oct-2020
04.21.02.01.01 EXCAVACION ZANJA c/EQUIPO HASTA 2.50 m; af = 1.00 m 30.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.02 REFINE y NIVELACION DE ZANJAS 3.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.02.01 REFINE y NIVELACION FONDO ZANJA; a = 1.00 m 3.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.03 CAMA DE APOYO P/TUBERIAS 37.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.03.01 CAMA APOYO (equipo) c/RIPIO CORRIENTE; af = 1.00 m 37.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.04 RELLENO, APISONADO y COMPACTACION LATERAL CON MATERIAL DE PRESTAMO 35.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.04.01 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 315 mm; a = 1.00 m 35.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.05 RELLENO y COMPACTACION S/CLAVE TUBO C/MATERIAL DE PRESTAMO 55.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 55.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.05.01 RELLENO y COMPACTACION c/RIPIO CORRIENTE h = 0.30 m; c/EQUIPO p/TUBERIA Ø 315 mm; a = 1.00 m 55.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 55.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.06 RELLENO y COMPACTACIÓN CON MATERIAL PROPIO SELECCIONADO 31.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.06.01 RELLENO y COMPACTACION c/MATERIAL PROPIO SELECCIONADO CAPAS c/0.20 m; a = variable hasta Nivel de Terreno Natural 31.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.07 ACARREO y ELIMINACION MATERIAL EXCEDENTE 27.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 27.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.02.07.01 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 27.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 27.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.03 BOMBEO EN ZANJAS 24.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.03.01 DRENAJE ZANJA HASTA 2.50 m 24.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.04 ENTIBADO DE ZANJAS 66.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 66.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.04.01 ENTIBADO ZANJA HASTA 2.50 m 66.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 66.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.05 SUMINISTRO e INSTALACION DE TUBERIAS 78.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 78.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.05.01 TUBERIA PVC U; SN 2 = 2 KN/m² 78.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 78.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.05.01.01 SUMINISTRO e INSTALACION TUBERIA PVC U SN 2 Ø 200 mm x 6.00 m hasta h = 2.50 m 78.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 78.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.06 PRUEBAS HIDRAULICAS 125.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 125.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.06.01 DOBLE PRUEBA HIDRAULICA p/TUBERIA Ø 250 mm PVC 125.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 125.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.07 BUZONES y EMPALMES 3,447.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,447.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.07.01 BUZONES TIPO "B" 3,447.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,447.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.07.01.01 BUZON TIPO "B" Ø interior 1.20 m inc./TARRAJEO INTERIOR prof. = 3.00 m 3,374.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,374.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.21.07.01.02 CONCRETO f'c = 140 Kg/cm² p/ESTRUCTURA SALIDA 72.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 72.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22 LINEA DE IMPULSION P/SISTEMA DE LODOS 15,351.31 0.00 0.00 0.00 0.00 0.00 0.00 15,351.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.01 TRABAJOS PRELIMINARES 325.17 0.00 0.00 0.00 0.00 0.00 0.00 325.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.01.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 116.07 0.00 0.00 0.00 0.00 0.00 0.00 116.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.01.02 TRAZOS, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 209.10 0.00 0.00 0.00 0.00 0.00 0.00 209.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02 MOVIMIENTO DE TIERRAS 5,502.53 0.00 0.00 0.00 0.00 0.00 0.00 5,502.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.01 EXCAVACION DE ZANJAS 831.95 0.00 0.00 0.00 0.00 0.00 0.00 831.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.01.01 EXCAVACION ZANJA c/EQUIPO HASTA 2.00 m; af = 0.80 m 831.95 0.00 0.00 0.00 0.00 0.00 0.00 831.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.02 REFINE y NIVELACION DE ZANJAS 107.21 0.00 0.00 0.00 0.00 0.00 0.00 107.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.02.01 REFINE y NIVELACION FONDO ZANJA; a = 0.80 m 107.21 0.00 0.00 0.00 0.00 0.00 0.00 107.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.03 CAMA DE APOYO P/TUBERIAS 650.32 0.00 0.00 0.00 0.00 0.00 0.00 650.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.03.01 CAMA APOYO (equipo) c/ARENA FINA; af = 0.80 m 650.32 0.00 0.00 0.00 0.00 0.00 0.00 650.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.04 RELLENO, APISONADO y COMPACTACION LATERAL CON MATERIAL DE PRESTAMO 837.27 0.00 0.00 0.00 0.00 0.00 0.00 837.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.04.01 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 200 mm; a = 0.80 m 837.27 0.00 0.00 0.00 0.00 0.00 0.00 837.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.05 RELLENO y COMPACTACION S/CLAVE TUBERIA C/MATERIAL DE PRESTAMO 1,049.91 0.00 0.00 0.00 0.00 0.00 0.00 1,049.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.05.01 RELLENO y COMPACTACION c/RIPIO CORRIENTE h = 0.30 m; c/EQUIPO p/TUBERIA Ø 200 mm; a = 0.80 m 1,049.91 0.00 0.00 0.00 0.00 0.00 0.00 1,049.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.06 RELLENO y COMPACTACIÓN CON MATERIAL PROPIO SELECCIONADO 979.03 0.00 0.00 0.00 0.00 0.00 0.00 979.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.06.01 RELLENO y APISONADO ZANJA p/TUBERIA Ø = 200 mm c/MATERIAL PROPIO SELECCIONADO h = 1.80 m 979.03 0.00 0.00 0.00 0.00 0.00 0.00 979.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.07 ACARREO y ELIMINACION MATERIAL EXCEDENTE 1,046.84 0.00 0.00 0.00 0.00 0.00 0.00 1,046.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.02.07.01 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 1,046.84 0.00 0.00 0.00 0.00 0.00 0.00 1,046.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.03 BOMBEO EN ZANJAS 836.38 0.00 0.00 0.00 0.00 0.00 0.00 836.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.03.01 DRENAJE ZANJA HASTA 2.00 m, af=0.80m 836.38 0.00 0.00 0.00 0.00 0.00 0.00 836.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.04 ENTIBADO DE ZANJAS 2,257.53 0.00 0.00 0.00 0.00 0.00 0.00 2,257.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.04.01 ENTIBADO DE ZANJA HASTA 2.00 m, af=0.80m 2,257.53 0.00 0.00 0.00 0.00 0.00 0.00 2,257.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.05 SUMINISTRO e INSTALACION DE TUBERIAS 4,330.77 0.00 0.00 0.00 0.00 0.00 0.00 4,330.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.05.01 SUMINISTRO e INSTALACION TUBERIA Ø = 200 mm PVC UF CL 7.5; h = 1.50 m; c/3% desperdicio 4,330.77 0.00 0.00 0.00 0.00 0.00 0.00 4,330.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.06 PRUEBAS HIDRAULICAS 2,098.93 0.00 0.00 0.00 0.00 0.00 0.00 2,098.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.22.06.01 DOBLE PRUEBA HIDRAULICA p/TUBERIA Ø 200 mm PVC 2,098.93 0.00 0.00 0.00 0.00 0.00 0.00 2,098.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.23 SUMINISTRO Y MONTAJE DE LAS INSTALACIONES ELECTRICAS DE LA PTAP 1,680,678.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,915.88 15,282.70 15,282.70 42,609.97 105,958.44 200,938.66 166,936.16 158,325.32 216,936.16 202,492.79 550,000.00 0.00
04.23.01 SUMINISTRO Y MONTAJE DE LAS CONEXIONES ELECTRICAS DE LAS CASETAS EN 220V DE LA PTAP 44,369.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,915.88 15,282.70 15,282.70 7,887.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.23.02 SUMINISTRO Y MONTAJE DE LAS CONEXIONES ELECTRICAS DEL ALUMBRADO PERIMETRICO EN 220V 54,824.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 34,722.13 20,102.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.23.03 SUMINISTRO Y MONTAJE DE LAS CONEXIONES ELECTRICAS EN 440V DE LA PATAP 232,432.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20,030.10 38,738.82 40,030.11 38,738.82 60,030.11 34,864.94 0.00 0.00
04.23.04 SUMINISTRO Y MONTAJE DE LAS CONEXIONES Y ALIMENTADORES SUBTERRANEOS DE LA PTAP 31,533.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,920.01 12,613.34 0.00 0.00 0.00 0.00 0.00 0.00
04.23.05 CONEXIONES ELECTRICAS Y DE TELEMETRIA EN L SALA DE CONTROL Y LA PTAP 1,317,518.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 46,906.04 149,586.50 126,906.05 119,586.50 156,906.05 167,627.85 550,000.00 0.00
04.24 SUMINISTRO DE UTILIZACION EN MEDIA TENSION 10.0 KV - 3 Ø DE LA PTAP 148,616.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 145,195.69 3,420.83 0.00
04.24.01 SUMINISTRO Y MONTAJE ELECTRICO DE LA RED PRIMARIA 148,616.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 145,195.69 3,420.83 0.00
04.24.01.01 OBRAS PRELIMINARES Y EXPEDIENTE FINAL 15,550.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,129.98 3,420.83 0.00
04.24.01.01.01 LIMPIEZA DE TERRENOS MANUAL EN TRAZO DE RED EN MT 1,288.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,288.32 0.00 0.00
04.24.01.01.02 LIMPIEZA DE TERRENOS MANUAL EN UBICACION DE POSTES DE C.A.C, A INSTALAR 93.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 93.72 0.00 0.00
04.24.01.01.03 REPLANTEO TOPOGRAFICO y UBICACION ESTRUCTURA DE LA RP 1,240.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,240.74 0.00 0.00
04.24.01.01.04 TRANSPORTE DE PERSONAL TECNICO EN EJECUCION DE OBRA 7,027.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,027.20 0.00 0.00
04.24.01.01.05 PROTECCION Y SEGURIDAD A LOS TRABAJADORES DE OBRA 2,480.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,480.00 0.00 0.00
04.24.01.01.06 PRUEBAS ELECTRICAS Y CONFORMIDAD DE INSTALACIONES EN MT EN VACIO 620.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 620.83 0.00
04.24.01.01.07 EXPEDIENTES TECNICOS FINAL CONFORME A OBRA ( 1 ORIGINAL + 3COPIAS) DE LA RP, INCLUYE CD DE INFORMACION 2,800.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,800.00 0.00
04.24.01.02 POSTES y ACCESORIOS DE CONCRETO ARMADO 26,242.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26,242.11 0.00 0.00
04.24.01.02.01 POSTE CONCRETO ARMADO CENTRIFUGADO 13m/400Kg/165/360 mm 16,029.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,029.93 0.00 0.00
04.24.01.02.02 POSTE CONCRETO ARMADO CENTRIFUGADO 13m/300Kg/165/360 mm 2,236.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,236.88 0.00 0.00
04.24.01.02.03 MEDIA LOZA DE C.A.V M/1.10/750 1,553.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,553.30 0.00 0.00
04.24.01.02.04 MEDIA LOZA DE C.A.V M/1.30/750 616.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 616.65 0.00 0.00
04.24.01.02.05 PALOMILLA SIMPLE C.A M/1.10/100 621.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 621.08 0.00 0.00
04.24.01.02.06 PALOMILLA SIMPLE C.A M/1.50/100 330.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 330.54 0.00 0.00
04.24.01.02.07 MENSULA DE C.A V M/1.00/250 4,671.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,671.36 0.00 0.00
04.24.01.02.08 CRUCETA DE MADERA 90 x 120 mm x 1.00 m 182.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 182.37 0.00 0.00
04.24.01.03 AISLADORES POLIMERICOS Y ACCESORIOS 10,149.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,149.00 0.00 0.00
04.24.01.03.01 AISLADOR DE POLIMERICO TIPO PIN 24 KV; LF 744m , DE 0-1000 msnm 3,708.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,708.00 0.00 0.00
04.24.01.03.02 AISLADOR POLIMERICO 24 KV; TIPO SUSPENSION DE LF 744mm 6,441.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,441.00 0.00 0.00
04.24.01.04 CONDUCTORES DE ENERGIA ELECTRICA 18,690.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,690.13 0.00 0.00
04.24.01.04.01 CONDUCTOR DE ALEACION DE ALUMINIO AAAC 50 mm² 5,995.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,995.08 0.00 0.00
04.24.01.04.02 CONDUCTOR DE COBRE DESNUDO T BLANDO 35 mm2 2,887.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,887.88 0.00 0.00
04.24.01.04.03 CONDUCTOR DE COBRE DESNUDO T D DE 50 mm2 996.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 996.80 0.00 0.00
04.24.01.04.04 CABLE ELECTRICO NS2X 1,0KV DE 3x16mm2 1,592.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,592.80 0.00 0.00
04.24.01.04.05 CABLE ELECTRICO NS2X 1,0KV DE 3x50mm2 4,300.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,300.00 0.00 0.00
04.24.01.04.06 FERRETERIA ELECTRICA PARA POSTES, CRUCETAS, MENSULAS, CONDUCTORES Y EQUIPOS 2,917.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,917.57 0.00 0.00
04.24.01.05 PUESTA A TIERRA EN MEDIA Y BAJA TENSION 7,807.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,807.48 0.00 0.00
04.24.01.05.01 PUESTA A TIERRA EN ESTRUCTURAS DE LINEAS DE TRANSMISION 10-25 OHMS 1,918.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,918.50 0.00 0.00
04.24.01.05.02 PUESTA A TIERRA EN ESTRUCTURAS DE SAM Y SAB 10 HMS 3,935.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,935.64 0.00 0.00
04.24.01.05.03 PUESTA A TIERRA EN TABLEROS CON EQUIPOS ELECTRONICOS 5 OHMS 940.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 940.44 0.00 0.00
04.24.01.05.04 MEGHADO Y PROTOCOLO DE PUESTAS A TIERRA 1,012.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,012.90 0.00 0.00
04.24.01.06 RETENIDAS Y ANCLAJES EN MEDIA TENSION 3,463.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,463.96 0.00 0.00
04.24.01.06.01 RETENIDA SIMPLE EN MEDIA TENSION 2,840.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,840.30 0.00 0.00
04.24.01.06.02 RETENIDA CON CONTRAPUNTA EN MEDIA TENSION 623.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 623.66 0.00 0.00
04.24.01.07 ARMADOS CON EQUIPOS DE POTENCIA Y ACCESORIOS 66,713.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 66,713.03 0.00 0.00
04.24.01.07.01 ARMADO DE PUNTO DE DERIVACION 3,662.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,662.67 0.00 0.00
04.24.01.07.02 ARMADO DE SECCIONAMIENTO , TIPO PSEC 2,980.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,980.76 0.00 0.00
04.24.01.07.03 ARMADO DE SECCIONAMIENTO , TIPO PMI 16,100.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,100.97 0.00 0.00
04.24.01.07.04 ARMADO DE SISTEMA DE MEDICION TIPO TFX Y ACCESORIOS 17,017.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,017.63 0.00 0.00
04.24.01.07.05 ARMADO VERTICAL DE ANCLAJE VANO FLOJO (0-60°), TIPO EV2 509.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 509.22 0.00 0.00
04.24.01.07.06 ARMADO DE SUB ESTACION AEREA BIPOSTE, TIPO EV3+B1, DE 125 KVA 23,207.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23,207.28 0.00 0.00
04.24.01.07.07 TABLERO DE PROTECCION METALICO PARA ADOSAR A POSTE 460/230 V - 3 CKTOS PARA PTAP 3,234.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,234.50 0.00 0.00
05 LINEA DE IMPULSION PTAP-R 1600M3 1,791,654.16 0.00 0.00 0.00 0.00 0.00 0.00 160,876.19 268,407.73 417,135.32 220,771.40 224,463.53 258,036.00 241,963.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01 TRABAJOS PRELIMINARES 15,865.41 0.00 0.00 0.00 0.00 0.00 0.00 7,948.44 2,530.17 2,448.55 2,530.17 408.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 5,663.13 0.00 0.00 0.00 0.00 0.00 5,663.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.02 TRAZOS, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 10,202.28 0.00 0.00 0.00 0.00 0.00 0.00 2,285.31 2,530.17 2,448.55 2,530.17 408.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02 MOVIMIENTO DE TIERRAS 385,263.76 0.00 0.00 0.00 0.00 0.00 0.00 50,627.38 107,373.35 127,749.77 86,576.24 12,937.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.01 EXCAVACION DE ZANJAS 40,592.97 0.00 0.00 0.00 0.00 0.00 0.00 11,964.24 13,246.13 12,818.83 2,563.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.01.01 EXCAVACION ZANJAS c/EQUIPO P/TUB 400mm a = 1.00m h=1.80m 40,592.97 0.00 0.00 0.00 0.00 0.00 0.00 11,964.24 13,246.13 12,818.83 2,563.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.02 REFINE y NIVELACION DE ZANJAS 5,230.83 0.00 0.00 0.00 0.00 0.00 0.00 1,322.08 1,781.93 1,724.45 402.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.02.01 REFINE y NIVELACION DE ZANJAS P/TUB 400mm 5,230.83 0.00 0.00 0.00 0.00 0.00 0.00 1,322.08 1,781.93 1,724.45 402.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.03 CAMA DE APOYO P/TUBERIAS 35,491.83 0.00 0.00 0.00 0.00 0.00 0.00 8,281.43 12,224.96 11,830.61 3,154.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.03.01 CAMA DE APOYO P/TUB 400mm c/ARENA FINA; e = 0.20 m 35,491.83 0.00 0.00 0.00 0.00 0.00 0.00 8,281.43 12,224.96 11,830.61 3,154.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.04 RELLENO, APISONADO y COMPACTACION LATERAL CON MATERIAL DE PRESTAMO 28,315.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,494.70 9,438.55 9,753.17 629.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.04.01 RELLENO APISONADO Y COMPACTACION LATERAL DE ZANJAS P/TUB Ø 400 mm C/ARENA FINA 28,315.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,494.70 9,438.55 9,753.17 629.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.05 RELLENO y COMPACTACION S/CLAVE TUBERIA C/MATERIAL DE PRESTAMO 51,227.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,799.07 17,075.85 17,645.05 1,707.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.05.01 RELLENO y COMPACTACION DE ZANJAS P/TUB. Ø 400 mm C/ARENA FINA HASTA 0.30m S/CLAVE DEL TUBO 51,227.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,799.07 17,075.85 17,645.05 1,707.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.06 RELLENO y COMPACTACION CON MATERIAL PROPIO SELECCIONADO 47,769.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,881.57 16,101.96 16,638.69 2,146.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.06.01 RELLENO y APISONADO ZANJA p/TUBERIA Ø = 400 mm c/MATERIAL PROPIO SELECCIONADO h = 1.80 m 47,769.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,881.57 16,101.96 16,638.69 2,146.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.07 ACARREO y ELIMINACION MATERIAL EXCEDENTE 78,932.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,813.22 29,599.75 30,586.41 4,933.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.07.01 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 78,932.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,813.22 29,599.75 30,586.41 4,933.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.08 ENTIBADO DE ZANJAS 92,339.28 0.00 0.00 0.00 0.00 0.00 0.00 27,215.79 30,131.77 29,159.77 5,831.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.08.01 ENTIBADO ZANJA HASTA 1.80 m 92,339.28 0.00 0.00 0.00 0.00 0.00 0.00 27,215.79 30,131.77 29,159.77 5,831.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.09 BY PASS DE ACEQUIAS 1,843.84 0.00 0.00 0.00 0.00 0.00 0.00 1,843.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.09.01 BY PASS DE ACEQUIAS CON MATERIAL DE TIERRA PROVISIONAL 1,843.84 0.00 0.00 0.00 0.00 0.00 0.00 1,843.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.10 RECONSTRUCCION DE ACEQUIA DE TIERRA 3,520.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,520.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.10.01 RECONSTRUCCION DE ACEQUIA CON MATERIAL PROPIO SELECCIONADO 3,520.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,520.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03 SUMINISTRO e INSTALACION DE TUBERIA PVC UF - PN 10 10bar 1,130,723.88 0.00 0.00 0.00 0.00 0.00 0.00 94,748.24 118,658.55 88,379.24 118,658.55 210,279.31 258,036.00 241,963.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.01 SUMINISTRO e INSTALACION TUBERIA Ø = 400 mm PVC UF PN 10 Prof. h = 1.80 m 1,130,723.88 0.00 0.00 0.00 0.00 0.00 0.00 94,748.24 118,658.55 88,379.24 118,658.55 210,279.31 258,036.00 241,963.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.04 ACCESORIOS 171,564.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26,839.22 144,724.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.04.01 SUMINISTRO e INSTALACION CODO 400 mm x 90° ISO PVC - PN10 18,948.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,948.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.04.02 SUMINISTRO e INSTALACION CODO 400 mm x 45° ISO PVC PN 10 1,895.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,895.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.04.03 SUMINISTRO e INSTALACION CODO 400 mm x 22.5° ISO PVC PN 10 5,995.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,995.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.04.04 SUMINISTRO e INSTALACION CODO 400 mm x 11.25° ISO PVC - PN10 1,097.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,097.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.04.05 SUMINISTRO e INSTALACION VALVULA COMPUERTA HFD DN 400 mm (Aire) 143,627.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 143,627.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.05 PRUEBA HIDRAULICA y DESINFECCION 46,991.01 0.00 0.00 0.00 0.00 0.00 0.00 7,552.13 13,006.44 12,586.88 13,006.44 839.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.05.01 DOBLE PRUEBA HIDRAULICA y DESINFECCION p/TUBERIA Ø 400 mm PVC 46,991.01 0.00 0.00 0.00 0.00 0.00 0.00 7,552.13 13,006.44 12,586.88 13,006.44 839.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.06 OBRAS DE CONCRETO ARMADO 2,206.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,206.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.06.01 CAJA Y TECHO PARA VALVULAS DE AIRE f'c=245 Kg/cm2 1,944.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,944.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.06.02 CAJA Y TECHO PARA MEDIDOR ELECTROMAGNETICO f'c=245 Kg/cm2 261.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 261.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07 VARIOS 39,039.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39,039.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.01 BOYAS NIVEL 716.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 716.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.02 MEDIDOR ELECTROMAGNETICO 13,182.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,182.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.03 PASE AEREO N° 01 EN DREN 12,570.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,570.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.03.01 EXCAVACION h>1.40 MT 96.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 96.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.03.02 SOLADO e = 3" 104.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 104.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.03.03 CONCRETO DE PASE AEREO f'c = 280 Kg/cm² 4,095.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,095.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.03.04 ENCOFRADO MURO DOS CARAS h=1.80m 3,211.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,211.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.03.05 ACERO DE REFUERZO f"y=4,200 gk/cm2 5,062.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,062.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.04 PASE AEREO N° 02 EN DREN 12,570.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,570.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.04.01 EXCAVACION h>1.40 MT 96.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 96.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.04.02 SOLADO e = 3" 104.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 104.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.04.03 CONCRETO DE PASE AEREO f'c = 280 Kg/cm² 4,095.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,095.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.04.04 ENCOFRADO MURO DOS CARAS h=1.80m 3,211.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,211.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.07.04.05 ACERO DE REFUERZO f"y=4,200 gk/cm2 5,062.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,062.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06 LINEA DE PURGA DE FONDO DE LAGUNA BORO II 290,286.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39,463.94 156,554.50 94,267.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01 EMPALME A ESTRUCTURA EXISTENTE 80,385.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 80,385.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01.01 INSTALACION Y DESINSTALACION DE EMPEDRADO DE PROTECCIÓN DIQUE 68,385.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 68,385.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01.02 DRENAJE DE ZANJAS 2,495.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,495.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01.03 INSTALACION Y DESINSTALACION DE ANDAMIO RIELES METALICOS TIPO CASTILLO 5,178.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,178.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01.04 SUMINISTRO E INSTALACION DE COMPUERTA METALICA TIPO ARMCO 1.00 x 1.00 m 3,475.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,475.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01.05 PERFORACION PARED ESTRUCTURA EXISTENTE 533.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 533.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01.06 ENTIBADO ZANJA HASTA 6.00 m 317.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 317.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02 ESTRUCTURAS PROYECTADAS DE SALIDA Y CONTROL DE PURGA 97,130.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39,463.94 57,666.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01 ESTRUCTURA DE SALIDA DE PURGA 40,196.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,914.45 17,282.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.01 TRABAJOS PRELIMINARES 15.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.01.01 TRAZO y REPLANTEO 15.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.02 MOVIMIENTO DE TIERRAS 4,975.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,975.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.02.01 EXCAVACION PARA ESTRUCTURAS 299.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 299.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.02.02 DRENAJE DE ZANJAS 3,993.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,993.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.02.03 REFINE, NIVELACION y COMPACTACION ZONA EXCAVADA 48.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.02.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 634.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 634.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.03 OBRAS DE CONCRETO SIMPLE 139.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 139.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.03.01 SOLADO, CONCRETO f'c =100 Kg/cm² e=0.10m 139.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 139.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.04 OBRAS DE CONCRETO ARMADO 16,977.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,977.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.04.01 CONCRETO f'c = 280 Kg/cm² p/ESTRUCTURA 6,364.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,364.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.04.02 ENCOFRADO y DESENCOFRADO DE ESTRUCTURAS 4,005.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,005.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 6,607.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,607.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.05 REVOQUES y ENLUCIDOS 1,484.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 806.25 678.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.05.01 REVESTIMIENTO c/IMPERMEABILIZANTE p/LOSA FONDO 127.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 127.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.05.02 REVESTIMIENTO c/IMPERMEABILIZANTE p/MURO DE ESTRUCTURAS 1,357.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 678.67 678.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.06 CARPINTERIA METALICA 16,603.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,603.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01.06.01 SUMINISTRO E INSTALACION DE COMPUERTA METALICA TIPO ARMCO 1.40 x 1.80 m 16,603.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,603.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02 ESTRUCTURA DE CONTROL DE PURGA 56,934.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,549.49 40,384.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.01 TRABAJOS PRELIMINARES 15.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.01.01 TRAZO y REPLANTEO 15.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.02 MOVIMIENTOS DE TIERRAS 6,007.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,007.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.02.01 EXCAVACION PARA ESTRUCTURAS 586.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 586.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.02.02 DRENAJE DE ZANJAS 3,993.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,993.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.02.03 REFINE, NIVELACION y COMPACTACION ZONA EXCAVADA 130.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 130.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.02.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 1,297.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,297.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.03 OBRAS DE CONCRETO SIMPLE 375.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 375.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.03.01 SOLADO, CONCRETO f'c =100 Kg/cm² e=0.10m 375.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 375.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.04 OBRAS DE CONCRETO ARMADO 30,607.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,150.68 20,456.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.04.01 CONCRETO f'c = 280 Kg/cm² p/ESTRUCTURA 13,834.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,834.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.04.02 ENCOFRADO y DESENCOFRADO NORMAL p/ESTRUCTURA 8,258.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,258.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 8,514.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,892.03 6,622.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.05 REVOQUES y ENLUCIDOS 3,324.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,324.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.05.01 REVESTIMIENTO c/IMPERMEABILIZANTE p/LOSA FONDO 407.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 407.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.05.02 REVESTIMIENTO c/IMPERMEABILIZANTE EN MUROS DE ESTRUCTURAS 2,917.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,917.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.06 CARPINTERIA METALICA 16,603.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,603.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02.06.01 SUMINISTRO E INSTALACION DE COMPUERTA METALICA TIPO ARMCO 1.40 x 1.80 m 16,603.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,603.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03 LINEA DE PURGA 112,769.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 98,887.54 13,882.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.01 TRABAJOS PRELIMINARES 226.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 226.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.01.01 TRAZOS Y REPLANTEO 226.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 226.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02 MOVIMIENTO DE TIERRAS 37,784.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26,041.69 11,742.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.01 EXCAVACION DE ZANJAS 10,957.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,957.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.01.01 EXCAVACION ZANJA A MAQ. P/TUB 800mm a = 1.20 m h=6.00m 10,957.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,957.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.02 REFINE Y NIVELACION DE ZANJAS 242.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 242.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.02.01 REFINE y NIVELACION DE ZANJAS P/TUB, Ø=800mm, a=1.20m 242.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 242.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.03 CAMA DE APOYO P/TUBERIAS 2,494.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,494.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.03.01 CAMA APOYO P/TUB 800mm c/RIPIO CORRIENTE e=0.20m 2,494.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,494.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.04 RELLENO, APISONADO Y COMPACTACION LATERAL CON MATERIAL DE PRESTAMO 3,501.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,501.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.04.01 RELLENO APISONADO Y COMP.LATERAL DE ZANJAS P/TUBERIA Ø 800 mm C/RIPIO CORRIENTE 3,501.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,501.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.05 RELLENO Y COMPACTACION S/CLAVE DELTUBO CON MATERIAL DE PRESTAMO 4,183.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,183.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.05.01 RELLENO y COMPACTACION DE ZANJAS P/TUB 800mm C/RIPIO CORRIENTE HASTA 0.30m S/CLAVE DEL TUBO 4,183.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,183.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.06 RELLENO Y COMPACTACION CON MATERIAL DE PROPIO SELECCIONADO 2,084.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,084.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.06.01 RELLENO y COMPACTACION DE ZANJAS P/TUB. Ø 800 mm c/MAT. PROP. SELECCIONADO CAPAS c/0.20 m; hasta NTN 2,084.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,084.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.07 ACARREO y ELIMINACION MATERIAL EXCEDENTE 5,475.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,475.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.07.01 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 5,475.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,475.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.08 BOMBEO DE ZANJAS 3,352.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,352.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.08.01 DRENAJE ZANJA HASTA 6.00 m 3,352.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,352.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.09 ENTIBADO DE ZANJAS 5,492.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,492.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02.09.01 ENTIBADO ZANJA HASTA 6.00 m 5,492.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,492.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.03 TUBERIAS 71,014.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 71,014.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.03.01 SUMINISTRO E INSTALACION TUB Ø 800 mm HDPE CORRUGADO Prof = 5.00m c/3% desp 71,014.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 71,014.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.04 PRUEBAS HIDRAULICAS Y DESINFECCION 3,743.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,604.45 2,139.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.04.01 DOBLE PRUEBA HIDRAULICA y DESINFECCION p/TUBERIA Ø 800 mm HDPE 3,743.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,604.45 2,139.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07 OBRAS COMPLEMENTARIAS P/PLANTA DE TRATAMIENTO 587,485.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,573.43 89,454.03 312,005.19 43,150.74 93,141.60 40,160.09 0.00 0.00
07.01 PAVIMENTACION DE ACCESO P/PLANTA DE TRATAMIENTO 380,335.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 76,194.79 304,140.69 0.00 0.00 0.00 0.00 0.00
07.01.01 TRABAJOS PRELIMINARES 49,974.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48,450.14 1,524.70 0.00 0.00 0.00 0.00 0.00
07.01.01.01 LIMPIEZA y DEFORESTACION 422.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 422.11 0.00 0.00 0.00 0.00 0.00 0.00
07.01.01.02 TRAZO, NIVELACION y REPLANTEO 10,528.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,528.65 0.00 0.00 0.00 0.00 0.00 0.00
07.01.01.03 TRAZO, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 15,247.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,722.35 1,524.70 0.00 0.00 0.00 0.00 0.00
07.01.01.04 MOVILIZACION y DESMOVILIZACION MAQUINARIAS, EQUIPOS y HERRAMIENTAS 23,777.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23,777.03 0.00 0.00 0.00 0.00 0.00 0.00
07.01.02 MOVIMIENTO DE TIERRAS 172,452.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 27,744.65 144,707.87 0.00 0.00 0.00 0.00 0.00
07.01.02.01 CORTE MATERIAL SUELTO HASTA NIVEL SUB RASANTE 14,724.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,724.51 0.00 0.00 0.00 0.00 0.00 0.00
07.01.02.02 PERFILADO y COMPACTACION SUB RASANTE 6,239.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,239.20 0.00 0.00 0.00 0.00 0.00 0.00
07.01.02.03 RELLENO MATERIAL CORTE HASTA NIVEL SUB RASANTE 1,575.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,575.27 0.00 0.00 0.00 0.00 0.00
07.01.02.04 CAPA ANTICONTAMINANTE (e = 0.50 m) 53,462.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 53,462.15 0.00 0.00 0.00 0.00 0.00
07.01.02.05 SUB BASE GRANULAR (e = 0.30 m) 46,887.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 46,887.59 0.00 0.00 0.00 0.00 0.00
07.01.02.06 BASE GRANULAR (e = 0.15 m) 25,830.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,830.51 0.00 0.00 0.00 0.00 0.00
07.01.02.07 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 23,733.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,780.94 16,952.35 0.00 0.00 0.00 0.00 0.00
07.01.03 PAVIMENTO 157,052.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 157,052.12 0.00 0.00 0.00 0.00 0.00
07.01.03.01 IMPRIMACION ASFALTICA 14,662.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,662.12 0.00 0.00 0.00 0.00 0.00
07.01.03.02 CARPETA ASFALTICA EN CALIENTE p/CALZADA (e = 3") 129,091.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 129,091.29 0.00 0.00 0.00 0.00 0.00
07.01.03.03 CARPETA ASFALTICA EN CALIENTE p/BERMA (e = 1") 13,298.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,298.71 0.00 0.00 0.00 0.00 0.00
07.01.04 SEÑALIZACION 856.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 856.00 0.00 0.00 0.00 0.00 0.00
07.01.04.01 PINTADO y SEÑALIZACION p/PAVIMENTO 856.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 856.00 0.00 0.00 0.00 0.00 0.00
07.02 VEREDAS 95,953.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,864.50 43,150.74 44,938.38 0.00 0.00 0.00
07.02.01 OBRAS PROVISIONALES 6,617.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,617.27 0.00 0.00 0.00 0.00 0.00
07.02.01.01 TRAZO, NIVELACION y REPLANTEO 2,702.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,702.97 0.00 0.00 0.00 0.00 0.00
07.02.01.02 TRAZO, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 3,914.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,914.30 0.00 0.00 0.00 0.00 0.00
07.02.02 MOVIMIENTO DE TIERRAS 32,629.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,247.23 31,382.43 0.00 0.00 0.00 0.00
07.02.02.01 EXCAVACION MANUAL p/UÑA LATERAL 4,490.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,247.23 3,242.79 0.00 0.00 0.00 0.00
07.02.02.02 CONFORMACION c/MATERIAL PRESTAMO AFIRMADO P/VEREDAS (e = 0.10 m) 13,276.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,276.72 0.00 0.00 0.00 0.00
07.02.02.03 CONFORMACION c/MATERIAL PRESTAMO ARENA FINA P/VEREDAS (e = 0.10 m) 12,701.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,701.41 0.00 0.00 0.00 0.00
07.02.02.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 2,161.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,161.51 0.00 0.00 0.00 0.00
07.02.03 OBRAS DE CONCRETO SIMPLE 55,299.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,768.31 43,530.92 0.00 0.00 0.00
07.02.03.01 VEREDA c/CONCRETO f' = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base de afirmado 50,996.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,768.31 39,227.72 0.00 0.00 0.00
07.02.03.02 JUNTA DILATACION ASFALTICA c/3.00 m 4,303.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,303.20 0.00 0.00 0.00
07.02.04 SEÑALIZACION 1,407.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,407.46 0.00 0.00 0.00
07.02.04.01 PINTADO BORDE LATERAL p/VEREDA 1,407.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,407.46 0.00 0.00 0.00
07.03 RAMPAS P/PEATON 1,223.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,223.57 0.00 0.00 0.00
07.03.01 OBRAS PROVISIONALES 158.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 158.64 0.00 0.00 0.00
07.03.01.01 TRAZO, NIVELACION y REPLANTEO 64.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64.80 0.00 0.00 0.00
07.03.01.02 TRAZO, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 93.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 93.84 0.00 0.00 0.00
07.03.02 MOVIMIENTO DE TIERRAS 728.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 728.63 0.00 0.00 0.00
07.03.02.01 EXCAVACION MANUAL p/UÑA LATERAL 40.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 40.88 0.00 0.00 0.00
07.03.02.02 CONFORMACION BASE c/MATERIAL PRESTAMO (e = 0.10 m) 648.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 648.47 0.00 0.00 0.00
07.03.02.03 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 39.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39.28 0.00 0.00 0.00
07.03.03 OBRAS DE CONCRETO SIMPLE 336.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 336.30 0.00 0.00 0.00
07.03.03.01 RAMPA c/CONCRETO f' = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base de afirmado 245.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 245.02 0.00 0.00 0.00
07.03.03.02 JUNTA DILATACION ASFALTICA c/3.00 m 91.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 91.28 0.00 0.00 0.00
07.04 SARDINELES DE CONCRETO 87,139.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 46,979.65 40,160.09 0.00 0.00
07.04.01 OBRAS PROVISIONALES 3,535.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,535.97 0.00 0.00 0.00
07.04.01.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 1,262.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,262.16 0.00 0.00 0.00
07.04.01.02 TRAZOS, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 2,273.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,273.81 0.00 0.00 0.00
07.04.02 MOVIMIENTO DE TIERRAS 4,781.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,781.67 0.00 0.00 0.00
07.04.02.01 EXCAVACION MANUAL p/UÑA LATERAL 2,436.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,436.11 0.00 0.00 0.00
07.04.02.02 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 2,345.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,345.56 0.00 0.00 0.00
07.04.03 OBRAS DE CONCRETO SIMPLE 76,760.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38,662.01 38,098.24 0.00 0.00
07.04.03.01 ENCOFRADO y DESENCOFRADO p/SARDINEL 53,532.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38,662.01 14,870.00 0.00 0.00
07.04.03.02 CONCRETO f'c = 140 Kg/cm² (h = 0.15 m) p/SARDINEL 22,983.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,983.74 0.00 0.00
07.04.03.03 JUNTA DILATACION ASFALTICA c/3.00 m 244.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 244.50 0.00 0.00
07.04.04 SEÑALIZACION 2,061.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,061.85 0.00 0.00
07.04.04.01 PINTADO BORDE LATERAL p/SARDINEL 2,061.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,061.85 0.00 0.00
07.05 ALCANTARILLA DE CONCRETO ARMADO DE 1.50x1.50 22,832.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,573.43 13,259.24 0.00 0.00 0.00 0.00 0.00 0.00
07.05.01 OBRAS PRELIMINARES 1,178.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,178.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.05.01.01 DEMOLICION DE ALCANTARILLA 1,089.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,089.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 de 10
CALENDARIO DE AVANCE DE OBRA VALORIZADO ACTUALIZADO A LA FECHA DE INICIO DE OBRA
OBRA : INSTALACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DE LOS PP.JJ. VILLA PROGRESO, MIRAFLORES, LAS VEGAS, SAMAN, SAN FRANCISCO DE ASIS, LA UNION, SAN JUAN DE DIOS Y RAMIRO PRIALE II - CHICLAYO
ENTIDAD : ENTIDAD PRESTADORA DE SERVICIOS DE SANEAMIENTO DE LAMBAYEQUE S.A. - EPSEL S.A.
CONTRATISTA : CONSORCIO PROGRESO
SUPERVISION : CONSORCIO SUPERVISOR ASIS
UBICACIÓN : CHICLAYO - CHICLAYO - LAMBAYEQUE
Duración (Meses)
Item Descripción Parcial (S/.)
Mar-2019 Abr-2019 May-2019 Jun-2019 Jul-2019 Ago-2019 Sep-2019 Oct-2019 Nov-2019 Dic-2019 Ene-2020 Feb-2020 Mar-2020 Abr-2020 May-2020 Jun-2020 Jul-2020 Ago-2020 Sep-2020 Oct-2020
07.05.01.02 TRAZO y REPLANTEO 89.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 89.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.05.02 MOVIMIENTO DE TIERRAS 3,178.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,178.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.05.02.01 EXCAVACION PARA ALCANTARILLA 1,265.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,265.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.05.02.02 REFINE Y NIVELACION DE EXCAVACION 71.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 71.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.05.02.03 RELLENO CON MATERIAL PROPIO 533.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 533.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.05.02.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 1,307.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,307.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.05.03 CONCRETO SIMPLE 793.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 793.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.05.03.01 EMBOQUILLADO DE PIEDRA 8" C/MORTERO 103.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 103.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.05.03.02 SOLADO concreto f'c = 140 kg/cm2 (e = 0.10 m) p/ESTRUCTURA 690.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 690.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.05.04 CONCRETO ARMADO EN ALCANTARILLAS 14,205.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,422.59 9,782.42 0.00 0.00 0.00 0.00 0.00 0.00
07.05.04.01 CONCRETO f'c = 210 Kg/cm² LOSA DE FONDO 1,172.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,172.89 0.00 0.00 0.00 0.00 0.00 0.00
07.05.04.02 CONCRETO f'c = 210 Kg/cm² LOSA SUPERIOR 1,222.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,222.17 0.00 0.00 0.00 0.00 0.00 0.00
07.05.04.03 CONCRETO f'c = 210 Kg/cm² MUROS Y ALETAS 3,354.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,354.39 0.00 0.00 0.00 0.00 0.00 0.00
07.05.04.04 ENCOFRADO y DESENCOFRADO DE ALCANTARILLAS 1,379.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,379.41 0.00 0.00 0.00 0.00 0.00 0.00
07.05.04.05 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 7,076.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,422.59 2,653.56 0.00 0.00 0.00 0.00 0.00 0.00
07.05.05 TARRAJEO DE ALCANTARILLAS 3,476.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,476.82 0.00 0.00 0.00 0.00 0.00 0.00
07.05.05.01 TARRAJEO EN MUROS 3,476.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,476.82 0.00 0.00 0.00 0.00 0.00 0.00
08 RESERVORIO ELEVADO V = 1,600 m3 P/AGUA POTABLE 4,082,187.10 0.00 0.00 0.00 74,220.10 266,429.92 160,264.42 99,439.30 227,651.16 48,516.70 172,894.34 719,434.05 347,880.16 241,186.11 237,627.75 369,300.23 350,364.97 323,554.83 116,360.04 112,664.56 214,398.46
08.01 RESERVORIO ELEVADO P/AGUA POTABLE 3,859,758.13 0.00 0.00 0.00 74,220.10 266,429.92 160,264.42 99,439.30 227,651.16 48,516.70 172,894.34 666,422.83 294,470.75 140,766.20 222,039.32 369,300.23 350,364.97 323,554.83 116,360.04 112,664.56 214,398.46
08.01.01 OBRAS PROVISIONALES 120,059.07 0.00 0.00 0.00 73,927.87 46,131.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01.01 CARTEL IDENTIFICACION OBRA 3.60 * 2.40 m 1,127.07 0.00 0.00 0.00 1,127.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01.02 CASETA p/GUARDIANIA y/o DEPOSITO 32,436.00 0.00 0.00 0.00 32,436.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01.03 CASETA OBRA p/EQUIPO PILOTAJE 86,496.00 0.00 0.00 0.00 40,364.80 46,131.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.02 TRABAJOS PRELIMINARES 7,707.68 0.00 0.00 0.00 292.23 7,015.01 29.56 28.60 29.56 28.60 29.56 29.54 27.65 29.56 28.60 29.56 28.60 29.56 29.56 21.93 0.00
08.01.02.01 LIMPIEZA y DEFORESTACION 292.23 0.00 0.00 0.00 292.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.02.02 TRAZO, NIVELACION y REPLANTEO 296.27 0.00 0.00 0.00 0.00 296.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.02.03 TRAZO, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 429.04 0.00 0.00 0.00 0.00 28.60 29.56 28.60 29.56 28.60 29.56 29.54 27.65 29.56 28.60 29.56 28.60 29.56 29.56 21.93 0.00
08.01.02.04 MOVILIZACION y DESMOVILIZACION MAQUINARIAS, EQUIPOS y HERRAMIENTAS 5,579.36 0.00 0.00 0.00 0.00 5,579.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.02.05 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 1,110.78 0.00 0.00 0.00 0.00 1,110.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.03 MOVIMIENTO DE TIERRAS 239,379.13 0.00 0.00 0.00 0.00 166,789.51 72,589.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.03.01 EXCAVACION MASIVA TERRENO NORMAL 18,544.53 0.00 0.00 0.00 0.00 18,544.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.03.02 ENTIBADO ZANJA HASTA 3.00 m 972.49 0.00 0.00 0.00 0.00 972.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.03.03 DRENAJE DE ZANJAS HASTA 3.00 m P/ RESERVORIO ELEVADO. 87,868.80 0.00 0.00 0.00 0.00 65,901.60 21,967.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.03.04 REFINE y NIVELACION TERRENO NATURAL 8,274.56 0.00 0.00 0.00 0.00 5,947.34 2,327.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.03.05 RELLENO y COMPACTACION c/MATERIAL PROPIO SELECCIONADO CAPAS c/0.20 m 113,135.33 0.00 0.00 0.00 0.00 75,423.55 37,711.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.03.06 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 10,583.42 0.00 0.00 0.00 0.00 0.00 10,583.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.04 OBRAS DE CONCRETO SIMPLE 18,080.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,068.37 7,012.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.04.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/SOLADO y/o SUB BASE 11,068.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,068.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.04.02 PISO C/CONCRETO f´c = 140 kg/cm2 (8.5 cm) PASTA (1.50 cm) 1:5. INCLUYE ENCOF./DESENCOF/BASE DE AFIRMADO. 4,512.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,512.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.04.03 VEREDA C/CONCRETO f'c=140 kg/cm2 (8.5 cm) PASTA (1.50 cm) 1:5. INCLUYE ENCOF ./DESENCOF/BASE DE AFIRMADO. 2,500.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,500.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05 OBRAS DE CONCRETO ARMADO 2,858,259.76 0.00 0.00 0.00 0.00 46,494.20 87,645.24 99,410.70 227,621.60 48,488.10 161,796.41 659,279.17 291,922.00 140,736.64 222,010.72 369,270.67 342,599.53 129,475.29 31,509.49 0.00 0.00
08.01.05.01 PILOTES EXCAVADOS 554,609.45 0.00 0.00 0.00 0.00 46,494.20 87,645.24 99,410.70 227,621.60 18,572.40 74,865.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.01.01 PLATAFORMA DE TRABAJO PARA PILOTAJE 32,790.61 0.00 0.00 0.00 0.00 7,869.75 24,920.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.01.02 MOVILIZACION, INSTALACION y MONTAJE EQUIPOS PILOTAJE inc./DESMOVILIZACION 22,056.01 0.00 0.00 0.00 0.00 22,056.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.01.03 EXCAVACION DE PILOTES 126,609.02 0.00 0.00 0.00 0.00 7,033.83 43,609.77 42,203.01 33,762.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.01.04 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 p/PILOTE HABILITADO 183,064.60 0.00 0.00 0.00 0.00 9,534.61 19,114.61 57,207.69 97,207.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.01.05 CONCRETO f'c = 280 Kg/cm² p/PILOTE 96,032.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 96,032.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.01.06 CORTE DE CABEZALES p/PILOTE 27,239.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 619.08 18,572.40 8,048.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.01.07 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 9,151.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,151.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.01.08 PRUEBA DE CARGA E INTEGRIDAD DE PILOTE 57,665.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57,665.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.02 LOSA DE CIMENTACION 343,401.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 29,915.70 80,275.63 233,210.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 HABILITADO 145,304.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 29,915.70 35,389.13 80,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.02.02 ENCOFRADO y DESENCOFRADO NORMAL P/LOSA CIMENTACION 14,461.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,230.53 7,230.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.02.03 CONCRETO f'c = 280 Kg/cm² p/LOSA CIMENTACION 183,635.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37,655.97 145,980.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.03 VIGA DE CIMENTACION 108,695.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,655.47 102,039.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.03.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 HABILITADO 13,886.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,272.72 9,613.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA CIMENTACION 9,530.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,382.75 7,148.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.03.03 CONCRETO f'c = 280 Kg/cm² p/VIGA CIMENTACION 85,277.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 85,277.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04 FUSTE CIRCULAR 719,591.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 324,028.97 291,922.00 103,640.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 HASTA 5.00 m sobre NTN p/FUSTE CIRCULAR HABILITADO 105,035.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 105,035.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04.02 ENCOFRADO y DESENCOFRADO NORMAL HASTA 5.00 m sobre NTN 67,456.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 67,456.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04.03 CONCRETO f'c = 280 Kg/cm² HASTA 5.00 m sobre NTN p/FUSTE CIRCULAR 45,800.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 45,800.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04.04 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 5.00 m a 10.00 m sobre NTN p/FUSTE CIRCULAR HABILITADO 58,247.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 49,285.94 8,961.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04.05 ENCOFRADO y DESENCOFRADO NORMAL 5.00 m a 10.00 m sobre NTN p/FUSTE CIRCULAR 70,562.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 56,450.08 14,112.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04.06 CONCRETO f'c = 280 Kg/cm² 5.00 m a 10.00 m sobre NTN p/FUSTE CIRCULAR 37,624.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37,624.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04.07 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 10.00 m a 15.00 m sobre NTN p/FUSTE CIRCULAR HABILITADO 58,247.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 58,247.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04.08 ENCOFRADO y DESENCOFRADO NORMAL 10.00 m a 15.00 m sobre NTN p/FUSTE CIRCULAR 70,562.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 70,562.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04.09 CONCRETO f'c = 280 Kg/cm² 10.00 m a 15.00 m sobre NTN p/FUSTE CIRCULAR 38,072.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38,072.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04.10 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 15.00 m a 19.65 m sobre NTN p/FUSTE CIRCULAR HABILITADO 68,565.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38,092.21 30,473.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04.11 ENCOFRADO y DESENCOFRADO NORMAL 15.00 m a 19.65 m sobre NTN p/FUSTE CIRCULAR 65,623.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26,249.58 39,374.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.04.12 CONCRETO f'c = 280 Kg/cm² 15.00 m a 19.65 m sobre NTN p/FUSTE CIRCULAR 33,792.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33,792.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.05 VIGA MURO ANILLO (VA-3) 77,081.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 963.89 42,098.20 34,019.02 0.00 0.00 0.00 0.00 0.00
08.01.05.05.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 15.00 m a 19.65 m sobre NTN p/VIGA MURO ANILLO HABILITADO 20,241.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 963.89 19,277.82 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.05.02 ENCOFRADO y DESENCOFRADO NORMAL 15.00 m a 19.65 m sobre NTN p/VIGA MURO ANILLO 31,118.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,820.38 8,298.32 0.00 0.00 0.00 0.00 0.00
08.01.05.05.03 CONCRETO f'c = 280 Kg/cm² 15.00 m a 19.65 m sobre NTN p/VIGA MURO ANILLO 25,720.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,720.70 0.00 0.00 0.00 0.00 0.00
08.01.05.06 CASQUETE ESFERICO DE FONDO DE CUBA 99,622.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36,132.27 63,489.99 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.06.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 19.65 m a 20.00 m sobre NTN p/FONDO CUBA HABILITADO 60,951.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23,637.75 37,314.24 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.06.02 ENCOFRADO y DESENCOFRADO NORMAL 19.65 m a 20.00 m sobre NTN p/FONDO CUBA 19,634.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,494.52 7,139.73 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.06.03 CONCRETO f'c = 280 Kg/cm² 19.65 m a 20.00 m sobre NTN p/FONDO CUBA 19,036.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,036.02 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05.07 CASQUETE TRONCOCONICO 402,586.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 116,422.53 286,164.00 0.00 0.00 0.00 0.00 0.00
08.01.05.07.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 20.00 m a 25.00 m sobre NTN p/CASQUETE TRONCOCONICO HABILITADO284,756.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 58,915.19 225,841.56 0.00 0.00 0.00 0.00 0.00
08.01.05.07.02 ENCOFRADO y DESENCOFRADO NORMAL 20.00 m a 25.00 m sobre NTN p/CASQUETE TRONCOCONICO 59,807.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57,507.34 2,300.29 0.00 0.00 0.00 0.00 0.00
08.01.05.07.03 CONCRETO f'c = 280 Kg/cm² 20.00 m a 25.00 m sobre NTN p/CASQUETE TRONCOCONICO 58,022.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 58,022.15 0.00 0.00 0.00 0.00 0.00
08.01.05.08 PARED DE CUBA 391,687.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 49,087.65 342,599.53 0.00 0.00 0.00 0.00
08.01.05.08.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 20.00 m a 25.00 m sobre NTN p/PARED CUBA HABILITADO 180,006.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36,001.22 144,004.90 0.00 0.00 0.00 0.00
08.01.05.08.02 ENCOFRADO y DESENCOFRADO NORMAL 20.00 m a 25.00 m sobre NTN p/PARED CUBA 139,588.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,086.43 126,502.13 0.00 0.00 0.00 0.00
08.01.05.08.03 CONCRETO f'c = 280 Kg/cm² 20.00 m a 25.00 m sobre NTN p/PARED CUBA 72,092.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 72,092.50 0.00 0.00 0.00 0.00
08.01.05.09 LOSA DE TECHO TRONCOCONICA 112,663.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 112,663.38 0.00 0.00 0.00
08.01.05.09.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 25.00 m a 30.00 m sobre NTN p/LOSA TECHO TRONCOCONICA HABILITADO14,169.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,169.97 0.00 0.00 0.00
08.01.05.09.02 ENCOFRADO y DESENCOFRADO NORMAL 25.00 m a 30.00 m sobre NTN p/LOSA TECHO TRONCOCONICA 79,568.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 79,568.44 0.00 0.00 0.00
08.01.05.09.03 CONCRETO f'c = 280 Kg/cm² 25.00 m a 30.00 m sobre NTN p/LOSA TECHO TRONCOCONICA 18,924.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,924.97 0.00 0.00 0.00
08.01.05.10 LOSA DE SOPORTE DE DOMO PARTE SUPERIOR 4,524.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,524.75 0.00 0.00 0.00
08.01.05.10.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 p/LOSA SOPORTE DOMO PARTE SUPERIOR HABILITADO 654.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 654.70 0.00 0.00 0.00
08.01.05.10.02 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA SOPORTE DOMO PARTE SUPERIOR 3,012.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,012.22 0.00 0.00 0.00
08.01.05.10.03 CONCRETO f'c = 280 Kg/cm² p/LOSA SOPORTE DOMO PARTE SUPERIOR 857.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 857.83 0.00 0.00 0.00
08.01.05.11 DOMO EN PARTE SUPERIOR 3,141.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,141.30 0.00 0.00 0.00
08.01.05.11.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 p/DOMO PARTE SUPERIOR HABILITADO 497.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 497.10 0.00 0.00 0.00
08.01.05.11.02 ENCOFRADO y DESENCOFRADO NORMAL p/DOMO PARTE SUPERIOR 1,697.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,697.30 0.00 0.00 0.00
08.01.05.11.03 CONCRETO f'c = 280 Kg/cm² p/DOMO PARTE SUPERIOR 946.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 946.90 0.00 0.00 0.00
08.01.05.12 CHIMENEA 15,061.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,145.86 5,916.11 0.00 0.00
08.01.05.12.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 p/CHIMENEA HABILITADO 1,601.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,601.45 0.00 0.00 0.00
08.01.05.12.02 ENCOFRADO y DESENCOFRADO NORMAL p/CHIMENEA 11,316.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,544.41 3,772.21 0.00 0.00
08.01.05.12.03 CONCRETO f'c = 245 Kg/cm² p/CHIMENEA 2,143.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,143.90 0.00 0.00
08.01.05.13 VIGA PASARELA 15,894.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,894.05 0.00 0.00
08.01.05.13.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 p/VIGA PASARELA HABILITADO 3,561.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,561.91 0.00 0.00
08.01.05.13.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA PASARELA 10,387.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,387.42 0.00 0.00
08.01.05.13.03 CONCRETO f'c = 210 Kg/cm² p/VIGA PASARELA 1,944.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,944.72 0.00 0.00
08.01.05.14 ESCALERA 9,699.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,699.33 0.00 0.00
08.01.05.14.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 p/ESCALERA HABILITADO 4,694.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,694.47 0.00 0.00
08.01.05.14.02 ENCOFRADO y DESENCOFRADO NORMAL p/ESCALERA 3,189.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,189.42 0.00 0.00
08.01.05.14.03 CONCRETO f'c = 210 Kg/cm² p/ESCALERA 1,815.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,815.44 0.00 0.00
08.01.06 REVOQUES y REVESTIMIENTOS 57,248.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,736.84 49,511.75 0.00 0.00 0.00
08.01.06.01 TARRAJEO c/IMPERMEABILIZANTE p/LOSA FONDO CUBA 54,157.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,736.84 46,421.07 0.00 0.00 0.00
08.01.06.02 TARRAJEO c/MORTERO C:A 1:3 (e = 2 cm) p/ESCALERA 3,090.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,090.68 0.00 0.00 0.00
08.01.07 CARPINTERIA METALICA y HERRERIA 9,883.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,908.72 1,975.11 0.00 0.00
08.01.07.01 PUERTA METALICA LAC 1/16" y VENTANA PLEGADA c/MARCO 2" x 2" x 1/4" (INCLUYE PINTURA) 2,717.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,717.00 0.00 0.00 0.00
08.01.07.02 SUMINISTRO E INSTALACION TUBERIA ACERO DN 2000 mm s/DISEÑO p/VENTILACION 1,899.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,899.88 0.00 0.00 0.00
08.01.07.03 BARANDA c/TUBERIA ACERO (INCLUYE PINTURA) 5,266.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,291.84 1,975.11 0.00 0.00
08.01.08 PINTURA 31,481.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,982.00 19,276.35 10,223.11
08.01.08.01 PINTURA LATEX EXTERIOR 02 MANOS INC./IMPRIMANTE 1.80 m a 5.00 m SOBRE NTN p/FUSTE 3,792.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,792.70
08.01.08.02 PINTURA LATEX EXTERIOR 02 MANOS INC./IMPRIMANTE 5.00 m a 10.00 m SOBRE NTN p/FUSTE 4,270.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 656.94 3,613.19
08.01.08.03 PINTURA LATEX EXTERIOR 02 MANOS INC./IMPRIMANTE 10.00 m a 15.00 m SOBRE NTN p/FUSTE 4,470.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,470.92 0.00
08.01.08.04 PINTURA LATEX EXTERIOR 02 MANOS INC./IMPRIMANTE 15.00 m a 19.65 m SOBRE NTN p/FUSTE 4,614.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,614.47 0.00
08.01.08.05 PINTURA LATEX EXTERIOR 02 MANOS INC./IMPRIMANTE p/PARED TRONCO CONICA 3,756.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 939.07 2,817.22
08.01.08.06 PINTURA LATEX EXTERIOR 02 MANOS INC./IMPRIMANTE p/PARED CILINDRICA 4,557.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,557.66 0.00
08.01.08.07 PINTURA LATEX EXTERIOR 02 MANOS INC./IMPRIMANTE p/LOSA TECHO 5,590.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,552.81 4,037.29 0.00
08.01.08.08 PINTURA LATEX EXTERIOR 02 MANOS INC./IMPRIMANTE p/LOSA SOPORTE y DOMO SUPERIOR 429.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 429.19 0.00 0.00
08.01.09 VARIOS 2,622.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 101.71 2,521.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.09.01 ENSAYO COMPRESION p/CONCRETO f'c = 140 - 280 Kg/cm² p/RESERVORIO ELEVADO 2,521.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,521.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.09.02 JUNTA DILATACION ASFALTICA c/3.00 m 101.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 101.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.10 EQUIPAMIENTO HIDRAULICO 191,884.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 136,629.51 55,255.44 0.00 0.00
08.01.10.01 TUBERIAS y VALVULAS 172,680.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 136,629.51 36,051.00 0.00 0.00
08.01.10.01.01 SUMINISTRO e INSTALACION TUBERIA DN 400 mm ACERO SCH - 40 55,038.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 55,038.48 0.00 0.00 0.00
08.01.10.01.02 SUMINISTRO e INSTALACION TUBERIA DN 250 mm ACERO SCH - 40 45,126.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 45,126.38 0.00 0.00 0.00
08.01.10.01.03 SUMINISTRO e INSTALACION CODO 90° x 400 mm ACERO SCH - 40 5,429.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,429.88 0.00 0.00 0.00
08.01.10.01.04 SUMINISTRO e INSTALACION CODO 90° x 250 mm ACERO SCH - 40 1,474.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,474.90 0.00 0.00 0.00
08.01.10.01.05 SUMINISTRO e INSTALACION CODO 45° x 400 mm ACERO SCH - 40 2,084.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,084.94 0.00 0.00 0.00
08.01.10.01.06 SUMINISTRO e INSTALACION CODO 45° x 250 mm ACERO SCH - 40 1,059.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,059.92 0.00 0.00 0.00
08.01.10.01.07 SUMINISTRO e INSTALACION CODO 22.5° x 250 mm ACERO SCH - 40 329.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 329.96 0.00 0.00 0.00
08.01.10.01.08 SUMINISTRO e INSTALACION UNION DRESSER DN 400 mm HFD 6,107.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,107.16 0.00 0.00 0.00
08.01.10.01.09 SUMINISTRO e INSTALACION UNION DRESSER DN 250 mm HFD 4,947.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,947.24 0.00 0.00 0.00
08.01.10.01.10 SUMINISTRO e INSTALACION VALVULA COMPUERTA DN 400 mm HFD 9,381.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,381.94 0.00 0.00 0.00
08.01.10.01.11 SUMINISTRO e INSTALACION VALVULA COMPUERTA DN 250 mm HFD 2,559.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,559.90 0.00 0.00 0.00
08.01.10.01.12 SUMINISTRO e INSTALACION TEE 400 x 400 mm ACERO SCH - 40 974.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 974.98 0.00 0.00 0.00
08.01.10.01.13 SUMINISTRO e INSTALACION TEE 250 x 250 mm ACERO SCH - 40 494.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 494.98 0.00 0.00 0.00
08.01.10.01.14 SUMINISTRO e INSTALACION REDUCCION DN 250 x 400 mm ACERO SCH - 40 1,114.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,114.98 0.00 0.00 0.00
08.01.10.01.15 SUMINISTRO e INSTALACION BRIDA ROMPE AGUA p/SOLDAR DN 400 mm ACERO SCH - 40 503.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 503.87 0.00 0.00 0.00
08.01.10.01.16 SUMINISTRO e INSTALACION BRIDA ROMPE AGUA p/SOLDAR DN 250 mm ACERO SCH - 40 450.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 450.34 0.00 0.00
08.01.10.01.17 SUMINISTRO e INSTALACION BRIDA p/SOLDAR y EMPERNAR DN 400 mm ACERO SCH - 40 16,105.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,105.74 0.00 0.00
08.01.10.01.18 SUMINISTRO e INSTALACION BRIDA p/SOLDAR y EMPERNAR DN 250 mm ACERO SCH - 40 19,494.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,494.92 0.00 0.00
08.01.10.02 OTROS ACCESORIOS 19,204.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,204.44 0.00 0.00
08.01.10.02.01 SUMINISTRO e INSTALACION TUBERIA PVC SAP Ø 2" 241.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 241.25 0.00 0.00
08.01.10.02.02 SUMINISTRO e INSTALACION TUBERIA PVC SAP Ø 1 1/2" 162.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 162.60 0.00 0.00
08.01.10.02.03 SUMINISTRO e INSTALACION TUBERIA PVC SAP Ø 1" 69.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 69.24 0.00 0.00
08.01.10.02.04 SUMINISTRO e INSTALACION TUBERIA PVC SAP Ø 3/4" 275.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 275.94 0.00 0.00
08.01.10.02.05 SUMINISTRO e INSTALACION CODO PVC SAP Ø 2" 1,105.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,105.20 0.00 0.00
08.01.10.02.06 SUMINISTRO e INSTALACION CODO PVC SAP Ø 1 1/2" 826.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 826.46 0.00 0.00
08.01.10.02.07 SUMINISTRO e INSTALACION CODO PVC SAP Ø 1" 465.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 465.84 0.00 0.00
08.01.10.02.08 SUMINISTRO e INSTALACION CODO PVC SAP Ø 1/2" 453.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 453.36 0.00 0.00
08.01.10.02.09 SUMINISTRO e INSTALACION MANOMETRO GLICERINA c/RANGO 0 a 300 lb/pg² 445.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 445.28 0.00 0.00
08.01.10.02.10 SUMINISTRO e INSTALACION TRANSICION BRIDA ESPIGA PVC DN 150 mm 394.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 394.68 0.00 0.00
08.01.10.02.11 SUMINISTRO e INSTALACION TRANSICION BRIDA ESPIGA PVC DN 200 mm 646.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 646.68 0.00 0.00
08.01.10.02.12 SUMINISTRO e INSTALACION CANASTILLA BRIDA DN 200 mm ACERO INOXIDABLE 2,879.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,879.39 0.00 0.00
08.01.10.02.13 SUMINISTRO e INSTALACION MEDIDOR CAUDAL ELECTROMAGNETICO DN 200 mm 11,059.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,059.08 0.00 0.00
08.01.10.02.14 SUMINISTRO e INSTALACION EMPAQUES e = 1/4" 179.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 179.44 0.00 0.00
08.01.11 CONEXIONES ELECTRICAS Y DE TELEMETRIA EN EL RESERVORIO ELEVADO 323,150.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,608.44 93,366.28 204,175.35
08.01.11.01 SUMINISTRO Y MONTAJE DE LAS CONEXIONES ELECTRICAS DEL RESERVORIO 16,271.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,271.81 0.00 0.00
08.01.11.01.01 SUMINISTRO Y MONTAJE DE LAS CONEXIONES ELECTRICAS DEL RESERVORIO 1600m3 16,271.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,271.81 0.00 0.00
08.01.11.02 CONEXIONES DE TELEMETRIA EN EL RESERVORIO ELEVADO 140,049.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,336.63 93,366.28 37,346.51
08.01.11.02.01 CONEXIONES DE TELEMETRIA EN EL RESERVORIO ELEVADO 140,049.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,336.63 93,366.28 37,346.51
08.01.11.03 TABLEROS ELECTRICOS Y OTROS 166,828.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 166,828.84
08.01.11.03.01 SUMINISTRO e INSTALACION SISTEMA ELECTROMECANICO CUBA 1,600 m3 166,828.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 166,828.84
08.02 CERCO PERIMETRICO 192,042.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 42,942.91 33,091.49 100,419.91 15,588.43 0.00 0.00 0.00 0.00 0.00 0.00
08.02.01 TRABAJOS PRELIMINARES 2,196.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,472.78 299.95 320.63 103.43 0.00 0.00 0.00 0.00 0.00 0.00
08.02.01.01 LIMPIEZA TERRENO MANUAL 710.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 710.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.01.02 TRAZO, NIVELACION y REPLANTEO 607.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 607.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.01.03 TRAZO, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 879.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 155.15 299.95 320.63 103.43 0.00 0.00 0.00 0.00 0.00 0.00
08.02.02 MOVIMIENTO DE TIERRAS 5,664.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,664.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.02.01 EXCAVACION MANUAL ZANJA HASTA 1.00 m; a = 0.60 m 1,691.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,691.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.02.02 REFINE y NIVELACION FONDO ZANJA; a = 0.60 m 221.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 221.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.02.03 RELLENO y COMPACTACION c/MATERIAL PROPIO SELECCIONADO CAPAS c/0.20 m 728.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 728.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.02.04 RELLENO y COMPACTACION c/ARENA FINA 440.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 440.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.02.05 RELLENO y COMPACTACION c/AFIRMADO CAPAS c/0.20 m 1,171.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,171.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.02.06 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 1,411.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,411.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.03 OBRAS DE CONCRETO SIMPLE 33,094.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33,094.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.03.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDDO 16,790.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,790.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.03.02 VEREDA c/CONCRETO f' = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base de afirmado 8,745.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,745.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.03.03 ENCOFRADO y DESENCOFRADO p/SARDINEL 1,794.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,794.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.03.04 CONCRETO f'c = 140 Kg/cm² (h = 0.15 m) p/SARDINEL 1,690.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,690.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.03.05 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS 2,738.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,738.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.03.06 CONCRETO F'C=140 KG/CM2.+30% PM.PARA SOBRECIMIENTOS 963.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 963.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.03.07 JUNTA DILATACION ASFALTICA c/3.00 m 372.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 372.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04 OBRAS DE CONCRETO ARMADO 28,959.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,711.37 20,472.78 5,775.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04.01 VIGAS DE CIMENTACION 13,652.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,711.37 10,941.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04.01.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 3,361.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,361.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04.01.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA CIMENTACION 3,795.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,711.37 1,084.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04.01.03 CONCRETO F'C=210 KG/CM2. PARA VIGAS DE CIMENTACION 6,495.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,495.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04.02 COLUMNAS 9,531.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,531.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 4,956.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,956.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04.02.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 2,931.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,931.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04.02.03 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 1,644.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,644.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04.03 VIGAS 5,775.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,775.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04.03.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 2,403.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,403.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 2,169.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,169.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04.03.03 CONCRETO f'c = 210 Kg/cm² p/VIGA 1,202.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,202.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.05 MUROS y TABIQUES DE ALBAÑILERIA 17,800.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,680.58 7,120.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.05.01 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 17,800.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,680.58 7,120.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.06 REVOQUES, ENLUCIDOS y MOLDURAS 18,850.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,638.18 15,247.21 1,964.83 0.00 0.00 0.00 0.00 0.00 0.00
08.02.06.01 TARRAJEO INTERIOR/EXTERIOR c/MORTERO C:A 1:5 11,467.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,638.18 9,829.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.06.02 TARRAJEO SUPERFICIE COLUMNA c/MORTERO C:A 1:5 2,416.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,416.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.06.03 TARRAJEO SUPERFICIE VIGA c/MORTERO C:A 1:5 2,412.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,412.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.06.04 BRUÑA s/DETALLE (1 x 1 cm) 2,554.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 589.45 1,964.83 0.00 0.00 0.00 0.00 0.00 0.00
08.02.07 CARPINTERIA METALICA y HERRERIA 69,690.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 69,690.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.07.01 PUERTA METALICA (inc. pintura) 1,132.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,132.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.07.02 PORTON METALICO INGRESO 3.60 x 3.80 m (inc. pintura) 68,558.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 68,558.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.08 PINTURA 3,236.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,265.73 971.03 0.00 0.00 0.00 0.00 0.00 0.00
08.02.08.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 3,236.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,265.73 971.03 0.00 0.00 0.00 0.00 0.00 0.00
08.02.09 VARIOS, LIMPIEZA y JARDINERIA 12,549.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,549.14 0.00 0.00 0.00 0.00 0.00 0.00
08.02.09.01 SEMBRADO AREAS VERDES p/RESERVORIO ELEVADO 12,549.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,549.14 0.00 0.00 0.00 0.00 0.00 0.00
08.03 CASETA DE VIGILANCIA 30,386.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,068.31 20,317.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.01 TRABAJOS PRELIMINARES 95.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 95.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.01.01 LIMPIEZA TERRENO MANUAL 30.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.01.02 TRAZO, NIVELACION y REPLANTEO 26.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.01.03 TRAZO, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 38.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02 ESTRUCTURAS 10,840.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,510.13 1,330.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.01 MOVIMIENTO DE TIERRAS 494.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 494.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.01.01 EXCAVACION TERRENO NORMAL SECO HASTA 3.00 m 98.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 98.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.01.02 RELLENO y APISONADO PARED c/MATERIAL PROPIO SELECCIONADO 21.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.01.03 RELLENO MANUAL c/MATERIAL PRESTAMO 189.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 189.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.01.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 185.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 185.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.02 CONCRETO SIMPLE 3,148.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,148.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.02.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDDO 2,338.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,338.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.02.02 ENCOFRADO y DESENCOFRADO HASTA 0.30 m p/SOBRECIMIENTO 387.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 387.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.02.03 CONCRETO C:H 1:8 + 25 % PM; f'c = 100 Kg/cm² p/SOBRECIMIENTO 137.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 137.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.02.04 CONCRETO C:H 1:8 (e = 4") p/FALSO PISO 284.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 284.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03 CONCRETO ARMADO 7,197.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,866.97 1,330.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.01 VIGAS DE CIMENTACION 2,424.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,424.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.01.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 457.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 457.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.01.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA CIMENTACION 528.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 528.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.01.03 CONCRETO f'c = 210 Kg/cm² p/VIGA CIMENTACION 1,438.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,438.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.02 COLUMNAS 1,531.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,531.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 744.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 744.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.02.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 509.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 509.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.02.03 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 277.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 277.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.03 VIGAS 1,218.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 568.96 649.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.03.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 568.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 568.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 262.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 262.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.03.03 CONCRETO f'c = 210 Kg/cm² p/VIGA 387.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 387.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.04 LOSAS ALIGERADAS 2,022.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,341.76 680.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.04.01 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA ALIGERADA 874.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 874.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.04.02 LADRILLO HUECO ARCILLA 15 x 30 x 30 cm p/LOSA ALIGERADA 467.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 467.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 235.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 235.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02.03.04.04 CONCRETO f'c = 210 Kg/cm² p/LOSA ALIGERADA 444.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 444.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03 ARQUITECTURA 16,247.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 462.63 15,784.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.01 MUROS y TABIQUES DE ALBAÑILERIA 1,850.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 462.63 1,387.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.01.01 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 1,850.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 462.63 1,387.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.02 REVOQUES y REVESTIMIENTOS 4,103.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,103.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.02.01 TARRAJEO INTERIOR/EXTERIOR c/MORTERO C:A 1:5 2,842.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,842.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.02.02 TARRAJEO SUPERFICIE COLUMNA c/MORTERO C:A 1:5 419.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 419.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.02.03 TARRAJEO SUPERFICIE VIGA c/MORTERO C:A 1:5 389.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 389.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.02.04 BRUÑA s/DETALLE (1 x 1 cm) 369.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 369.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.02.05 JUNTA DILATACION c/ESPUMA PLASTICA + JEBE MICROPOROSO 81.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 81.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.03 CIELO RASO y FALSO CIELO RASO 845.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 845.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.03.01 CIELO RASO c/MORTERO C:A 1:5 845.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 845.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.04 PISOS y PAVIMENTOS 787.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 787.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.04.01 CONTRAPISO (e = 48 mm) 240.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 240.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.04.02 PISO CERAMICA (20 x 20 cm) p/BAÑO 547.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 547.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.05 ZOCALOS y CONTRAZOCALOS 671.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 671.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.05.01 ZOCALOS 671.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 671.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.05.01.01 ZOCALO CERAMICO COLOR (20 x 20 cm) 671.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 671.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.06 CARPINTERIA METALICA y HERRERIA 7,265.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,265.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.06.01 PUERTA METAL LAC 1/16" y VENTANA PLEGADA c/MARCO 2" x 2" x 1/4" (inc. pintura) 6,422.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,422.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.06.02 VENTANA FIERRO (inc. pintura) 843.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 843.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.07 VIDRIOS, CRISTALES y SIMILARES 52.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 52.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.07.01 VIDRIO NACIONAL DOBLE 52.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 52.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.08 PINTURA 670.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 670.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.08.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 418.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 418.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03.08.02 PINTURA LATEX CIELO RASO 02 MANOS inc./IMPRIMANTE 251.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 251.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04 INSTALACIONES SANITARIAS 3,203.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,203.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.01 SISTEMA DE AGUA FRIA 620.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 620.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.01.01 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 3/4" 297.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 297.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.01.02 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 1/2" 40.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 40.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.01.03 SALIDA AGUA FRIA c/TUBERIA PVC SAP 1/2" 190.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 190.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.01.04 VALVULAS COMPUERTA BRONCE 1/2" 91.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 91.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.02 SISTEMA DE AGUA RESIDUAL 1,666.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,666.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.02.01 TUBERIA PVC SAL 4" 670.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 670.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.02.02 TUBERIA PVC SAL 2" 146.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 146.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.02.03 SALIDA DESAGUE PVC 4" 76.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 76.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.02.04 SALIDA DESAGUE PVC 2" 70.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 70.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.02.05 REGISTRO BRONCE 4" 129.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 129.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.02.06 REGISTRO BRONCE 2" 174.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 174.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.02.07 SALIDA VENTILACION PVC 2" 154.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 154.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 de 10
CALENDARIO DE AVANCE DE OBRA VALORIZADO ACTUALIZADO A LA FECHA DE INICIO DE OBRA
OBRA : INSTALACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DE LOS PP.JJ. VILLA PROGRESO, MIRAFLORES, LAS VEGAS, SAMAN, SAN FRANCISCO DE ASIS, LA UNION, SAN JUAN DE DIOS Y RAMIRO PRIALE II - CHICLAYO
ENTIDAD : ENTIDAD PRESTADORA DE SERVICIOS DE SANEAMIENTO DE LAMBAYEQUE S.A. - EPSEL S.A.
CONTRATISTA : CONSORCIO PROGRESO
SUPERVISION : CONSORCIO SUPERVISOR ASIS
UBICACIÓN : CHICLAYO - CHICLAYO - LAMBAYEQUE
Duración (Meses)
Item Descripción Parcial (S/.)
Mar-2019 Abr-2019 May-2019 Jun-2019 Jul-2019 Ago-2019 Sep-2019 Oct-2019 Nov-2019 Dic-2019 Ene-2020 Feb-2020 Mar-2020 Abr-2020 May-2020 Jun-2020 Jul-2020 Ago-2020 Sep-2020 Oct-2020
08.03.04.02.08 CAJA REGISTRO DESAGUE 12" x 24" 242.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 242.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.03 APARATOS Y ACCESORIOS SANITARIOS 916.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 916.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.03.01 INODORO TANQUE BAJO BLANCO 205.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 205.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.03.02 LAVATORIO FONTANA COLOR BLANCO 396.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 396.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.03.03 DUCHA CROMADA 01 LLAVE inc./ACCESORIOS 90.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 90.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.03.04 JABONERA LOSA BLANCO 118.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 118.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04.03.05 GRIFO CROMADO 105.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 105.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09 RED GENERAL DE AGUA POTABLE y CONEXIONES DOMICILIARIAS 4,674,149.95 0.00 0.00 18,735.49 193,057.77 111,250.95 123,850.95 252,962.43 311,496.46 556,218.49 544,497.42 674,068.64 638,191.80 514,223.34 405,882.72 329,713.49 0.00 0.00 0.00 0.00 0.00
09.01 RED GENERAL DE AGUA POTABLE 3,293,471.02 0.00 0.00 18,735.49 193,057.77 111,250.95 123,850.95 252,962.43 311,496.46 541,627.77 431,721.05 553,808.90 445,421.81 309,537.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.01 TRABAJOS PRELIMINARES 117,289.93 0.00 0.00 18,735.49 23,548.92 0.00 0.00 0.00 11,250.83 16,072.61 16,608.37 16,608.36 14,465.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.01.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 41,634.42 0.00 0.00 18,735.49 22,898.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.01.02 TRAZOS, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 75,005.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,250.83 16,072.61 16,608.37 16,608.36 14,465.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.01.03 DEMOLICION PAVIMENTO FLEXIBLE 649.99 0.00 0.00 0.00 649.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02 MOVIMIENTO DE TIERRAS 2,170,574.72 0.00 0.00 0.00 153,373.34 61,210.76 71,210.76 192,605.63 201,359.15 202,605.63 241,128.36 359,892.20 377,651.45 309,537.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.01 EXCAVACION DE ZANJAS 301,611.18 0.00 0.00 0.00 11,381.55 11,381.55 11,381.55 42,680.83 44,103.52 42,680.83 44,103.52 28,453.89 32,721.97 32,721.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.01.01 EXCAVACION ZANJA c/MAQUINA p/TUBERIA Ø = 110 mm a 250 mm; a = 0.60 m; h = 1.50 m 301,611.18 0.00 0.00 0.00 11,381.55 11,381.55 11,381.55 42,680.83 44,103.52 42,680.83 44,103.52 28,453.89 32,721.97 32,721.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.02 REFINE y NIVELACION DE ZANJAS 80,090.64 0.00 0.00 0.00 2,644.50 2,644.50 2,644.50 11,333.58 11,711.37 11,333.58 11,711.37 7,933.50 9,066.87 9,066.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.02.01 REFINE y NIVELACION ZANJA p/TUBERIA Ø 110 a 250 mm 80,090.64 0.00 0.00 0.00 2,644.50 2,644.50 2,644.50 11,333.58 11,711.37 11,333.58 11,711.37 7,933.50 9,066.87 9,066.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.03 CAMA DE APOYO P/TUBERIAS 162,723.84 0.00 0.00 0.00 4,605.39 4,605.39 4,605.39 23,026.96 23,794.52 23,026.96 23,794.52 16,886.45 19,189.13 19,189.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.03.01 CAMA APOYO p/TUBERIA Ø 110 mm a 250 mm c/RIPIO CORRIENTE a = 0.15 m 162,723.84 0.00 0.00 0.00 4,605.39 4,605.39 4,605.39 23,026.96 23,794.52 23,026.96 23,794.52 16,886.45 19,189.13 19,189.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.04 RELLENO, APISONADO y COMPACTACION LATERAL CON MATERIAL DE PRESTAMO 282,240.79 0.00 0.00 0.00 4,761.22 4,761.22 4,761.22 35,709.13 36,899.44 35,709.13 52,579.84 32,168.29 37,445.65 37,445.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.04.01 RELLENO LATERAL Y APISONADO DE ZANJA p/TUBERIA Ø 110 mm c/RIPIO CORRIENTE 242,822.09 0.00 0.00 0.00 4,761.22 4,761.22 4,761.22 35,709.13 36,899.44 35,709.13 36,899.44 19,044.85 32,138.22 32,138.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.04.02 RELLENO LATERAL Y APISONADO DE ZANJA p/TUBERIA Ø 160 mm c/RIPIO CORRIENTE 10,518.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,518.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.04.03 RELLENO LATERAL Y APISONADO DE ZANJA p/TUBERIA Ø 200 mm c/RIPIO CORRIENTE 10,324.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,162.30 5,162.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.04.04 RELLENO LATERAL Y APISONADO DE ZANJA p/TUBERIA Ø 250 mm c/RIPIO CORRIENTE 18,576.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,961.14 5,307.43 5,307.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.05 RELLENO y COMPACTACION S/CLAVE TUBO C/MATERIAL DE PRESTAMO 447,808.38 0.00 0.00 0.00 8,449.21 8,449.21 8,449.21 43,369.11 45,481.41 43,369.11 45,481.41 50,695.31 57,032.20 137,032.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.05.01 RELLENO y COMPACTACION ZANJA p/TUBERIA Ø 110 mm a 250 mm c/RIPIO CORRIENTE 447,808.38 0.00 0.00 0.00 8,449.21 8,449.21 8,449.21 43,369.11 45,481.41 43,369.11 45,481.41 50,695.31 57,032.20 137,032.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.06 RELLENO y COMPACTACION CON MATERIAL PROPIO SELECCIONADO 611,167.86 0.00 0.00 0.00 121,531.47 29,368.89 39,368.89 36,486.02 39,368.89 46,486.02 49,368.89 69,188.81 110,042.00 69,957.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.06.01 RELLENO y COMPACTACION c/MATERIAL PROPIO SELECCIONADO y PRESTAMO CAPAS c/0.20 m; a = variable hasta Nivel de Terreno 611,167.86
Natural 0.00 0.00 0.00 121,531.47 29,368.89 39,368.89 36,486.02 39,368.89 46,486.02 49,368.89 69,188.81 110,042.00 69,957.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.07 PERFORACION HORIZONTAL DIRIGIDA 18,457.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,333.86 4,123.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.07.01 PERFORACION HORIZONTAL DIRIGIDA (CRUCE DE VIA N° 02 y 05) C/TUBERIA HDPE 160mm 12,787.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,787.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.07.02 PERFORACION HORIZONTAL DIRIGIDA (CRUCE DE VIA N° 06) C/TUBERIA HDPE 200mm 5,670.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,546.36 4,123.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.08 ACARREO y ELIMINACION MATERIAL EXCEDENTE 266,474.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,088.81 154,565.95 97,819.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.02.08.01 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 266,474.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,088.81 154,565.95 97,819.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03 SUMINISTRO e INSTALACION DE TUBERIAS y ACCESORIOS 1,005,606.37 0.00 0.00 0.00 16,135.51 50,040.19 52,640.19 60,356.80 98,886.48 322,949.53 173,984.32 177,308.34 53,305.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.01 SUMINISTRO e INSTALACION DE TUBERIAS PVC C-7.5 642,887.79 0.00 0.00 0.00 16,135.51 50,040.19 50,040.19 46,813.09 60,040.19 143,669.55 142,039.07 134,110.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.01.01 SUMINISTRO e INSTALACION TUBERIA DN 110 mm PVC UF CL 7.5; h = 1.50 m; c/3% desperdicio 461,475.71 0.00 0.00 0.00 16,135.51 50,040.19 50,040.19 46,813.09 60,040.19 48,406.54 55,890.00 134,110.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.01.02 SUMINISTRO e INSTALACION TUBERIA DN 160 mm PVC UF CL 7.5; h = 1.50 m; c/3% desperdicio 33,919.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33,919.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.01.03 SUMINISTRO e INSTALACION TUBERIA DN 200 mm PVC UF CL 7.5; h = 1.50 m; c/3% desperdicio 44,114.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 44,114.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.01.04 SUMINISTRO e INSTALACION TUBERIA DN 250 mm PVC UF CL 7.5; h = 1.50 m; c/3% desperdicio 103,378.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,229.81 86,149.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.02 SUMINISTRO DE TUBERIA HDPE 3,894.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,894.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.02.01 SUMINISTRO DE TUBERIA HDPE PE-100 PN10 Ø 160 mm x 6.00 m 2,641.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,641.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.02.02 SUMINISTRO DE TUBERIA HDPE PE-100 PN10 Ø 200 mm x 6.00 m 1,252.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,252.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03 SUMINISTRO e INSTALACION DE ACCESORIOS 217,486.93 0.00 0.00 0.00 0.00 0.00 2,600.00 2,600.00 27,902.58 167,277.21 17,107.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.01 SUMINISTRO e INSTALACION VALVULA Ø 110 mm f°f° ISO (equipada) 54,619.25 0.00 0.00 0.00 0.00 0.00 2,600.00 2,600.00 27,902.58 21,516.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.02 SUMINISTRO e INSTALACION VALVULA Ø 160 mm f°f° ISO (equipada) 2,088.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,088.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.03 SUMINISTRO e INSTALACION VALVULA Ø 200 mm f°f° ISO (equipada) 1,699.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,699.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.04 SUMINISTRO e INSTALACION VALVULA Ø 250 mm f°f° ISO (equipada) 5,093.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,093.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.05 SUMINISTRO e INSTALACION TEE Ø 110 mm x 110 mm PVC UF ISO (equipada) 26,862.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26,862.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.06 SUMINISTRO e INSTALACION TEE Ø 160 mm x 110 mm PVC UF ISO (equipada) 3,206.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,206.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.07 SUMINISTRO e INSTALACION TEE Ø 200 mm x 110 mm PVC UF ISO (equipada) 6,731.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,731.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.08 SUMINISTRO e INSTALACION TEE Ø 250 mm x 110 mm PVC UF ISO (equipada) 11,088.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,088.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.09 SUMINISTRO e INSTALACION TEE Ø 160 mm x 160 mm PVC UF ISO (equipada) 738.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 738.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.10 SUMINISTRO e INSTALACION TEE Ø 200 mm x 200 mm PVC UF ISO (equipada) 1,447.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,447.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.11 SUMINISTRO e INSTALACION TEE Ø 200 mm x 160 mm PVC UF ISO (equipada) 675.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 675.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.12 SUMINISTRO e INSTALACION TEE Ø 250 mm x 200 mm PVC UF ISO (equipada) 1,045.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,045.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.13 SUMINISTRO e INSTALACION TEE Ø 250 mm x 250 mm PVC UF ISO (equipada) 2,153.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,153.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.14 SUMINISTRO e INSTALACION CRUZ Ø 110 mm x 110 mm PVC UF ISO (equipada) 12,388.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,388.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.15 SUMINISTRO e INSTALACION CRUZ Ø 160 mm x 110 mm PVC UF ISO (equipada) 2,532.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,532.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.16 SUMINISTRO e INSTALACION TAPON Ø 110 mm PVC-UF ISO (equipado) 4,111.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,111.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.17 SUMINISTRO e INSTALACION TAPON Ø 160 mm PVC-UF ISO (equipado) 165.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 165.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.18 SUMINISTRO e INSTALACION CODO Ø 110 mm x 90° PVC UF ISO (equipado) 6,184.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,184.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.19 SUMINISTRO e INSTALACION CODO Ø 110 mm x 45° PVC UF ISO (equipado) 1,256.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,256.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.20 SUMINISTRO e INSTALACION CODO Ø 110 mm x 22.5° PVC UF ISO (equipado) 824.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 824.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.21 SUMINISTRO e INSTALACION CODO Ø 110 mm x 11.25° PVC UF ISO (equipado) 4,361.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,361.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.22 SUMINISTRO e INSTALACION CODO Ø 160 mm x 90° PVC UF ISO (equipado) 268.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 268.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.23 SUMINISTRO e INSTALACION CODO Ø 160 mm x 45° PVC UF ISO (equipado) 224.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 224.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.24 SUMINISTRO e INSTALACION CODO Ø 160 mm x 22.5° PVC UF ISO (equipado) 243.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 243.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.25 SUMINISTRO e INSTALACION CODO Ø 160 mm x 11.25° PVC UF ISO (equipado) 225.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 225.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.26 SUMINISTRO E INSTALACION CODO Ø 200 mm x 90° PVC UF ISO (equipado) 1,200.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,200.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.27 SUMINISTRO E INSTALACION CODO Ø 200 mm x 45° PVC UF ISO (equipado) 393.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 393.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.28 SUMINISTRO e INSTALACION REDUCCION Ø 160 mm x 110 mm PVC UF ISO (equipada) 503.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 503.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.29 SUMINISTRO e INSTALACION REDUCCION Ø 200 mm x 110 mm PVC UF ISO (equipada) 248.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 248.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.30 SUMINISTRO e INSTALACION REDUCCION Ø 200 mm x 160 mm PVC UF ISO (equipada) 342.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 342.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.31 SUMINISTRO e INSTALACION REDUCCION Ø 250 mm x 200 mm PVC UF ISO (equipada) 467.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 467.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.32 SUMINISTRO e INSTALACION REDUCCION Ø 250 mm x 110 mm PVC UF ISO (equipada) 361.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 361.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.03.33 SUMINISTRO e INSTALACION GRIFO CONTRA INCENDIO f°f° ISO (equipado) 63,731.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 63,731.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.04 PRUEBAS HIDRAULICAS y DE DESINFECCION 77,166.24 0.00 0.00 0.00 0.00 0.00 0.00 10,943.71 10,943.71 12,002.77 10,943.69 10,943.71 21,388.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.04.01 DOBLE PRUEBA HIDRAULICA y DESINFECCION p/TUBERIA DN 110 mm PVC 62,838.04 0.00 0.00 0.00 0.00 0.00 0.00 10,943.71 10,943.71 12,002.77 10,943.69 10,943.71 7,060.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.04.02 DOBLE PRUEBA HIDRAULICA y DESINFECCION p/TUBERIA DN 160 mm PVC/HDPE 3,905.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,905.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.04.03 DOBLE PRUEBA HIDRAULICA y DESINFECCION p/TUBERIA DN 200 mm PVC/HDPE 3,239.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,239.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.04.04 DOBLE PRUEBA HIDRAULICA y DESINFECCION p/TUBERIA DN 250 mm PVC 7,182.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,182.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.05 VARIOS 64,170.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32,254.63 31,916.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.05.01 CAJA CONCRETO p/PROTECCION VALVULA 46,231.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32,254.63 13,977.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.03.05.02 TAPA CONCRETO ARMADO p/PROTECCION VALVULA 17,939.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,939.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02 CONEXIONES DOMICILIARIAS 1,380,678.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,590.72 112,776.37 120,259.74 192,769.99 204,685.90 405,882.72 329,713.49 0.00 0.00 0.00 0.00 0.00
09.02.01 TRABAJOS PRELIMINARES 24,942.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,569.88 10,958.41 1,413.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.01.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 21,209.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,837.43 10,958.41 1,413.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.01.02 DEMOLICION PAVIMENTO FLEXIBLE 689.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 689.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.01.03 DEMOLICION VEREDA CONCRETO (e = 0.10 m) 3,042.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,042.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.02 MOVIMIENTO DE TIERRAS 614,919.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,020.84 81,134.02 85,515.10 77,417.36 98,528.72 270,303.47 0.00 0.00 0.00 0.00 0.00 0.00
09.02.02.01 EXCAVACION MANUAL ZANJA p/TUBERIA Ø 1/2"; a = 0.40 m; h = 1.00 m 272,813.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,020.84 22,646.02 22,646.01 18,604.34 22,646.02 184,250.07 0.00 0.00 0.00 0.00 0.00 0.00
09.02.02.02 REFINE y NIVELACION FONDO ZANJA p/TUBERIA Ø 1/2"; a = 0.40 m 51,162.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,748.45 11,748.45 10,990.49 11,748.45 4,926.77 0.00 0.00 0.00 0.00 0.00 0.00
09.02.02.03 CAMA APOYO P/TUBERIA Ø 1/2" c/ARENA FINA; e = 0.05 m; a = 0.40 m 38,210.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,491.12 8,774.17 8,208.08 8,774.16 3,962.52 0.00 0.00 0.00 0.00 0.00 0.00
09.02.02.04 RELLENO y APISONADO p/TUBERIA Ø 1/2" c/ARENA FINA; h = 0.30 m 65,086.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,499.45 14,945.81 13,981.57 14,945.81 7,713.97 0.00 0.00 0.00 0.00 0.00 0.00
09.02.02.05 RELLENO y COMPACTACION ZANJA p/TUBERIA Ø 1/2" 119,325.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24,748.98 27,400.66 25,632.88 27,400.66 14,142.28 0.00 0.00 0.00 0.00 0.00 0.00
09.02.02.06 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 68,321.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,013.62 55,307.86 0.00 0.00 0.00 0.00 0.00 0.00
09.02.03 SUMINISTRO e INSTALACION DE TUBERIAS 68,000.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,725.91 16,593.20 24,990.18 18,691.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.03.01 SUMINISTRO e INSTALACION TUBERIA Ø 1/2" PVC SP CL 10 29,305.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,725.91 8,258.73 7,725.91 5,594.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.03.02 DOBLE PRUEBA HIDRAULICA y DESINFECCION p/TUBERIA Ø 1/2" PVC 38,695.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,334.47 17,264.27 13,097.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.04 SUMINISTRO e INSTALACION DE ACCESORIOS 659,618.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,958.03 16,737.46 90,362.45 87,465.53 135,579.25 316,516.00 0.00 0.00 0.00 0.00 0.00
09.02.04.01 SUMINISTRO e INSTALACION ABRAZADERA 110 mm x 1/2" PVC (equipada) 46,432.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,958.03 16,737.46 15,657.62 1,079.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.04.02 SUMINISTRO e INSTALACION ABRAZADERA 160 mm x 1/2" PVC (equipada) 1,395.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,395.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.04.03 SUMINISTRO e INSTALACION ABRAZADERA 200 mm x 1/2" PVC (equipada) 594.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 594.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.04.04 SUMINISTRO e INSTALACION ABRAZADERA 250 mm x 1/2" PVC (equipada) 1,963.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,963.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.04.05 SUMINISTRO e INSTALACION ACCESORIOS p/CONEXION DOMICILIARIA Ø 1/2" 101,739.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24,005.94 35,437.35 34,294.20 8,001.98 0.00 0.00 0.00 0.00 0.00
09.02.04.06 SUMINISTRO e INSTALACION CAJA p/MEDIDOR AGUA INC. LOSA CONCRETO 1x1 218,886.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 27,072.47 22,962.33 50,608.71 118,243.48 0.00 0.00 0.00 0.00 0.00
09.02.04.07 SUMINISTRO e INSTALACION DE MEDIDOR Ø 1/2" 288,605.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23,626.42 24,032.22 50,676.34 190,270.54 0.00 0.00 0.00 0.00 0.00
09.02.05 OTROS 13,197.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,197.49 0.00 0.00 0.00 0.00 0.00
09.02.05.01 REPOSICION PAVIMENTO FLEXIBLE EN CALIENTE e = 2" 8,476.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,476.37 0.00 0.00 0.00 0.00 0.00
09.02.05.02 REPOSICION VEREDA c/CONCRETO f'c = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base de afirmado 4,721.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,721.12 0.00 0.00 0.00 0.00 0.00
10 RED GENERAL DE AGUA RESIDUAL y CONEXIONES DOMICILIARIAS 9,248,120.23 15,907.75 492,375.96 717,364.16 449,031.24 595,036.00 690,464.50 532,375.40 708,318.09 1,074,975.55 1,065,433.65 807,046.56 600,561.37 910,404.16 143,923.93 147,815.68 250,924.70 46,161.53 0.00 0.00 0.00
10.01 RED GENERAL DE AGUA RESIDUAL 7,426,164.36 15,907.75 492,375.96 717,364.16 449,031.24 595,036.00 690,464.50 532,375.40 638,554.39 968,298.29 937,888.28 630,083.84 374,086.17 359,974.63 24,003.75 720.00 0.00 0.00 0.00 0.00 0.00
10.01.01 TRABAJOS PRELIMINARES 205,010.79 15,907.75 45,769.11 23,678.49 21,822.80 22,560.74 22,577.40 19,285.30 6,681.84 6,466.30 6,681.84 6,681.84 6,250.75 646.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.01.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 42,488.71 15,907.75 26,580.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.01.02 TRAZOS, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 68,111.67 0.00 1,724.35 6,681.84 6,466.30 6,681.84 6,681.84 6,466.30 6,681.84 6,466.30 6,681.84 6,681.84 6,250.75 646.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.01.03 DEMOLICION PAVIMENTO FLEXIBLE 1,299.63 0.00 1,299.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.01.04 REMOCION RED EXISTENTE ALCANTARILLADO PVC 23,946.92 0.00 16,164.17 7,782.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.01.05 REMOCION RED EXISTENTE ALCANTARILLADO CSN 34,296.18 0.00 0.00 9,213.90 15,356.50 9,725.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.01.06 REMOCION POZOS SEPTICOS, BUZONES y BUZONETAS 34,867.68 0.00 0.00 0.00 0.00 6,153.12 15,895.56 12,819.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02 MOVIMIENTO DE TIERRAS 2,761,701.18 0.00 139,920.26 201,702.15 193,670.83 209,024.92 215,070.04 245,623.51 236,039.95 183,828.76 299,321.84 377,145.72 143,008.20 294,560.00 22,065.00 720.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01 EXCAVACION DE ZANJAS 593,281.36 0.00 47,795.70 54,681.45 48,882.81 59,410.63 61,920.95 57,896.89 58,975.07 16,302.04 107,799.36 66,316.46 13,300.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.01 EXCAVACION DE ZANJAS C/EQUIPO HASTA 1.50 m; af = 0.80 m 84,439.07 0.00 47,795.70 36,643.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.02 EXCAVACION DE ZANJAS C/EQUIPO HASTA 2.00 m; af = 0.80 m 54,114.25 0.00 0.00 18,038.08 36,076.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.03 EXCAVACION DE ZANJAS C/EQUIPO HASTA 2.50 m; af = 1.00 m 43,908.48 0.00 0.00 0.00 12,806.64 31,101.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.04 EXCAVACION DE ZANJAS C/EQUIPO HASTA 3.00 m; af = 1.00 m 35,857.80 0.00 0.00 0.00 0.00 28,308.79 7,549.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.05 EXCAVACION DE ZANJAS C/EQUIPO HASTA 3.50 m; af = 1.00 m 34,463.23 0.00 0.00 0.00 0.00 0.00 34,463.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.06 EXCAVACION DE ZANJAS C/EQUIPO HASTA 4.00 m; af = 1.00 m 18,083.25 0.00 0.00 0.00 0.00 0.00 18,083.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.07 EXCAVACION DE ZANJAS C/EQUIPO HASTA 4.50 m; af = 1.00 m 31,032.83 0.00 0.00 0.00 0.00 0.00 1,825.46 29,207.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.08 EXCAVACION DE ZANJAS C/EQUIPO HASTA 5.00 m; af = 1.00 m 21,661.90 0.00 0.00 0.00 0.00 0.00 0.00 21,661.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.09 EXCAVACION DE ZANJAS C/EQUIPO HASTA 5.50 m; af = 1.00 m 14,055.25 0.00 0.00 0.00 0.00 0.00 0.00 7,027.62 7,027.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.10 EXCAVACION DE ZANJAS C/EQUIPO HASTA 6.00 m; af = 1.00 m 34,551.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 34,551.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.11 EXCAVACION DE ZANJAS C/EQUIPO HASTA 6.50 m; af = 1.00 m 13,642.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,642.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.12 EXCAVACION DE ZANJAS C/EQUIPO HASTA 7.00 m; af = 1.00 m 91,960.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,753.47 16,302.04 71,904.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.13 EXCAVACION DE ZANJAS C/EQUIPO HASTA 7.50 m; af = 1.00 m 68,011.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35,894.87 32,116.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.01.14 EXCAVACION DE ZANJAS C/EQUIPO HASTA 8.00 m; af = 1.00 m 47,500.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 34,200.00 13,300.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.02 REFINE y NIVELACION DE ZANJAS 41,381.81 0.00 4,562.16 5,682.13 6,732.81 6,957.24 6,642.60 2,013.33 2,080.44 2,013.33 2,080.44 2,080.44 536.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.02.01 REFINE y NIVELACION FONDO ZANJA; a = 0.80 m 23,597.40 0.00 4,562.16 4,876.80 4,719.48 4,876.80 4,562.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.02.02 REFINE y NIVELACION FONDO ZANJA; a = 1.00 m 17,784.41 0.00 0.00 805.33 2,013.33 2,080.44 2,080.44 2,013.33 2,080.44 2,013.33 2,080.44 2,080.44 536.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.03 CAMA DE APOYO P/TUBERIAS 398,286.26 0.00 30,729.55 34,022.00 32,924.52 34,022.00 34,022.00 64,030.45 52,176.49 34,562.15 35,714.23 35,714.22 10,368.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.03.01 CAMA APOYO (equipo) c/RIPIO CORRIENTE; af = 0.80 m 215,106.84 0.00 30,729.55 34,022.00 32,924.52 34,022.00 34,022.00 32,924.51 16,462.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.03.02 CAMA APOYO (equipo) c/RIPIO CORRIENTE; af = 1.00 m 183,179.42 0.00 0.00 0.00 0.00 0.00 0.00 31,105.94 35,714.23 34,562.15 35,714.23 35,714.22 10,368.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.04 RELLENO, APISONADO y COMPACTACION LATERAL CON MATERIAL DE PRESTAMO 327,421.37 0.00 25,508.11 30,413.52 29,432.44 30,413.52 34,262.96 42,605.93 29,833.17 28,870.81 29,744.71 34,963.34 11,372.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.04.01 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 200 mm; a = 0.80 m 159,916.24 0.00 25,508.11 30,413.52 29,432.44 30,413.52 30,413.52 13,735.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.04.02 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 200 mm; a = 1.00 m 113,558.50 0.00 0.00 0.00 0.00 0.00 3,849.44 28,870.80 29,833.17 28,870.81 22,134.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.04.03 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 250 mm; a = 1.00 m 8,561.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,610.43 951.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.04.04 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 315 mm; a = 1.00 m 8,091.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,091.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.04.05 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 355 mm; a = 1.00 m 21,798.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21,798.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.04.06 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 400 mm; a = 1.00 m 6,184.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,122.84 2,061.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.04.07 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 455 mm; a = 1.00 m 9,311.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,311.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.05 RELLENO y COMPACTACION S/CLAVE TUBO C/MATERIAL DE PRESTAMO 489,119.13 0.00 0.00 39,554.32 39,554.32 40,872.80 40,872.80 39,554.33 30,887.93 39,577.02 51,896.25 145,984.38 20,364.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.05.01 RELLENO y COMPACTACION c/ARENA FINA h = 0.30 m; c/EQUIPO p/TUBERIA Ø 200 mm; a = 0.80 m 214,911.82 0.00 0.00 39,554.32 39,554.32 40,872.80 40,872.80 39,554.33 14,503.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.05.02 RELLENO y COMPACTACION c/RIPIO CORRIENTE h = 0.30 m; c/EQUIPO p/TUBERIA Ø 200 mm; a = 1.00 m 199,454.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,384.68 39,577.02 51,896.25 91,596.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.05.03 RELLENO y COMPACTACION c/RIPIO CORRIENTE h = 0.30 m; c/EQUIPO p/TUBERIA Ø 250 mm; a = 1.00 m 13,539.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,539.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.05.04 RELLENO y COMPACTACION c/RIPIO CORRIENTE h = 0.30 m; c/EQUIPO p/TUBERIA Ø 315 mm; a = 1.00 m 11,510.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,510.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.05.05 RELLENO y COMPACTACION c/RIPIO CORRIENTE h = 0.30 m; c/EQUIPO p/TUBERIA Ø 355 mm; a = 1.00 m 29,338.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 29,338.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.05.06 RELLENO y COMPACTACION c/RIPIO CORRIENTE h = 0.30 m; c/EQUIPO p/TUBERIA Ø 400 mm; a = 1.00 m 8,901.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,901.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.05.07 RELLENO y COMPACTACION c/RIPIO CORRIENTE h = 0.30 m; c/EQUIPO p/TUBERIA Ø 455 mm; a = 1.00 m 11,463.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,463.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.06 RELLENO y COMPACTACION CON MATERIAL DE PRESTAMO 19,479.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,479.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.06.01 RELLENO y COMPACTACION c/MAT. PRESTAMO (ARENA FINA) Cap. 0.20 m; a = variable hasta Nivel de Terreno natural 19,479.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,479.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.07 RELLENO Y COMPACTACION CON MATERIAL PROPIO SELECCIONADO 385,535.29 0.00 31,324.74 37,348.73 36,143.93 37,348.73 37,348.73 36,143.93 37,348.73 36,143.93 37,348.73 37,348.75 21,686.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.07.01 RELLENO y COMPACTACION c/MATERIAL PROPIO SELECCIONADO CAPAS c/0.20 m; a = variable hasta Nivel de Terreno Natural 385,535.29 0.00 31,324.74 37,348.73 36,143.93 37,348.73 37,348.73 36,143.93 37,348.73 36,143.93 37,348.73 37,348.75 21,686.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.08 PERFORACION HORIZONTAL DIRIGIDA 47,700.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,355.00 19,560.00 22,065.00 720.00 0.00 0.00 0.00 0.00 0.00
10.01.02.08.01 PERFORACION HORIZONTAL DIRIGIDA (CRUCE DE VIA N° 3 y 4) C/TUBERIA HDPE 200mm 7,560.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,355.00 2,205.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.08.02 PERFORACION HORIZONTAL DIRIGIDA (CRUCE ACEQUIA LA CACHAZA) C/TUBERIA HDPE 250mm 9,555.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,555.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.08.03 PERFORACION HORIZONTAL DIRIGIDA (CRUCE ACEQUIA LA CACHAZA) C/TUBERIA HDPE 315 mm 10,920.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,800.00 3,120.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.08.04 PERFORACION HORIZONTAL DIRIGIDA (CRUCE DE CANAL C°) C/TUBERIA HDPE 400mm 14,625.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,625.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.08.05 PERFORACION HORIZONTAL DIRIGIDA (CRUCE DE VIA N° 1) C/TUBERIA HDPE 450 mm 5,040.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,320.00 720.00 0.00 0.00 0.00 0.00 0.00
10.01.02.09 ACARREO y ELIMINACION MATERIAL EXCEDENTE 459,496.29 0.00 0.00 0.00 0.00 0.00 0.00 3,378.65 24,738.12 26,359.48 34,738.12 54,738.13 40,543.79 275,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.02.09.01 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 459,496.29 0.00 0.00 0.00 0.00 0.00 0.00 3,378.65 24,738.12 26,359.48 34,738.12 54,738.13 40,543.79 275,000.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03 BOMBEO EN ZANJAS 336,958.48 0.00 54,648.41 56,470.02 75,582.54 20,496.07 26,726.56 17,655.27 10,034.00 25,773.03 22,660.41 24,069.24 2,842.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.01 DRENAJE ZANJA HASTA 2.00 m 165,766.83 0.00 54,648.41 56,470.02 54,648.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.02 DRENAJE ZANJA HASTA 2.50 m 34,890.24 0.00 0.00 0.00 20,934.14 13,956.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.03 DRENAJE ZANJA HASTA 3.00 m 22,614.86 0.00 0.00 0.00 0.00 6,219.09 16,395.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.04 DRENAJE ZANJA HASTA 3.50 m 19,253.00 0.00 0.00 0.00 0.00 320.88 9,947.38 8,984.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.05 DRENAJE ZANJA HASTA 4.00 m 8,626.66 0.00 0.00 0.00 0.00 0.00 383.41 5,751.10 2,492.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.06 DRENAJE ZANJA HASTA 4.50 m 12,164.28 0.00 0.00 0.00 0.00 0.00 0.00 2,919.43 7,541.85 1,703.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.07 DRENAJE ZANJA HASTA 5.00 m 10,491.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,491.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.08 DRENAJE ZANJA HASTA 5.50 m 6,178.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,178.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.09 DRENAJE ZANJA HASTA 6.00 m 10,571.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,400.25 3,171.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.10 DRENAJE ZANJA HASTA 6.50 m 3,826.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,826.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.11 DRENAJE ZANJA HASTA 7.00 m 24,471.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,661.93 8,809.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.12 DRENAJE ZANJA HASTA 7.50 m 12,010.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,010.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.03.13 DRENAJE ZANJA HASTA 8.00 m 6,092.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,249.07 2,842.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04 ENTIBADO DE ZANJAS 858,515.75 0.00 151,365.35 230,639.24 120,800.82 239,784.56 46,198.04 18,743.86 14,557.21 11,466.51 11,024.41 11,354.06 2,581.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.01 ENTIBADO ZANJA HASTA 2.00 m 465,707.28 0.00 126,252.26 147,262.26 6,642.59 185,550.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.02 ENTIBADO ZANJA HASTA 2.50 m 94,174.08 0.00 25,113.09 48,656.61 20,404.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.03 ENTIBADO ZANJA HASTA 3.00 m 62,954.89 0.00 0.00 26,755.83 36,199.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.04 ENTIBADO ZANJA HASTA 3.50 m 52,338.42 0.00 0.00 7,964.54 34,133.75 10,240.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.05 ENTIBADO ZANJA HASTA 4.00 m 22,255.72 0.00 0.00 0.00 12,631.62 9,624.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.06 ENTIBADO ZANJA HASTA 4.50 m 30,826.92 0.00 0.00 0.00 10,789.42 20,037.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.07 ENTIBADO ZANJA HASTA 5.00 m 18,388.95 0.00 0.00 0.00 0.00 7,662.06 10,726.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.08 ENTIBADO ZANJA HASTA 5.50 m 9,915.61 0.00 0.00 0.00 0.00 0.00 9,915.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.09 ENTIBADO ZANJA HASTA 6.00 m 19,567.09 0.00 0.00 0.00 0.00 6,670.60 12,896.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.10 ENTIBADO ZANJA HASTA 6.50 m 6,984.35 0.00 0.00 0.00 0.00 0.00 2,328.12 4,656.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.11 ENTIBADO ZANJA HASTA 7.00 m 42,262.88 0.00 0.00 0.00 0.00 0.00 10,330.93 14,087.63 14,557.21 3,287.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.12 ENTIBADO ZANJA HASTA 7.50 m 21,337.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,179.40 11,024.41 2,133.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.04.13 ENTIBADO ZANJA HASTA 8.00 m 11,802.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,220.31 2,581.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05 SUMINISTRO e INSTALACION DE TUBERIAS PVC 1,413,044.50 0.00 0.00 0.00 0.00 0.00 63,301.29 83,800.22 261,356.70 511,169.12 336,947.90 78,183.47 44,158.53 32,188.52 1,938.75 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.01 TUBERIA PVC U; SN 2 = 2 KN/m² 692,147.68 0.00 0.00 0.00 0.00 0.00 63,301.29 83,800.22 142,026.07 228,910.10 174,110.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.01.01 SUMINISTRO e INSTALACION TUBERIA PVC U SN 2 Ø 200 mm x 6.00 m hasta h = 1.50 m 350,292.04 0.00 0.00 0.00 0.00 0.00 63,301.29 59,223.65 47,767.10 55,890.00 124,110.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.01.02 SUMINISTRO e INSTALACION TUBERIA PVC U SN 2 Ø 200 mm x 6.00 m hasta h = 2.00 m 230,273.40 0.00 0.00 0.00 0.00 0.00 0.00 24,576.57 57,472.78 148,224.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.01.03 SUMINISTRO e INSTALACION TUBERIA PVC U SN 2 Ø 200 mm x 6.00 m hasta h = 2.50 m 111,582.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36,786.19 24,796.05 50,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.02 TUBERIA PVC U; SN 4 = 4 KN/m² 182,400.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 60,363.40 86,912.30 35,125.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.02.01 SUMINISTRO e INSTALACION TUBERIA PVC U SN 4 Ø 200 mm x 6.00 m hasta h = 3.00 m 84,935.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31,118.03 18,692.87 35,125.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.02.02 SUMINISTRO e INSTALACION TUBERIA PVC U SN 4 Ø 200 mm x 6.00 m hasta h = 3.50 m 68,219.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 68,219.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.02.03 SUMINISTRO e INSTALACION TUBERIA PVC U SN 4 Ø 200 mm x 6.00 m hasta h = 4.00 m 29,245.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 29,245.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03 TUBERIA PVC U; SN 8 = 8 KN/m² 538,496.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 58,967.23 195,346.72 127,712.90 78,183.47 44,158.53 32,188.52 1,938.75 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.01 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 200 mm x 6.00 m hasta h = 4.50 m 30,204.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24,640.42 5,563.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.02 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 250 mm x 6.00 m hasta h = 4.50 m 9,586.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,890.40 2,696.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.03 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 315 mm x 6.00 m hasta h = 4.50 m 19,185.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,849.58 7,335.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.04 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 200 mm x 6.00 m hasta h = 5.00 m 6,258.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,258.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.05 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 250 mm x 6.00 m hasta h = 5.00 m 20,399.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,999.93 11,399.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.06 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 315 mm x 6.00 m hasta h = 5.00 m 20,961.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20,961.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.07 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 200 mm x 6.00 m hasta h = 5.50 m 1,747.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,747.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.08 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 250 mm x 6.00 m hasta h = 5.50 m 7,530.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,530.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.09 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 315 mm x 6.00 m hasta h = 5.50 m 22,191.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,191.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.10 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 250 mm x 6.00 m hasta h = 6.00 m 9,597.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,597.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.11 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 355 mm x 6.00 m hasta h = 6.00 m 56,360.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 43,835.89 12,524.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.12 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 250 mm x 6.00 m hasta h = 6.50 m 687.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 487.85 199.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.13 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 355 mm x 6.00 m hasta h = 6.50 m 23,558.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,991.84 8,566.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.14 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 355 mm x 6.00 m hasta h = 7.00 m 23,054.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,586.90 10,978.17 5,489.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.15 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 400 mm x 6.00 m hasta h = 7.00 m 88,998.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,249.70 45,982.71 20,766.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.16 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 450 mm x 6.00 m hasta h = 7.00 m 102,711.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,118.60 35,378.44 35,378.44 14,836.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.17 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 355 mm x 6.00 m hasta h = 7.50 m 49,869.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,973.88 19,324.39 18,077.66 2,493.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.18 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 450 mm x 6.00 m hasta h = 7.50 m 17,674.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,674.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.05.03.19 SUMINISTRO e INSTALACION TUBERIA PVC U SN 8 Ø 355 mm x 6.00 m hasta h = 8.00 m 27,918.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,714.25 11,244.75 12,020.25 1,938.75 0.00 0.00 0.00 0.00 0.00 0.00
10.01.06 SUMINISTRO DE TUBERIA HDPE 17,751.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,751.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.06.01 SUMINISTRO DE TUBERIA HDPE, PE100 - PN 10, Ø200mm X 6.00m 1,669.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,669.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.06.02 SUMINISTRO DE TUBERIA HDPE, PE100 - PN 10, Ø250mm X 6.00m 2,695.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,695.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.06.03 SUMINISTRO DE TUBERIA HDPE, PE100 - PN 10, Ø315mm X 6.00m 3,861.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,861.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.06.04 SUMINISTRO DE TUBERIA HDPE, PE100 - PN 10, Ø400mm X 6.00m 6,440.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,440.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.06.05 SUMINISTRO DE TUBERIA HDPE, PE100 - PN 10, Ø450mm X 6.00m 3,084.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,084.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.07 PRUEBAS HIDRAULICAS 105,864.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,313.81 23,609.73 24,396.73 23,517.17 17,027.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.07.01 DOBLE PRUEBA HIDRAULICA p/TUBERIA PVC/HDPE Ø 200 mm 81,847.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,313.81 23,609.73 24,396.73 16,526.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.07.02 DOBLE PRUEBA HIDRAULICA p/TUBERIA PVC/HDPE Ø 250 mm 3,270.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,270.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.07.03 DOBLE PRUEBA HIDRAULICA p/TUBERIA PVC/HDPE Ø 315 mm 3,719.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,719.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.07.04 DOBLE PRUEBA HIDRAULICA p/TUBERIA PVC Ø 355 mm 9,027.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,027.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.07.05 DOBLE PRUEBA HIDRAULICA p/TUBERIA PVC/HDPE Ø 400 mm 3,493.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,493.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.07.06 DOBLE PRUEBA HIDRAULICA p/TUBERIA PVC/HDPE Ø 450 mm 4,505.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,505.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08 BUZONES y EMPALMES 1,711,346.75 0.00 100,672.83 204,874.26 37,154.25 103,169.71 316,591.17 147,267.24 92,570.88 205,984.84 236,855.15 109,132.34 140,465.24 16,608.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.01 BUZONES TIPO "A" 738,456.56 0.00 100,672.83 204,874.26 37,154.25 103,169.71 292,585.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.01.01 BUZON TIPO "A" Ø interior 1.20 m inc./TARRAJEO INTERIOR prof. = 1.50 m 271,211.10 0.00 100,672.83 170,538.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.01.02 BUZON TIPO "A" Ø interior 1.20 m inc./TARRAJEO INTERIOR prof. = 2.00 m 299,213.64 0.00 0.00 34,335.99 37,154.25 67,526.60 160,196.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.01.03 BUZON TIPO "A" Ø interior 1.20 m inc./TARRAJEO INTERIOR prof. = 2.50 m 168,031.82 0.00 0.00 0.00 0.00 35,643.11 132,388.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.02 BUZONES TIPO "B" 325,238.72 0.00 0.00 0.00 0.00 0.00 20,683.89 127,336.63 71,975.91 105,242.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.02.01 BUZON TIPO "B" Ø interior 1.20 m inc./TARRAJEO INTERIOR prof. = 3.00 m 128,240.12 0.00 0.00 0.00 0.00 0.00 20,683.89 107,556.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.02.02 BUZON TIPO "B" Ø interior 1.20 m inc./TARRAJEO INTERIOR prof. = 3.50 m 118,682.40 0.00 0.00 0.00 0.00 0.00 0.00 19,780.40 28,902.00 70,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.02.03 BUZON TIPO "B" Ø interior 1.20 m inc./TARRAJEO INTERIOR prof. = 4.00 m 78,316.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 43,073.91 35,242.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.03 BUZONES TIPO "C" 647,651.47 0.00 0.00 0.00 0.00 0.00 3,321.77 19,930.61 20,594.97 100,742.55 236,855.15 109,132.34 140,465.24 16,608.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.03.01 BUZON TIPO "C" Ø interior 1.50 m inc./TARRAJEO INTERIOR prof. = 4.50 m 98,638.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 49,319.47 49,319.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.03.02 BUZON TIPO "C" Ø interior 1.50 m inc./TARRAJEO INTERIOR prof. = 5.00 m 80,980.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31,492.47 49,488.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.03.03 BUZON TIPO "C" Ø interior 1.50 m inc./TARRAJEO INTERIOR prof. = 5.50 m 40,081.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 40,081.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.03.04 BUZON TIPO "C" Ø interior 1.50 m inc./TARRAJEO INTERIOR prof. = 6.00 m 42,972.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 42,972.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.03.05 BUZON TIPO "C" Ø interior 1.50 m inc./TARRAJEO INTERIOR prof. = 6.50 m 38,412.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 29,876.70 8,536.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.03.06 BUZON TIPO "C" Ø interior 1.50 m inc./TARRAJEO INTERIOR prof. = 7.00 m 140,159.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,521.27 37,078.12 98,560.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.03.07 BUZON TIPO "C" Ø interior 1.50 m inc./TARRAJEO INTERIOR prof. = 7.50 m 35,376.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35,376.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.03.08 BUZON TIPO "C" Ø interior 1.50 m inc./TARRAJEO INTERIOR prof. = 8.00 m 30,185.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,546.33 22,638.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.08.03.09 EMPALME BUZON y CONSTRUCCION DADO CONCRETO f'c = 175 Kg/cm² (0.55 x 0.55 x 0.55 m) 140,843.00 0.00 0.00 0.00 0.00 0.00 3,321.77 19,930.61 20,594.97 19,930.61 20,594.97 20,594.97 19,266.26 16,608.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.09 REPOSICION DE PAVIMENTOS 15,970.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,970.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01.09.01 REPOSICION PAVIMENTO FLEXIBLE EN CALIENTE e = 2" 15,970.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,970.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02 CONEXIONES DOMICILIARIAS DE ALCANTARILLADO 1,821,955.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 69,763.70 106,677.26 127,545.37 176,962.72 226,475.20 550,429.53 119,920.18 147,095.68 250,924.70 46,161.53 0.00 0.00 0.00
10.02.01 TRABAJOS PRELIMINARES 31,185.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31,185.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.01.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 18,258.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,258.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.01.02 REMOCION CAJA DOMICILIARIA CONCRETO 9,171.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,171.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.01.03 REMOCION CONEXION ALCANTARILLADO 473.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 473.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.01.04 DEMOLICION PAVIMENTO FLEXIBLE 185.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 185.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.01.05 DEMOLICION VEREDA CONCRETO (e = 0.10 m) 3,096.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,096.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.02 MOVIMIENTO DE TIERRAS 927,669.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38,578.06 44,899.83 52,720.36 82,137.71 133,135.66 240,697.83 43,247.97 145,172.24 143,730.64 3,349.42 0.00 0.00 0.00
10.02.02.01 EXCAVACION MANUAL p/TUBERIA Ø 160 mm; a = 0.60 m 293,534.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,915.98 29,195.69 30,835.55 30,835.54 47,555.83 129,195.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.02.02 REFINE y NIVELACION ZANJA p/TUBERIA Ø 160 mm 17,422.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,484.50 3,733.39 3,857.84 3,857.84 2,488.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.02.03 CAMA APOYO c/RIPIO CORRIENTE Ø 3/4"; a = 0.60 m 78,749.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38,707.48 40,042.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.02.04 RELLENO APISONADO Y COMPACT.LATERAL c/MAT. PRESTAMO P/CONEX. DOMICIL (RIPIO CORRIENTE) 69,829.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,177.58 11,970.75 12,369.78 12,369.76 11,571.73 12,369.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.02.05 RELLENO Y COMPACT. c/MAT. PRESTAMO S/CLAVE TUBO P/CONEX. DOM (ARENA FINA) 96,172.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,657.19 35,074.57 32,811.69 22,628.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.02.06 RELLENO Y COMPACT. c/MAT. PRESTAMO HASTA NIVEL DE SUB BASE CAP 0.20m (ARENA FINA) 1,863.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,863.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.02.07 RELLENO y COMPACTACION c/MATERIAL PROPIO SELECCIONADO CAPAS c/0.20 m; a = variable hasta nivel de terreno natural 165,783.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 34,598.39 43,247.97 44,689.57 43,247.97 0.00 0.00 0.00 0.00
10.02.02.08 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 204,314.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100,482.67 100,482.67 3,349.42 0.00 0.00 0.00
10.02.03 SUMINISTRO e INSTALACION DE TUBERIAS 280,990.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,451.48 18,071.28 18,071.29 14,324.75 218,071.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.03.01 SUMINISTRO e INSTALACION TUBERIA PVC U SN 2 Ø 160 mm 280,990.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,451.48 18,071.28 18,071.29 14,324.75 218,071.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.02.04 PRUEBAS HIDRAULICAS 38,468.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,212.92 14,906.69 14,425.83 1,923.44 0.00 0.00 0.00 0.00 0.00
10.02.04.01 DOBLE PRUEBA HIDRAULICA p/TUBERIA Ø 160 mm PVC 38,468.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,212.92 14,906.69 14,425.83 1,923.44 0.00 0.00 0.00 0.00 0.00
10.02.05 CAJAS y EMPALMES 393,635.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 49,325.95 56,753.73 76,753.72 71,801.87 76,753.73 62,246.38 0.00 0.00 0.00 0.00 0.00 0.00
10.02.05.01 SUMINISTRO e INSTALACION CAJA D/REGISTRO (dado 0.50 x 0.40 x 0.20 m; f'c = 140 Kg/cm²; mortero 1:3) INC SOLADO 201,520.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,403.66 20,304.05 40,304.05 37,703.79 40,304.05 46,500.65 0.00 0.00 0.00 0.00 0.00 0.00
10.02.05.02 EMPALME D/CONEXION DOMICILIARIA A TUB. PVC Ø 200 mm 188,127.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32,922.29 36,449.68 36,449.67 34,098.08 36,449.68 11,757.96 0.00 0.00 0.00 0.00 0.00 0.00
10.02.05.03 EMPALME D/CONEXION DOMICILIARIA A TUB. PVC Ø 250 mm 3,825.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,825.90 0.00 0.00 0.00 0.00 0.00 0.00
10.02.05.04 EMPALME D/CONEXION DOMICILIARIA A TUB. PVC Ø 315 mm 161.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 161.87 0.00 0.00 0.00 0.00 0.00 0.00
10.02.06 REPOSICION DE PAVIMENTOS 2,276.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,276.10 0.00 0.00 0.00
10.02.06.01 REPOSICION PAVIMENTO FLEXIBLE EN CALIENTE e = 2" 2,276.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,276.10 0.00 0.00 0.00
10.02.07 REPOSICION DE VEREDAS 4,804.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,804.66 0.00 0.00 0.00
10.02.07.01 REPOSICION VEREDA c/CONCRETO f' = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base de afirmado 4,804.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,804.66 0.00 0.00 0.00
10.02.08 CONSTRUCCION DE LOSA C/CONCRETO F'c=140 Kg/cm2 142,925.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 107,194.06 35,731.35 0.00 0.00 0.00
10.02.08.01 CONSTRUCCION LOSA CONCRETO e = 0.10 m; f'c = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base d 142,925.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 107,194.06 35,731.35 0.00 0.00 0.00
6 de 10
CALENDARIO DE AVANCE DE OBRA VALORIZADO ACTUALIZADO A LA FECHA DE INICIO DE OBRA
OBRA : INSTALACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DE LOS PP.JJ. VILLA PROGRESO, MIRAFLORES, LAS VEGAS, SAMAN, SAN FRANCISCO DE ASIS, LA UNION, SAN JUAN DE DIOS Y RAMIRO PRIALE II - CHICLAYO
ENTIDAD : ENTIDAD PRESTADORA DE SERVICIOS DE SANEAMIENTO DE LAMBAYEQUE S.A. - EPSEL S.A.
CONTRATISTA : CONSORCIO PROGRESO
SUPERVISION : CONSORCIO SUPERVISOR ASIS
UBICACIÓN : CHICLAYO - CHICLAYO - LAMBAYEQUE
Duración (Meses)
Item Descripción Parcial (S/.)
Mar-2019 Abr-2019 May-2019 Jun-2019 Jul-2019 Ago-2019 Sep-2019 Oct-2019 Nov-2019 Dic-2019 Ene-2020 Feb-2020 Mar-2020 Abr-2020 May-2020 Jun-2020 Jul-2020 Ago-2020 Sep-2020 Oct-2020
11 ESTACION DE BOMBEO DE AGUAS RESIDUALES I 1,125,878.49 0.00 0.00 0.00 23,872.30 119,258.90 204,285.83 186,284.50 207,506.78 110,231.14 95,921.03 38,576.32 20,871.72 34,073.64 71,903.68 12,159.32 933.33 0.00 0.00 0.00 0.00
11.01 CERCO PERIMETRICO, CASETA DE VIGILANCIA, SALA DE OPERACIONES Y SS.HH 160,800.94 0.00 0.00 0.00 9,439.60 1,429.17 0.00 0.00 998.90 30,182.13 22,858.29 24,147.74 20,871.72 24,319.95 26,553.44 0.00 0.00 0.00 0.00 0.00 0.00
11.01.01 TRABAJOS PRELIMINARES 10,868.77 0.00 0.00 0.00 9,439.60 1,429.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.01.01 CASETA p/GUARDIANIA y/o DEPOSITO 2,703.00 0.00 0.00 0.00 2,703.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.01.02 SEÑALIZACION DESVIO OBRA 545.96 0.00 0.00 0.00 545.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.01.03 MOVILIZACION y DESMOVILIZACION MAQUINARIAS, EQUIPOS y HERRAMIENTAS 5,579.36 0.00 0.00 0.00 5,579.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.01.04 LIMPIEZA TERRENO MANUAL 1,100.31 0.00 0.00 0.00 611.28 489.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.01.05 TRAZO ,NIVELACION Y REPLANTEO INICIAL 940.14 0.00 0.00 0.00 0.00 940.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.02 MOVIMIENTO DE TIERRAS 15,907.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 998.90 1,872.93 0.00 0.00 13,035.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.02.01 EXCAVACION TERRENO NORMAL HASTA 1.50 m p/CIMIENTO 2,871.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 998.90 1,872.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.02.02 RELLENO CON MATERIAL DE PRESTAMO 13,035.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,035.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.02.02.01 RELLENO C/MATERIAL DE PRESTAMO, PIEDRA CHANCADA DE 1/2" e=0.05m 829.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 829.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.02.02.02 RELLENO C/MATERIAL DE PRESTAMO AFIRMADO e=0.20m 2,577.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,577.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.02.02.03 RELLENO C/MATERIAL DE PRESTAMO, ARENA FINA e=0.17m 1,948.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,948.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.02.02.04 RELLENO C/MATERIAL DE PRESTAMO AFIRMADO e=0.10m 1,075.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,075.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.02.02.05 RELLENO C/MATERIAL DE PRESTAMO, ARENA FINA e=0.10m 1,338.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,338.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.02.02.06 RELLENO c/MATERIAL PROPIO SELECCIONADO 4,568.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,568.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.02.02.07 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 697.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 697.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03 ESTRUCTURAS 69,646.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28,309.20 21,691.81 13,066.15 6,579.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01 OBRAS DE CONCRETO SIMPLE 29,021.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,750.66 3,691.74 0.00 6,579.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01.01 SOLADOS 48.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01.01.01 SOLADO P/ZAPATA e = 0.10 m 48.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01.02 CIMIENTOS CORRIDOS 18,702.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,702.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01.02.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDDO 18,702.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,702.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01.03 SOBRECIMIENTO 3,691.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,691.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01.03.01 ENCOFRADO y DESENCOFRADO HASTA 0.40 m p/SOBRECIMIENTO 2,778.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,778.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01.03.02 CONCRETO C:H 1:8 + 25 % PM; f'c = 100 Kg/cm² p/SOBRECIMIENTO 912.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 912.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01.04 PISOS 1,040.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,040.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01.04.01 CONCRETO P/PISOS f'c = 140 Kg/cm2; a = 0.075 m 1,040.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,040.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01.05 VEREDAS 5,539.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,539.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01.05.01 ENCOFRADO y DESENCOFRADO p/VEREDA 599.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 599.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.01.05.02 CONCRETO f'c = 140 Kg/cm²; h = 0.10 m p/VEREDA 4,939.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,939.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02 OBRAS DE CONCRETO ARMADO 40,624.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,558.54 18,000.07 13,066.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.01 ZAPATAS 603.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 603.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.01.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 65.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 65.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.01.02 CONCRETO ZAPATAS f'c = 280 Kg/cm2 538.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 538.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.02 VIGAS DE CIMENTACION 14,979.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,954.67 6,025.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 6,867.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,867.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.02.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA CIMENTACION 5,217.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,086.99 3,130.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.02.03 CONCRETO f'c = 210 Kg/cm² p/VIGA CIMENTACION 2,894.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,894.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.03 COLUMNAS 11,974.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,974.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.03.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 4,013.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,013.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 4,765.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,765.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.03.03 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 3,196.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,196.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.04 VIGAS 6,958.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,958.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.04.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 3,542.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,542.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.04.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 2,196.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,196.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.04.03 CONCRETO f'c = 210 Kg/cm² p/VIGA 1,219.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,219.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.05 LOSAS ALIGERADAS 6,107.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,107.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.05.01 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA ALIGERADA 2,593.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,593.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.05.02 LADRILLO HUECO DE ARCILLA 15 x 30 x 30 cm p/LOSA ALIGERADA 1,225.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,225.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.05.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 729.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 729.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.03.02.05.04 CONCRETO f'c = 210 Kg/cm² p/LOSA ALIGERADA 1,558.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,558.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04 ARQUITECTURA 59,510.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,166.48 11,081.59 0.00 20,709.27 26,553.44 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.01 MUROS DE ALBAÑILERIA 12,248.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,166.48 11,081.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.01.01 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 12,248.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,166.48 11,081.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.02 REVOQUES, ENLUCIDOS y MOLDURAS 17,881.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,748.31 1,133.41 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO c/MORTERO C:A 1:5 202.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 202.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.02.02 TARRAJEO INTERIOR/EXTERIOR c/MORTERO C:A 1:5 11,334.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,200.73 1,133.41 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.02.03 TARRAJEO SUPERFICIE COLUMNA c/MORTERO C:A 1:5 3,143.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,143.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.02.04 TARRAJEO SUPERFICIE VIGA c/MORTERO C:A 1:5 2,443.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,443.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.02.05 VESTIDURA DERRAME 758.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 758.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.03 CIELORRASOS 2,945.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,945.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.03.01 CIELO RASO c/MORTERO C:A 1:5 2,945.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,945.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.04 PISOS y PAVIMENTOS 1,489.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 207.24 1,281.84 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.04.01 PISO CEMENTO PULIDO y BRUÑADO (0.50 x 0.50 m); e = 2" 1,281.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,281.84 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.04.02 PISO CERAMICA (20 x 20 cm) p/BAÑO 207.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 207.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.05 CONTRAZOCALO 808.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 808.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.05.01 CONTRAZOCALO CEMENTO s/COLOREAR h = 0.15 m 808.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 808.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.06 CARPINTERIA DE MADERA 328.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 328.25 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.06.01 PUERTA CONTRAPLACADA TRIPLAY (50 mm) 328.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 328.25 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.07 CARPINTERIA METALICA 15,032.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,032.70 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.07.01 VENTANA FIERRO (inc. pintura) 1,819.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,819.17 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.07.02 PUERTA METALICA (inc. pintura) 11,253.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,253.83 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.07.03 SUMINISTRO e INSTALACION DE ALAMBRADO DE PUAS 1,959.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,959.70 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.08 PINTURA 8,666.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,666.50 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.08.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 2,300.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,300.24 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.08.02 PINTURA EN COLUMNAS 588.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 588.11 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.08.03 PINTURA EN VIGAS 391.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 391.69 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.08.04 PINTURA LATEX CIELO RASO 02 MANOS inc./IMPRIMANTE 877.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 877.01 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.08.05 PINTURA CON BARNIZ EN CERCO PERIMETRICO INTERIOR Y EXTERIOR 4,057.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,057.20 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.08.06 PINTURA ESMALTE CONTRAZOCALO h=15 cm 452.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 452.25 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.09 VIDRIOS, CRISTALES y SIMILARES 110.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 110.74 0.00 0.00 0.00 0.00 0.00 0.00
11.01.04.09.01 VIDRIO NACIONAL DOBLE 110.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 110.74 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05 INSTALACIONES SANITARIAS 4,867.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,257.01 3,610.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.01 SISTEMA DE AGUA FRIA 1,432.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,257.01 175.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.01.01 SALIDA AGUA FRIA c/TUBERIA PVC SAP 1/2" 254.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 254.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.01.02 RED DISTRIBUCION p/TUBERIA PVC SAP 1/2" 322.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 322.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.01.03 CODO PVC SAP 1/2" x 90° 351.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 175.89 175.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.01.04 CODO F°G° 1/2" x 90° 66.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 66.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.01.05 TEE PVC SAP 1/2" x 90° 65.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 65.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.01.06 VALVULA COMPUERTA BRONCE 1/2" 164.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 164.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.01.07 UNION UNIVERSAL PVC SAP 1/2" 207.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 207.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.02 SISTEMA DE DESAGUE 2,306.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,306.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.02.01 SALIDA DESAGUE PVC 4" 305.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 305.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.02.02 TUBERIA PVC SAL 2" 344.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 344.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.02.03 TUBERIA PVC SAL 4" 580.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 580.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.02.04 CODO PVC SAL 2" x 45° 156.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 156.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.02.05 CODO PVC SAL 2" x 90° 94.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 94.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.02.06 CODO PVC SAL 4" x 90° 77.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 77.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.02.07 TEE PVC SAL 4" x 4" 77.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 77.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.02.08 REDUCCION PVC SAL 4" x 2" 96.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 96.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.02.09 REGISTRO BRONCE 2" 87.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 87.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.02.10 CAJA REGISTRO DESAGUE 12" x 24" 487.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 487.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.03 APARATOS SANITARIOS y ACCESORIOS 1,128.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,128.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.03.01 INODORO TANQUE BAJO BLANCO 205.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 205.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.03.02 LAVATORIO FONTANA COLOR BLANCO 396.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 396.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.03.03 DUCHA CROMADA 01 LLAVE inc./ACCESORIOS 90.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 90.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.03.04 GRIFO CROMADO 317.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 317.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.05.03.05 JABONERA LOSA BLANCO 118.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 118.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02 CAMARA HUMEDA, DE REJAS y DE VALVULAS 260,893.55 0.00 0.00 0.00 0.00 25,751.18 48,706.97 54,599.29 46,561.10 45,582.58 39,393.58 0.00 0.00 0.00 298.85 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01 CAMARA HUMEDA 123,878.65 0.00 0.00 0.00 0.00 25,751.18 48,706.97 41,165.45 0.00 0.00 8,255.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.01 MOVIMIENTO DE TIERRAS 57,153.48 0.00 0.00 0.00 0.00 25,751.18 23,147.25 0.00 0.00 0.00 8,255.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.01.01 EXCAVACION MASIVA 18,814.64 0.00 0.00 0.00 0.00 12,873.17 5,941.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.01.02 DRENAJE 24,957.00 0.00 0.00 0.00 0.00 12,478.50 12,478.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.01.03 ENTIBADO CON PUNTALES DE 6"x4" h=10.60m 1,167.81 0.00 0.00 0.00 0.00 399.51 768.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.01.04 RELLENO y APISONADO c/MATERIAL PROPIO CAPAS c/0.20 m 8,255.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,255.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.01.05 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 3,958.98 0.00 0.00 0.00 0.00 0.00 3,958.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.02 ESTRUCTURAS 62,074.47 0.00 0.00 0.00 0.00 0.00 25,559.72 36,514.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.02.01 OBRAS DE CONCRETO SIMPLE 412.54 0.00 0.00 0.00 0.00 0.00 412.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.02.01.01 SOLADO e = 0.10 m p/ESTRUCTURA 412.54 0.00 0.00 0.00 0.00 0.00 412.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.02.02 OBRAS DE CONCRETO ARMADO 61,661.93 0.00 0.00 0.00 0.00 0.00 25,147.18 36,514.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.02.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 20,379.47 0.00 0.00 0.00 0.00 0.00 15,747.77 4,631.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.02.02.02 ENCOFRADO y DESENCOFRADO NORMAL P/CAMARA HUMEDA 14,928.47 0.00 0.00 0.00 0.00 0.00 9,399.41 5,529.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.02.02.03 CONCRETO f'c = 280 Kg/cm² P/CAMARA HUMEDA 26,353.99 0.00 0.00 0.00 0.00 0.00 0.00 26,353.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.03 ARQUITECTURA 4,650.70 0.00 0.00 0.00 0.00 0.00 0.00 4,650.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.03.01 REVOQUES ENLUCIDOS Y MOLDURAS 4,650.70 0.00 0.00 0.00 0.00 0.00 0.00 4,650.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01.03.01.01 TARRAJEO C/IMPERMEABILIZANTES P/PARED INTERIOR 4,650.70 0.00 0.00 0.00 0.00 0.00 0.00 4,650.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02 CAMARA DE REJAS 110,133.45 0.00 0.00 0.00 0.00 0.00 0.00 13,433.84 46,561.10 31,118.25 18,721.41 0.00 0.00 0.00 298.85 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.01 MOVIMIENTO DE TIERRAS 43,174.53 0.00 0.00 0.00 0.00 0.00 0.00 13,433.84 21,368.12 0.00 8,372.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.01.01 EXCAVACION MASIVA 14,089.18 0.00 0.00 0.00 0.00 0.00 0.00 8,050.96 6,038.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.01.02 DRENAJE DE ZANJAS 16,638.00 0.00 0.00 0.00 0.00 0.00 0.00 5,382.88 11,255.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.01.03 ENTIBADO CON PUNTALES DE 6"x4" h=10.60m 1,626.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,626.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.01.04 RELLENO y APISONADO c/MATERIAL PROPIO CAPAS c/0.20 m 8,229.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,229.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.01.05 RELLENO p/FILTRO c/PIEDRA 1" e = 1.20 m 143.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 143.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.01.06 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 2,448.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,448.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.02 ESTRUCTURAS 49,487.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,192.98 24,294.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.02.01 OBRAS DE CONCRETO SIMPLE 289.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 289.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.02.01.01 SOLADO e = 0.10 m p/ESTRUCTURA 289.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 289.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.02.02 OBRAS DE CONCRETO ARMADO 49,198.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24,903.91 24,294.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.02.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 15,727.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,727.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.02.02.02 ENCOFRADO y DESENCOFRADO NORMAL P/CAMARA REJAS 15,114.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,176.49 5,937.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.02.02.03 CONCRETO f'c = 280 Kg/cm² P/CAMARA REJAS 18,356.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,356.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.03 ARQUITECTURA 17,471.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,823.63 10,348.84 0.00 0.00 0.00 298.85 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.03.01 MUROS Y TABIQUES DE ALBAÑILERIA 2,285.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,285.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.03.01.01 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 2,285.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,285.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.03.02 REVOQUES ENLUCIDOS Y MOLDURAS 11,559.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,537.78 7,021.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.03.02.01 TARRAJEO EXTERIOR c/MORTERO C:A 1:5 1,472.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,472.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.03.02.02 TARRAJEO SUPERFICIE TECHO CAMARA DE REJAS c/MORTERO C:A 1:5 378.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 378.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.03.02.03 TARRAJEO C/IMPERMEABILIZANTES P/PARED INTERIOR 9,478.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,457.49 7,021.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.03.02.04 VESTIDURA DERRAME 229.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 229.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.03.03 CARPINTERIA METALICA 3,327.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,327.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.03.03.01 PUERTA METALICA (inc. pintura) 3,327.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,327.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.03.04 PINTURA 298.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 298.85 0.00 0.00 0.00 0.00 0.00 0.00
11.02.02.03.04.01 PINTURA LATEX EXTERIOR 02 MANOS inc./IMPRIMANTE 298.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 298.85 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03 CAMARA DE VALVULAS 26,881.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,464.33 12,417.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.01 MOVIMIENTO DE TIERRAS 10,365.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,114.78 2,250.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.01.01 EXCAVACION MASIVA 4,312.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,312.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.01.02 DRENAJE 1,663.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,663.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.01.03 ENTIBADO CON PUNTALES DE 6"x4" h=3.80m 1,321.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,321.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.01.04 RELLENO y APISONADO c/MATERIAL PROPIO CAPAS c/0.20 m 2,250.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,250.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.01.05 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 817.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 817.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.02 ESTRUCTURAS 14,930.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,349.55 8,580.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.02.01 OBRAS DE CONCRETO SIMPLE 414.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 414.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.02.01.01 SOLADO e = 0.10 m p/ESTRUCTURA 414.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 414.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.02.02 OBRAS DE CONCRETO ARMADO 14,516.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,935.32 8,580.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.02.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 2,908.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,908.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.02.02.02 ENCOFRADO y DESENCOFRADO NORMAL P/CAMARA VALVULAS 5,044.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,026.83 2,017.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.02.02.03 CONCRETO f'c = 280 Kg/cm² P/CAMARA VALVULAS 6,482.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,482.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.02.02.04 DADO CONCRETO f'c = 280 Kg/cm² (0.30 x 0.40 x 0.50 m) 80.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 80.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.03 ARQUITECTURA 1,585.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,585.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.03.01 REVOQUES ENLUCIDOS Y MOLDURAS 1,585.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,585.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.03.03.01.01 TARRAJEO C/IMPERMEABILIZANTES P/PARED INTERIOR 1,585.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,585.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03 INSTALACIONES ELECTROMECANICAS DE LA EBAR I 571,408.88 0.00 0.00 0.00 14,432.70 92,078.55 155,578.86 104,859.61 53,997.26 34,466.43 33,669.16 14,428.58 0.00 9,753.69 45,051.39 12,159.32 933.33 0.00 0.00 0.00 0.00
11.03.01 SUMINISTRO Y MONTAJE DE EQUIPAMIENTO ELECTROMECANICO DE LA CAMARA HUMEDA DE BOMBEO 258,716.31 0.00 0.00 0.00 14,432.70 92,078.55 63,916.23 68,206.93 20,081.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.01 SUMINISTRO Y MONTAJE DE EQUIPOS DE ELECTROBOMBAS SUMERGIBLES E INMERSIBLES 213,725.58 0.00 0.00 0.00 14,432.70 92,078.55 63,916.23 43,298.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.01.01 SUMINISTRO ELECTROBOMBAS PARA AGUAS SERVIDAS DE 35.2 LPS, 36.9 m ADT, 20.4 KW 440/380/220V, 3F 60 Hz, 1755 rpm y185,563.26
22 m de cable. 0.00 0.00 0.00 14,432.70 63,916.23 63,916.23 43,298.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.01.02 SUMINISTRO E INSTALACION DE VALVULAS DE LIMPIEZA ACOPLADA A BASE DE ELECTROBOMBA 22,751.07 0.00 0.00 0.00 0.00 22,751.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.01.03 SUMINISTRO E INSTALACION DE CODO ESTACIONARIO DE DESCARGA 1,041.42 0.00 0.00 0.00 0.00 1,041.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.01.04 DADO DE CONCRETO 280Kg/cm2 y ANCLAJE AL PATACODO REFORZADO CON F°C DE 4"x2" 78.44 0.00 0.00 0.00 0.00 78.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.01.05 SUMINISTRO E INSTALACION SENSOR PARA MEDIR Y CONTROLAR NIVELES DE AGUA RESIDUALES MODELO LTU 601 4,023.69 0.00 0.00 0.00 0.00 4,023.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.01.06 TUBO DE PVC SAP 3" Y SOPORTE DE FIJACION DE TUBO Y PLATINAS DE ACERO INOXIDABLE 267.70 0.00 0.00 0.00 0.00 267.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.02 SUMINISTRO Y MONTAJE DE GUIAS PARA IZADO RAPIDO DE ELECTROBOMBAS 12,632.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,632.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.02.01 TUBO GUIA DE ACERO INOXIDABLE DE 2" AISI 316 ,SCH10S 4,346.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,346.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.02.02 SOPORTE SUPERIOR DE LOS TUBOS GUIAS 6,536.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,536.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.02.03 CADENA CORTA MAS OJAL DE ENGANCHE 1,749.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,749.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.03 SUMINISTRO Y MONTAJE DE SOPORTE TIPO BANDERA Y TECLE DE 1 TN 8,665.18 0.00 0.00 0.00 0.00 0.00 0.00 1,215.92 7,449.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.03.01 SOPORTE PORTATIL Y GIRATORIO TIPO BANDERA DE FIERRO NEGRO ELECTROSOLDABLE 1,215.92 0.00 0.00 0.00 0.00 0.00 0.00 1,215.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.03.02 TECLE YALE ELECTRICO 1 TN DE CADENA LARGA (12m) 7,449.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,449.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.04 SUMINISTRO Y MONTAJE DE COLUMNA DE IMPULSION 22,563.36 0.00 0.00 0.00 0.00 0.00 0.00 22,563.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.04.01 NIPLES DE TUBO DE ACERO NEGRO ELECTROSOLDABLE 10" SCH40 ASTM A53 GRADO B 8,926.11 0.00 0.00 0.00 0.00 0.00 0.00 8,926.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.04.02 ACCESORIOS DE LA COLUMNA DE IMPULSION Y OTROS 13,637.25 0.00 0.00 0.00 0.00 0.00 0.00 13,637.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.05 SUMINISTRO Y MONTAJE DE MARCOS Y REJILLAS DE FIBRA DE VIDRIO 1,129.55 0.00 0.00 0.00 0.00 0.00 0.00 1,129.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.05.01 MARCO DE PLATINAS Y ANGULOS DE ACERO INOXIDABLE DE 1Mx 0.8M 585.84 0.00 0.00 0.00 0.00 0.00 0.00 585.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.01.05.02 REJILLAS DE FIBRA DE VIDRIO DE 1M x 0.8M (4 piezas) 543.71 0.00 0.00 0.00 0.00 0.00 0.00 543.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02 SUMINISTRO Y MONTAJE DE EQUIPAMIENTO ELECTROMECANICO DE LA CAMARA DEL ARBOL DE IMPULSION 108,340.42 0.00 0.00 0.00 0.00 0.00 91,662.63 16,677.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.01 SUMINISTRO Y MONTAJE DE EQUIPOS DE ELECTROBOMBAS SUMERGIBLES E INMERSIBLES 76,793.27 0.00 0.00 0.00 0.00 0.00 75,653.39 1,139.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.01.01 ELECTROBOMBAS PARA AGUAS SERVIDAS DE 10 LPS 4m ADT, 440/220 V, 3F, 60 Hz, 1800 rpm 75,368.42 0.00 0.00 0.00 0.00 0.00 75,368.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.01.02 MANGUERA DE JEBE Y LONA DE 3" Y ACCESORIO DE INSTALACION 1,424.85 0.00 0.00 0.00 0.00 0.00 284.97 1,139.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.02 SUMINISTRO Y MONTAJE DE ACCESORIOS DEL ARBOL DE IMPULSION DE 10" 19,342.62 0.00 0.00 0.00 0.00 0.00 8,612.22 10,730.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.02.01 NIPLES DE TUBO DE 10" x 1 ELECTROSOLDABLE 9,934.56 0.00 0.00 0.00 0.00 0.00 2,483.64 7,450.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.02.02 VALVULA DE RETENCION DE 10" DE ASIENTO RECTO CON EJE INTERNO BRIDADA - CHECK 2,111.64 0.00 0.00 0.00 0.00 0.00 2,111.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.02.03 VALVULA DE COMPUERTA BRIDADA DE AGUAS RESIDUALES DE 10" PN10 4,016.94 0.00 0.00 0.00 0.00 0.00 4,016.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.02.04 UNION DRESSES DE 10" 881.64 0.00 0.00 0.00 0.00 0.00 0.00 881.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.02.05 REDUCCION ELECTROSOLDABLES DE 12" A 10" 2,397.84 0.00 0.00 0.00 0.00 0.00 0.00 2,397.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.03 SUMINISTRO Y MONTAJE DE ACCESORIOS DEL ARBOL DE IMPULSION DE 14" 9,461.14 0.00 0.00 0.00 0.00 0.00 7,397.02 2,064.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.03.01 NIPLES DE TUBO DE 14" x 1 ELECTROSOLDABLE 4,128.24 0.00 0.00 0.00 0.00 0.00 2,064.12 2,064.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.03.02 NIPLES DE TUBO DE 14" x 1 ELECTROSOLDABLE CON BRIDA CIEGA 708.08 0.00 0.00 0.00 0.00 0.00 708.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.03.03 NIPLES DE TUBO DE 350mm x 1M ELECTROSOLDABLE 695.62 0.00 0.00 0.00 0.00 0.00 695.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.03.04 YEE DE ACERO AL CARBONO SCH40 CON REDUCCION DE 14" a 12" 2,153.04 0.00 0.00 0.00 0.00 0.00 2,153.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.03.05 CODOS ACERO AL CARBONO SCH40 45° DE 14" 1,776.16 0.00 0.00 0.00 0.00 0.00 1,776.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.04 SUMINISTRO Y MONTAJE DE MARCOS Y REJILLAS DE FIBRA DE VIDRIO 1,935.37 0.00 0.00 0.00 0.00 0.00 0.00 1,935.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.04.01 REJILLAS DE FIBRA DE VIDRIO DE 1.90M x 0.4M (5 piezas) CON MARCOS DE ANGULO DE F° 1,657.71 0.00 0.00 0.00 0.00 0.00 0.00 1,657.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.04.02 MARCO DE PLATINAS Y ANGULOS DE ACERO INOXIDABLE DE 1Mx 0.8M 277.66 0.00 0.00 0.00 0.00 0.00 0.00 277.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.05 SUMINISTRO DE ESCALERA DE GATO 808.02 0.00 0.00 0.00 0.00 0.00 0.00 808.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.02.05.01 ESCALERA METALICA DE TUBO DE F°G° DE 1" 808.02 0.00 0.00 0.00 0.00 0.00 0.00 808.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03 SUMINISTRO Y MONTAJE DE EQUIPAMIENTO ELECTROMECANICO DE LA CAMARA DE REJAS 35,133.63 0.00 0.00 0.00 0.00 0.00 0.00 19,974.89 15,158.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.01 SUMINISTRO Y MONTAJE DE ELECTROBOMBAS SUMERGIBLES E INMERSBLES EN LODOS 20,314.01 0.00 0.00 0.00 0.00 0.00 0.00 19,974.89 339.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.01.01 SUMINISTRO E INSTALACION DE ELECTROBOMBA SUMERGIBLE E INMERSIBLE PARA LODOS 45 lps; ADT = 10 m 440v 60 hZ 1755 18,618.42
RPM, 10 HP 0.00 0.00 0.00 0.00 0.00 0.00 18,618.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.01.02 MANGUERA DE JEBE Y LONA DE 4" Y ACCESORIO DE INSTALACION 1,695.59 0.00 0.00 0.00 0.00 0.00 0.00 1,356.47 339.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.02 SUMINISTRO Y MONTAJE DE SOPORTE WINCHE ELECTRICO DE 0.5 TN 5,539.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,539.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.02.01 SOPORTE TIPO RIEL DE FIERRO NEGRO TIPO H DE 6" x 4" 1,643.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,643.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.02.02 WINCHE ELECTRICO 0.50 TN DE CADENA LARGA (10m) 3,896.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,896.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.03 SUMINISTRO Y MONTAJE DE VALVULA COMPUERTA BRIDADA DE 350mm PN10 Y ACCESORIOS 5,444.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,444.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.03.01 VALVULA DE COMPUERTA BRIDADA DE AGUAS RESIDUALES DE 350mm PN10 1,790.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,790.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.03.02 EXTENSION DE EJE INOXIDABLE 416 PARA VOLANTE DE VALVULA Y ACOPLADA A 2 CHUMACERAS 3,050.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,050.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.03.03 NIPLES DE TUBO DE ACERO NEGRO ELECTROSOLDABLE DE 350mm SCH40, GRADO B 603.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 603.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.04 SUMINISTRO Y MONTAJE DE MARCOS Y REJILLAS DE FIBRA DE VIDRIO 3,835.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,835.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.04.01 MARCO DE PLATINAS Y ANGULOS DE ACERO INOXIDABLE DE 416 DE 0.95x0.71 1,049.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,049.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.04.02 REJILLA DE FIBRA DE VIDRIO DE 0.95x0.71m SOPORTE 150Kg E=MAYOR 1 1/4" (5 PZAS) 687.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 687.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.04.03 MARCO DE PLATINAS Y ANGULOS DE ACERO INOXIDABLE DE 416 DE 0.95x095 219.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 219.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.04.04 REJILLA DE FIBRA DE VIDRIO DE 0.95x0.95m SOPORTE 150Kg E=MAYOR 1 1/4" 199.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 199.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.04.05 MARCO DE PLATINAS Y ANGULOS DE ACERO INOXIDABLE 416 DE LA REJILLA DE RETENCION DE SOLIDOS 1,499.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,499.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.03.04.06 REJILLA DE FIBRA DE VIDRIO SOPORTE 150Kg E=MAYOR 1 1/4" 180.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 180.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.04 SUMINISTRO Y MONTAJE DE EQUIPAMIENTO ELECTROMECANICO DE LA CASETA DE MANDO, CONTROL Y DEL GRUPO GENERADOR 98,435.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,756.62 34,466.43 33,669.16 11,543.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.04.01 SUMINISTRO Y MONTAJE DE EQUIPAMIENTO ELECTROMECANICO DE LA CASETA DEL GRUPO GENERADOR 24,228.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,388.83 9,730.87 8,109.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.04.01.01 TABLERO DE TRANSFERENCIA Y DE ENCENDIDO AUTOMATICO DE UN GENERADOR DE 75Kw 440V 22,850.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,093.58 9,140.37 7,616.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.04.01.02 GRUPO GENERADOR DE 75 Kw TRIFASICO EN 440/380/220 V EQUIPADO CON MODULO DE CONTROL DIGITAL ELECTRONICO 1,377.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 295.25 590.50 492.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.04.02 SUMINISTRO Y MONTAJE DE EQUIPAMIENTO ELECTROMECANICO DE LA CASETA DE MANDO Y CONTROL DE ELECTROBOMBAS 74,206.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,367.79 24,735.56 25,560.09 11,543.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.04.02.01 TABLERO ELECTRICO DE 3 ELECTROBOMBAS DE LA CAMARA HUMEDA 62,204.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,367.46 20,734.91 21,426.08 9,676.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.04.02.02 TABLERO ELECTRICO DE ELECTROBOMBA DE LA CAMARA DE REJAS Y DE CAMARA DE VALVULAS 12,001.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,000.33 4,000.65 4,134.01 1,866.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05 SUMINISTRO Y MONTAJE DE INSTALACIONES ELECTRICAS EN LA ESTACION DE LA CAMARA DE BOMBEO 19,856.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,885.32 0.00 9,753.69 7,217.50 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01 SUMINISTRO Y MONTAJE DE CONEXIONES ELECTRICAS SUBTERRANEAS 2,885.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,885.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.01 EXCAVACION DE ZANJAS 453.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 453.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.02 ACARREO Y ELIMINACION DE MATERIAL EXCEDENTE Dist. min = 5.0Km 130.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 130.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.03 CAMA DE APOYO C/ARENA FINA 151.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 151.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.04 DUCTO DE CONCRETO ARMADO DE 4 VIAS 380.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 380.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.05 CANALETAS DE CONCRETO ARMADO 234.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 234.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.06 REJILLA DE FIBRA DE VIDRIO SOPORTE 150Kg E=MAYOR 1 1/4" 602.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 602.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.07 TUBERIA DE PVC SAP 4" x 6M 100.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.08 CODO DE PVC SAP DE 4" 66.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 66.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.09 TEE DE PVC SAP DE 4" 75.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 75.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.10 ABRAZADERA SOPORTE 4" ADOSADA A MURO DE CONCRETO 422.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 422.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.11 CAJAS DE PASE DE CONCRETO ARMADO 245KG/CM2 DE 0.55x0.55x0.65m 72.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 72.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.12 RELLENO LATERAL C/ARENA FINA 31.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.13 RELLENO SUPERIOR C/ARENA FINA 69.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 69.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.01.14 RELLENO CON MATERIAL PROPIO 94.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 94.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.02 SUMINISTRO Y MONTAJE DE INSTALACIONES ELECTRICAS DE INTERIORES 7,349.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,349.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.02.01 SALIDA p/CENTRO LUZ DE CASETAS 708.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 708.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.02.02 LAMPARAS Y LUMINARIAS AHORRADORAS 185.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 185.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.02.03 SALIDA p/TOMACORRIENTE BIPOLAR DOBLE c/PUESTA A TIERRA 648.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 648.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.02.04 SALIDA p/INTERRUPTOR BIPOLAR DOBLE 423.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 423.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.02.05 SALIDA p/INTERRUPTOR SIMPLE 215.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 215.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.02.06 TABLERO PRINCIPAL METALICO 3 CIRCUITOS/TERMOM CON DIFERENCIAL 3,413.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,413.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.02.07 POZO A TIERRA 1,754.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,754.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.03 SUMINISTRO Y MONTAJE DEL SISTEMA DE ILUMINACION PERIMETRICO 9,621.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,404.42 7,217.50 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.03.01 SALIDA p/CENTROS DE LUZ 2,258.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,505.84 752.92 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.03.02 LUMINARIA TIPO FAROLA Y LAMPARA DE ALURO METALICO DE 70 WATTS 2,927.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,927.20 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.03.03 LUMINARIA TIPO FAROLA Y LAMPARA DE ALURO METALICO DE 100 WATTS 3,537.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,537.38 0.00 0.00 0.00 0.00 0.00 0.00
11.03.05.03.04 SALIDA p/INTERRUPTOR BIPOLAR CON INTERRUPTOR TERMOMAGNETICO 898.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 898.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03.06 SUMINISTRO Y MONTAJE DEL SISTEMA DE AUTOMATIZACION Y DE TELEMETRIA DE LA EBAR 1 50,926.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37,833.89 12,159.32 933.33 0.00 0.00 0.00 0.00
11.03.06.01 SUMINISTRO E INSTALACION DEL EQUIPO DE MONITOREO Y CONTROL TELEMETRIA EBAR 1 13,463.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,463.27 0.00 0.00 0.00 0.00 0.00 0.00
11.03.06.02 EQUIPAMIENTO DE COMPUTO EN EL CENTRO CONTROL CON SCADA (Licencia Aquaview7 Run time+HardKey, New Customer, 1 Web 30,463.27
Client, Computadora0.00
Workstation para 0.00
sistema SCADA, Monitor
0.00 Samsung MD46C,
0.00 46" LED, 0.00
1920X1080 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24,370.62 6,092.65 0.00 0.00 0.00 0.00 0.00
11.03.06.03 SERVICIO DE CAPACITACION CONFIGURACION Y ATENCION REMOTA DEL SISTEMA DE TELEMETRIA A TRAVES DEL SCADA AL7,000.00 PERSONAL TECNICO 0.00Y OPERATIVO DE 0.00
EPSEL S.A 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,066.67 933.33 0.00 0.00 0.00 0.00
11.04 SUMINISTRO DE UTILIZACION EN MEDIA TENSION 10.0 KV - 3 Ø DE LA EBAR 1 132,775.12 0.00 0.00 0.00 0.00 0.00 0.00 26,825.60 105,949.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01 SUMINISTRO Y MONTAJE ELECTRICO DE LA RED PRIMARIA 132,775.12 0.00 0.00 0.00 0.00 0.00 0.00 26,825.60 105,949.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.01 OBRAS PRELIMINARES Y EXPEDIENTE FINAL 14,058.25 0.00 0.00 0.00 0.00 0.00 0.00 3,610.36 10,447.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.01.01 LIMPIEZA DE TERRENOS MANUAL EN TRAZO DE RED EN MT 528.00 0.00 0.00 0.00 0.00 0.00 0.00 528.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.01.02 LIMPIEZA DE TERRENOS MANUAL EN UBICACION DE POSTES DE C.A.C, A INSTALAR 93.72 0.00 0.00 0.00 0.00 0.00 0.00 93.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.01.03 REPLANTEO TOPOGRAFICO y UBICACION ESTRUCTURA DE LA RP 508.50 0.00 0.00 0.00 0.00 0.00 0.00 508.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.01.04 TRANSPORTE DE PERSONAL TECNICO EN EJECUCION DE OBRA 7,027.20 0.00 0.00 0.00 0.00 0.00 0.00 1,833.18 5,194.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.01.05 PROTECCION Y SEGURIDAD A LOS TRABAJADORES DE OBRA 2,480.00 0.00 0.00 0.00 0.00 0.00 0.00 646.96 1,833.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.01.06 PRUEBAS ELECTRICAS Y CONFORMIDAD DE INSTALACIONES EN MT EN VACIO 620.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 620.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.01.07 EXPEDIENTES TECNICOS FINAL CONFORME A OBRA ( 1 ORIGINAL + 3COPIAS) DE LA RP, INCLUYE CD DE INFORMACION 2,800.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,800.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.02 POSTES y ACCESORIOS DE CONCRETO ARMADO 23,215.24 0.00 0.00 0.00 0.00 0.00 0.00 23,215.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.02.01 POSTE CONCRETO ARMADO CENTRIFUGADO 13m/400Kg/180/375 mm 15,239.94 0.00 0.00 0.00 0.00 0.00 0.00 15,239.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.02.02 MEDIA LOZA DE C.A.V M/1.10/750 1,553.30 0.00 0.00 0.00 0.00 0.00 0.00 1,553.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.02.03 MEDIA LOZA DE C.A.V M/1.30/750 616.65 0.00 0.00 0.00 0.00 0.00 0.00 616.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.02.04 PALOMILLA SIMPLE C.A M/1.10/100 621.08 0.00 0.00 0.00 0.00 0.00 0.00 621.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.02.05 PALOMILLA SIMPLE C.A M/1.50/100 330.54 0.00 0.00 0.00 0.00 0.00 0.00 330.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.02.06 MENSULA DE C.A V M/1.00/250 4,671.36 0.00 0.00 0.00 0.00 0.00 0.00 4,671.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.02.07 CRUCETA DE MADERA 90 x 120 mm x 1.00 m 182.37 0.00 0.00 0.00 0.00 0.00 0.00 182.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 de 10
CALENDARIO DE AVANCE DE OBRA VALORIZADO ACTUALIZADO A LA FECHA DE INICIO DE OBRA
OBRA : INSTALACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DE LOS PP.JJ. VILLA PROGRESO, MIRAFLORES, LAS VEGAS, SAMAN, SAN FRANCISCO DE ASIS, LA UNION, SAN JUAN DE DIOS Y RAMIRO PRIALE II - CHICLAYO
ENTIDAD : ENTIDAD PRESTADORA DE SERVICIOS DE SANEAMIENTO DE LAMBAYEQUE S.A. - EPSEL S.A.
CONTRATISTA : CONSORCIO PROGRESO
SUPERVISION : CONSORCIO SUPERVISOR ASIS
UBICACIÓN : CHICLAYO - CHICLAYO - LAMBAYEQUE
Duración (Meses)
Item Descripción Parcial (S/.)
Mar-2019 Abr-2019 May-2019 Jun-2019 Jul-2019 Ago-2019 Sep-2019 Oct-2019 Nov-2019 Dic-2019 Ene-2020 Feb-2020 Mar-2020 Abr-2020 May-2020 Jun-2020 Jul-2020 Ago-2020 Sep-2020 Oct-2020
11.04.01.03 AISLADORES POLIMERICOS Y ACCESORIOS 8,314.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,314.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.03.01 AISLADOR DE POLIMERICO TIPO PIN 24 KV; LF 744m , DE 0-1000 msnm 4,449.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,449.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.03.02 AISLADOR POLIMERICO 24 KV; TIPO SUSPENSION DE LF 744mm 3,864.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,864.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.04 CONDUCTORES DE ENERGIA ELECTRICA 14,861.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,861.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.04.01 CONDUCTOR DE ALEACION DE ALUMINIO AAAC 50 mm² 2,600.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,600.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.04.02 CONDUCTOR DE COBRE DESNUDO T BLANDO 35 mm2 2,454.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,454.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.04.03 CONDUCTOR DE COBRE DESNUDO T D DE 50 mm2 996.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 996.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.04.04 CABLE ELECTRICO NS2X 1,0KV DE 3x16mm2 1,592.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,592.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.04.05 CABLE ELECTRICO NS2X 1,0KV DE 3x50mm2 4,300.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,300.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.04.06 FERRETERIA ELECTRICA PARA POSTES, CRUCETAS, MENSULAS, CONDUCTORES Y EQUIPOS 2,917.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,917.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.05 PUESTA A TIERRA EN MEDIA Y BAJA TENSION 7,660.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,660.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.05.01 PUESTA A TIERRA EN ESTRUCTURAS DE LINEAS DE TRANSMISION 10-25 OHMS 1,871.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,871.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.05.02 PUESTA A TIERRA EN ESTRUCTURAS DE SAM Y SAB 10 HMS 3,835.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,835.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.05.03 PUESTA A TIERRA EN TABLEROS CON EQUIPOS ELECTRONICOS 5 OHMS 940.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 940.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.05.04 MEGHADO Y PROTOCOLO DE PUESTAS A TIERRA 1,012.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,012.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.06 RETENIDAS Y ANCLAJES EN MEDIA TENSION 3,007.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,007.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.06.01 RETENIDA SIMPLE EN MEDIA TENSION 1,136.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,136.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.06.02 RETENIDA CON CONTRAPUNTA EN MEDIA TENSION 1,870.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,870.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.07 ARMADOS CON EQUIPOS DE POTENCIA Y ACCESORIOS 61,658.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 61,658.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.07.01 ARMADO DE PUNTO DE DERIVACION 3,662.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,662.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.07.02 ARMADO DE SECCIONAMIENTO , TIPO PSEC 2,980.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,980.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.07.03 ARMADO DE SECCIONAMIENTO , TIPO PMI 11,831.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,831.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.07.04 ARMADO DE SISTEMA DE MEDICION TIPO TFX Y ACCESORIOS 17,017.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,017.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.07.05 ARMADO VERTICAL DE ANCLAJE VANO FLOJO (0-60°), TIPO EV2 450.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 450.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.07.06 INSTALACION DE PUESTA A TIERRA P/SUB ESTACION MONOPOSTE 22,480.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,480.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.04.01.07.07 TABLERO DE PROTECCION METALICO PARA ADOSAR A POSTE 460/230 V - 3 CKTOS PARA EBAR 1 3,234.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,234.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12 LINEA DE IMPULSION DE AGUAS RESIDUALES I 1,475,288.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48,064.79 306,516.16 497,959.93 299,047.58 323,699.64
12.01 TRABAJOS PRELIMINARES 13,201.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,437.54 2,016.28 2,016.28 1,951.24 780.48
12.01.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 5,071.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,071.67 0.00 0.00 0.00 0.00
12.01.02 TRAZOS, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 8,130.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,365.87 2,016.28 2,016.28 1,951.24 780.48
12.02 MOVIMIENTO DE TIERRAS 481,458.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 41,627.25 121,378.40 103,718.16 156,353.26 58,381.87
12.02.01 EXCAVACION DE ZANJAS 36,353.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,596.11 19,757.28 0.00 0.00 0.00
12.02.01.01 EXCAVACION ZANJA c/EQUIPO HASTA 2.00 m; af = 0.80 m 36,353.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,596.11 19,757.28 0.00 0.00 0.00
12.02.02 REFINE y NIVELACION DE ZANJAS 4,684.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,465.54 2,218.98 0.00 0.00
12.02.02.01 REFINE y NIVELACION FONDO ZANJA; a = 0.80 m 4,684.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,465.54 2,218.98 0.00 0.00
12.02.03 CAMA DE APOYO P/TUBERIAS 44,444.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33,048.71 11,396.11 0.00 0.00
12.02.03.01 CAMA DE APOYO (equipo) c/RIPIO CORRIENTE; af = 0.80 m 44,444.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33,048.71 11,396.11 0.00 0.00
12.02.04 RELLENO, APISONADO y COMPACTACION LATERAL CON MATERIAL DE PRESTAMO 56,721.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,918.29 29,733.48 25,070.06 0.00 0.00
12.02.04.01 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 200 mm; a = 0.80 m 132.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 132.30 0.00 0.00
12.02.04.02 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 355 mm; a = 0.80 m 56,589.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,918.29 29,733.48 24,937.76 0.00 0.00
12.02.05 RELLENO y COMPACTACION S/CLAVE TUBERIA CON MATERIAL DE PRESTAMO 95,037.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,536.06 61,787.09 24,714.83
12.02.05.01 RELLENO y COMPACTACION c/RIPIO CORRIENTE h = 0.30 m; c/EQUIPO s/CLAVE TUBERIA Ø 200 mm; a = 0.80 m 297.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 297.78 0.00 0.00
12.02.05.02 RELLENO y COMPACTACION c/RIPIO CORRIENTE h = 0.30 m; c/EQUIPO s/CLAVE TUBERIA Ø 355 mm; a = 0.80 m 94,740.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,238.28 61,787.09 24,714.83
12.02.06 RELLENO y COMPACTACION CON MATERIAL DE PRESTAMO 46,651.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,980.97 35,885.83 4,784.78
12.02.06.01 RELLENO y COMPACTACION c/MATERIAL PROPIO SELECCIONADO CAPAS c/0.20 m; a = variable hasta nivel de terreno natural 46,651.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,980.97 35,885.83 4,784.78
12.02.07 ACARREO y ELIMINACION MATERIAL EXCEDENTE 72,205.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 43,323.39 28,882.26
12.02.07.01 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 72,205.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 43,323.39 28,882.26
12.02.08 BOMBEO EN ZANJAS 32,907.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 548.46 17,002.34 15,356.95 0.00
12.02.08.01 DRENAJE ZANJA HASTA 2.00 m 32,907.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 548.46 17,002.34 15,356.95 0.00
12.02.09 ENTIBADO DE ZANJAS 92,451.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23,112.85 35,824.93 33,513.64 0.00 0.00
12.02.09.01 ENTIBADO ZANJA HASTA 2.00 m 92,451.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23,112.85 35,824.93 33,513.64 0.00 0.00
12.03 SUMINISTRO e INSTALACION DE TUBERIAS 813,358.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 96,007.41 317,351.38 135,462.71 264,537.29
12.03.01 TUBERIA PVC UF PN 10 = 10 bar 761,602.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 96,007.41 265,595.55 135,462.71 264,537.29
12.03.01.01 SUMINISTRO e INSTALACION TUBERIA Ø 200 mm PVC UF PN 10; h = 2.00 m; c/3% desperdicio 1,058.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,058.26 0.00 0.00
12.03.01.02 SUMINISTRO e INSTALACION TUBERIA Ø 355 mm PVC UF PN 10; h = 2.00 m; c/3% desperdicio 760,544.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 96,007.41 264,537.29 135,462.71 264,537.29
12.03.02 TUBERIA FIERRO NEGRO SCH 40 51,755.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 51,755.83 0.00 0.00
12.03.02.01 TUBERIA DE ACERO SCHEDULE - 40 P/EQ. 14" (350 mm) INC./1% desp. 51,755.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 51,755.83 0.00 0.00
12.04 PRUEBAS HIDRAULICAS 23,811.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,850.97 3,960.37 0.00
12.04.01 DOBLE PRUEBA HIDRAULICA p/TUBERIA Ø 200 mm PVC 49.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 49.14 0.00 0.00
12.04.02 DOBLE PRUEBA HIDRAULICA p/TUBERIA Ø 355 mm PVC 23,762.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19,801.83 3,960.37 0.00
12.05 ACCESORIOS 111,413.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 87,114.07 24,299.19 0.00 0.00
12.05.01 SUMINISTRO e INSTALACION CODO ISO 2531 HFD BB 100 mm x 90° 989.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 989.16 0.00 0.00 0.00
12.05.02 SUMINISTRO e INSTALACION CODO ISO 2531 HFD 355 mm x 90° 5,660.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,660.58 0.00 0.00 0.00
12.05.03 SUMINISTRO e INSTALACION CODO ISO 2531 HFD 355 mm x 45° 7,826.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,826.70 0.00 0.00 0.00
12.05.04 SUMINISTRO e INSTALACION CODO ISO 2531 HFD 355 mm x 22.5° 4,030.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,030.90 0.00 0.00 0.00
12.05.05 SUMINISTRO e INSTALACION CODO ISO 2531 HFD 355 mm x 11.25° 5,923.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,923.59 0.00 0.00 0.00
12.05.06 SUMINISTRO e INSTALACION NIPLE HFD BB 100 mm x 0.60 m 3,245.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,245.66 0.00 0.00 0.00
12.05.07 SUMINISTRO e INSTALACION NIPLE HFD BB 100 mm x 0.70 m 3,320.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,320.40 0.00 0.00 0.00
12.05.08 SUMINISTRO e INSTALACION NIPLE HFD BB 100 mm x 2.15 m 4,685.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,685.76 0.00 0.00 0.00
12.05.09 SUMINISTRO e INSTALACION NIPLE HFD BB 200 mm x 0.80 m 6,238.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,238.46 0.00 0.00 0.00
12.05.10 SUMINISTRO e INSTALACION NIPLE HFD BB 350 mm x 0.50 m 29,472.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 29,472.84 0.00 0.00 0.00
12.05.11 SUMINISTRO e INSTALACION NIPLE HFD BB 350 mm x 0.75 m 15,298.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,298.68 0.00 0.00 0.00
12.05.12 SUMINISTRO e INSTALACION TAPON MACHO ISO 2531 HFD 100 mm 421.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 421.34 0.00 0.00 0.00
12.05.13 SUMINISTRO e INSTALACION TEE ISO 2531 HFD 350 x 100 mm 5,469.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,469.32 0.00 0.00
12.05.14 SUMINISTRO e INSTALACION TEE ISO 2531 HFD 350 x 200 mm 3,049.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,049.46 0.00 0.00
12.05.15 SUMINISTRO e INSTALACION TRANSICION A BRIDA CAMPANA ISO 2531 HFD 200 mm 470.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 470.22 0.00 0.00
12.05.16 SUMINISTRO e INSTALACION TRANSICION A BRIDA CAMPANA ISO 2531 HFD 350 mm 5,578.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,578.44 0.00 0.00
12.05.17 SUMINISTRO e INSTALACION TRANSICION ISO 2531 HFD-PVC 355 mm 2,788.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,788.92 0.00 0.00
12.05.18 SUMINISTRO e INSTALACION UNION DRESSER ISO 2531 HFD 100 mm 531.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 531.28 0.00 0.00
12.05.19 SUMINISTRO e INSTALACION UNION DRESSER ISO 2531 HFD 200 mm 485.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 485.78 0.00 0.00
12.05.20 SUMINISTRO e INSTALACION UNION DRESSER ISO 2531 HFD 350 mm 2,529.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,529.39 0.00 0.00
12.05.21 VALVULA COMPUERTA HFD BB 200 mm (Purga) 1,859.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,859.42 0.00 0.00
12.05.22 VALVULA COMPUERTA HFD BB 100 mm (Aire) 1,536.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,536.96 0.00 0.00
12.06 BY PASS DE CANAL DE RIEGO 4,463.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,463.64 0.00 0.00
12.06.01 BY PASS CON TUBERIA Ø 500 mm PVC UF CL 10 4,463.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,463.64 0.00 0.00
12.07 RECONSTRUCCION DE CANAL DE TIERRA 1,320.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,320.00 0.00
12.07.01 RECONSTRUCCION DE CANAL CON MATERIAL SELECCIONADO 1,320.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,320.00 0.00
12.08 OBRAS DE CONCRETO ARMADO 26,260.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26,260.31 0.00 0.00
12.08.01 CAJAS DE VALVULAS 25,869.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,869.72 0.00 0.00
12.08.01.01 CAJA y TECHO p/VALVULA AIRE f'c = 245 Kg/cm² 16,352.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,352.78 0.00 0.00
12.08.01.02 CAJA y TECHO p/VALVULA PURGA f'c = 245 Kg/cm² 9,516.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,516.94 0.00 0.00
12.08.02 ESTRUCTURA DE PROTECCION 390.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 390.59 0.00 0.00
12.08.02.01 ESTRUCTURA DE PROTECCION DE CONCRETO ARMADO f'c = 210 Kg/cm2 (0.70x0.70x4.00m) e =0.15 390.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 390.59 0.00 0.00
13 ESTACION DE BOMBEO DE AGUAS RESIDUALES II 866,802.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,480.90 41,162.56 64,596.78 125,562.86 221,222.35 47,245.54 45,663.03 22,685.09 89,656.64 45,614.18 35,553.54 117,359.04
13.01 CERCO PERIMETRICO, CASETA DE VIGILANCIA, SALA DE OPERACIONES Y SS HH 231,242.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,480.90 1,411.59 252.59 39,312.30 24,383.01 20,394.19 27,036.44 16,087.68 79,887.79 11,995.77 0.00 0.00
13.01.01 TRABAJOS PRELIMINARES 11,892.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,480.90 1,411.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.01.01 CASETA p/GUARDIANIA y/o DEPOSITO 2,703.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,703.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.01.02 SEÑALIZACION DESVIO OBRA 545.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 545.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.01.03 MOVILIZACION y DESMOVILIZACION MAQUINARIAS, EQUIPOS y HERRAMIENTAS 5,579.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,579.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.01.04 LIMPIEZA TERRENO MANUAL 1,652.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,652.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.01.05 TRAZOS, NIVELACION y REPLANTEO INICIAL 1,411.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,411.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.02 MOVIMIENTO DE TIERRAS 23,891.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 252.59 4,180.46 0.00 0.00 3,600.59 10,624.30 5,233.22 0.00 0.00 0.00
13.01.02.01 EXCAVACION TERRENO NORMAL HASTA 1.50 m p/CIMIENTO 2,399.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 252.59 2,146.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.02.02 RELLENO CON MATERIAL DE PRESTAMO 21,491.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,033.47 0.00 0.00 3,600.59 10,624.30 5,233.22 0.00 0.00 0.00
13.01.02.02.01 RELLENO C/MATERIAL DE PRESTAMO, PIEDRA CHANCADA DE 1/2" e=0.05m 2,033.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,033.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.02.02.02 RELLENO C/MATERIAL DE PRESTAMO AFIRMADO e=0.20m 7,528.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,600.59 3,927.91 0.00 0.00 0.00 0.00
13.01.02.02.03 RELLENO C/MATERIAL DE PRESTAMO, ARENA FINA e=0.11m 3,657.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,657.44 0.00 0.00 0.00 0.00
13.01.02.02.04 RELLENO C/MATERIAL DE PRESTAMO AFIRMADO e=0.10m P/VEREDA 1,495.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,495.50 0.00 0.00 0.00 0.00
13.01.02.02.05 RELLENO C/MATERIAL DE PRESTAMO, ARENA FINA e=0.10m P/VEREDA INTERIOR 569.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 569.97 0.00 0.00 0.00 0.00
13.01.02.02.06 RELLENO C/MATERIAL DE PRESTAMO, ARENA FINA e=0.16m P/VEREDA EXTERIOR 1,216.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 973.48 243.37 0.00 0.00 0.00
13.01.02.02.07 RELLENO C/MATERIAL DE PRESTAMO, ARENA FINA e=0.26m P/EDIFICACION 1,403.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,403.22 0.00 0.00 0.00
13.01.02.02.08 RELLENO c/MATERIAL PROPIO SELECCIONADO 2,077.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,077.24 0.00 0.00 0.00
13.01.02.02.09 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0 Km 1,509.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,509.39 0.00 0.00 0.00
13.01.03 ESTRUCTURAS 123,417.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35,131.84 24,383.01 7,254.60 19,852.33 0.00 36,795.74 0.00 0.00 0.00
13.01.03.01 OBRAS DE CONCRETO SIMPLE 72,733.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31,749.56 0.00 4,188.17 0.00 0.00 36,795.74 0.00 0.00 0.00
13.01.03.01.01 SOLADOS 48.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.01.01.01 SOLADO P/ZAPATA e = 0.10 m 48.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.01.02 CIMIENTOS CORRIDOS 31,701.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31,701.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.01.02.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDDO 31,701.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31,701.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.01.03 SOBRECIMIENTO 4,188.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,188.17 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.01.03.01 ENCOFRADO y DEDESENCOFRADO HASTA 0.30 m p/SOBRECIMIENTO 2,981.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,981.92 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.01.03.02 CONCRETO C:H 1:8 + 25 % PM; f'c = 100 Kg/cm² p/SOBRECIMIENTO 1,206.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,206.25 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.01.04 PISOS 1,471.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,471.68 0.00 0.00 0.00
13.01.03.01.04.01 CONCRETO f'c = 140 Kg/cm²; e = 0.075 m p/PISO 1,471.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,471.68 0.00 0.00 0.00
13.01.03.01.05 VEREDAS 35,324.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35,324.06 0.00 0.00 0.00
13.01.03.01.05.01 ENCOFRADO y DESENCOFRADO p/VEREDA 767.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 767.06 0.00 0.00 0.00
13.01.03.01.05.02 CONCRETO f'c = 140 Kg/cm²; h = 0.10 m p/VEREDA 34,557.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 34,557.00 0.00 0.00 0.00
13.01.03.02 OBRAS DE CONCRETO ARMADO 50,684.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,382.28 24,383.01 3,066.43 19,852.33 0.00 0.00 0.00 0.00 0.00
13.01.03.02.01 ZAPATAS 571.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 571.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.02.01.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 32.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.02.01.02 CONCRETO ZAPATAS f'c = 280 Kg/cm2 538.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 538.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.02.02 VIGAS DE CIMENTACION 16,327.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,811.19 13,516.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.02.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 7,496.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,811.19 4,685.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.02.02.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA CIMENTACION 5,667.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,667.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.02.02.03 CONCRETO f'c = 210 Kg/cm² p/VIGA CIMENTACION 3,164.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,164.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.02.03 COLUMNAS 13,932.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,866.22 3,066.43 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.02.03.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 4,336.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,336.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.02.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 6,529.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,529.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.02.03.03 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 3,066.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,066.43 0.00 0.00 0.00 0.00 0.00 0.00
13.01.03.02.04 VIGAS 13,354.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,354.85 0.00 0.00 0.00 0.00 0.00
13.01.03.02.04.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 4,540.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,540.14 0.00 0.00 0.00 0.00 0.00
13.01.03.02.04.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 4,462.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,462.93 0.00 0.00 0.00 0.00 0.00
13.01.03.02.04.03 CONCRETO f'c = 210 Kg/cm² p/VIGA 4,351.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,351.78 0.00 0.00 0.00 0.00 0.00
13.01.03.02.05 LOSAS ALIGERADAS 6,497.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,497.48 0.00 0.00 0.00 0.00 0.00
13.01.03.02.05.01 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA ALIGERADA 1,564.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,564.69 0.00 0.00 0.00 0.00 0.00
13.01.03.02.05.02 LADRILLO HUECO ARCILLA 15 x 30 x 30 cm p/LOSA ALIGERADA 844.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 844.17 0.00 0.00 0.00 0.00 0.00
13.01.03.02.05.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,003.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,003.95 0.00 0.00 0.00 0.00 0.00
13.01.03.02.05.04 CONCRETO f'c = 210 Kg/cm² p/LOSA ALIGERADA 3,084.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,084.67 0.00 0.00 0.00 0.00 0.00
13.01.04 ARQUITECTURA 66,915.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,139.59 3,583.52 338.08 37,858.83 11,995.77 0.00 0.00
13.01.04.01 MUROS DE ALBAÑILERIA 16,723.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,139.59 3,583.52 0.00 0.00 0.00 0.00 0.00
13.01.04.01.01 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 16,723.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,139.59 3,583.52 0.00 0.00 0.00 0.00 0.00
13.01.04.02 REVOQUES, ENLUCIDOS Y MOLDURAS 18,536.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,536.27 0.00 0.00 0.00
13.01.04.02.01 TARRAJEO RAYADO PRIMARIO 365.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 365.56 0.00 0.00 0.00
13.01.04.02.02 TARRAJEO INTERIOR/EXTERIOR c/MORTERO C:A 1:5 6,991.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,991.04 0.00 0.00 0.00
13.01.04.02.03 TARRAJEO SUPERFICIE COLUMNA c/MORTERO C:A 1:5 5,500.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,500.58 0.00 0.00 0.00
13.01.04.02.04 TARRAJEO SUPERFICIE VIGA c/MORTERO C:A 1:5 4,963.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,963.95 0.00 0.00 0.00
13.01.04.02.05 VESTIDURA DERRAME 715.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 715.14 0.00 0.00 0.00
13.01.04.03 CIELO RASOS 2,028.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 338.08 1,690.41 0.00 0.00 0.00
13.01.04.03.01 CIELO RASO c/MORTERO C:A 1:5 2,028.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 338.08 1,690.41 0.00 0.00 0.00
13.01.04.04 PISOS y PAVIMENTOS 2,092.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,092.61 0.00 0.00 0.00
13.01.04.04.01 PISO CEMENTO PULIDO y BRUÑADO (50 x 0.50 cm); e = 2" 1,841.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,841.54 0.00 0.00 0.00
13.01.04.04.02 PISO CERAMICA (20 x 20 cm) p/BAÑO 251.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 251.07 0.00 0.00 0.00
13.01.04.05 CONTRAZOCALO 841.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 841.90 0.00 0.00 0.00
13.01.04.05.01 CONTRAZOCALO CEMENTO s/COLOREAR h = 0.15 m 841.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 841.90 0.00 0.00 0.00
13.01.04.06 CARPINTERIA DE MADERA 375.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 375.14 0.00 0.00 0.00
13.01.04.06.01 PUERTA CONTRAPLACADA TRIPLAY 50 mm 375.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 375.14 0.00 0.00 0.00
13.01.04.07 CARPINTERIA METALICA 16,715.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,726.66 8,989.19 0.00 0.00
13.01.04.07.01 VENTANA FIERRO (inc. pintura) 2,392.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,392.33 0.00 0.00 0.00
13.01.04.07.02 PUERTA METALICA (inc. pintura) 12,002.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,334.33 6,667.91 0.00 0.00
13.01.04.07.03 SUMINISTRO e INSTALACION DE ALAMBRADO DE PUAS 2,321.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,321.28 0.00 0.00
13.01.04.08 PINTURA 9,377.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,595.84 2,781.59 0.00 0.00
13.01.04.08.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 1,407.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,407.01 0.00 0.00 0.00
13.01.04.08.02 PINTURA EN COLUMNAS 1,042.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,042.08 0.00 0.00 0.00
13.01.04.08.03 PINTURA EN VIGAS 795.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 795.85 0.00 0.00 0.00
13.01.04.08.04 PINTURA LATEX CIELO RASO 02 MANOS inc./IMPRIMANTE 603.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 603.99 0.00 0.00 0.00
13.01.04.08.05 PINTURA CON BARNIZ EN CERCO PERIMETRICO INTERIOR Y EXTERIOR 5,057.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,275.84 2,781.59 0.00 0.00
13.01.04.08.06 PINTURA ESMALTE CONTRAZOCALO h=0.15m 471.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 471.07 0.00 0.00 0.00
13.01.04.09 VIDRIOS, CRISTALES y SIMILARES 224.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 224.99 0.00 0.00
13.01.04.09.01 VIDRIO NACIONAL DOBLE 224.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 224.99 0.00 0.00
13.01.05 INSTALACIONES SANITARIAS 5,125.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,125.30 0.00 0.00 0.00 0.00
13.01.05.01 SISTEMA DE AGUA FRIA 1,696.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,696.97 0.00 0.00 0.00 0.00
13.01.05.01.01 SALIDA AGUA FRIA c/TUBERIA PVC SAP 1/2" 254.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 254.32 0.00 0.00 0.00 0.00
13.01.05.01.02 RED DISTRIBUCION p/TUBERIA PVC SAP 1/2" 426.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 426.82 0.00 0.00 0.00 0.00
13.01.05.01.03 CODO PVC SAP 1/2" x 90° 378.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 378.84 0.00 0.00 0.00 0.00
13.01.05.01.04 CODO F°G° 1/2" x 90° 199.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 199.44 0.00 0.00 0.00 0.00
13.01.05.01.05 TEE PVC SAP 1/2" x 90° 65.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 65.58 0.00 0.00 0.00 0.00
13.01.05.01.06 VALVULA COMPUERTA BRONCE 1/2" 164.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 164.73 0.00 0.00 0.00 0.00
13.01.05.01.07 UNION UNIVERSAL PVC SAP 1/2" 207.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 207.24 0.00 0.00 0.00 0.00
13.01.05.02 SISTEMA DE DESAGUE 2,300.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,300.28 0.00 0.00 0.00 0.00
13.01.05.02.01 SALIDA DESAGUE PVC 4" 305.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 305.40 0.00 0.00 0.00 0.00
13.01.05.02.02 TUBERIA PVC SAL 2" 356.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 356.77 0.00 0.00 0.00 0.00
13.01.05.02.03 TUBERIA PVC SAL 4" 1,108.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,108.38 0.00 0.00 0.00 0.00
13.01.05.02.04 CODO PVC SAL 2" x 45° 62.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62.70 0.00 0.00 0.00 0.00
13.01.05.02.05 CODO PVC SAL 4"X45° 75.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 75.34 0.00 0.00 0.00 0.00
13.01.05.02.06 CODO PVC SAL 2" x 90° 62.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62.70 0.00 0.00 0.00 0.00
13.01.05.02.07 CODO PVC SAL 4" x 90° 38.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38.56 0.00 0.00 0.00 0.00
13.01.05.02.08 YEE PVC SAL 4" x 4" 106.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 106.26 0.00 0.00 0.00 0.00
13.01.05.02.09 REDUCCION PVC SAL 4" x 2" 96.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 96.93 0.00 0.00 0.00 0.00
13.01.05.02.10 REGISTRO BRONCE 2" 87.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 87.24 0.00 0.00 0.00 0.00
13.01.05.03 APARATOS SANITARIOS y ACCESORIOS 1,128.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,128.05 0.00 0.00 0.00 0.00
13.01.05.03.01 INODORO TANQUE BAJO BLANCO 205.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 205.39 0.00 0.00 0.00 0.00
13.01.05.03.02 LAVATORIO FONTANA COLOR BLANCO 396.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 396.59 0.00 0.00 0.00 0.00
13.01.05.03.03 DUCHA CROMADA 01 LLAVE inc./ACCESORIOS 90.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 90.29 0.00 0.00 0.00 0.00
13.01.05.03.04 GRIFO CROMADO 317.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 317.22 0.00 0.00 0.00 0.00
13.01.05.03.05 JABONERA LOSA BLANCO 118.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 118.56 0.00 0.00 0.00 0.00
13.02 CAMARA HUMEDA, DE REJAS y DE VALVULAS 185,867.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39,750.97 57,688.05 50,771.49 37,358.37 0.00 0.00 0.00 298.85 0.00 0.00 0.00
13.02.01 CAMARA HUMEDA 76,078.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39,750.97 31,532.41 0.00 4,795.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.01 MOVIMIENTO DE TIERRAS 38,314.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,532.21 7,986.24 0.00 4,795.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.01.01 EXCAVACION MASIVA 8,611.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,611.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.01.02 DRENAJE 22,461.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,475.06 7,986.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.01.03 ENTIBADO CON PUNTALES DE 6"x4" h=8.55m 889.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 889.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.01.04 RELLENO y APISONADO c/MATERIAL PROPIO CAPAS c/0.20 m 4,795.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,795.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.01.05 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 1,555.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,555.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.02 ESTRUCTURAS 35,141.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,218.76 20,922.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.02.01 OBRAS DE CONCRETO SIMPLE 198.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 198.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.02.01.01 SOLADO e = 0.10 m p/ESTRUCTURA 198.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 198.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.02.02 OBRAS DE CONCRETO ARMADO 34,943.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,020.24 20,922.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.02.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 11,910.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,162.29 2,748.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.02.02.02 ENCOFRADO y DESENCOFRADO NORMAL P/CAMARA HUMEDA 8,636.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,857.95 3,778.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.02.02.03 CONCRETO f'c = 280 Kg/cm² P/CAMARA HUMEDA 14,395.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,395.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.03 ARQUITECTURA 2,623.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,623.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.03.01 REVOQUES ENLUCIDOS Y MOLDURAS 2,623.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,623.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.01.03.01.01 TARRAJEO C/IMPERMEABILIZANTES P/PARED INTERIOR 2,623.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,623.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02 CAMARA DE REJAS 88,645.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26,155.64 47,573.15 14,617.80 0.00 0.00 0.00 298.85 0.00 0.00 0.00
13.02.02.01 MOVIMIENTO DE TIERRAS 34,665.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,096.37 3,493.98 6,075.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.01.01 EXCAVACION MASIVA 10,206.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,206.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.01.02 DRENAJE 14,974.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,480.22 3,493.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.01.03 ENTIBADO CON PUNTALES DE 6"x4" h=8.10m 1,626.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,626.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.01.04 RELLENO y APISONADO c/MATERIAL PROPIO CAPAS c/0.20 m 5,925.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,925.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.01.05 RELLENO p/FILTRO c/PIEDRA 1" e = 1.20 m 149.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 149.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.01.06 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 1,783.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,783.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.02 ESTRUCTURAS 41,265.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,059.27 40,206.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.02.01 OBRAS DE CONCRETO SIMPLE 148.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 148.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.02.01.01 SOLADO e = 0.10 m p/ESTRUCTURA 148.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 148.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.02.02 OBRAS DE CONCRETO ARMADO 41,116.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 910.62 40,206.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.02.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 13,659.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 910.62 12,748.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.02.02.02 ENCOFRADO y DESENCOFRADO NORMAL P/CAMARA REJAS 10,698.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,698.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.02.02.03 CONCRETO f'c = 280 Kg/cm² P/CAMARA REJAS 16,758.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,758.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.03 ARQUITECTURA 12,714.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,873.10 8,542.63 0.00 0.00 0.00 298.85 0.00 0.00 0.00
13.02.02.03.01 MUROS Y TABIQUES DE ALBAÑILERIA 2,285.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,285.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.03.01.01 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 2,285.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,285.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.03.02 REVOQUES ENLUCIDOS Y MOLDURAS 6,802.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,587.25 5,215.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.03.02.01 TARRAJEO EXTERIOR c/MORTERO C:A 1:5 1,472.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,472.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.03.02.02 TARRAJEO SUPERFICIE TECHO CAMARA DE REJAS c/MORTERO C:A 1:5 378.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 378.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.03.02.03 TARRAJEO C/IMPERMEABILIZANTES P/PARED INTERIOR 4,836.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,836.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.03.02.04 VESTIDURA DERRAME 114.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 114.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.03.03 CARPINTERIA METALICA 3,327.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,327.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.03.03.01 PUERTA METALICA (inc. pintura) 3,327.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,327.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.02.03.04 PINTURA 298.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 298.85 0.00 0.00 0.00
13.02.02.03.04.01 PINTURA LATEX EXTERIOR 02 MANOS inc./IMPRIMANTE 298.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 298.85 0.00 0.00 0.00
13.02.03 CAMARA DE VALVULAS 21,143.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,198.34 17,944.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.01 MOVIMIENTO DE TIERRAS 8,599.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,198.34 5,401.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.01.01 EXCAVACION MASIVA 3,786.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,366.44 1,419.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.01.02 DRENAJE 1,663.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 831.90 831.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.01.03 ENTIBADO CON PUNTALES DE 6"x4" h=3.80m 1,132.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,132.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.01.04 RELLENO y APISONADO c/MATERIAL PROPIO CAPAS c/0.20 m 1,071.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,071.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.01.05 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 945.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 945.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.02 ESTRUCTURAS 11,507.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,507.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.02.01 OBRAS DE CONCRETO SIMPLE 332.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 332.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.02.01.01 SOLADO e = 0.10 m p/ESTRUCTURA 332.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 332.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.02.02 OBRAS DE CONCRETO ARMADO 11,174.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,174.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.02.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 2,864.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,864.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.02.02.02 ENCOFRADO y DESENCOFRADO NORMAL P/CAMARA VALVULAS 3,403.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,403.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.02.02.03 CONCRETO f'c = 280 Kg/cm² P/CAMARA VALVULAS 4,826.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,826.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.02.02.04 DADO CONCRETO f'c = 280 Kg/cm² (0.30 x 0.40 x 0.50 m) 80.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 80.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.03 ARQUITECTURA 1,035.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,035.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.03.01 REVOQUES ENLUCIDOS Y MOLDURAS 1,035.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,035.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02.03.03.01.01 TARRAJEO C/IMPERMEABILIZANTES P/PARED INTERIOR 1,035.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,035.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03 INSTALACIONES ELECTROMECANICAS DE LA EBAR II 356,813.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,656.14 35,479.07 159,480.97 26,851.35 18,626.59 6,597.41 9,470.00 32,804.54 25,588.74 35,259.00
13.03.01 SUMINISTRO Y MONTAJE DE EQUIPAMIENTO ELECTROMECANICO DE LA CAMARA HUMEDA DE BOMBEO 90,382.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,656.14 12,868.54 63,508.91 7,349.02 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.01 SUMINISTRO Y MONTAJE DE EQUIPOS DE ELECTROBOMBAS SUMERGIBLES E INMERSIBLES 61,079.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,656.14 12,868.54 34,898.29 6,656.14 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.01.01 SUMINISTRO E INSTALACION DE ELECTROBOMBA SUMERGIBLE P/AGUAS RESIDUALES 38 lps; ADT = 10.00 m, 440/380/220V, 3F39,936.84
60Hz , 1735rpm,5.6Kw con
0.0023m cable electrico
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,656.14 12,868.54 13,756.02 6,656.14 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.01.02 SUMINISTRO E INSTALACION DE VALVULAS DE LIMPIEZA ACOPLADA A BASE DE ELECTROBOMBA 15,167.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,167.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.01.03 SUMINISTRO E INSTALACION DE CODO ESTACIONARIO DE DESCARGA-PATA CODO 100mm 694.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 694.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.01.04 DADO DE CONCRETO 280Kg/cm2 y ANCLAJE AL PATACODO REFORZADO CON F°C DE 4"x2" 989.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 989.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.01.05 SENSOR PARA MEDIR Y CONTROLAR NIVELES DE AGUA RESIDUALES MODELO LTU 601 4,023.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,023.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.01.06 TUBO DE PVC SAP 3" Y SOPORTE DE FIJACION DE TUBO Y PLATINAS DE ACERO INOXIDABLE 267.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 267.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.02 SUMINISTRO Y MONTAJE DE GUIAS PARA IZADO RAPIDO DE ELECTROBOMBAS 8,421.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,421.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.02.01 TUBO GUIAS DE ACERO INOXIDABLE DE 2" AISI 316, SCH10S 2,897.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,897.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.02.02 SOPORTE SUPERIOR DE LOS TUBOS GUIAS 4,357.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,357.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.02.03 CADENA CORTA MAS OJAL DE ENGANCHE 1,166.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,166.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.03 SUMINISTRO Y MONTAJE DE SOPORTE TIPO BANDERA Y TECLE DE 1 TN 8,665.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,665.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.03.01 SOPORTE PORTATIL Y GIRATORIO TIPO BANDERA DE FIERRO NEGRO ELECTROSOLDABLE 1,215.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,215.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.03.02 TECLE YALE ELECTRICO 1 TN DE CADENA LARGA (10m) 7,449.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,449.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.04 SUMINISTRO Y MONTAJE DE COLUMNA DE IMPULSION 11,523.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,523.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.04.01 NIPLES DE TUBO DE ACERO NEGRO ELECTROSOLDABLE 8" SCH40 ASTM A53 GRADO B 3,967.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,967.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.04.02 ACCESORIOS DE LA COLUMNA DE IMPULSION Y OTROS 7,556.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,556.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.05 SUMINISTRO Y MONTAJE DE MARCOS Y REJILLAS DE FIBRA DE VIDRIO 692.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 692.88 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.05.01 MARCO DE PLATINAS Y ANGULOS DE ACERO INOXIDABLE DE 0.9Mx 0.7M 585.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 585.84 0.00 0.00 0.00 0.00 0.00 0.00
13.03.01.05.02 REJILLAS DE FIBRA DE VIDRIO DE 0.9M x 0.7M (3 piezas) 107.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 107.04 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02 SUMINISTRO Y MONTAJE DE EQUIPAMIENTO ELECTROMECANICO DE LA CAMARA DEL ARBOL DE IMPULSION 100,772.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,610.53 77,353.64 808.02 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.01 SUMINISTRO Y MONTAJE DE EQUIPOS DE ELECTROBOMBAS SUMERGIBLES E INMERSIBLES 76,758.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,610.53 54,147.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 de 10
CALENDARIO DE AVANCE DE OBRA VALORIZADO ACTUALIZADO A LA FECHA DE INICIO DE OBRA
OBRA : INSTALACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DE LOS PP.JJ. VILLA PROGRESO, MIRAFLORES, LAS VEGAS, SAMAN, SAN FRANCISCO DE ASIS, LA UNION, SAN JUAN DE DIOS Y RAMIRO PRIALE II - CHICLAYO
ENTIDAD : ENTIDAD PRESTADORA DE SERVICIOS DE SANEAMIENTO DE LAMBAYEQUE S.A. - EPSEL S.A.
CONTRATISTA : CONSORCIO PROGRESO
SUPERVISION : CONSORCIO SUPERVISOR ASIS
UBICACIÓN : CHICLAYO - CHICLAYO - LAMBAYEQUE
Duración (Meses)
Item Descripción Parcial (S/.)
Mar-2019 Abr-2019 May-2019 Jun-2019 Jul-2019 Ago-2019 Sep-2019 Oct-2019 Nov-2019 Dic-2019 Ene-2020 Feb-2020 Mar-2020 Abr-2020 May-2020 Jun-2020 Jul-2020 Ago-2020 Sep-2020 Oct-2020
13.03.02.01.01 ELECTROBOMBAS PARA AGUAS SERVIDAS DE 14 LPS 5.5m ADT, 440/220 V, 3F, 60 Hz, 1800 rpm 75,368.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,610.53 52,757.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.01.02 MANGUERA DE JEBE Y LONA DE 2" Y ACCESORIO DE INSTALACION 1,389.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,389.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.02 SUMINISTRO Y MONTAJE DE ACCESORIOS DEL ARBOL DE IMPULSION DE 8" 12,889.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,889.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.02.01 NIPLES DE TUBO DE 8" x 1.5, ELECTROSOLDABLE 6,617.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,617.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.02.02 VALVULA DE RETENCION DE 8" DE ASIENTO RECTO CON EJE INTERNO BRIDADA - CHECK 1,407.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,407.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.02.03 VALVULA DE COMPUERTA BRIDADA DE AGUAS RESIDUALES DE 8" PN10 2,677.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,677.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.02.04 UNION DRESSES DE 8" 587.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 587.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.02.05 REDUCCION ELECTROSOLDABLES DE 10" A 8" 1,598.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,598.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.03 SUMINISTRO Y MONTAJE DE ACCESORIOS DEL ARBOL DE IMPULSION DE 10" 9,056.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,056.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.03.01 NIPLES DE TUBO DE 10" x 1.5, ELECTROSOLDABLE 2,467.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,467.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.03.02 NIPLES DE TUBO DE 10" x 1 ELECTROSOLDABLE CON BRIDA CIEGA 1,161.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,161.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.03.03 NIPLES DE TUBO DE 250mm x 1M ELECTROSOLDABLE 1,101.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,101.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.03.04 YEE DE ACERO AL CARBONO SCH40 CON REDUCCION DE 10" a 10" 2,550.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,550.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.03.05 CODOS ACERO AL CARBONO SCH40 45° DE 10" 1,776.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,776.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.04 SUMINISTRO Y MONTAJE DE MARCOS Y REJILLAS DE FIBRA DE VIDRIO 1,260.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,260.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.04.01 REJILLAS DE FIBRA DE VIDRIO DE 1.60M x 0.4M (4 piezas) 982.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 982.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.04.02 MARCO DE PLATINAS Y ANGULOS DE ACERO INOXIDABLE DE 1Mx 0.8M 277.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 277.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.05 SUMINISTRO DE ESCALERA DE GATO 808.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 808.02 0.00 0.00 0.00 0.00 0.00 0.00
13.03.02.05.01 ESCALERA METALICA DE TUBO DE F°G° DE 1" 808.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 808.02 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03 SUMINISTRO Y MONTAJE DE EQUIPAMIENTO ELECTROMECANICO DE LA CAMARA DE REJAS 36,488.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,618.42 17,869.69 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.01 SUMINISTRO Y MONTAJE DE ELECTROBOMBAS SUMERGIBLES E INMERSIBLES EN LODOS 20,240.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,618.42 1,621.79 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.01.01 SUMINISTRO E INSTALACION DE ELECTROBOMBA SUMERGIBLE E INMERSIBLE PARA LODOS 35 lps; ADT = 12 m 440v 60 hZ 1800
18,618.42
RPM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,618.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.01.02 MANGUERA DE JEBE Y LONA DE 4" Y ACCESORIO DE INSTALACION 1,621.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,621.79 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.02 SUMINISTRO Y MONTAJE DE SOPORTE TIPO RIEL Y TECLE DE 0.75 TN 5,539.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,539.68 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.02.01 SOPORTE TIPO RIEL DE FIERRO NEGRO TIPO H DE 6" x 4" 1,643.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,643.19 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.02.02 WINCHE ELECTRICO 0.50 TN DE CADENA LARGA (10m) 3,896.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,896.49 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.03 SUMINISTRO Y MONTAJE DE VALVULA COMPUERTA BRIDADA DE 250mm PN10 Y ACCESORIOS 5,432.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,432.21 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.03.01 VALVULA DE COMPUERTA BRIDADA DE AGUAS RESIDUALES DE 250mm PN10 1,778.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,778.38 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.03.02 EXTENSION DE EJE INOXIDABLE 416 PARA VOLANTE DE VALVULA Y ACOPLADA A 2 CHUMACERAS 3,050.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,050.41 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.03.03 NIPLES DE TUBO DE ACERO NEGRO ELECTROSOLDABLE DE 250mm SCH40, GRADO B 603.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 603.42 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.04 SUMINISTRO Y MONTAJE DE MARCOS Y REJILLAS DE FIBRA DE VIDRIO 5,276.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,276.01 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.04.01 MARCO DE PLATINAS Y ANGULOS DE ACERO INOXIDABLE DE 416 DE 0.95x0.71 1,049.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,049.25 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.04.02 REJILLA DE FIBRA DE VIDRIO DE 0.95x0.71m SOPORTE 150Kg E=MAYOR 1 1/4" 681.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 681.01 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.04.03 MARCO DE PLATINAS Y ANGULOS DE ACERO INOXIDABLE DE 416 DE 0.95x095 219.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 219.85 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.04.04 REJILLA DE FIBRA DE VIDRIO DE 0.95x0.95m SOPORTE 150Kg E=MAYOR 1 1/4" 199.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 199.37 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.04.05 MARCO DE PLATINAS Y ANGULOS DE ACERO INOXIDABLE 416 DE LA REJILLA DE RETENCION DE SOLIDOS 1,499.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,499.40 0.00 0.00 0.00 0.00 0.00 0.00
13.03.03.04.06 REJILLA DE FIBRA DE VIDRIO 0.95x0.95M SOPORTE 150Kg E=MAYOR 1 1/4" 1,627.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,627.13 0.00 0.00 0.00 0.00 0.00 0.00
13.03.04 SUMINISTRO Y MONTAJE DE EQUIPAMIENTO ELECTROMECANICO DE LA CASETA DE MANDO, CONTROL Y DEL GRUPO GENERADOR 98,675.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,419.05 6,597.41 9,470.00 32,804.54 25,588.74 21,795.73
13.03.04.01 SUMINISTRO Y MONTAJE DE EQUIPAMIENTO ELECTROMECANICO DE LA CASETA DEL GRUPO GENERADOR 24,468.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,419.05 6,597.41 6,996.44 7,244.45 853.18 358.24
13.03.04.01.01 TABLERO DE TRANSFERENCIA Y DE ENCENDIDO AUTOMATICO DE UN GENERADOR DE 30Kw 440V 23,090.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,419.05 6,597.41 6,817.32 6,817.32 439.83 0.00
13.03.04.01.02 GRUPO GENERADOR DE 30 Kw TRIFASICO EN 480 V EN EMERGENCIA ,EQUIPO CON POWER WIZAR 2.0 1,377.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 179.12 427.13 413.35 358.24
13.03.04.02 SUMINISTRO Y MONTAJE DE EQUIPAMIENTO ELECTROMECANICO DE LA CASETA DE MANDO Y CONTROL DE ELECTROBOMBAS 74,206.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,473.56 25,560.09 24,735.56 21,437.49
13.03.04.02.01 TABLERO ELECTRICO DE 3 ELECTROBOMBAS DE LA CAMARA HUMEDA 62,204.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,073.49 21,426.08 20,734.91 17,970.26
13.03.04.02.02 TABLERO ELECTRICO DE ELECTROBOMBA DE LA CAMARA DE REJAS Y DE CAMARA DE VALVULAS 12,001.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 400.07 4,134.01 4,000.65 3,467.23
13.03.05 SUMINISTRO Y MONTAJE DE INSTALACIONES ELECTRICAS EN LA ESTACION DE LA CAMARA DE BOMBEO 17,032.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 824.62 16,207.54 0.00 0.00 0.00 0.00 0.00
13.03.05.01 SUMINISTRO Y MONTAJE DE CONEXIONES ELECTRICAS SUBTERRANEAS 1,643.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 824.62 819.32 0.00 0.00 0.00 0.00 0.00
13.03.05.01.01 EXCAVACION DE ZANJAS 0.8x0.6m 242.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 242.73 0.00 0.00 0.00 0.00 0.00 0.00
13.03.05.01.02 ACARREO Y ELIMINACION DE MATERIAL EXCEDENTE Dist. min = 5.0Km 70.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 70.11 0.00 0.00 0.00 0.00 0.00 0.00
13.03.05.01.03 CAMA DE APOYO C/ARENA FINA 107.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 107.62 0.00 0.00 0.00 0.00 0.00 0.00
13.03.05.01.04 DUCTO DE CONCRETO ARMADO DE 4 VIAS 304.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 304.00 0.00 0.00 0.00 0.00 0.00 0.00
13.03.05.01.05 TUBERIA DE PVC SAP 4" x 6M 100.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100.16 0.00 0.00 0.00 0.00 0.00 0.00
13.03.05.01.06 CODO DE PVC SAP DE 4" 99.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 99.30 0.00 0.00 0.00 0.00 0.00
13.03.05.01.07 TEE DE PVC SAP DE 4" 75.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 75.30 0.00 0.00 0.00 0.00 0.00
13.03.05.01.08 ABRAZADERA SOPORTE 4" ADOSADA A MURO DE CONCRETO 422.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 422.60 0.00 0.00 0.00 0.00 0.00
13.03.05.01.09 CAJA DE REGISTRO DE CONCRETO 83.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 83.36 0.00 0.00 0.00 0.00 0.00
13.03.05.01.10 RELLENO LATERAL C/ARENA FINA 22.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22.06 0.00 0.00 0.00 0.00 0.00
13.03.05.01.11 RELLENO SUPERIOR C/ARENA FINA 49.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 49.64 0.00 0.00 0.00 0.00 0.00
13.03.05.01.12 RELLENO Y COMPACTACION CON MATERIAL PROPIO SELECCIONADO 67.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 67.06 0.00 0.00 0.00 0.00 0.00
13.03.05.02 SUMINISTRO Y MONTAJE DE INSTALACIONES ELECTRICAS DE INTERIORES 6,595.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,595.72 0.00 0.00 0.00 0.00 0.00
13.03.05.02.01 SALIDA p/CENTRO LUZ DE CASETAS 708.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 708.80 0.00 0.00 0.00 0.00 0.00
13.03.05.02.02 LAMPARAS Y LUMINARIAS AHORRADORAS 309.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 309.00 0.00 0.00 0.00 0.00 0.00
13.03.05.02.03 SALIDA p/TOMACORRIENTE BIPOLAR DOBLE c/PUESTA A TIERRA 648.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 648.24 0.00 0.00 0.00 0.00 0.00
13.03.05.02.04 SALIDA p/INTERRUPTOR BIPOLAR DOBLE 423.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 423.68 0.00 0.00 0.00 0.00 0.00
13.03.05.02.05 SALIDA p/INTERRUPTOR SIMPLE 215.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 215.24 0.00 0.00 0.00 0.00 0.00
13.03.05.02.06 TABLERO PRINCIPAL METALICO 3 CIRCUITOS/TERMOM CON DIFERENCIAL 3,413.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,413.61 0.00 0.00 0.00 0.00 0.00
13.03.05.02.07 POZO A TIERRA 877.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 877.15 0.00 0.00 0.00 0.00 0.00
13.03.05.03 SUMINISTRO Y MONTAJE DEL SISTEMA DE ILUMINACION DE LA ESTACION DE LA CAMARA DE BOMBEO 8,792.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,792.50 0.00 0.00 0.00 0.00 0.00
13.03.05.03.01 SALIDA p/CENTROS DE LUZ 2,043.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,043.64 0.00 0.00 0.00 0.00 0.00
13.03.05.03.02 LUMINARIA TIPO FAROLA Y LAMPARA DE ALURO METALICO DE 70 WATTS 2,634.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,634.48 0.00 0.00 0.00 0.00 0.00
13.03.05.03.03 LUMINARIA TIPO FAROLA Y LAMPARA DE ALURO METALICO DE 100 WATTS 3,215.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,215.80 0.00 0.00 0.00 0.00 0.00
13.03.05.03.04 SALIDA p/INTERRUPTOR BIPOLAR CON INTERRUPTOR TERMOMAGNETICO 898.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 898.58 0.00 0.00 0.00 0.00 0.00
13.03.06 SUMINISTRO Y MONTAJE DEL SISTEMA DE AUTOMATIZACION Y DE TELEMETRIA DE LA EBAR II 13,463.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,463.27
13.03.06.01 SUMINISTRO E INSTALACION DEL EQUIPO DE MONITOREO Y CONTROL TELEMETRIA EBAR II 13,463.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,463.27
13.04 SUMINISTRO DE UTILIZACION EN MEDIA TENSION 10.0 KV - 3 Ø DE LA EBAR II 92,878.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 813.87 9,964.80 82,100.04
13.04.01 SUMINISTRO Y MONTAJE ELECTRICO DE LA RED PRIMARIA 92,878.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 813.87 9,964.80 82,100.04
13.04.01.01 OBRAS PRELIMINARES Y EXPEDIENTE FINAL 11,399.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 813.87 9,964.80 620.83
13.04.01.01.01 LIMPIEZA DE TERRENOS MANUAL EN TRAZO DE RED EN MT 390.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 390.72 0.00 0.00
13.04.01.01.02 LIMPIEZA DE TERRENOS MANUAL EN UBICACION DE POSTES DE C.A.C, A INSTALAR 46.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 46.86 0.00 0.00
13.04.01.01.03 REPLANTEO TOPOGRAFICO y UBICACION ESTRUCTURA DE LA RP 376.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 376.29 0.00 0.00
13.04.01.01.04 TRANSPORTE DE PERSONAL TECNICO EN EJECUCION DE OBRA 4,684.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,684.80 0.00
13.04.01.01.05 PROTECCION Y SEGURIDAD A LOS TRABAJADORES DE OBRA 2,480.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,480.00 0.00
13.04.01.01.06 PRUEBAS ELECTRICAS Y CONFORMIDAD DE INSTALACIONES EN MT EN VACIO 620.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 620.83
13.04.01.01.07 EXPEDIENTES TECNICOS FINAL CONFORME A OBRA ( 1 ORIGINAL + 3COPIAS) DE LA RP, INCLUYE CD DE INFORMACION 2,800.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,800.00 0.00
13.04.01.02 POSTES y ACCESORIOS DE CONCRETO ARMADO 12,032.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,032.40
13.04.01.02.01 POSTE CONCRETO ARMADO CENTRIFUGADO 13m/400Kg/180/375 mm 7,619.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,619.97
13.04.01.02.02 MEDIA LOZA DE C.A.V M/1.30/750 1,233.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,233.30
13.04.01.02.03 PALOMILLA SIMPLE C.A M/1.50/100 661.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 661.08
13.04.01.02.04 MENSULA DE C.A V M/1.00/250 2,335.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,335.68
13.04.01.02.05 CRUCETA DE MADERA 90 x 120 mm x 1.00 m 182.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 182.37
13.04.01.03 AISLADORES POLIMERICOS Y ACCESORIOS 4,554.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,554.00
13.04.01.03.01 AISLADOR DE POLIMERICO TIPO LINE POST 25 KV, LF 559mm 1,977.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,977.60
13.04.01.03.02 AISLADOR POLIMERICO 28 KV; TIPO SUSPENSION DE LF 700mm 2,576.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,576.40
13.04.01.04 CONDUCTORES DE ENERGIA ELECTRICA 13,409.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,409.70
13.04.01.04.01 CONDUCTOR DE ALEACION DE ALUMINIO AAAC 50 mm² 2,017.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,017.60
13.04.01.04.02 CONDUCTOR DE COBRE DESNUDO T BLANDO 35 mm2 1,834.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,834.13
13.04.01.04.03 CONDUCTOR DE COBRE DESNUDO T D DE 50 mm2 747.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 747.60
13.04.01.04.04 CABLE ELECTRICO NS2X 1,0KV DE 3x16mm2 1,592.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,592.80
13.04.01.04.05 CABLE ELECTRICO NS2X 1,0KV DE 3x50mm2 4,300.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,300.00
13.04.01.04.06 FERRETERIA ELECTRICA PARA POSTES, CRUCETAS, MENSULAS, CONDUCTORES Y EQUIPOS 2,917.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,917.57
13.04.01.05 PUESTA A TIERRA EN MEDIA Y BAJA TENSION 6,209.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,209.94
13.04.01.05.01 PUESTA A TIERRA EN ESTRUCTURAS DE LINEAS DE TRANSMISION 10-25 OHMS 623.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 623.74
13.04.01.05.02 PUESTA A TIERRA EN ESTRUCTURAS DE SAM Y SAB 10 HMS 3,835.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,835.44
13.04.01.05.03 PUESTA A TIERRA EN TABLEROS CON EQUIPOS ELECTRONICOS 5 OHMS 940.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 940.44
13.04.01.05.04 MEGHADO Y PROTOCOLO DE PUESTAS A TIERRA 810.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 810.32
13.04.01.06 RETENIDAS Y ANCLAJES EN MEDIA TENSION 1,815.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,815.38
13.04.01.06.01 RETENIDA SIMPLE EN MEDIA TENSION 568.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 568.06
13.04.01.06.02 RETENIDA CON CONTRAPUNTA EN MEDIA TENSION 1,247.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,247.32
13.04.01.07 ARMADOS CON EQUIPOS DE POTENCIA Y ACCESORIOS 43,457.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 43,457.79
13.04.01.07.01 ARMADO DE PUNTO DE DERIVACION 3,662.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,662.67
13.04.01.07.02 ARMADO DE SECCIONAMIENTO , TIPO PSEC 2,980.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,980.76
13.04.01.07.03 ARMADO DE SISTEMA DE MEDICION TIPO TFX Y ACCESORIOS 17,017.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,017.63
13.04.01.07.04 ARMADO VERTICAL DE ANCLAJE VANO FLOJO (0-60°), TIPO EV2 450.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 450.72
13.04.01.07.05 ARMADO DE SUB ESTACION AEREA TIPO EV2+M1, DE 37.5 KVA 17,597.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,597.51
13.04.01.07.06 TABLERO DE PROTECCION METALICO PARA ADOSAR A POSTE 460/230 V - 3 CKTOS PARA EBAR II 1,748.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,748.50
14 LINEA DE IMPULSION DE AGUAS RESIDUALES II 88,147.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,209.10 62,938.18
14.01 TRABAJOS PRELIMINARES 1,171.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 788.35 383.33
14.01.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 450.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 450.12 0.00
14.01.02 TRAZOS, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 721.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 338.23 383.33
14.02 MOVIMIENTO DE TIERRAS 38,480.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,740.20 21,740.62
14.02.01 EXCAVACION DE ZANJAS 3,226.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,226.40 0.00
14.02.01.01 EXCAVACION ZANJA c/EQUIPO HASTA 2.00 m; af = 0.80 m 3,226.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,226.40 0.00
14.02.02 REFINE y NIVELACION DE ZANJAS 415.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 415.76 0.00
14.02.02.01 REFINE y NIVELACION FONDO ZANJA; a = 0.80 m 415.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 415.76 0.00
14.02.03 CAMA DE APOYO P/TUBERIAS 3,944.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,972.27 1,972.26
14.02.03.01 CAMA APOYO (equipo) c/RIPIO CORRIENTE; af = 0.80 m 3,944.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,972.27 1,972.26
14.02.04 RELLENO, APISONADO y COMPACTACION LATERAL CON MATERIAL DE PRESTAMO 3,844.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,844.88
14.02.04.01 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 250 mm; a = 0.80 m 3,844.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,844.88
14.02.05 RELLENO y COMPACTACION S/CLAVE TUBERIA CON MATERIAL DE PRESTAMO 7,060.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,060.98
14.02.05.01 RELLENO y COMPACTACION c/RIPIO CORRIENTE h = 0.30 m; c/EQUIPO s/CLAVE TUBERIA Ø 250 mm; a = 0.80 m 7,060.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,060.98
14.02.06 RELLENO y COMPACTACION CON MATERIAL DE PRESTAMO 3,697.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,697.14
14.02.06.01 RELLENO C/MATERIAL PROPIO CAPAS c/0.20 m 3,697.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,697.14
14.02.07 ACARREO y ELIMINACION MATERIAL EXCEDENTE 5,165.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,165.36
14.02.07.01 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.0Km 5,165.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,165.36
14.02.08 BOMBEO EN ZANJAS 2,920.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,920.60 0.00
14.02.08.01 DRENAJE ZANJA HASTA 2.00 m 2,920.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,920.60 0.00
14.02.09 ENTIBADO DE ZANJAS 8,205.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,205.17 0.00
14.02.09.01 ENTIBADO ZANJA HASTA 2.00 m 8,205.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,205.17 0.00
14.03 SUMINISTRO e INSTALACION DE TUBERIAS 32,555.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32,555.56
14.03.01 TUBERIA PVC UF PN 10 = 10 bar 31,523.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31,523.61
14.03.01.01 SUMINISTRO e INSTALACION TUBERIA Ø 250 mm PVC UF PN10 10; h = 2.00 m; c/3% desperdicio 31,523.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31,523.61
14.03.02 TUBERIA PVC U, SN4 = 2KN/M2 1,031.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,031.95
14.03.02.01 SUMINISTRO e INSTALACION TUBERIA PVC U SN 4 Ø 250 mm x 6.00 m hasta h = 3.00 m 1,031.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,031.95
14.04 PRUEBAS HIDRAULICAS 1,924.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,924.71
14.04.01 DOBLE PRUEBA HIDRAULICA P/TUB PVC Ø 250 mm PN10 1,844.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,844.48
14.04.02 DOBLE PRUEBA HIDRAULICA p/TUBERIA PVC Ø 250 mm ,SN4 80.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 80.23
14.05 ACCESORIOS 5,779.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,779.46
14.05.01 SUMINISTRO e INSTALACION CODO ISO 250 mm x 90° 5,258.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,258.52
14.05.02 SUMINISTRO e INSTALACION TRANSICION a BRIDA CAMPANA ISO 2531 HFD 250 mm 520.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 520.94
14.06 BUZONES ROMPE PRESION y CAIDA ESPECIAL 8,235.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,680.55 554.50
14.06.01 BUZON ROMPE PRESION Ø interior 1.20 m inc./TARRAJEO INTERIOR prof. = 2.50 m 3,374.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,374.74 0.00
14.06.02 CAIDA ESPECIAL BUZON p/TUBERIA PVC Ø 250 mm h = 3.00 m 4,305.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,305.81 0.00
14.06.03 EMPALME BUZON y CONSTRUCCION DADO CONCRETO f'c = 175 Kg/cm² 554.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 554.50
15 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES 5,280,589.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,389.25 25,108.78 26,343.01 197,371.42 255,910.37 775,050.25 681,556.09 704,973.98 745,671.54 726,430.12 501,683.01 625,101.48
15.01 TRABAJOS PRELIMINARES 96,086.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,389.25 25,108.78 19,069.30 17,650.69 18,867.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.01.01 DESBROCE Y ELIMINACION DE MALEZA C/EQUIPO 41,308.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15,389.25 25,108.78 809.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.01.02 TRAZO Y REPLANTEO PARA PTAR 54,778.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,259.33 17,650.69 18,867.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.02 MOVIMIENTO DE TIERRAS 3,364,394.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,780.65 40,678.61 496,018.46 629,319.04 403,483.10 521,435.81 299,890.08 342,686.78 625,101.48
15.02.01 EXCAVACION MASIVA C/EQUIPO EN TERRENO NORMAL 23,122.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,780.65 17,341.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.02.02 NIVELACION EN ZONA DE CORTE 94,290.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23,336.67 70,953.33 0.00 0.00 0.00 0.00 0.00 0.00
15.02.03 CONFORMACION DE DIQUES C/MAT. DE PRESTAMO SELECCIONADO, DISTANCIA 7km 2,038,867.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 425,065.13 629,319.04 403,483.10 441,000.00 140,000.00 0.00
15.02.04 CONFORMACION DE PLATAFORMA P/CAJA ROMPE CARGA C/MAT. DE PRESTAMO 21,025.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21,025.00 0.00 0.00 0.00
15.02.05 REFINE DE TALUD DE DIQUES 52,354.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 52,354.88 0.00 0.00 0.00
15.02.06 MEJORAMIENTO DE AREA DE INGRESO C/MATERIAL DE AFIRMADO, e=0.10m 14,111.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,055.93 7,055.93 0.00 0.00
15.02.07 ELIMINACION MATERIAL EXCEDENTE Dist. min=5.0Km 41,811.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38,561.55 3,250.00
15.02.08 CONFORMACION CAPA ANTICONTAMINANTE(AFIRMADO e=20) 51,394.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 51,394.20 0.00 0.00
15.02.09 RELLENO CON MATERIAL DE PRESTAMO SELECCIONADO , DISTANCIA 7 KM 1,010,446.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 101,439.95 304,125.23 604,881.18
15.02.10 MEJORAMIENTO DE BASE DEL TERRENO CON MATERIAL OVER 16,970.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,970.30
15.03 IMPERMEABILIZACION DE LAGUNAS 768,114.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,159.79 274,899.37 139,781.02 244,471.92 106,802.04 0.00
15.03.01 EXCAVACION MANUAL DE ZANJA PARA ANCLAJES DE GEOMEMBRANA (0.30X0.30) 3,023.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,159.79 863.91 0.00 0.00 0.00 0.00
15.03.02 RELLENO DE ZANJAS C/MATERIAL DE CONCRETO 55,204.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 55,204.93 0.00
15.03.03 SUMINISTRO E INSTALACION DE GEOMENBRANA DE HDPE DE 1.50mm, TIPO SIMPLE P/FONDO DE LAGUNA 513,816.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 274,035.46 139,781.02 100,000.00 0.00 0.00
15.03.04 SUMINISTRO E INSTALACION DE GEOMEMBRANA DE HDPE DE 1.50 mm, TIPO SIMPLE P/TALUD DE LAGUNA 196,069.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 144,471.92 51,597.11 0.00
15.04 OBRAS DE ARTE 777,936.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,273.71 173,940.08 124,796.59 157,021.42 50,077.26 26,591.51 84,454.71 116,675.62 37,105.62 0.00
15.04.01 CAJA ROMPE CARGA 3,124.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,354.60 1,769.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.01.01 EXCAVACION MANUAL EN T.N. 22.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.01.02 CONCRETO f'c =100 Kg/cm² P/SOLADO 69.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 69.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.01.03 CONCRETO F'C=280 KG/CM2, CON CEMENTO PORTLAND TIPO V 988.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 988.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.01.04 ENCOFRADO Y DESENCOFRADO P/CAJA ROMPE CARGA 827.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 827.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.01.05 ARMADURA REFUERZO F'y = 4200 Kg/cm2 GRADO 60 434.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 434.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.01.06 TARRAJEO CON IMPERMEABILIZANTE, ESPESOR 0.015M 781.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 781.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.02 MEDIDOR PARSHALL 13,792.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,415.34 11,376.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.02.01 EXCAVACION MANUAL EN T.N. 189.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 189.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.02.02 CONCRETO f'c =100 Kg/cm² P/SOLADO 408.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 408.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.02.03 CONCRETO F'C=280 KG/CM2, CON CEMENTO PORTLAND TIPO V 3,727.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,727.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.02.04 ENCOFRADO Y DESENCOFRADO P/MEDIDOR PARSHALL 3,543.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,543.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.02.05 ARMADURA REFUERZO F'y = 4200 Kg/cm2 GRADO 60 2,726.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,817.45 908.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.02.06 TARRAJEO CON IMPERMEABILIZANTE, ESPESOR 0.015M 3,197.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,197.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.03 CANALES DE INGRESO A LAGUNA PRIMARIA N°1 25,657.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 696.42 23,860.52 1,100.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.03.01 EXCAVACION MANUAL EN T.N. 1,253.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 696.42 557.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO SELECC. 997.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 997.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.03.03 CONCRETO f'c =100 Kg/cm² P/SOLADO 555.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 555.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.03.04 CONCRETO F'C=280 KG/CM2, CON CEMENTO PORTLAND TIPO V 8,095.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,095.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.03.05 ENCOFRADO Y DESENCOFRADO P/CANALES DE INGRESO 4,180.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,180.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.03.06 ARMADURA REFUERZO F'y = 4200 Kg/cm2 GRADO 60 5,979.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,979.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.03.07 TARRAJEO CON IMPERMEABILIZANTE, ESPESOR 0.015M 3,932.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,495.20 436.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.03.08 JUNTA DE DILATACION 663.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 663.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.04 CANALES DE INGRESO A LAGUNA PRIMARIA N°2 47,249.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 694.63 46,554.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.04.01 EXCAVACION MANUAL EN T.N. 1,944.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 694.63 1,250.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.04.02 RELLENO COMPACTADO CON MATERIAL PROPIO SELECC. 811.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 811.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.04.03 CONCRETO f'c =100 Kg/cm² P/SOLADO 1,175.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,175.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.04.04 CONCRETO F'C=280 KG/CM2, CON CEMENTO PORTLAND TIPO V 10,839.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,839.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.04.05 ENCOFRADO Y DESENCOFRADO P/CANAL DE INGRESO 10,407.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,407.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.04.06 ARMADURA REFUERZO F'y = 4200 Kg/cm2 GRADO 60 9,950.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,950.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.04.07 TARRAJEO CON IMPERMEABILIZANTE, ESPESOR 0.015M 9,613.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,613.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.04.08 JUNTA DE DILATACION 2,506.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,506.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05 CANAL RECTANGULAR C°A° INTERCONEXION DE LAGUNAS Y 02 BUZONES, PRIMARIA A SECUNDARIA 144,465.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 704.06 61,610.45 41,934.43 40,216.17 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.01 EXCAVACION MANUAL EN T.N. 2,816.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 704.06 2,112.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.02 CONCRETO f'c =100 Kg/cm² P/SOLADO 1,865.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,865.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.03 CONCRETO F'C=280 KG/CM2, CON CEMENTO PORTLAND TIPO V 31,417.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23,563.42 7,854.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.04 ENCOFRADO Y DESENCOFRADO P/CANAL RECTANGULAR 13,767.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,767.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.05 ARMADURA REFUERZO F'y = 4200 Kg/cm2 GRADO 60 18,327.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,327.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.06 TARRAJEO CON IMPERMEABILIZANTE, ESPESOR 0.015M 14,485.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,975.26 12,509.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.07 JUNTA DE DILATACION 8,493.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,493.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.08 TAPA CALADA DE MADERA 860.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 860.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.09 PERFIL GALVANIZADO PARA TAPAS CALADAS DE MADERA 1,481.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,481.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.10 BARANDAS 46,519.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,735.33 35,784.42 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.11 ANCLAJES 1,538.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,538.40 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.12 PLATINAS 2,781.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,781.60 0.00 0.00 0.00 0.00 0.00 0.00
15.04.05.13 TUBO PVC DN 250MM 111.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 111.75 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06 CANAL RECTANGULAR C°A° INTERCONEXION DE LAGUNAS Y 02 BUZONES, SECUNDARIA A TERCIARIA 121,577.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 698.16 24,646.80 42,729.66 53,502.54 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.01 EXCAVACION MANUAL EN T.N. 2,513.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 698.16 1,815.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.02 CONCRETO f'c =100 Kg/cm² P/SOLADO 1,620.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,620.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.03 CONCRETO F'C=280 KG/CM2, CON CEMENTO PORTLAND TIPO V 25,717.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,717.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.04 ENCOFRADO Y DESENCOFRADO P/CANAL RECTANGULAR 10,204.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6,632.90 3,571.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.05 ARMADURA REFUERZO F'y = 4200 Kg/cm2 GRADO 60 16,522.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,578.57 1,943.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.06 TARRAJEO CON IMPERMEABILIZANTE, ESPESOR 0.015M 11,496.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,496.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.07 JUNTA DE DILATACION 8,493.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,493.25 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.08 TAPA CALADA DE MADERA 860.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 860.17 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.09 PERFIL GALVANIZADO PARA TAPAS CALADAS DE MADERA 1,036.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,036.87 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.10 BARANDAS 38,680.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38,680.50 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.11 ANCLAJES 1,538.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,538.40 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.12 PLATINAS 2,781.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,781.60 0.00 0.00 0.00 0.00 0.00 0.00
15.04.06.13 TUBO PVC DN 250MM 111.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 111.75 0.00 0.00 0.00 0.00 0.00 0.00
15.04.07 CANAL Y ESTRUCTURA DE SALIDA DE LAGUNA TERCIARIA N°1 Y N°2 156,664.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 710.50 4,120.93 39,032.16 63,302.71 49,498.05 0.00 0.00 0.00 0.00 0.00
15.04.07.01 EXCAVACION MANUAL EN T.N. 5,826.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 710.50 4,120.93 994.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.07.02 CONCRETO f'c =100 Kg/cm² P/SOLADO 2,142.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,142.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.04.07.03 CONCRETO F'C=280 KG/CM2, CON CEMENTO PORTLAND TIPO V 48,800.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48,800.10 0.00 0.00 0.00 0.00 0.00 0.00
15.04.07.04 ENCOFRADO Y DESENCOFRADO P/CANAL Y ESTRUCTURA DE SALIDA 12,507.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,380.70 3,126.90 0.00 0.00 0.00 0.00 0.00 0.00
15.04.07.05 ARMADURA REFUERZO F'y = 4200 Kg/cm2 GRADO 60 28,820.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26,514.65 2,305.62 0.00 0.00 0.00 0.00 0.00 0.00
15.04.07.06 TARRAJEO CON IMPERMEABILIZANTE, ESPESOR 0.015M 12,597.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,070.09 3,527.26 0.00 0.00 0.00 0.00 0.00
15.04.07.07 JUNTA DE DILATACION 961.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 961.50 0.00 0.00 0.00 0.00 0.00
15.04.07.08 TAPA CALADA DE MADERA 860.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 860.17 0.00 0.00 0.00 0.00 0.00
15.04.07.09 PERFIL GALVANIZADO PARA TAPAS CALADAS DE MADERA 1,036.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,036.87 0.00 0.00 0.00 0.00 0.00
15.04.07.10 BARANDAS 38,680.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38,680.50 0.00 0.00 0.00 0.00 0.00
15.04.07.11 ANCLAJES 1,538.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,538.40 0.00 0.00 0.00 0.00 0.00
15.04.07.12 PLATINAS 2,781.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,781.60 0.00 0.00 0.00 0.00 0.00
15.04.07.13 TUBO PVC DN 250MM 111.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 111.75 0.00 0.00 0.00 0.00 0.00
15.04.08 PUENTES DE CONCRETO ARMADO (05 UND) 76,304.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 579.21 26,591.51 49,134.04 0.00 0.00 0.00
15.04.08.01 EXCAVACION MANUAL EN T.N. 2,896.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 579.21 2,316.83 0.00 0.00 0.00 0.00
15.04.08.02 RELLENO COMPACTADO CON MATERIAL PROPIO SELECC. 1,554.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,554.39 0.00 0.00 0.00 0.00
15.04.08.03 CONCRETO f'c =100 Kg/cm² P/SOLADO 992.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 992.61 0.00 0.00 0.00 0.00
15.04.08.04 CONCRETO F'C=280 KG/CM2, CON CEMENTO PORTLAND TIPO V 23,303.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23,303.37 0.00 0.00 0.00
15.04.08.05 ENCOFRADO Y DESENCOFRADO P/PUENTE DE CONCRETO ARMADO 7,531.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,518.86 3,012.57 0.00 0.00 0.00
15.04.08.06 ARMADURA REFUERZO F'y = 4200 Kg/cm2 GRADO 60 21,511.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,208.82 4,302.21 0.00 0.00 0.00
15.04.08.07 TARRAJEO CON IMPERMEABILIZANTE, ESPESOR 0.015M 3,096.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,096.73 0.00 0.00 0.00
15.04.08.08 JUNTA DE DILATACION 2,307.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,307.60 0.00 0.00 0.00
15.04.08.09 CONCRETO F'C=140 KG/CM2 CON CEMENTO PORTLAND TIPO V 13,111.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,111.56 0.00 0.00 0.00
15.04.09 RAMPA DE ACCESO GENERAL Y A LAGUNAS 38,901.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32,433.15 6,467.94 0.00 0.00
15.04.09.01 CONFORMACION DE PLATAFORMA PARA ACCESO A LAGUNAS C/MAT.DE AFIRMADO 22,003.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,003.20 0.00 0.00 0.00
15.04.09.02 ENROCADO LATERAL DE ACCESO A LAGUNAS 7,125.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,932.75 2,192.34 0.00 0.00
15.04.09.03 ENROCADO DE SUPERFICIE DE ACCESO A LAGUNAS 9,772.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,497.20 4,275.60 0.00 0.00
15.04.10 LOSA DE ACCESO EN TALUDES DE LOS DIQUES 150,200.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,887.52 110,207.68 37,105.62 0.00
15.04.10.01 EXCAVACION MANUAL DE DIQUES EN ZONAS DE COLOCACION DE LOSA DE PROTECCION 11,838.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,887.52 8,951.32 0.00 0.00
15.04.10.02 ELIMINACION MATERIAL EXCEDENTE Dist. min=5.0Km 4,245.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,245.43 0.00
15.04.10.03 LOSA DE PROTECCION DE TALUDES DE DIQUES DE CONCRETO F´C=280 KG/CM2 E=2" 134,116.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 101,256.36 32,860.19 0.00
15.05 CASA DEL OPERADOR 51,502.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24,431.73 27,070.77 0.00 0.00 0.00 0.00 0.00 0.00
15.05.01 TRABAJOS PRELIMINARES 181.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 181.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.01.01 LIMPIEZA TERRENO MANUAL 97.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 97.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.01.02 TRAZO y REPLANTEO 83.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 83.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02 ESTRUCTURAS 19,807.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18,130.40 1,676.60 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.01 MOVIMIENTO DE TIERRAS 1,801.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,801.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.01.01 EXCAVACION TERRENO NORMAL SECO HASTA 3.00 m 632.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 632.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.01.02 RELLENO y APISONADO PARED c/MATERIAL PROPIO SELECCIONADO 204.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 204.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.01.03 RELLENO MANUAL c/MATERIAL PRESTAMO 643.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 643.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.01.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 321.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 321.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.02 CONCRETO SIMPLE 3,101.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,101.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.02.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDDO 764.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 764.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.02.02 ENCOFRADO y DESENCOFRADO HASTA 0.30 m p/SOBRECIMIENTO 1,063.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,063.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.02.03 CONCRETO C:H 1:8 + 25 % PM; f'c = 100 Kg/cm² p/SOBRECIMIENTO 378.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 378.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.02.04 CONCRETO C:H 1:8 (e = 4") p/FALSO PISO 893.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 893.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03 CONCRETO ARMADO 14,903.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,227.18 1,676.60 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.01 ZAPATAS 1,924.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,924.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.01.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 444.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 444.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.01.02 CONCRETO f'c = 210 Kg/cm² p/ZAPATA 1,479.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,479.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.02 VIGAS DE CIMENTACION 2,707.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,707.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,686.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,686.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.02.02 CONCRETO f'c = 210 Kg/cm² p/VIGA CIMENTACION 1,020.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,020.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.03 COLUMNAS 2,814.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,814.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.03.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 868.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 868.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 1,250.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,250.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.03.03 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 695.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 695.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.04 VIGAS 3,599.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,922.60 1,676.60 0.00 0.00 0.00 0.00 0.00 0.00
9 de 10
CALENDARIO DE AVANCE DE OBRA VALORIZADO ACTUALIZADO A LA FECHA DE INICIO DE OBRA
OBRA : INSTALACION DE LOS SISTEMAS DE AGUA POTABLE Y ALCANTARILLADO DE LOS PP.JJ. VILLA PROGRESO, MIRAFLORES, LAS VEGAS, SAMAN, SAN FRANCISCO DE ASIS, LA UNION, SAN JUAN DE DIOS Y RAMIRO PRIALE II - CHICLAYO
ENTIDAD : ENTIDAD PRESTADORA DE SERVICIOS DE SANEAMIENTO DE LAMBAYEQUE S.A. - EPSEL S.A.
CONTRATISTA : CONSORCIO PROGRESO
SUPERVISION : CONSORCIO SUPERVISOR ASIS
UBICACIÓN : CHICLAYO - CHICLAYO - LAMBAYEQUE
Duración (Meses)
Item Descripción Parcial (S/.)
Mar-2019 Abr-2019 May-2019 Jun-2019 Jul-2019 Ago-2019 Sep-2019 Oct-2019 Nov-2019 Dic-2019 Ene-2020 Feb-2020 Mar-2020 Abr-2020 May-2020 Jun-2020 Jul-2020 Ago-2020 Sep-2020 Oct-2020
15.05.02.03.04.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 1,277.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 638.61 638.61 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.04.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 1,283.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,283.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.04.03 CONCRETO f'c = 210 Kg/cm² p/VIGA 1,037.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,037.99 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.05 LOSAS ALIGERADAS 3,858.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,858.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.05.01 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA ALIGERADA 1,507.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,507.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.05.02 LADRILLO HUECO ARCILLA 15 x 30 x 30 cm p/LOSA ALIGERADA 827.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 827.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.05.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 530.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 530.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.02.03.05.04 CONCRETO f'c = 210 Kg/cm² p/LOSA ALIGERADA 993.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 993.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03 ARQUITECTURA 25,978.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,693.21 20,285.63 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.01 MUROS y TABIQUES DE ALBAÑILERIA 3,985.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,985.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.01.01 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 3,358.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,358.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.01.02 MURO CABEZA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 627.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 627.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.02 REVOQUES y REVESTIMIENTOS 5,717.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,717.65 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.02.01 TARRAJEO PRIMARIO c/MORTERO C:A 1:5 274.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 274.32 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.02.02 TARRAJEO INTERIOR/EXTERIOR c/MORTERO C:A 1:5 4,812.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,812.37 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.02.03 VESTIDURA DERRAME 630.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 630.96 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.03 CIELO RASO y FALSO CIELO RASO 2,356.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,356.36 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.03.01 CIELO RASO c/MORTERO C:A 1:5 2,356.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,356.36 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.04 PISOS y PAVIMENTOS 2,663.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,707.57 955.86 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.04.01 CONTRAPISO (e = 48 mm) 737.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 737.80 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.04.02 PISO CERAMICA (20 x 20 cm) p/BAÑO 218.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 218.06 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.04.03 VEREDA c/CONCRETO f' = 140 Kg/cm² (8.50 cm); PASTA (1.50 cm) 1:5; inc./encof/desencof/base de afirmado 1,707.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,707.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.05 ZOCALOS y CONTRAZOCALOS 1,482.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,482.54 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.05.01 ZOCALOS 735.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 735.48 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.05.01.01 ZOCALO CERAMICO COLOR (20 x 20 cm) 735.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 735.48 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.05.02 CONTRAZOCALOS 747.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 747.06 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.05.02.01 CONTRAZOCALO CEDRO 3/4" x 4" RODON 3/4" 747.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 747.06 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.06 CARPINTERIA METALICA y HERRERIA 8,269.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,269.67 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.06.01 PUERTA METAL LAC 1/16" y VENTANA PLEGADA c/MARCO 2" x 2" x 1/4" (inc. pintura) 7,163.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,163.00 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.06.02 VENTANA FIERRO (inc. pintura) 1,106.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,106.67 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.07 VIDRIOS, CRISTALES y SIMILARES 149.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 149.40 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.07.01 VIDRIO NACIONAL DOBLE 149.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 149.40 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.08 PINTURA 1,354.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,354.15 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.08.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 652.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 652.54 0.00 0.00 0.00 0.00 0.00 0.00
15.05.03.08.02 PINTURA LATEX CIELO RASO 02 MANOS inc./IMPRIMANTE 701.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 701.61 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04 INSTALACIONES SANITARIAS 4,310.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 426.46 3,884.50 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04.01 SISTEMA DE AGUA FRIA 3,236.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 426.46 2,810.13 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04.01.01 RED DISTRIBUCION TUBERIA PVC SAP 1 1/2" 2,132.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 426.46 1,705.85 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04.01.02 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 1 1/4" 655.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 655.56 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04.01.03 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 3/4" 9.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.92 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04.01.04 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 1/2" 13.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.92 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04.01.05 SUMINISTRO TANQUE ELEVADO DE 1.10 M3 424.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 424.88 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04.02 SISTEMA DE AGUA RESIDUAL 472.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 472.39 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04.02.01 SALIDA DESAGUE PVC 4" 229.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 229.41 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04.02.02 CAJA REGISTRO DESAGUE 12" x 24" 242.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 242.98 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04.03 APARATOS y ACCESORIOS SANITARIOS 601.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 601.98 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04.03.01 INODORO TANQUE BAJO BLANCO 205.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 205.39 0.00 0.00 0.00 0.00 0.00 0.00
15.05.04.03.02 LAVATORIO FONTANA COLOR BLANCO 396.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 396.59 0.00 0.00 0.00 0.00 0.00 0.00
15.05.05 MOBILIARIO y/o EQUIPAMIENTO 1,224.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,224.04 0.00 0.00 0.00 0.00 0.00 0.00
15.05.05.01 SUMINISTRO e INSTALACION MOBILIARIO p/CASETA 452.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 452.21 0.00 0.00 0.00 0.00 0.00 0.00
15.05.05.02 SUMINISTRO e INSTALACION ARMARIO p/VESTIDOR 771.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 771.83 0.00 0.00 0.00 0.00 0.00 0.00
15.06 CASETA DE VIGILANCIA 35,753.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24,311.14 11,442.47 0.00 0.00 0.00 0.00 0.00 0.00
15.06.01 TRABAJOS PRELIMINARES 157.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 157.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.01.01 LIMPIEZA TERRENO MANUAL 51.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 51.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.01.02 TRAZO, NIVELACION y REPLANTEO 43.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 43.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.01.03 TRAZO, NIVELACION y REPLANTEO DURANTE EJECUCION OBRA 63.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 63.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02 ESTRUCTURAS 10,068.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,068.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.01 MOVIMIENTO DE TIERRAS 1,307.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,307.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.01.01 EXCAVACION TERRENO NORMAL SECO HASTA 3.00 m 408.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 408.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.01.02 RELLENO y APISONADO PARED c/MATERIAL PROPIO SELECCIONADO 623.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 623.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.01.03 RELLENO MANUAL c/MATERIAL PRESTAMO 68.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 68.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.01.04 ACARREO y ELIMINACION MATERIAL EXCEDENTE Dist. min = 5.00 Km 207.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 207.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.02 CONCRETO SIMPLE 1,221.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,221.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.02.01 CONCRETO C:H 1:10 + 30 % PG; f'c = 100 Kg/cm² p/CIMIENTO CORRIDDO 382.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 382.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.02.02 ENCOFRADO y DESENCOFRADO HASTA 0.30 m p/SOBRECIMIENTO 275.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 275.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.02.03 CONCRETO C:H 1:8 + 25 % PM; f'c = 100 Kg/cm² p/SOBRECIMIENTO 98.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 98.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.02.04 CONCRETO C:H 1:8 (e = 4") p/FALSO PISO 465.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 465.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03 CONCRETO ARMADO 7,538.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,538.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.01 VIGAS DE CIMENTACION 2,014.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,014.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.01.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 953.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 953.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.01.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA CIMENTACION 551.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 551.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.01.03 CONCRETO f'c = 210 Kg/cm² p/VIGA CIMENTACION 510.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 510.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.02 COLUMNAS 2,279.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,279.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.02.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 983.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 983.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.02.02 ENCOFRADO y DESENCOFRADO NORMAL p/COLUMNA 833.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 833.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.02.03 CONCRETO f'c = 210 Kg/cm² p/COLUMNA 462.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 462.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.03 VIGAS 1,655.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,655.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.03.01 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 647.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 647.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.03.02 ENCOFRADO y DESENCOFRADO NORMAL p/VIGA 583.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 583.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.03.03 CONCRETO f'c = 210 Kg/cm² p/VIGA 424.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 424.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.04 LOSAS ALIGERADAS 1,588.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,588.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.04.01 ENCOFRADO y DESENCOFRADO NORMAL p/LOSA ALIGERADA 614.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 614.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.04.02 LADRILLO HUECO ARCILLA 15 x 30 x 30 cm p/LOSA ALIGERADA 327.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 327.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.04.03 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 181.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 181.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.02.03.04.04 CONCRETO f'c = 210 Kg/cm² p/LOSA ALIGERADA 464.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 464.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03 ARQUITECTURA 15,227.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,701.53 10,525.90 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.01 MUROS y TABIQUES DE ALBAÑILERIA 2,109.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,109.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.01.01 MURO SOGA LADRILLO KK TIPO IV c/CEMENTO:ARENA:CAL 1:1:4 (e = 1.5 cm) 2,109.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,109.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.02 REVOQUES y REVESTIMIENTOS 4,743.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,698.41 3,044.83 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.02.01 TARRAJEO INTERIOR/EXTERIOR c/MORTERO C:A 1:5 3,396.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,698.41 1,698.41 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.02.02 TARRAJEO SUPERFICIE COLUMNA c/MORTERO C:A 1:5 439.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 439.49 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.02.03 TARRAJEO SUPERFICIE VIGA c/MORTERO C:A 1:5 573.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 573.42 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.02.04 BRUÑA s/DETALLE (1 x 1 cm) 144.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 144.12 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.02.05 JUNTA DILATACION c/ESPUMA PLASTICA + JEBE MICROPOROSO 189.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 189.39 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.03 CIELO RASO y FALSO CIELO RASO 893.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 893.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.03.01 CIELO RASO c/MORTERO C:A 1:5 893.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 893.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.04 PISOS y PAVIMENTOS 474.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 474.18 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.04.01 CONTRAPISO (e = 48 mm) 293.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 293.45 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.04.02 PISO CERAMICA (20 x 20 cm) p/BAÑO 180.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 180.73 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.05 ZOCALOS y CONTRAZOCALOS 882.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 882.58 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.05.01 ZOCALOS 882.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 882.58 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.05.01.01 ZOCALO CERAMICO COLOR (20 x 20 cm) 882.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 882.58 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.06 CARPINTERIA METALICA y HERRERIA 5,114.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,114.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.06.01 PUERTA METAL LAC 1/16" y VENTANA PLEGADA c/MARCO 2" x 2" x 1/4" (inc. pintura) 3,952.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,952.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.06.02 VENTANA FIERRO (inc. pintura) 1,162.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,162.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.07 VIDRIOS, CRISTALES y SIMILARES 54.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 54.88 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.07.01 VIDRIO NACIONAL DOBLE 54.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 54.88 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.08 PINTURA 955.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 955.43 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.08.01 PINTURA LATEX INTERIOR/EXTERIOR 02 MANOS inc./IMPRIMANTE 689.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 689.38 0.00 0.00 0.00 0.00 0.00 0.00
15.06.03.08.02 PINTURA LATEX CIELO RASO 02 MANOS inc./IMPRIMANTE 266.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 266.05 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04 INSTALACIONES SANITARIAS 10,300.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,383.64 916.57 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.01 SISTEMA DE AGUA FRIA 194.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 194.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.01.01 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 3/4" 24.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.01.02 SUMINISTRO e INSTALACION TUBERIA PVC C 10 DN 1/2" 13.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.01.03 SALIDA AGUA FRIA c/TUBERIA PVC SAP 1/2" 63.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 63.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.01.04 VALVULAS COMPUERTA BRONCE 1/2" 91.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 91.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.02 SISTEMA DE AGUA RESIDUAL 9,189.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9,189.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.02.01 TUBERIA PVC SAL 4" 223.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 223.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.02.02 TUBERIA PVC SAL 2" 97.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 97.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.02.03 SALIDA DESAGUE PVC 4" 76.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 76.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.02.04 SALIDA DESAGUE PVC 2" 70.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 70.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.02.05 REGISTRO BRONCE 4" 129.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 129.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.02.06 REGISTRO BRONCE 2" 87.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 87.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.02.07 SALIDA VENTILACION PVC 2" 77.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 77.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.02.08 CAJA REGISTRO DESAGUE 12" x 24" 485.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 485.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.02.09 SUMINISTRO E INSTALACION DE TANQUE BIODIGESTOR 7,940.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,940.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.03 APARATOS Y ACCESORIOS SANITARIOS 916.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 916.57 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.03.01 INODORO TANQUE BAJO BLANCO 205.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 205.39 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.03.02 LAVATORIO FONTANA COLOR BLANCO 396.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 396.59 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.03.03 DUCHA CROMADA 01 LLAVE inc./ACCESORIOS 90.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 90.29 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.03.04 JABONERA LOSA BLANCO 118.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 118.56 0.00 0.00 0.00 0.00 0.00 0.00
15.06.04.03.05 GRIFO CROMADO 105.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 105.74 0.00 0.00 0.00 0.00 0.00 0.00
15.07 INGRESO Y CERCO PERIMETRICO DE PROTECCION 106,321.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22,824.32 83,497.13 0.00 0.00 0.00 0.00 0.00 0.00
15.07.01 PUERTA METALICA 7,127.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,127.27 0.00 0.00 0.00 0.00 0.00 0.00
15.07.02 MURO DE PORTADA, CON CERCO METALICO 1,824.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,824.51 0.00 0.00 0.00 0.00 0.00 0.00
15.07.03 CERCO METALICO C/ALAMBRE DE PUAS 64,440.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64,440.48 0.00 0.00 0.00 0.00 0.00 0.00
15.07.04 CERCO PERIMETRICO VIVO 22,735.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,631.09 10,104.87 0.00 0.00 0.00 0.00 0.00 0.00
15.07.05 PISO EN ENTRADA PRINCIPAL CONCRETO ARMADO 6.00x5,00 M 10,193.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,193.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.07.05.01 EXCAVACION MANUAL EN T.N. 650.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 650.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.07.05.02 CONCRETO f'c =100 Kg/cm² P/SOLADO 1,008.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,008.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.07.05.03 CONCRETO f'c = 280 Kg/cm² 5,484.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,484.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.07.05.04 ARMADURA REFUERZO f'y = 4,200 Kg/cm²; GRADO 60 3,049.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,049.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.08 DRENAJE DE AGUAS SUPERFICIALES 61,822.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 61,822.39 0.00 0.00
15.08.01 EXCAVACION DE ZANJAS C/EQUIPO HASTA 1.50 m; af = 0.80 m 7,718.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,718.34 0.00 0.00
15.08.02 REFINE y NIVELACION FONDO ZANJA; a = 0.80 m 1,308.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,308.01 0.00 0.00
15.08.03 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 200 mm; a = 0.80 m 8,864.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,864.20 0.00 0.00
15.08.04 RELLENO y COMPACTACION c/ARENA FINA h = 0.30 m; c/EQUIPO p/TUBERIA Ø 200 mm; a = 0.80 m 11,912.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,912.62 0.00 0.00
15.08.05 SUMINISTRO e INSTALACION TUBERIA PVC U SN 2 Ø 200 mm x 6.00 m hasta h = 1.50 m 32,019.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32,019.22 0.00 0.00
15.09 LINEA DE DESCARGA PARA USO DE AGUAS RESIDUALES DE TALLO ALTO 18,658.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,570.11 15,088.57 0.00
15.09.01 TRAZOS, NIVELACION y REPLANTEO INICIAL 196.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 196.50 0.00 0.00
15.09.02 EXCAVACION DE ZANJAS C/EQUIPO HASTA 2.00 m; af = 0.80 m 1,012.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,012.87 0.00 0.00
15.09.03 EXCAVACION MANUAL EN T.N. 263.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 263.01 0.00 0.00
15.09.04 REFINE y NIVELACION FONDO ZANJA; a = 0.80 m 181.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 181.50 0.00 0.00
15.09.05 CAMA APOYO (equipo) c/RIPIO CORRIENTE; af = 0.80 m 1,654.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 827.25 827.25 0.00
15.09.06 RELLENO LATERAL c/RIPIO CORRIENTE c/EQUIPO p/TUBERIA Ø 200 mm; a = 0.80 m 1,230.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,230.00 0.00
15.09.07 RELLENO y COMPACTACION c/ARENA FINA h = 0.30 m; c/EQUIPO p/TUBERIA Ø 200 mm; a = 0.80 m 1,653.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,653.00 0.00
15.09.08 RELLENO y COMPACTACION c/MATERIAL PROPIO SELECCIONADO CAPAS c/0.20 m; a = variable hasta Nivel de Terreno Natural 1,807.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,807.50 0.00
15.09.09 SUMINISTRO e INSTALACION TUBERIA PVC U SN 2 Ø 200 mm x 6.00 m hasta h = 2.00 m 4,635.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,635.00 0.00
15.09.10 DOBLE PRUEBA HIDRAULICA p/TUBERIA PVC/HDPE Ø 200 mm 437.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 437.24 0.00
15.09.11 SUMINISTRO E INSTALACION CODO Ø 200 mm x 90° PVC UF ISO (equipado) 1,200.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,200.24 0.00
15.09.12 SUMINISTRO E INSTALACION CODO Ø 200 mm x 45° PVC UF ISO (equipado) 786.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 786.44 0.00
15.09.13 BUZON TIPO "A" Ø interior 1.20 m inc./TARRAJEO INTERIOR prof. = 2.00 m 2,266.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,266.77 0.00
15.09.14 CONCRETO f'c =100 Kg/cm² P/SOLADO 78.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 78.68 0.00 0.00
15.09.15 CONCRETO F'C=280 KG/CM2, CON CEMENTO PORTLAND TIPO V 395.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 395.37 0.00 0.00
15.09.16 ENCOFRADO Y DESENCOFRADO 251.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 251.25 0.00 0.00
15.09.17 ARMADURA REFUERZO F'y = 4200 Kg/cm2 GRADO 60 363.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 363.68 0.00 0.00
15.09.18 TARRAJEO CON IMPERMEABILIZANTE, ESPESOR 0.015M 245.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 245.13 0.00
16 MEDIDAS DE MITIGACION AMBIENTAL 555,191.43 13,610.62 27,759.58 28,684.89 27,759.58 28,684.89 28,684.89 27,759.58 28,684.89 27,759.58 28,684.85 28,684.89 26,834.26 28,684.89 27,759.58 28,684.89 27,759.58 28,684.89 28,664.34 27,780.13 33,580.63
16.01 MITIGACION Y CONTROL AMBIENTAL 361,074.13 7,522.40 18,053.71 18,655.50 18,053.71 18,655.50 18,655.50 18,053.71 18,655.50 18,053.71 18,655.46 18,655.50 17,451.92 18,655.50 18,053.71 18,655.50 18,053.71 18,655.50 18,634.95 18,074.26 23,168.88
16.01.01 PLAN DE MANEJO AMBIENTAL 117,422.10 2,446.30 5,871.11 6,066.81 5,871.11 6,066.81 6,066.81 5,871.11 6,066.81 5,871.11 6,066.80 6,066.81 5,675.40 6,066.81 5,871.11 6,066.81 5,871.11 6,066.81 6,046.26 5,891.66 7,534.54
16.01.02 PLAN DE CONTINGENCIA y SEGURIDAD 58,743.43 1,223.82 2,937.17 3,035.08 2,937.17 3,035.08 3,035.08 2,937.17 3,035.08 2,937.17 3,035.08 3,035.08 2,839.27 3,035.08 2,937.17 3,035.08 2,937.17 3,035.08 3,035.08 2,937.17 3,769.35
16.01.03 PLAN DE TRANSPORTE y DISPOSICION DE RESIDUOS SOLIDOS 85,500.00 1,781.25 4,275.00 4,417.50 4,275.00 4,417.50 4,417.50 4,275.00 4,417.50 4,275.00 4,417.50 4,417.50 4,132.50 4,417.50 4,275.00 4,417.50 4,275.00 4,417.50 4,417.50 4,275.00 5,486.25
16.01.04 PROGRAMA DE PARTICIPACION CIUDADANA 73,400.00 1,529.17 3,670.00 3,792.33 3,670.00 3,792.33 3,792.33 3,670.00 3,792.33 3,670.00 3,792.32 3,792.33 3,547.67 3,792.33 3,670.00 3,792.33 3,670.00 3,792.33 3,792.33 3,670.00 4,709.87
16.01.05 SUB PROGRAMA DE CONSULTA y COMUNICACION 22,308.60 464.77 1,115.43 1,152.61 1,115.43 1,152.61 1,152.61 1,115.43 1,152.61 1,115.43 1,152.60 1,152.61 1,078.25 1,152.61 1,115.43 1,152.61 1,115.43 1,152.61 1,152.61 1,115.43 1,431.48
16.01.06 PLAN DE ABANDONO 3,700.00 77.09 185.00 191.17 185.00 191.17 191.17 185.00 191.17 185.00 191.16 191.17 178.83 191.17 185.00 191.17 185.00 191.17 191.17 185.00 237.39
16.02 EDUCACION AMBIENTAL y SANITARIA 194,117.30 6,088.22 9,705.87 10,029.39 9,705.87 10,029.39 10,029.39 9,705.87 10,029.39 9,705.87 10,029.39 10,029.39 9,382.34 10,029.39 9,705.87 10,029.39 9,705.87 10,029.39 10,029.39 9,705.87 10,411.75
16.02.01 PLAN DE CAPACITACION y EDUCACION AMBIENTAL 50,415.70 2,100.65 2,520.79 2,604.81 2,520.79 2,604.81 2,604.81 2,520.79 2,604.81 2,520.79 2,604.81 2,604.81 2,436.76 2,604.81 2,520.79 2,604.81 2,520.79 2,604.81 2,604.81 2,520.79 2,184.66
16.02.02 SUB PROGRAMA DE GESTION SOCIAL 143,701.60 3,987.57 7,185.08 7,424.58 7,185.08 7,424.58 7,424.58 7,185.08 7,424.58 7,185.08 7,424.58 7,424.58 6,945.58 7,424.58 7,185.08 7,424.58 7,185.08 7,424.58 7,424.58 7,185.08 8,227.09
17 PLAN DE MONITOREO ARQUEOLOGICO 212,704.00 4,431.35 10,635.20 10,989.71 10,635.20 10,989.71 10,989.71 10,635.20 10,989.71 10,635.20 10,989.68 10,989.71 10,280.69 10,989.71 10,635.20 10,989.71 10,635.20 10,989.71 10,989.71 10,574.00 13,709.69
17.01 ELABORACION DEL PLAN DE MONITOREO E INFORME FINAL 13,720.00 285.84 686.00 708.87 686.00 708.87 708.87 686.00 708.87 686.00 708.86 708.87 663.13 708.87 686.00 708.87 686.00 708.87 708.87 686.00 880.34
17.02 PERSONAL DE CAMPO - IMPLEMENTACION DEL PLAN DE MONITOREO 194,480.00 4,051.67 9,724.00 10,048.13 9,724.00 10,048.13 10,048.13 9,724.00 10,048.13 9,724.00 10,048.12 10,048.13 9,399.87 10,048.13 9,724.00 10,048.13 9,724.00 10,048.13 10,048.13 9,724.00 12,479.17
17.03 MATERIALES Y MOVILIDAD 1,500.00 31.25 75.00 77.50 75.00 77.50 77.50 75.00 77.50 75.00 77.50 77.50 72.50 77.50 75.00 77.50 75.00 77.50 77.50 75.00 96.25
17.04 PAGOS AL MC 3,004.00 62.59 150.20 155.21 150.20 155.21 155.21 150.20 155.21 150.20 155.20 155.21 145.19 155.21 150.20 155.21 150.20 155.21 155.21 89.00 253.93
18 PRUEBAS HIDRÁULICAS PTAP Y PTAR 113,815.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31,351.15 22,910.46 0.00 25,144.95 34,408.89
18.01 PRUEBA HIDRÁULICA PLANTA DE TRATAMIENTO DE AGUA POTABLE 54,261.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31,351.15 22,910.46 0.00 0.00 0.00
18.02 PRUEBA HIDRÁULICA PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES 59,553.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,144.95 34,408.89
19 PUESTA EN MARCHA PTAP 52,190.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,917.55 38,273.27 0.00
19.01 PUESTA EN MARCHA PLANTA DE TRATAMIENTO DE AGUA POTABLE 52,190.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13,917.55 38,273.27 0.00
20 PLAN DE SEGURIDAD Y SALUD OCUPACIONAL 187,513.85 7,813.08 9,376.95 9,686.96 9,375.69 9,688.22 9,688.22 9,375.69 9,688.22 9,375.69 9,688.22 9,688.22 9,063.16 9,688.22 9,375.69 9,688.22 9,375.69 9,688.22 9,688.22 9,375.69 8,125.58
20.01 CINTA PLASTICA SEÑALIZADORA PARA LIMITE DE SEGURIDAD DE OBRA 64,445.46 2,685.23 3,222.27 3,329.68 3,222.27 3,329.68 3,329.68 3,222.27 3,329.68 3,222.27 3,329.68 3,329.68 3,114.86 3,329.68 3,222.27 3,329.68 3,222.27 3,329.68 3,329.68 3,222.27 2,792.68
20.02 MALLA HDP COLOR NARANJA 63,153.39 2,631.39 3,157.67 3,262.93 3,157.67 3,262.93 3,262.93 3,157.67 3,262.93 3,157.67 3,262.93 3,262.93 3,052.41 3,262.93 3,157.67 3,262.93 3,157.67 3,262.93 3,262.93 3,157.67 2,736.60
20.03 PUENTE DE MADERA PARA PASE PEATONAL SOBRE ZANJA 3,295.00 137.29 164.75 170.24 164.75 170.24 170.24 164.75 170.24 164.75 170.24 170.24 159.26 170.24 164.75 170.24 164.75 170.24 170.24 164.75 142.80
20.04 SEGURIDAD, HIGIENE OCUPACIONAL Y SALUD EN LA OBRA 45,000.00 1,875.00 2,251.26 2,323.74 2,250.00 2,325.00 2,325.00 2,250.00 2,325.00 2,250.00 2,325.00 2,325.00 2,175.00 2,325.00 2,250.00 2,325.00 2,250.00 2,325.00 2,325.00 2,250.00 1,950.00
20.05 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO 11,620.00 484.17 581.00 600.37 581.00 600.37 600.37 581.00 600.37 581.00 600.37 600.37 561.63 600.37 581.00 600.37 581.00 600.37 600.37 581.00 503.50
21 SEÑALIZACION Y DESVIO DE TRANSITO 78,512.13 0.00 2,355.36 4,867.76 4,710.73 4,867.76 4,867.76 4,710.73 4,867.76 4,710.73 4,867.76 4,867.69 4,553.70 4,867.76 4,710.73 4,867.76 4,710.73 4,867.76 4,239.65 0.00 0.00
21.01 SEÑALIZACIÓN NOCTURNA 20,000.00 0.00 600.00 1,240.00 1,200.00 1,240.00 1,240.00 1,200.00 1,240.00 1,200.00 1,240.00 1,240.00 1,160.00 1,240.00 1,200.00 1,240.00 1,200.00 1,240.00 1,080.00 0.00 0.00
21.02 CONO FIBRA DE VIDRIO FOSFORESCENTE PARA SEÑALIZACION 2,000.00 0.00 60.00 124.00 120.00 124.00 124.00 120.00 124.00 120.00 124.00 124.00 116.00 124.00 120.00 124.00 120.00 124.00 108.00 0.00 0.00
21.03 PARANTE PARA CINTA PLASTICA SEÑAL 32,434.13 0.00 973.02 2,010.92 1,946.05 2,010.92 2,010.92 1,946.05 2,010.92 1,946.05 2,010.92 2,010.88 1,881.18 2,010.92 1,946.05 2,010.92 1,946.05 2,010.92 1,751.44 0.00 0.00
21.04 TRANQUERAS DE MADERA 1.20X1.10M P/DESVIO TRANSITO VEHICULAR 15,078.00 0.00 452.34 934.84 904.68 934.84 934.84 904.68 934.84 904.68 934.84 934.81 874.52 934.84 904.68 934.84 904.68 934.84 814.21 0.00 0.00
21.05 PUENTE DE MADERA PARA PASE VEHICULAR 9,000.00 0.00 270.00 558.00 540.00 558.00 558.00 540.00 558.00 540.00 558.00 558.00 522.00 558.00 540.00 558.00 540.00 558.00 486.00 0.00 0.00
22 VARIOS 99,200.00 0.00 0.00 0.00 0.00 0.00 0.00 6,613.33 7,321.90 7,085.71 7,321.90 7,321.90 6,849.52 7,321.90 7,085.71 7,321.90 7,085.71 7,321.90 7,321.90 7,085.71 6,141.01
22.01 AFECTACIÓN DE TERRENO AGRICOLA 99,200.00 0.00 0.00 0.00 0.00 0.00 0.00 6,613.33 7,321.90 7,085.71 7,321.90 7,321.90 6,849.52 7,321.90 7,085.71 7,321.90 7,085.71 7,321.90 7,321.90 7,085.71 6,141.01
COSTO DIRECTO (S/.) 39,021,559.45 46,271.08 585,603.80 855,278.26 1,006,219.82 1,397,929.85 1,499,344.57 1,758,637.36 2,395,297.07 3,254,927.90 3,293,988.22 3,305,097.25 3,285,564.44 2,926,019.36 2,414,717.76 2,200,631.84 1,940,364.53 1,921,357.16 1,849,034.21 1,645,812.37 1,439,462.60
11.89058357% GASTOS GENERALES (11.89058357%) 4,639,891.14 5,501.90 69,631.71 101,697.58 119,645.41 166,222.02 178,280.82 209,112.24 284,814.80 387,029.92 391,674.42 392,995.35 390,672.79 347,920.78 287,124.03 261,667.97 230,720.67 228,460.58 219,860.96 195,696.70 171,160.49
2.3880% UTILIDAD (2.3880%) 931,834.84 1,104.95 13,984.22 20,424.04 24,028.53 33,382.56 35,804.35 41,996.26 57,199.69 77,727.68 78,660.44 78,925.72 78,459.28 69,873.34 57,663.46 52,551.09 46,335.90 45,882.01 44,154.94 39,302.00 34,374.38
SUB TOTAL (S/.) 44,593,285.43 52,877.93 669,219.73 977,399.88 1,149,893.76 1,597,534.43 1,713,429.74 2,009,745.86 2,737,311.56 3,719,685.50 3,764,323.08 3,777,018.32 3,754,696.51 3,343,813.48 2,759,505.25 2,514,850.90 2,217,421.10 2,195,699.75 2,113,050.11 1,880,811.07 1,644,997.47
18.00% I.G.V. (18.00%) 8,026,791.38 9,518.03 120,459.55 175,931.98 206,980.88 287,556.20 308,417.35 361,754.25 492,716.08 669,543.39 677,578.15 679,863.30 675,845.37 601,886.43 496,710.95 452,673.16 399,135.80 395,225.96 380,349.02 338,545.99 296,099.54
COSTO TOTAL 52,620,076.81 62,395.96 789,679.28 1,153,331.86 1,356,874.64 1,885,090.63 2,021,847.09 2,371,500.11 3,230,027.64 4,389,228.89 4,441,901.23 4,456,881.62 4,430,541.88 3,945,699.91 3,256,216.20 2,967,524.06 2,616,556.90 2,590,925.71 2,493,399.13 2,219,357.06 1,941,097.01
COSTO TOTAL ACUMULADO 52,620,076.81 62,395.96 852,075.24 2,005,407.10 3,362,281.74 5,247,372.37 7,269,219.46 9,640,719.57 12,870,747.21 17,259,976.10 21,701,877.33 26,158,758.95 30,589,300.83 34,535,000.74 37,791,216.94 40,758,741.00 43,375,297.90 45,966,223.61 48,459,622.74 50,678,979.80 52,620,076.81
% AVANCE MENSUAL 0.12% 1.50% 2.19% 2.58% 3.58% 3.84% 4.51% 6.14% 8.34% 8.44% 8.47% 8.42% 7.50% 6.19% 5.64% 4.97% 4.92% 4.74% 4.22% 3.69%
% AVANCE MENSUAL ACUMULADO 0.12% 1.62% 3.81% 6.39% 9.97% 13.81% 18.32% 24.46% 32.80% 41.24% 49.71% 58.13% 65.63% 71.82% 77.46% 82.43% 87.35% 92.09% 96.31% 100.00%

10 de 10

You might also like